CN106760567A - A kind of shear wall aluminum alloy mould plate fixes hanging apparatus - Google Patents

A kind of shear wall aluminum alloy mould plate fixes hanging apparatus Download PDF

Info

Publication number
CN106760567A
CN106760567A CN201710024746.XA CN201710024746A CN106760567A CN 106760567 A CN106760567 A CN 106760567A CN 201710024746 A CN201710024746 A CN 201710024746A CN 106760567 A CN106760567 A CN 106760567A
Authority
CN
China
Prior art keywords
back cord
template
wall
screw rod
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710024746.XA
Other languages
Chinese (zh)
Inventor
朱德玉
李兴党
朱德强
刘峰
丁善立
满爱莲
张智勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG ZHONGMEI ENERGY MECHINE CO Ltd
Original Assignee
SHANDONG ZHONGMEI ENERGY MECHINE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ZHONGMEI ENERGY MECHINE CO Ltd filed Critical SHANDONG ZHONGMEI ENERGY MECHINE CO Ltd
Priority to CN201710024746.XA priority Critical patent/CN106760567A/en
Publication of CN106760567A publication Critical patent/CN106760567A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to building field, specifically a kind of shear wall aluminum alloy mould plate fixes hanging apparatus, including:Inside wall formwork, outer wall template, screw rod, back cord and and boom hoisting, inner, external wall template is parallel to each other, accommodating chamber is defined between the two, screw rod through the two ends of the space of inner, external wall template and back cord and screw rod respectively by the first fastener for being located inside wall formwork side and the second fastener for being located at outer wall template side internally, outer wall template, back cord be fixed, and screw rod the end in outer wall template side be connected with the second fastener after do not protruded relative to the lateral surface of back cord.It is beneficial in that:It is of the invention to reduce the prominent length of outer wall template by improving the fixed form of the inner, external wall template of shear wall, so as to increase the distance between two sides shear wall, reduce difficulty of construction;And back cord and boom hoisting by optimizing, centring property is improve, improve the security performance of efficiency of construction and boom hoisting.

Description

A kind of shear wall aluminum alloy mould plate fixes hanging apparatus
Technical field
The present invention relates to building field, specifically a kind of shear wall aluminum alloy mould plate fixes hanging apparatus.
Background technology
In building field, according to relevant regulations, after wall span exceedes certain length, applying, man-hour requirement building is heavy Drop is stitched come to prevent building each several part from causing house to destroy due to uneven settlement of foundation.Between the wall of subsiding crack both sides Away from typically only 200mm or so.
And the shear wall aluminum alloy mould plate of currently available technology and the mode that is connected of back cord are as shown in figure 1, be to pass through Split bolt is fixed through the template of inner, external wall, and split bolt is passed from both sides, it is difficult to ensure that split bolt passes exterior wall Distance after template is less than 200mm, even if being less than 200mm, also can be very when the wall of subsiding crack both sides is constructed simultaneously It is difficult.
When being constructed using aluminum alloy mould plate, the template assembly for high-storey is often to lift by crane each template one by one Installed to specified location, and if integral lifting to specified location can undoubtedly be carried significantly after template system is installed on ground Efficiency of construction high, keeps system not deform upon integrally during the key problem in technology of integral hoisting during lifting, firm in structure, and And boom hoisting can be dismantled conveniently, and the boom hoisting of the template system for after installation of the prior art cannot often be protected Demonstrate,prove the requirement of this key technology.
The content of the invention
In order to solve above-mentioned technological deficiency, the invention provides following technical scheme:
The present invention is that a kind of shear wall aluminum alloy mould plate fixes hanging apparatus, including:Inside wall formwork, outer wall template and it is described it is interior, The screw rod of outer wall template connection and the back cord of screw rod connection and the boom hoisting being connected with the back cord, it is described inside and outside Wall form is parallel to each other, and accommodating chamber is defined between the two, and pouring into a mould concrete in the accommodating chamber during construction forms wall, described Back cord be two opposing parallel settings and between leave the square through-pipe structure of Two bors d's oeuveres in space, the screw rod is through described inside and outside The two ends of the space of wall form and the back cord and the screw rod are respectively by being located at the first fastener of inside wall formwork side The inner, external wall template, the back cord are fixed with the second fastener for being located at outer wall template side, and the screw rod Do not protruded relative to the lateral surface of the back cord after the end of outer wall template side is connected with second fastener, that is, Second fastener is connected the fixation carried out to the back cord by with the screw rod, wherein, outside second fastener Lateral surface of the side end face substantially with the back cord mutually maintains an equal level.So ensure that to be tried one's best in construction and reduce the relative of outer wall template Thickness, is easy to construction.
A kind of its specific optimal technical scheme is that first fastener is nut, and second fastener is built-in Formula nut, the built-in nut has nut body and the lid axially vertical with the nut body, the end of the screw rod Stopped by the lid after nut body described in portion's precession.
When needing to carry out lifting operation to this template, it is necessary to install boom hoisting on the back cord, as the present invention A kind of optimal technical scheme, the boom hoisting include connection sheet, the first bolt and rise chain sling, the connection sheet vertically side It is connected with described chain sling upwardly through the first bolt, the connection sheet includes interior and outer plate, it incites somebody to action described with being oppositely arranged Back cord is clamped between two panels, and the two ends of described inside and outside removably connect.
As a preferred technical solution of the present invention, space from the interior middle part and outer plate between to the back cord Sunken inside forms separation sleeve, and the separation sleeve two ends pass through the second bolt connection.
In the above-mentioned technical solutions, the back cord on the outside of the outer wall template except with the screw rod and second fastener Connection, is also attached with connector and the 3rd fastener, and its specific connected mode is that the inner, external wall formwork structure is identical, And its both sides has the template side rib vertical with its plate face, and some mounting holes are distributed at equal intervals on the rib of the template side, each The adjacent inside wall formwork or the outer wall template are spliced by the 3rd bolt through the mounting hole, on the rib of the template side Connector removably is connected with, the connector is connected with the 3rd fastener and back cord.
As a preferred technical solution of the present invention, the connector have installing plate, at least two can be by The installing plate is fixed on the 4th bolt on the rib of the template side, be fixed with the installing plate one it is vertical with plate face and to The intubation that outside is stretched out;The back cord be two ends to connection and it is opposing parallel setting and between have space the square siphunculus of Two bors d's oeuveres Structure;Platy structure with cylinder centered on 3rd fastener, the cylinder interior has screw thread, and it puts in the back of the body It is connected with the intubation of the connector by the 4th bolt in stupefied space.
In the inventive solutions, generally there are multiple back cords in construction on each wall form, therefore in peace Need that multiple boom hoistings are installed during dress, the 5th bolt connection is passed through between the boom hoisting and boom hoisting.
By the template system of said structure, the modular unit of assembled suitable size as needed in a practical situation, interior, Outer wall template is fixed by multigroup screw rod, back cord and boom hoisting.
The present invention is compared with prior art, it is beneficial that:The present invention is by improving the inner, external wall template of shear wall Fixed form reduces the prominent length of outer wall template, so as to increase the distance between two sides shear wall, further reduces construction Difficulty.By the back cord and boom hoisting that optimize, centring property is improve, effectively increase efficiency of construction, reduce the peace of back cord ETL estimated time of loading simultaneously improves the security performance of boom hoisting.
Brief description of the drawings
Fig. 1 is the schematic cross-section of inner, external wall template in the prior art;
Fig. 2 is the schematic cross-section of inner, external wall template of the invention;
Fig. 3 is the axial section of the second fastener of the invention;
Fig. 4 is the structural representation after template of the invention, back cord and boom hoisting are installed;
Fig. 5 is the lateral view of Fig. 4;
Fig. 6 is the enlarged drawing of the connection sheet part of boom hoisting in Fig. 5;
Fig. 7 is the structural representation after template of the invention, back cord and connector are installed;
Fig. 8 is the lateral enlarged drawing in A portions in Fig. 7;
Fig. 9 is the structural representation of connector of the invention;
Figure 10 is the section view of connector of the invention;
Figure 11 is the structural representation of the 3rd fastener of the invention;
The section view of Figure 12 the 3rd fasteners of the invention.
Specific embodiment
Further implementation of the invention is illustrated by accompanying drawing now.
Illustrated in fig. 1 is inside wall formwork 01, outer wall template 02 and the screw rod 03 of shear wall common in the art Section view, can clearly observe that its left and right is essentially symmetrical structure, has thus resulted in the outside of outer wall template 02 in figure Screw rod excessively protrude, and the distance of subsiding crack both sides wall 04 typically only have 200mm, construction when often bring inconvenience.
In order to improve above-mentioned prior art deficiency and obtain further effect of optimization, Fig. 2 is illustrated that of the invention changing The section view of the inside wall formwork, outer wall template and screw rod of the shear wall after entering, including:Inside wall formwork 1, outer wall template 2 and the screw rod 3 of the connection of the inner, external wall template 1,2 and the back cord 4 of the connection of the screw rod 3 and it is connected with the back cord 4 Boom hoisting 5, the inner, external wall template 1,2 is parallel to each other, and it is wall 10, institute to define between the two in accommodating chamber, accommodating chamber State back cord 4 for two opposing parallel settings and between leave the square through-pipe structure of Two bors d's oeuveres in space, the screw rod 3 is through described The space of inner, external wall template 1, the 2 and the back cord 4 and two ends of the screw rod 3 are respectively by being located at the side of inside wall formwork 1 First fastener 6 and be located at the side of outer wall template 2 the inner, external wall template 1 of the second fastener 7 pairs, 2, the back cord 4 carries out It is fixed, and the screw rod 3 the end in the side of outer wall template 2 be connected with second fastener 7 after relative to the back cord 4 Lateral surface do not protrude.
In order to further illustrate the connected mode of the screw rod 3 and the inner, external wall template 1,2, as shown in figure 3, described First fastener 6 is nut, and second fastener 7 is built-in nut, and the built-in nut has the He of nut body 71 The lid 72 axially vertical with the nut body 71, is subject to described after nut body 71 described in the end precession of the screw rod 3 Lid 72 stops.
Further, as shown in Figs. 4-6, the boom hoisting 5 includes connection sheet, the first bolt 53 and plays chain sling 54, institute State connection sheet in the vertical direction to be connected with described chain sling 54 by the first bolt 53, the connection sheet is including interior 51 and outer Piece 52, be clamped in the back cord 4 between two panels with being oppositely arranged by it, and the two ends of described inside and outside 51,52 removably connect Connect.Described interior 51 and the middle part between outer plate 52 form separation sleeve 55, the separation sleeve to the space sunken inside of the back cord 4 55 two ends are connected by the second bolt 56.
Shown by Fig. 7 and 8 is that two adjacent outer wall templates 2 are installed the structural representation of back cord 4 and cut after assembly Face view, the inner, external wall template 1,2 structures are identical, and its both sides has the template side rib 21 vertical with its plate face, the mould Some mounting holes 22 are distributed on edges of boards rib 21 at equal intervals, each adjacent inside wall formwork 1 or the outer wall template 2 pass through 3rd bolt 23 splices through the mounting hole 22, and removably connector 8, the connection are connected with template side rib 21 Part 8 is connected with the 3rd fastener 9 and back cord 4.What Fig. 9 and Figure 10 were represented is the connector 8, and it has an installing plate 81st, two the 4th bolts 82 that can be fixed on the installing plate on the rib of the template side, are fixed with the installing plate 81 One intubation 83 that is vertical with plate face and stretching out laterally;As is illustrated by figs. 11 and 12, the 3rd fastener 9 is middle part protrusion The projection 91 that formation is engaged with the gap of the back cord, the center of the projection 91 has the platy structure of circular hole 92, the circle The inside of hole 91 has screw thread, and the intubation of the 5th bolt 92 and the connector 8 is passed through in its space for putting in the back cord 4 83 connections.
The inner, external wall template 1,2 is fixed by multigroup screw rod 3, back cord 4 and boom hoisting 5, and described Connected by the 6th bolt 57 between boom hoisting 5 and boom hoisting 5.
Above-mentioned specific embodiment is only specific case of the invention, and scope of patent protection of the invention is included but is not limited to The product form and style of above-mentioned specific embodiment, any claims of the present invention and any art of meeting Appropriate change or modification that those of ordinary skill is done to it, should all fall into scope of patent protection of the invention.

Claims (8)

1. a kind of shear wall aluminum alloy mould plate fixes hanging apparatus, including:Inside wall formwork, outer wall template and the inner, external wall mould The screw rod of plate connection and the back cord of screw rod connection and the boom hoisting being connected with the back cord, the inner, external wall template It is parallel to each other, accommodating chamber is defined between the two, it is characterised in that the back cord be two it is opposing parallel setting and between leave The square through-pipe structure of Two bors d's oeuveres in space, the screw rod passes through space and the spiral shell of the inner, external wall template and the back cord The two ends of bar are respectively by being located at the first fastener of inside wall formwork side and being located at the second fastener pair of outer wall template side The inner, external wall template, the back cord are fixed, and the end in outer wall template side of the screw rod is tight with described second Do not protruded relative to the lateral surface of the back cord after firmware connection.
2. a kind of shear wall aluminum alloy mould plate according to claim 1 fixes hanging apparatus, it is characterised in that described first Fastener is nut, second fastener be built-in nut, the built-in nut have nut body and with the spiral shell The axially vertical lid of maternal body, is stopped after nut body described in the end precession of the screw rod by the lid.
3. a kind of shear wall aluminum alloy mould plate according to claim 1 fixes hanging apparatus, it is characterised in that the lifting Device includes connection sheet, the first bolt and plays chain sling, and the connection sheet in the vertical direction passes through the first bolt and the lifting Chain connect, the connection sheet include interior and outer plate, be clamped in the back cord between two panels with being oppositely arranged by it, it is described in, The two ends of outer plate removably connect.
4. a kind of shear wall aluminum alloy mould plate according to claim 3 fixes hanging apparatus, it is characterised in that described interior Middle part and outer plate between forms separation sleeve to the space sunken inside of the back cord, and the separation sleeve two ends are connected by the second bolt Connect.
5. a kind of shear wall aluminum alloy mould plate according to claim 1 fixes hanging apparatus, it is characterised in that in described, Outer wall template structure is identical, and its both sides has the template side rib vertical with its plate face, divides at equal intervals on the rib of the template side The some mounting holes of cloth, each adjacent inside wall formwork or the outer wall template are spelled by the 3rd bolt through the mounting hole Connect, removably connector is connected with the rib of the template side, the connector is connected with the 3rd fastener and back cord.
6. a kind of shear wall aluminum alloy mould plate according to claim 5 fixes hanging apparatus, it is characterised in that the connection Part has an installing plate, at least two the 4th bolts that can be fixed on the installing plate on the rib of the template side, described An intubation that is vertical with plate face and stretching out laterally is fixed with installing plate;There is cylinder centered on 3rd fastener Platy structure, the cylinder interior has screw thread, and the 4th bolt and the connector are passed through in its space for putting in the back cord The intubation connection.
7. a kind of shear wall aluminum alloy mould plate according to claim 5 or 6 fixes hanging apparatus, it is characterised in that described Pass through the 5th bolt connection between boom hoisting and boom hoisting.
8. a kind of shear wall aluminum alloy mould plate according to any of the above-described claim fixes hanging apparatus, and its feature exists In the inner, external wall template is fixed by multigroup screw rod, back cord and boom hoisting.
CN201710024746.XA 2017-01-13 2017-01-13 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus Pending CN106760567A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710024746.XA CN106760567A (en) 2017-01-13 2017-01-13 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710024746.XA CN106760567A (en) 2017-01-13 2017-01-13 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus

Publications (1)

Publication Number Publication Date
CN106760567A true CN106760567A (en) 2017-05-31

Family

ID=58945332

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710024746.XA Pending CN106760567A (en) 2017-01-13 2017-01-13 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus

Country Status (1)

Country Link
CN (1) CN106760567A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316644A (en) * 2018-03-22 2018-07-24 浙江谊科建筑技术发展有限公司 A kind of big mold device of aluminum alloy mould plate assembling
CN108590177A (en) * 2018-07-09 2018-09-28 中建铝新材料成都有限公司 K plates bracing means and its reinforcement means
CN110409825A (en) * 2019-08-23 2019-11-05 中国建筑第八工程局有限公司 Connection jaw arrangement and its construction method for reinforcing template system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5836132A (en) * 1996-04-10 1998-11-17 E-Z Anchor Bolt Template, Inc. Anchor template
CN203247506U (en) * 2013-04-28 2013-10-23 中铁十二局集团第二工程有限公司 Bridge high-pier construction creeping formwork internal formwork lifting frame
CN203394028U (en) * 2013-05-14 2014-01-15 中建保华建筑有限责任公司 Wall template system applied in seismic joint
CN204252530U (en) * 2014-11-14 2015-04-08 中建三局集团有限公司 A kind of exterior wall typified form to rise overally hanging apparatus with climbing frame
CN105178591A (en) * 2015-10-12 2015-12-23 江苏南通二建集团有限公司 Small-gap double-shear-wall deformation joint formwork and construction method thereof
CN105332508A (en) * 2015-11-28 2016-02-17 晟通科技集团有限公司 Formwork fastening device
CN206767423U (en) * 2017-01-13 2017-12-19 山东中煤能源机械有限责任公司 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5836132A (en) * 1996-04-10 1998-11-17 E-Z Anchor Bolt Template, Inc. Anchor template
CN203247506U (en) * 2013-04-28 2013-10-23 中铁十二局集团第二工程有限公司 Bridge high-pier construction creeping formwork internal formwork lifting frame
CN203394028U (en) * 2013-05-14 2014-01-15 中建保华建筑有限责任公司 Wall template system applied in seismic joint
CN204252530U (en) * 2014-11-14 2015-04-08 中建三局集团有限公司 A kind of exterior wall typified form to rise overally hanging apparatus with climbing frame
CN105178591A (en) * 2015-10-12 2015-12-23 江苏南通二建集团有限公司 Small-gap double-shear-wall deformation joint formwork and construction method thereof
CN105332508A (en) * 2015-11-28 2016-02-17 晟通科技集团有限公司 Formwork fastening device
CN206767423U (en) * 2017-01-13 2017-12-19 山东中煤能源机械有限责任公司 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316644A (en) * 2018-03-22 2018-07-24 浙江谊科建筑技术发展有限公司 A kind of big mold device of aluminum alloy mould plate assembling
CN108590177A (en) * 2018-07-09 2018-09-28 中建铝新材料成都有限公司 K plates bracing means and its reinforcement means
CN110409825A (en) * 2019-08-23 2019-11-05 中国建筑第八工程局有限公司 Connection jaw arrangement and its construction method for reinforcing template system

Similar Documents

Publication Publication Date Title
CN104196222B (en) The suspension scaffold of tools type section steel builder's jack
CN106760567A (en) A kind of shear wall aluminum alloy mould plate fixes hanging apparatus
CN109095343A (en) Assembled hanger
CN212689564U (en) Temporary supporting device and temporary supporting structure for floor bearing plate
CN108049628A (en) Assembled architecture outer wall quickly pacifies form removal system and construction method without outrigger
CN206767423U (en) A kind of shear wall aluminum alloy mould plate fixes hanging apparatus
CN111456425A (en) Temporary supporting device, temporary supporting structure and temporary supporting method for floor bearing plate
CN208502291U (en) Elevator horizontal protective device
CN205323047U (en) Perforation formula safety belt hanging device
CN217079667U (en) Elevator shaft and daylighting are handled well and are hung mould structure
CN216766397U (en) Building curtain wall mounting structure
CN109987500A (en) A kind of building material cage
CN207634046U (en) A kind of suspension type blowout preventer protective umbrella and its drilling fluid outlet pipe
CN211691536U (en) Simple lifting mechanism for bare concrete exterior wall cladding
CN212802504U (en) Deformation joint double-shear wall template system
CN211056521U (en) Prefabricated component installation hoist
CN210480607U (en) Hoisting device for disassembling and assembling shield machine
KR101707037B1 (en) A structure for assembled system scaffold and erecting method thereof
CN210286469U (en) Prefabricated part hoist
KR20130129151A (en) Clamp of system support for construction
CN208948679U (en) Assembled hanger
CN205637587U (en) Thick liquid processing apparatus is leaked to template bottom
CN205555870U (en) Hoisting equipment for engineering
CN108104486A (en) A kind of trench corner position waterproof roll liner is laid with instrument
CN217925865U (en) Steel plate clamp for temporary connection of vertical shaft construction hanging scaffold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531