CN106760255A - A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube - Google Patents

A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube Download PDF

Info

Publication number
CN106760255A
CN106760255A CN201710003495.7A CN201710003495A CN106760255A CN 106760255 A CN106760255 A CN 106760255A CN 201710003495 A CN201710003495 A CN 201710003495A CN 106760255 A CN106760255 A CN 106760255A
Authority
CN
China
Prior art keywords
light
roofing
steel
steel roofing
drainage piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710003495.7A
Other languages
Chinese (zh)
Inventor
刘敬伟
王庆江
邱爵廖
宋凌辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiamen City Yapha Optoelectronics Technology Co Ltd
Original Assignee
Xiamen City Yapha Optoelectronics Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen City Yapha Optoelectronics Technology Co Ltd filed Critical Xiamen City Yapha Optoelectronics Technology Co Ltd
Priority to CN201710003495.7A priority Critical patent/CN106760255A/en
Publication of CN106760255A publication Critical patent/CN106760255A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/04Roof drainage; Drainage fittings in flat roofs, balconies or the like
    • E04D13/0404Drainage on the roof surface
    • E04D13/0481Drainage guiding provisions, e.g. deflectors or stimulation by inclined surfaces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F21LIGHTING
    • F21SNON-PORTABLE LIGHTING DEVICES; SYSTEMS THEREOF; VEHICLE LIGHTING DEVICES SPECIALLY ADAPTED FOR VEHICLE EXTERIORS
    • F21S11/00Non-electric lighting devices or systems using daylight
    • F21S11/007Non-electric lighting devices or systems using daylight characterised by the means for transmitting light into the interior of a building

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • General Engineering & Computer Science (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The present invention relates to a kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube, the light-steel roofing for being provided with reinforcement, including dome skylight, rainhat, photoconductive tube, diffusing globe and pier base are installed on;The present invention also sets up drainage piece, and on the light-steel roofing reinforcement bearing of trend from high to low, the drainage piece is arranged at the front side of the pier base;The first end palette of the drainage piece is in light-steel roofing, second end is sealedly attached to the pier base and light-steel roofing, so that the light-steel roofing is connected to the pier base by the drainage piece, one end that the drainage piece is connected with pier base is in planar structure, avoid the problem that pools zone is formed between two reinforcements, current on light-steel roofing are guided to pier base side and flow out by the planar structure, solve the easy ponding of light guide tubular construction, the problems such as seepage is dirty.

Description

A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube
Technical field
The invention belongs to energy-saving lighting equipment technical field, more particularly to a kind of room of light-steel roofing construction and installation photoconductive tube The anti-ponding structure in face.
Background technology
In recent years, due to energy shortage, how carbon reduction turns into by the topic of extensive discussions, and the illumination of industrial premises is big It is primary illumination all to use wattage illuminating lamp high, then at thin portion collocation secondary light source, this kind of lighting system, its power consumption and illumination branch The expense for going out is considerable, therefore, market has occurred as soon as a kind of optical illumination equipment, can be by nature on daytime using this kind of equipment Light source, importing turns into primary illumination light source in factory building, reach the purpose of carbon reduction.
The utility model patent of the U of Authorization Notice No. CN 203893063 discloses a kind of factory building optical illumination equipment, including Dome skylight, LED packing rings, bucker, photoconductive tube, diffusing globe and pedestal, LED packing rings are placed in bucker top, dome skylight bottom Be locked on bucker top, and LED packing rings are folded between dome skylight and bucker, bucker be sheathed on photoconductive tube it is outer and with It is combined, and diffusing globe is fixedly arranged on light guide bottom of the tube, and photoconductive tube bottom is arranged in inside pedestal, and bucker is sheathed on outside pedestal, and Combined fixation with pedestal, and bucker being arranged angle and can arbitrarily adjust to pedestal, make the photoconductive tube combined with bucker and Dome skylight keeps vertical.
However, this kind of photoconductive tube lighting apparatus there is a problem of being also easy to produce ponding, as shown in figure 1, dome skylight 2, rainhat 3rd, photoconductive tube 9, diffusing globe 8 and pier base 4, the optical illumination equipment run through and are installed on light-steel roofing 1;The perforate position on roofing Put and pier base is fixed on roofing, then rainhat is buckled on pier base and is screwed;Photoconductive tube one end is fixed with Retainer ring, whole pipe is hung on rainhat inner circle flange by retainer ring, and lower end puts into indoor and fixed in end face through roofing There is diffusing globe;Dome skylight is buckled on rainhat, and sealing ring is provided between dome skylight and rainhat, by self threading pin by daylighting Cover is fixed on rainhat.
As seen from Figure 1, light-steel roofing 1 is generally obliquely installed, and to ensure the intensity of roofing, is set on the light-steel roofing 1 Reinforcement is equipped with, a gutter 6 is formed between two reinforcements;After pier base 4 is installed on light-steel roofing 1, gutter 6 is blocked up Plug, that is, produce pools zone 13, and long-term ponding can be penetrated under light-steel roofing 1 by the bottom of pier base 4, produce corrosion, dirty etc..
The content of the invention
The present invention is intended to provide a kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube, to solve existing light The problem of the easy ponding of guide-tube structure.
Concrete scheme is as follows:A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube, be installed on be provided with plus The light-steel roofing of strong muscle, mainly including dome skylight, rainhat, pier base, photoconductive tube, diffusing globe;Pier base is located at light-steel roofing upside, Then rainhat is arranged and is fixed on pier base, and the diffusing globe is installed on the lower end of photoconductive tube, and the upper end of the photoconductive tube is provided with admittedly It is fixed on rainhat by retainer ring after determining ring, the upper end that the dome skylight is installed on rainhat and just to the photoconductive tube sets Put;It is characterized in that:Also include drainage piece, the first end of the drainage piece form the storage tank that matches with reinforcement with Light-steel roofing fits fixation, and the second end is in planar structure, and the light-steel roofing to should the position at the end of drainage piece second be also Planar structure;On the light-steel roofing reinforcement bearing of trend from high to low, first, second end of the drainage piece fits in The light-steel roofing, and the second end of the drainage piece is connected to one week lower edge of side of the pier base, the drainage piece and light-steel roofing, All fit clearances of pier base seal setting, to cause that the current of light-steel roofing are guided to second from the first end of the drainage piece End, is then guided to the light-steel roofing of the pier base both wings by the second end.
Further, the first end of the drainage piece is fitted in above or below light-steel roofing.
Further, described light-steel roofing is made up of color steel tile laying, corresponding, and the drainage piece is the color steel of same specification Tile is made.
Further, the first end of the drainage piece is provided with fluid sealant with light-steel roofing institute overlapping region, is then connected by screw Connect, and then realize the first end palette of drainage piece in light-steel roofing.
Further, the drainage piece face that overlapped with the pier base is provided with fluid sealant, the both sides up and down at the second end of the drainage piece Face is tightly connected with the pier base and light-steel roofing respectively, is then fixed by screw, and then it is close to realize the second end of drainage piece Envelope is connected to one week lower edge of side of the pier base.
Further, the drainage piece is made up of plastics, rubber or stainless steel substrates.
The present invention by setting drainage piece, on the light-steel roofing reinforcement bearing of trend from high to low, the drainage piece It is arranged at the front side of the pier base;The first end palette of the drainage piece in light-steel roofing, the second end simultaneously with roofing and pier base Closely connection, so that the light-steel roofing is connected to the pier base by the drainage piece, one end that the drainage piece is connected with pier base is in flat Face structure, it is to avoid the problem of pools zone is formed between two reinforcements, the current on light-steel roofing pass through the planar structure water conservancy diversion To the outflow of pier base side, the easy ponding of light guide tubular construction is solved, the problems such as seepage is dirty.
Brief description of the drawings
Fig. 1 shows existing optical illumination equipment ponding principle schematic;
Fig. 2 shows the structural representation of the embodiment of the present invention one;
Fig. 3 shows Fig. 2 drainage piece structural representations;
Fig. 4 shows Fig. 2 sectional views;
Fig. 5 shows Fig. 4 partial enlarged drawings;
Fig. 6 shows the structural representation of the embodiment of the present invention two;
Fig. 7 shows Fig. 6 drainage principle schematics.
Specific embodiment
To further illustrate each embodiment, the present invention is provided with accompanying drawing.These accompanying drawings are the invention discloses one of content Point, it is mainly used to illustrate embodiment, and the associated description of specification can be coordinated to explain the operation principles of embodiment.Coordinate ginseng These contents are examined, those of ordinary skill in the art will be understood that other possible implementation methods and advantages of the present invention.In figure Component be not necessarily to scale, and similar element numbers are conventionally used to indicate similar component.
In conjunction with the drawings and specific embodiments, the present invention is further described.
Embodiment one
With reference to Fig. 2, the anti-ponding structure of roofing of the light-steel roofing construction and installation photoconductive tube of the embodiment is installed on light-steel roofing 1 On, it is parallel on the light-steel roofing 1 to be uniformly arranged reinforcement, and the light-steel roofing 1 is in dip down along the bearing of trend of reinforcement Tiltedly set.
With reference to Fig. 2 to Fig. 4, the anti-ponding structure of the roofing mainly include dome skylight 2, rainhat 3, photoconductive tube 9, diffusing globe 8, Pier base 4 and drainage piece 5.The first end of the drainage piece 5 form the storage tank that matches with the reinforcement of light-steel roofing 1 with it is light Steel roofing 1 fits fixation, and the second end is in planar structure, and the light-steel roofing 1 pair should the position at the end of drainage piece second be also Planar structure;The pier base 4 is installed on the top outside of light-steel roofing 1, and the pier base 4, light-steel roofing 1 are provided with run through logical Hole, then the photoconductive tube 9 installed through the pier base 4, light-steel roofing 1;Diffusing globe 8 is arranged on the lower end of photoconductive tube 9, on photoconductive tube End is arranged on rainhat 3 by retainer ring, and dome skylight 2 is installed on rainhat 3 and just to the upper end of the photoconductive tube 9, with complete Into light taken outdoors, the effect of room scattering;Rainhat 3 is sheathed on pier base 4 and is tightly connected with the appearance profile of pier base 4, The rainhat 3 is located between dome skylight 2 and pier base 4, and dome skylight 2 is completely covered annulus position on rainhat 3, then rear defence The outer rim of rain cap 3 is sheathed on the outer rim of the upper end of pier base 4, and is combined fixation with pier base 4,(1)Realize the fixed peace of photoconductive tube 9 Dress,(2)Flow to rainhat 3 after rain-impact dome skylight 2, and after be drained to light-steel roofing 1 through the rainhat 3.
With reference to Fig. 3, the drainage piece 5 is that, with plate-like structure, its rear and front end is respectively first end and the second end;This draws The first end of flow 5 forms several and arranged in parallel is adapted with the reinforcement profile of light-steel roofing 1 and spacing is adapted Storage tank, and then make the first end of the drainage piece 5 to fit to be fixed on light-steel roofing 1;Second end of the drainage piece 5 is in plane Structure.
With reference to Fig. 5, in the reinforcement of light-steel roofing 1 on level height bearing of trend from high to low, the drainage piece 5 First end fits in light-steel roofing 1, and the second end is connected to the lower edge and light-steel roofing 1 of one week side of the pier base 4, tool Body, the two sides up and down at the second end of the drainage piece 5 respectively with the pier base 4 and light-steel roofing 1, and be tightly connected;And Bottom surface, drainage piece 5 and the light-steel roofing 1 of pier base 4 are sequentially passed through with fixation by screw afterwards.The drainage piece 5 and light-steel roofing 1, All fit clearances of pier base 4 seal setting;The light-steel roofing 1 is connected to the pier base 4 by the drainage piece 5, light to cause The ponding of steel roofing 1 is directed at the second end from the first end of the drainage piece 5, and the light-steel roofing 1 of both wings is then guided to by the second end.
Specifically, the first end palette of the drainage piece 5 is in the bottom of light-steel roofing, the second end is sealedly attached to the pier The bottom of seat 4 and light-steel roofing 1, so that the light-steel roofing 1 is connected to the pier base 4 by the drainage piece.This kind of structure sets Put, light-steel roofing 1 is connected to pier base 4 by the drainage piece 5, bottom and the junction of drainage piece 5 of pier base 4 are equipped with fluid sealant 10, then locked and connected by self-tapping screw;Light-steel roofing 1 is covered in the first end of drainage piece 5, and is equally coated with therebetween Fluid sealant 10, then self-tapping screw lock and connect;This kind of structure makes the bottom of pier base 4 for planar structure, has separated on light-steel roofing 1 Drainage trough that adjacent two reinforcement is formed, it is to avoid the generation of pools zone.
In this embodiment, light-steel roofing 1 is made up of color steel tile laying, and light-steel roofing 1 has insulating foam-flat Plank house face 7, to play a part of to be incubated and support;Corresponding, the drainage piece 5 is the color steel tile with the same specification of light-steel roofing 1 Piece cuts and is made, and its second end extrusion-processing technology is processed as planar structure;In other specific implementations, drainage piece 5 Can also be and be made up of plastics, rubber or stainless steel substrates, be capable of achieving the embodiment technique effect.
Embodiment two
With reference to Fig. 6, the anti-ponding structure of roofing and the basic phase of embodiment one of the light-steel roofing construction and installation photoconductive tube of the embodiment Together, including dome skylight 2, rainhat 3, photoconductive tube 9, diffusing globe 8, pier base 4 and drainage piece 5.The pier base 4 is installed on light-steel roofing 1 top outside, and the pier base 4, light-steel roofing 1 are provided with the through hole for running through, then the photoconductive tube 9 runs through the light-steel roofing 1 Install.
Its main distinction is:Drainage piece 5 first end covering be installed on light-steel roofing 1 outer end upside, and drainage piece 5 with It is same using being tightly connected between light-steel roofing 1, can equally play the technique effect of drainage.
With reference to Fig. 7, drainage trough is formed on light-steel roofing 1 between two adjacent said ribs, rainwater is along drainage trough court from high to low Flowed to pier base 4;Due to the presence of drainage piece 5, rainwater flows to drainage from light-steel roofing 1 via the first end of drainage piece 5 Second end of piece 5, second end is plane, and that has broken reinforcement collects effect, makes the water can be along the bottom lateral flow of pier base 4 To the drainage trough of the both sides of pier base 4, the drainage for realizing rainwater is derived, and solves the problems, such as the easy ponding of light guide tubular construction.
Although specifically showing and describing the present invention with reference to preferred embodiment, those skilled in the art should be bright In vain, do not departing from the spirit and scope of the present invention that appended claims are limited, in the form and details can be right The present invention makes a variety of changes, and is protection scope of the present invention.

Claims (6)

1. a kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube, is installed on the light-steel roofing for being provided with reinforcement, Mainly include dome skylight, rainhat, pier base, photoconductive tube, diffusing globe;Located at light-steel roofing upside, then rainhat is arranged pier base It is fixed on pier base, the diffusing globe is installed on the lower end of photoconductive tube, the upper end of the photoconductive tube passes through to fix after being provided with retainer ring Ring is fixed on rainhat, and the upper end that the dome skylight is installed on rainhat and just to the photoconductive tube is set;It is characterized in that:Also Drainage piece is included, the first end of the drainage piece forms the storage tank matched with reinforcement and fitted admittedly with light-steel roofing Fixed, the second end is in planar structure, and the light-steel roofing to should the position at the end of drainage piece second be also planar structure;In the light steel On roofing reinforcement bearing of trend from high to low, first, second end of the drainage piece fits in the light-steel roofing, and this draws Second end of flow is connected to one week lower edge of side of the pier base, between the drainage piece and light-steel roofing, all cooperations of pier base Gap seals setting, to cause that the current of light-steel roofing are guided to the second end from the first end of the drainage piece, then by the second end It is guided to the light-steel roofing of the pier base both wings.
2. the anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube according to claim 1, it is characterised in that:Should The first end of drainage piece is fitted in above or below light-steel roofing.
3. the anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube according to claim 1, it is characterised in that:Institute The light-steel roofing stated is made up of color steel tile laying, and corresponding, the drainage piece is made up of the color steel tile piece of same specification.
4. the anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube according to claim 1, it is characterised in that:Should The first end of drainage piece is provided with fluid sealant with light-steel roofing institute overlapping region, then by mode connects for screw, and then realizes drainage piece First end palette in light-steel roofing.
5. the anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube according to claim 1, it is characterised in that:Should The drainage piece face that overlapped with the pier base is provided with fluid sealant, the two sides up and down at the second end of the drainage piece respectively with the pier base and light Steel roofing is tightly connected, and is then fixed by screw, and then realizes one week that the second end of drainage piece is sealedly attached to the pier base The lower edge of side.
6. the anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube according to claim 1, it is characterised in that:Should Drainage piece is made up of plastics, rubber or stainless steel substrates.
CN201710003495.7A 2017-01-04 2017-01-04 A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube Pending CN106760255A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710003495.7A CN106760255A (en) 2017-01-04 2017-01-04 A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710003495.7A CN106760255A (en) 2017-01-04 2017-01-04 A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube

Publications (1)

Publication Number Publication Date
CN106760255A true CN106760255A (en) 2017-05-31

Family

ID=58949355

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710003495.7A Pending CN106760255A (en) 2017-01-04 2017-01-04 A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube

Country Status (1)

Country Link
CN (1) CN106760255A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110792234A (en) * 2018-08-03 2020-02-14 光大光学股份有限公司 Ventilation lighting module

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009140724A (en) * 2007-12-06 2009-06-25 Inosho:Kk Light-collecting device and pierced-hole drilling method for roof
CN202214910U (en) * 2011-08-05 2012-05-09 精工工业建筑系统有限公司 Water-proof installation structure for fan and opening on roof
CN203893063U (en) * 2014-03-24 2014-10-22 阳昇綠能科技股份有限公司 Light guide lighting equipment for workshop
CN205804779U (en) * 2016-07-13 2016-12-14 李波 A kind of splash guard

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009140724A (en) * 2007-12-06 2009-06-25 Inosho:Kk Light-collecting device and pierced-hole drilling method for roof
CN202214910U (en) * 2011-08-05 2012-05-09 精工工业建筑系统有限公司 Water-proof installation structure for fan and opening on roof
CN203893063U (en) * 2014-03-24 2014-10-22 阳昇綠能科技股份有限公司 Light guide lighting equipment for workshop
CN205804779U (en) * 2016-07-13 2016-12-14 李波 A kind of splash guard

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110792234A (en) * 2018-08-03 2020-02-14 光大光学股份有限公司 Ventilation lighting module

Similar Documents

Publication Publication Date Title
CN206130880U (en) Light pipe daylighting system
CN205746584U (en) A kind of photoconduction daylight illuminating system
CN204163343U (en) Underground garage loses ventilating shaft
CN106760255A (en) A kind of anti-ponding structure of the roofing of light-steel roofing construction and installation photoconductive tube
CN206352370U (en) A kind of roofing pier base waterproof flow guiding structure of light-steel roofing building
CN205399941U (en) Building ventilation daylighting lighting device
CN208764857U (en) A kind of light pipe hardened system
CN207094486U (en) Based on underground pipe gallery solar illumination apparatus
CN210771905U (en) Light guide structure
CN209470130U (en) A kind of light pipe system
CN205399853U (en) Embedded roofing system structure of solar energy
CN205560629U (en) Light guide lighting device
CN209924237U (en) Interior drainage daylighting top curtain wall construction
CN203487709U (en) Aluminum tile
CN203932906U (en) A kind of new antenna mounting structure
CN205690289U (en) Large-scale interior space duct type daylight formula illuminator
CN106369544A (en) Day lighting system with light guide tube
CN202227606U (en) Ridge water baffle
CN207112632U (en) A high efficiency daylighting device for utility tunnel daylighting system
CN101200968B (en) Antiseep connector for protrudent part of roofing water supply pipe and water drain pipe
CN205480477U (en) Waterproof street lamp of LED
CN206205520U (en) A kind of public bicycles multi-function service canopy
CN204962550U (en) Solar energy easily washs street lamp
CN216644036U (en) Landscape bridge illumination waterproof structure
CN203174924U (en) Solar sunshade awning communicated with building outdoor water discharging pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication