CN106759293A - The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing - Google Patents

The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing Download PDF

Info

Publication number
CN106759293A
CN106759293A CN201710012027.6A CN201710012027A CN106759293A CN 106759293 A CN106759293 A CN 106759293A CN 201710012027 A CN201710012027 A CN 201710012027A CN 106759293 A CN106759293 A CN 106759293A
Authority
CN
China
Prior art keywords
casing
pile
pile body
high performance
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710012027.6A
Other languages
Chinese (zh)
Inventor
陈宝春
苏家战
江世好
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN201710012027.6A priority Critical patent/CN106759293A/en
Publication of CN106759293A publication Critical patent/CN106759293A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/40Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater

Abstract

The present invention relates to the bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing, pile body including being inserted vertically into deep water, the casing being made up of ultra-high performance concrete is socketed with the outside of pile body, steel reinforcement cage is provided with pile body, the upper end of casing is higher by the water surface, below riverbed mud face, pile body and casing are molded using concrete formed by integrally casting for the bottom of casing;When making construction:(1)According to the design requirement prefabricated casing of ultra-high performance concrete;(2)Casing is placed on the design attitude of pile body with mechanical hoisting, the center line of casing is overlapped with the center line of pile body;(3)The lower end of casing is sunk to by riverbed using pile sinking mode, the bottom of casing is reached below the limiting scour in designed elevation or riverbed at 2m positions;(4)Steel reinforcement cage is inserted toward casing, normal concrete is irrigated, casing is wrapped pile body.Simple structure of the present invention, effectively improves the ability of sandstone impact in the anti-river degradation of pile foundation and water, extends the service life of bridge.

Description

The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing
Technical field:
The present invention relates to the bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing.
Background technology:
Deposited reinforced concrete pile basis because bearing capacity is high, settling amount is small uniform, anti-seismic performance it is good and construct in nothing The advantages of big noise and vibration, it is widely used in the basis of bridge structure.For pile of deep water pile foundation, pile foundation is received The impact of sandstone in the anxious river degradation of flow velocity and water, easily produces the diseases such as erosion, peeling, dew muscle, reduces making for bridge Use the life-span;Therefore, in order to improve the service life of bridge, it is necessary to be socketed a casing on the outside of pile foundation to resist river punching The impact of brush and sandstone.
The content of the invention:
It is an object of the invention to provide the bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing, knot Structure is simple, easy construction, effectively improves the service life of bridge.
To achieve these goals, the technical solution adopted by the present invention is:A kind of use ultra-high performance concrete casing Bored concrete pile, including the pile body of deep water is inserted vertically into, the casing being made up of ultra-high performance concrete is socketed with the outside of the pile body, Steel reinforcement cage is provided with the pile body, the upper end of the casing is higher by the water surface, and the bottom of the casing is described below riverbed mud face Pile body and casing are molded using concrete formed by integrally casting.
Further, the internal diameter of the casing and the intended diameter of pile body are identical, and the wall thickness of casing is the 1/ of casing internal diameter 25~1/20, and not less than 2cm.
Further, the casing is made up of the splicing of multiple prefabricated subsections.
A kind of making construction method of the bored concrete pile of use ultra-high performance concrete casing, comprises the following steps:(1)It is prefabricated Pour casing:The prefabricated casing of ultra-high performance concrete is used according to design requirement;(2)Using mechanical hoisting operating type, will protect Cylinder is placed at the design attitude of pile body, and the center line of casing is coincided with the center line of pile body;(3)Using pile sinking mode The lower end of casing is sunk in riverbed, until the bottom of casing is reached 2m below the limiting scour in designed elevation or riverbed Put place;(4)Steel reinforcement cage is inserted toward casing, and irrigates normal concrete, casing is wrapped pile body and be integrally formed.
Compared with prior art, the present invention has the following effects that:Simple structure of the present invention, easy construction, using by superelevation The casing that performance concrete is made, can save huge steel consumption, reduce construction costs;Casing is used as the permanent of free removal Template so that the overall mechanical property of bored concrete pile is good, improves the ability of sandstone impact in the anti-river degradation of bored concrete pile pile foundation and water, Extend the service life of bridge.
Brief description of the drawings:
Fig. 1 is the organigram of the embodiment of the present invention;
Fig. 2 is A-A cross section views in Fig. 1.
In figure:
1- casings;2- pile bodies;3- steel reinforcement cages;4- normal concretes.
Specific embodiment:
The present invention will be further described in detail with reference to the accompanying drawings and detailed description.
As shown in Figure 1-2, the bored concrete pile of a kind of use ultra-high performance concrete casing of the invention, including it is inserted vertically into deep water Pile body 2, the outside of the pile body 2 is socketed with the casing 1 being made up of ultra-high performance concrete, reinforcing bar is provided with the pile body 2 Cage 3, the upper end of the casing 1 is higher by the water surface, and below riverbed mud face, the pile body 2 and casing 1 are adopted for the bottom of the casing 1 It is molded with concrete formed by integrally casting.
In the present embodiment, the ultra-high performance concrete refers to fine sand as aggregate, is with cement and active mineral admixture Binder Materials, and efficient additive and high intensity micro steel fiber are added, with high intensity, high solidity, high-durability and height The concrete material of toughness.
In the present embodiment, the internal diameter of the casing 1 is identical with the intended diameter of pile body 2, can be 1.5m, 1.8m and 2.2m tri- Type.
In the present embodiment, the wall thickness of the casing 1 is the 1/25~1/20 of casing internal diameter, and not less than 2cm, can for 6cm, 8cm and 10cm.
In the present embodiment, the casing 1 is made up of the splicing of multiple prefabricated subsections, and the two ends of each prefabricated subsection are provided with Splicing steel joint, welds together between prefabricated subsection.
In the present embodiment, the madial wall of casing 1 can also vertically arranged some reinforcing bars, further to improve pile body and casing Intensity.
In the present embodiment, using the casing being made up of ultra-high performance concrete, the anti-river punching of bored concrete pile pile foundation is effectively improved The ability of sandstone impact, improves the quality and durability of pile foundation in brush and water, extends the service life of bridge, saves grout pile The maintenance cost of base, there is good social and economic benefit, with future in engineering applications widely.
A kind of making construction method of the bored concrete pile of use ultra-high performance concrete casing of the present invention, comprises the following steps: (1)It is prefabricated to pour casing:The prefabricated casing of ultra-high performance concrete is used according to design requirement;(2)Using mechanical hoisting operator Formula, casing is placed at the design attitude of pile body, and the center line of casing is coincided with the center line of pile body;(3)Using Pile sinking mode sinks in riverbed the lower end of casing, until the bottom of casing reaches the limiting scour in designed elevation or riverbed At following 2m positions;(4)Steel reinforcement cage is inserted toward casing, and irrigates normal concrete, casing is wrapped pile body and be integrally formed.
The foregoing is only presently preferred embodiments of the present invention, all impartial changes done according to scope of the present invention patent with Modification, should all belong to covering scope of the invention.

Claims (4)

1. a kind of bored concrete pile of use ultra-high performance concrete casing, it is characterised in that:Pile body including being inserted vertically into deep water, institute The casing for being socketed with the outside of pile body and being made up of ultra-high performance concrete is stated, steel reinforcement cage is provided with the pile body, the casing Upper end is higher by the water surface, the bottom of the casing below riverbed mud face, the pile body and casing using concrete formed by integrally casting into Type.
2. the bored concrete pile of a kind of use ultra-high performance concrete casing according to claim 1, it is characterised in that:The shield The internal diameter of cylinder is identical with the intended diameter of pile body, and the wall thickness of casing is the 1/25~1/20 of casing internal diameter, and not less than 2cm.
3. the bored concrete pile of a kind of use ultra-high performance concrete casing according to claim 2, it is characterised in that:The shield Cylinder is made up of the splicing of multiple prefabricated subsections.
4. a kind of making construction method of the bored concrete pile of use ultra-high performance concrete casing, it is characterised in that:Using such as right It is required that a kind of bored concrete pile of the use ultra-high performance concrete casing described in 3, comprises the following steps:(1)It is prefabricated to pour casing:Root The prefabricated casing of ultra-high performance concrete is used according to design requirement;(2)Using mechanical hoisting operating type, casing is placed on pile body Design attitude at, and the center line of casing is coincided with the center line of pile body;(3)Using pile sinking mode by the lower end of casing Sink in riverbed, until the bottom of casing is reached below the limiting scour in designed elevation or riverbed at 2m positions;(4)Toward shield Steel reinforcement cage is inserted in cylinder, and irrigates normal concrete, casing is wrapped pile body and be integrally formed.
CN201710012027.6A 2017-01-09 2017-01-09 The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing Pending CN106759293A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710012027.6A CN106759293A (en) 2017-01-09 2017-01-09 The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710012027.6A CN106759293A (en) 2017-01-09 2017-01-09 The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing

Publications (1)

Publication Number Publication Date
CN106759293A true CN106759293A (en) 2017-05-31

Family

ID=58950248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710012027.6A Pending CN106759293A (en) 2017-01-09 2017-01-09 The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing

Country Status (1)

Country Link
CN (1) CN106759293A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108482582A (en) * 2018-06-13 2018-09-04 福州大学 Using the buoy and its making construction method of ultra-high performance concrete
CN109868805A (en) * 2019-02-28 2019-06-11 天津大学 Steel pile casting formula heavy-tamping method underwater reinforced construction method
CN110622823A (en) * 2019-09-20 2019-12-31 中国科学院东北地理与农业生态研究所 Construction method of substrate for recovering reed clumps in constructed wetland deep water area
CN114227900A (en) * 2021-12-20 2022-03-25 河南五建第二建筑安装有限公司 Prefabricating method of reinforcement cage for long spiral drilling pressure-grouting pile

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102423A (en) * 2011-03-09 2011-06-22 湖南大学 Sleeve reinforced concrete column
CN102776985A (en) * 2012-07-13 2012-11-14 湖南大学 Composite casing pipe restrained reinforced concrete column
CN103964778A (en) * 2014-04-29 2014-08-06 中交第二航务工程局有限公司 Preparation method for novel ultrahigh-performance concrete pile casing used in pile foundation project
CN105442590A (en) * 2015-12-28 2016-03-30 湖南大学 Reactive powder concrete pipe column for ocean engineering
CN106013611A (en) * 2016-07-05 2016-10-12 湖南大学 Ocean engineering composite column

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102423A (en) * 2011-03-09 2011-06-22 湖南大学 Sleeve reinforced concrete column
CN102776985A (en) * 2012-07-13 2012-11-14 湖南大学 Composite casing pipe restrained reinforced concrete column
CN103964778A (en) * 2014-04-29 2014-08-06 中交第二航务工程局有限公司 Preparation method for novel ultrahigh-performance concrete pile casing used in pile foundation project
CN105442590A (en) * 2015-12-28 2016-03-30 湖南大学 Reactive powder concrete pipe column for ocean engineering
CN106013611A (en) * 2016-07-05 2016-10-12 湖南大学 Ocean engineering composite column

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108482582A (en) * 2018-06-13 2018-09-04 福州大学 Using the buoy and its making construction method of ultra-high performance concrete
CN109868805A (en) * 2019-02-28 2019-06-11 天津大学 Steel pile casting formula heavy-tamping method underwater reinforced construction method
CN110622823A (en) * 2019-09-20 2019-12-31 中国科学院东北地理与农业生态研究所 Construction method of substrate for recovering reed clumps in constructed wetland deep water area
CN114227900A (en) * 2021-12-20 2022-03-25 河南五建第二建筑安装有限公司 Prefabricating method of reinforcement cage for long spiral drilling pressure-grouting pile

Similar Documents

Publication Publication Date Title
CN106759293A (en) The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing
CN105041336B (en) A kind of very-high performance hybrid fiber concrete shield duct piece and preparation method thereof
CN101806096B (en) Steel tube-concrete composite structure
CN107447646B (en) Preparation method of steel-continuous fiber composite bar ECC-concrete composite column/pier
CN202519664U (en) High tensile reinforcement reinforced prestressed UHPC (Ultra High Performance Concrete) thin-wall tubular pile component
CN102587578A (en) High-strength steel bar enhanced engineered cementitious composites (ECC)-hollow steel pipe ultra high performance concrete (UHPC) combination column member and manufacturing method thereof
CN204325919U (en) A kind of bridge deck pavement structure
CN207260440U (en) A kind of FRP pipes seawater sea sand regenerates self-compacting concrete environment protection architecture component
CN104878875B (en) A kind of FRP muscle ultra-high performance concrete cover plate and preparation method thereof
CN106907016A (en) The lossless ruggedized construction and its construction method of historical protective buildings wall
CN204266439U (en) Based on the novel compositions girder construction of steel-ultra-high performance concrete
CN104762961B (en) A kind of ultra-high performance concrete and ordinary concrete compound pile and construction method thereof
CN111975934A (en) Prefabricated ultrahigh-performance concrete guard plate and preparation method thereof
CN108824696A (en) A kind of FRP tendons seawater sea sand-UHDCC composite beam and its construction method
CN107882271A (en) A kind of marine sand concrete superposed column using UHPC outsourcings
KR101566131B1 (en) Fiber reinforced concrete dam
CN207405875U (en) A kind of non-adhesive superhigh tenacity cement-base composite material functionally gradient beam
CN105781016A (en) Cement-based composite and steel pipe combined compound column and manufacturing method thereof
CN106760205A (en) A kind of high strength steel pipe constraint post using cementing microorganism cement
CN106677552A (en) Method for solidifying steel pipe column through external sleeveing of circular steel pipe concrete
CN106759512A (en) For municipal administration and the ultra-high performance concrete well lid and manufacture craft of power engineering
CN215210490U (en) Tenon-and-mortise combined type ultra-high performance concrete permanent formwork
CN205348170U (en) In dig method prestressed concrete pipe pile
CN205088677U (en) Low hollow side of prestressed concrete stake of high performance
CN205348103U (en) Gabion and river course revetment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531