CN106759293A - The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing - Google Patents
The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing Download PDFInfo
- Publication number
- CN106759293A CN106759293A CN201710012027.6A CN201710012027A CN106759293A CN 106759293 A CN106759293 A CN 106759293A CN 201710012027 A CN201710012027 A CN 201710012027A CN 106759293 A CN106759293 A CN 106759293A
- Authority
- CN
- China
- Prior art keywords
- casing
- pile
- pile body
- high performance
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/40—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/665—Mould-pipes or other moulds for making piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0061—Production methods for working underwater
Abstract
The present invention relates to the bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing, pile body including being inserted vertically into deep water, the casing being made up of ultra-high performance concrete is socketed with the outside of pile body, steel reinforcement cage is provided with pile body, the upper end of casing is higher by the water surface, below riverbed mud face, pile body and casing are molded using concrete formed by integrally casting for the bottom of casing;When making construction:(1)According to the design requirement prefabricated casing of ultra-high performance concrete;(2)Casing is placed on the design attitude of pile body with mechanical hoisting, the center line of casing is overlapped with the center line of pile body;(3)The lower end of casing is sunk to by riverbed using pile sinking mode, the bottom of casing is reached below the limiting scour in designed elevation or riverbed at 2m positions;(4)Steel reinforcement cage is inserted toward casing, normal concrete is irrigated, casing is wrapped pile body.Simple structure of the present invention, effectively improves the ability of sandstone impact in the anti-river degradation of pile foundation and water, extends the service life of bridge.
Description
Technical field:
The present invention relates to the bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing.
Background technology:
Deposited reinforced concrete pile basis because bearing capacity is high, settling amount is small uniform, anti-seismic performance it is good and construct in nothing
The advantages of big noise and vibration, it is widely used in the basis of bridge structure.For pile of deep water pile foundation, pile foundation is received
The impact of sandstone in the anxious river degradation of flow velocity and water, easily produces the diseases such as erosion, peeling, dew muscle, reduces making for bridge
Use the life-span;Therefore, in order to improve the service life of bridge, it is necessary to be socketed a casing on the outside of pile foundation to resist river punching
The impact of brush and sandstone.
The content of the invention:
It is an object of the invention to provide the bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing, knot
Structure is simple, easy construction, effectively improves the service life of bridge.
To achieve these goals, the technical solution adopted by the present invention is:A kind of use ultra-high performance concrete casing
Bored concrete pile, including the pile body of deep water is inserted vertically into, the casing being made up of ultra-high performance concrete is socketed with the outside of the pile body,
Steel reinforcement cage is provided with the pile body, the upper end of the casing is higher by the water surface, and the bottom of the casing is described below riverbed mud face
Pile body and casing are molded using concrete formed by integrally casting.
Further, the internal diameter of the casing and the intended diameter of pile body are identical, and the wall thickness of casing is the 1/ of casing internal diameter
25~1/20, and not less than 2cm.
Further, the casing is made up of the splicing of multiple prefabricated subsections.
A kind of making construction method of the bored concrete pile of use ultra-high performance concrete casing, comprises the following steps:(1)It is prefabricated
Pour casing:The prefabricated casing of ultra-high performance concrete is used according to design requirement;(2)Using mechanical hoisting operating type, will protect
Cylinder is placed at the design attitude of pile body, and the center line of casing is coincided with the center line of pile body;(3)Using pile sinking mode
The lower end of casing is sunk in riverbed, until the bottom of casing is reached 2m below the limiting scour in designed elevation or riverbed
Put place;(4)Steel reinforcement cage is inserted toward casing, and irrigates normal concrete, casing is wrapped pile body and be integrally formed.
Compared with prior art, the present invention has the following effects that:Simple structure of the present invention, easy construction, using by superelevation
The casing that performance concrete is made, can save huge steel consumption, reduce construction costs;Casing is used as the permanent of free removal
Template so that the overall mechanical property of bored concrete pile is good, improves the ability of sandstone impact in the anti-river degradation of bored concrete pile pile foundation and water,
Extend the service life of bridge.
Brief description of the drawings:
Fig. 1 is the organigram of the embodiment of the present invention;
Fig. 2 is A-A cross section views in Fig. 1.
In figure:
1- casings;2- pile bodies;3- steel reinforcement cages;4- normal concretes.
Specific embodiment:
The present invention will be further described in detail with reference to the accompanying drawings and detailed description.
As shown in Figure 1-2, the bored concrete pile of a kind of use ultra-high performance concrete casing of the invention, including it is inserted vertically into deep water
Pile body 2, the outside of the pile body 2 is socketed with the casing 1 being made up of ultra-high performance concrete, reinforcing bar is provided with the pile body 2
Cage 3, the upper end of the casing 1 is higher by the water surface, and below riverbed mud face, the pile body 2 and casing 1 are adopted for the bottom of the casing 1
It is molded with concrete formed by integrally casting.
In the present embodiment, the ultra-high performance concrete refers to fine sand as aggregate, is with cement and active mineral admixture
Binder Materials, and efficient additive and high intensity micro steel fiber are added, with high intensity, high solidity, high-durability and height
The concrete material of toughness.
In the present embodiment, the internal diameter of the casing 1 is identical with the intended diameter of pile body 2, can be 1.5m, 1.8m and 2.2m tri-
Type.
In the present embodiment, the wall thickness of the casing 1 is the 1/25~1/20 of casing internal diameter, and not less than 2cm, can for 6cm,
8cm and 10cm.
In the present embodiment, the casing 1 is made up of the splicing of multiple prefabricated subsections, and the two ends of each prefabricated subsection are provided with
Splicing steel joint, welds together between prefabricated subsection.
In the present embodiment, the madial wall of casing 1 can also vertically arranged some reinforcing bars, further to improve pile body and casing
Intensity.
In the present embodiment, using the casing being made up of ultra-high performance concrete, the anti-river punching of bored concrete pile pile foundation is effectively improved
The ability of sandstone impact, improves the quality and durability of pile foundation in brush and water, extends the service life of bridge, saves grout pile
The maintenance cost of base, there is good social and economic benefit, with future in engineering applications widely.
A kind of making construction method of the bored concrete pile of use ultra-high performance concrete casing of the present invention, comprises the following steps:
(1)It is prefabricated to pour casing:The prefabricated casing of ultra-high performance concrete is used according to design requirement;(2)Using mechanical hoisting operator
Formula, casing is placed at the design attitude of pile body, and the center line of casing is coincided with the center line of pile body;(3)Using
Pile sinking mode sinks in riverbed the lower end of casing, until the bottom of casing reaches the limiting scour in designed elevation or riverbed
At following 2m positions;(4)Steel reinforcement cage is inserted toward casing, and irrigates normal concrete, casing is wrapped pile body and be integrally formed.
The foregoing is only presently preferred embodiments of the present invention, all impartial changes done according to scope of the present invention patent with
Modification, should all belong to covering scope of the invention.
Claims (4)
1. a kind of bored concrete pile of use ultra-high performance concrete casing, it is characterised in that:Pile body including being inserted vertically into deep water, institute
The casing for being socketed with the outside of pile body and being made up of ultra-high performance concrete is stated, steel reinforcement cage is provided with the pile body, the casing
Upper end is higher by the water surface, the bottom of the casing below riverbed mud face, the pile body and casing using concrete formed by integrally casting into
Type.
2. the bored concrete pile of a kind of use ultra-high performance concrete casing according to claim 1, it is characterised in that:The shield
The internal diameter of cylinder is identical with the intended diameter of pile body, and the wall thickness of casing is the 1/25~1/20 of casing internal diameter, and not less than 2cm.
3. the bored concrete pile of a kind of use ultra-high performance concrete casing according to claim 2, it is characterised in that:The shield
Cylinder is made up of the splicing of multiple prefabricated subsections.
4. a kind of making construction method of the bored concrete pile of use ultra-high performance concrete casing, it is characterised in that:Using such as right
It is required that a kind of bored concrete pile of the use ultra-high performance concrete casing described in 3, comprises the following steps:(1)It is prefabricated to pour casing:Root
The prefabricated casing of ultra-high performance concrete is used according to design requirement;(2)Using mechanical hoisting operating type, casing is placed on pile body
Design attitude at, and the center line of casing is coincided with the center line of pile body;(3)Using pile sinking mode by the lower end of casing
Sink in riverbed, until the bottom of casing is reached below the limiting scour in designed elevation or riverbed at 2m positions;(4)Toward shield
Steel reinforcement cage is inserted in cylinder, and irrigates normal concrete, casing is wrapped pile body and be integrally formed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710012027.6A CN106759293A (en) | 2017-01-09 | 2017-01-09 | The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710012027.6A CN106759293A (en) | 2017-01-09 | 2017-01-09 | The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106759293A true CN106759293A (en) | 2017-05-31 |
Family
ID=58950248
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710012027.6A Pending CN106759293A (en) | 2017-01-09 | 2017-01-09 | The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106759293A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108482582A (en) * | 2018-06-13 | 2018-09-04 | 福州大学 | Using the buoy and its making construction method of ultra-high performance concrete |
CN109868805A (en) * | 2019-02-28 | 2019-06-11 | 天津大学 | Steel pile casting formula heavy-tamping method underwater reinforced construction method |
CN110622823A (en) * | 2019-09-20 | 2019-12-31 | 中国科学院东北地理与农业生态研究所 | Construction method of substrate for recovering reed clumps in constructed wetland deep water area |
CN114227900A (en) * | 2021-12-20 | 2022-03-25 | 河南五建第二建筑安装有限公司 | Prefabricating method of reinforcement cage for long spiral drilling pressure-grouting pile |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102102423A (en) * | 2011-03-09 | 2011-06-22 | 湖南大学 | Sleeve reinforced concrete column |
CN102776985A (en) * | 2012-07-13 | 2012-11-14 | 湖南大学 | Composite casing pipe restrained reinforced concrete column |
CN103964778A (en) * | 2014-04-29 | 2014-08-06 | 中交第二航务工程局有限公司 | Preparation method for novel ultrahigh-performance concrete pile casing used in pile foundation project |
CN105442590A (en) * | 2015-12-28 | 2016-03-30 | 湖南大学 | Reactive powder concrete pipe column for ocean engineering |
CN106013611A (en) * | 2016-07-05 | 2016-10-12 | 湖南大学 | Ocean engineering composite column |
-
2017
- 2017-01-09 CN CN201710012027.6A patent/CN106759293A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102102423A (en) * | 2011-03-09 | 2011-06-22 | 湖南大学 | Sleeve reinforced concrete column |
CN102776985A (en) * | 2012-07-13 | 2012-11-14 | 湖南大学 | Composite casing pipe restrained reinforced concrete column |
CN103964778A (en) * | 2014-04-29 | 2014-08-06 | 中交第二航务工程局有限公司 | Preparation method for novel ultrahigh-performance concrete pile casing used in pile foundation project |
CN105442590A (en) * | 2015-12-28 | 2016-03-30 | 湖南大学 | Reactive powder concrete pipe column for ocean engineering |
CN106013611A (en) * | 2016-07-05 | 2016-10-12 | 湖南大学 | Ocean engineering composite column |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108482582A (en) * | 2018-06-13 | 2018-09-04 | 福州大学 | Using the buoy and its making construction method of ultra-high performance concrete |
CN109868805A (en) * | 2019-02-28 | 2019-06-11 | 天津大学 | Steel pile casting formula heavy-tamping method underwater reinforced construction method |
CN110622823A (en) * | 2019-09-20 | 2019-12-31 | 中国科学院东北地理与农业生态研究所 | Construction method of substrate for recovering reed clumps in constructed wetland deep water area |
CN114227900A (en) * | 2021-12-20 | 2022-03-25 | 河南五建第二建筑安装有限公司 | Prefabricating method of reinforcement cage for long spiral drilling pressure-grouting pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106759293A (en) | The bored concrete pile and its making construction method of a kind of use ultra-high performance concrete casing | |
CN105041336B (en) | A kind of very-high performance hybrid fiber concrete shield duct piece and preparation method thereof | |
CN101806096B (en) | Steel tube-concrete composite structure | |
CN107447646B (en) | Preparation method of steel-continuous fiber composite bar ECC-concrete composite column/pier | |
CN202519664U (en) | High tensile reinforcement reinforced prestressed UHPC (Ultra High Performance Concrete) thin-wall tubular pile component | |
CN102587578A (en) | High-strength steel bar enhanced engineered cementitious composites (ECC)-hollow steel pipe ultra high performance concrete (UHPC) combination column member and manufacturing method thereof | |
CN204325919U (en) | A kind of bridge deck pavement structure | |
CN207260440U (en) | A kind of FRP pipes seawater sea sand regenerates self-compacting concrete environment protection architecture component | |
CN104878875B (en) | A kind of FRP muscle ultra-high performance concrete cover plate and preparation method thereof | |
CN106907016A (en) | The lossless ruggedized construction and its construction method of historical protective buildings wall | |
CN204266439U (en) | Based on the novel compositions girder construction of steel-ultra-high performance concrete | |
CN104762961B (en) | A kind of ultra-high performance concrete and ordinary concrete compound pile and construction method thereof | |
CN111975934A (en) | Prefabricated ultrahigh-performance concrete guard plate and preparation method thereof | |
CN108824696A (en) | A kind of FRP tendons seawater sea sand-UHDCC composite beam and its construction method | |
CN107882271A (en) | A kind of marine sand concrete superposed column using UHPC outsourcings | |
KR101566131B1 (en) | Fiber reinforced concrete dam | |
CN207405875U (en) | A kind of non-adhesive superhigh tenacity cement-base composite material functionally gradient beam | |
CN105781016A (en) | Cement-based composite and steel pipe combined compound column and manufacturing method thereof | |
CN106760205A (en) | A kind of high strength steel pipe constraint post using cementing microorganism cement | |
CN106677552A (en) | Method for solidifying steel pipe column through external sleeveing of circular steel pipe concrete | |
CN106759512A (en) | For municipal administration and the ultra-high performance concrete well lid and manufacture craft of power engineering | |
CN215210490U (en) | Tenon-and-mortise combined type ultra-high performance concrete permanent formwork | |
CN205348170U (en) | In dig method prestressed concrete pipe pile | |
CN205088677U (en) | Low hollow side of prestressed concrete stake of high performance | |
CN205348103U (en) | Gabion and river course revetment structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170531 |