CN106741068B - A kind of new energy fuel storage bin - Google Patents

A kind of new energy fuel storage bin Download PDF

Info

Publication number
CN106741068B
CN106741068B CN201611026747.XA CN201611026747A CN106741068B CN 106741068 B CN106741068 B CN 106741068B CN 201611026747 A CN201611026747 A CN 201611026747A CN 106741068 B CN106741068 B CN 106741068B
Authority
CN
China
Prior art keywords
sliding rail
new energy
cart
storing box
material storing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611026747.XA
Other languages
Chinese (zh)
Other versions
CN106741068A (en
Inventor
阮茶英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jingwang New Energy Technology Co.,Ltd.
Original Assignee
Taizhou Taijie Chemical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taizhou Taijie Chemical Technology Co Ltd filed Critical Taizhou Taijie Chemical Technology Co Ltd
Priority to CN201611026747.XA priority Critical patent/CN106741068B/en
Publication of CN106741068A publication Critical patent/CN106741068A/en
Application granted granted Critical
Publication of CN106741068B publication Critical patent/CN106741068B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B62LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
    • B62BHAND-PROPELLED VEHICLES, e.g. HAND CARTS OR PERAMBULATORS; SLEDGES
    • B62B3/00Hand carts having more than one axis carrying transport wheels; Steering devices therefor; Equipment therefor
    • B62B3/04Hand carts having more than one axis carrying transport wheels; Steering devices therefor; Equipment therefor involving means for grappling or securing in place objects to be carried; Loading or unloading equipment

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Handcart (AREA)

Abstract

The present invention relates to a kind of storage bin more particularly to a kind of new energy fuel storage bins.The technical problem to be solved in the present invention is to provide one kind of multiple functions, low energy consumption and new energy fuel storage bin easy to use.In order to solve the above-mentioned technical problem, the present invention provides such a new energy fuel storage bins, include cart, the first sliding rail, the first rack gear, connecting rod, the second rack gear, the second sliding rail, support rod, pedal, guide sleeve, connecting rod, the second sliding block, supporting plate etc.;Cart right wall is provided with the second discharge port, and cart bottom left end is connected with guide sleeve by welding, and left and right side is connected with support rod by welding in cart bottom, is provided with first through hole on the support rod of left.Invention achieves the effects of fast storage new energy, while this storage bin can carry new energy when storing new energy, and in the handling process without using electric power.

Description

A kind of new energy fuel storage bin
Technical field
The present invention relates to a kind of storage bin more particularly to a kind of new energy fuel storage bins.
Background technique
While global energy anxiety, energy prices constantly rise, and various non-renewable energy resources more use is fewer.Make the energy There is a serious shortage in the supply.For the problem that such demand, tapping a new source of energy becomes primary solution now, while the exploitation of new energy is adjoint Want new storage bin, new storage bin is used to store new energy, and various new energy will have various new storage bins, so as to more preferable Storage new energy.Some new energy continue to use existing storage bin, are as a result easy to cause the leakage of new energy, to cause Air pollution.The new storage bin of some designs stores new energy, however this storage bin only one storage function, cannot Realize multifunction.
Existing new energy storage bin haves the shortcomings that have a single function, high energy consumption and inconvenient to use, therefore needs to design One kind of multiple functions, low energy consumption and new energy fuel storage bin easy to use.
Summary of the invention
(1) technical problems to be solved
The present invention has a single function, high energy consumption and inconvenient to use lacks to overcome present new energy storage bin to exist Point, the technical problem to be solved in the present invention is to provide one kind of multiple functions, low energy consumption and new energy fuel easy to use storage Case.
(2) technical solution
In order to solve the above-mentioned technical problems, the present invention provides such a new energy fuel storage bins, include to push away Vehicle, the first sliding rail, the first rack gear, connecting rod, the second rack gear, the second sliding rail, support rod, pedal, guide sleeve, connecting rod, second are slided Block, supporting plate, the second push rod, the first push rod, push plate, material storing box, framework, valve, discharge nozzle, the first sliding block, gear, handle and lid Son;Handle is connected in cart right wall by welding, cart right wall is provided with the second discharge port, and cart bottom left end passes through The mode of welding is connected with guide sleeve, and left and right side is connected with support rod, left by welding in cart bottom Support rod on be provided with first through hole, support bar top is connected with framework, framework right wall and cart by bolted connection Inner right wall contacts, and is provided with the first discharge port in the right wall of framework, the first discharge port and the second discharge outlet are in same horizontal line, frame The second through-hole is provided in the left wall of body, the top left side of framework is provided with feed inlet, and the bottom center of framework is provided with card slot, card slot bottom Portion's left and right side is provided with third through-hole, and bottom is placed with material storing box in framework, passes through flanged joint below storing right wall of box Mode be connected with discharge nozzle, discharge nozzle is equipped with valve, be connected with the first push rod by welding in material storing box left wall, First push rod passes through the second through-hole, and the first push rod left end is connected with push plate by welding, passes through spiral shell at the top of material storing box The mode of line connection is connected with lid, and bottom is bolted in the cart between the support rod of left and the support rod of right Mode be connected with the first sliding rail and the second sliding rail, the first sliding rail is located at the right of the second sliding rail, and supporting plate is placed on the first sliding rail With the top of the second sliding rail, supporting plate top left side and right side are connected with the second push rod by welding, and the second push rod passes through Third through-hole, slidingtype is connected with the first sliding block, the first sliding block and the cooperation of the first sliding rail on the first sliding rail, on the left of the first sliding block Be connected with the first rack gear by bolted connection, slidingtype is connected with the second sliding block on the second sliding rail, the second sliding block and The cooperation of second sliding rail, the second sliding block right side are connected with the second rack gear by bolted connection, pass through weldering on front side of the second sliding block The mode connect is connected with connecting rod, and connecting rod sequentially passes through first through hole and guide sleeve, and connecting rod left wall bottom end connects by welding It is connected to pedal, gear is welded on bottom in cart by connecting rod, and gear is rotatable, and connecting rod is located at the first sliding rail and second and slides Between rail, the first rack gear and the second rack gear are engaged with gear respectively.
It preferably, further include having the first rubber pad and the second rubber pad, the periphery of push plate is connected with by way of bonding First rubber pad, card slot bottom are connected with the second rubber pad by way of bonding.
Preferably, further include having friction protrusion, be connected with friction protrusion by way of bonding at the top of pedal.
Preferably, the material of support rod is Q235 steel.
Preferably, the material of the first push rod and the second push rod is Q235 steel.
Working principle: when new energy is stored into material storing box, and carries new energy, worker passes through handle and cart Material storing box is pushed to the place of production new energy, at this moment worker pulls push plate to the left, and push plate drives storing by the first push rod Case is moved to the left.When material storing box is moved to left end, worker opens lid, and worker can be put into new energy in material storing box, When material storing box places full new energy, worker screws a lid on, and closes material storing box, and at this moment worker pushes to the right push plate, and push plate is logical Crossing the first push rod drives material storing box to move right.When worker is clearly felt that material storing box is stuck in card slot, worker can pass through handle Hand push moves cart, so that the material storing box for filling new energy be driven to reach the place that use new energy.When cart arrival will use When the place of new energy, worker steps on downwards pedal with foot, and pedal drives the second rack gear to move down by connecting rod, the second rack gear Band moving gear rotates counterclockwise, and gear drives the first rack gear to move up, and the first rack gear will push supporting plate to move up.Branch strip Dynamic second push rod pushes the material storing box in card slot to move up, and at this moment the hand of worker will push to the right push plate, and push plate passes through first Push rod will push material storing box to move right.When material storing box is pushed to right end, the discharge nozzle and valve of material storing box pass through One discharge port and the second discharge port, at this moment, worker open valve, and new energy will be flowed out from discharge nozzle, at this time can be new energy Put into place to be used.When the new energy in material storing box is discharged by discharge nozzle to be completed, worker shuts valve, and worker pulls Push plate is moved to the left, and push plate will drive material storing box to be moved to the left, and when material storing box reaches card slot, material storing box will press the second push rod It moves down, the second push rod drives supporting plate, the first rack gear, gear and the second rack gear to move down reset.It is new when to carry again When the energy, worker steps on downwards pedal with foot, and final second push rod will push material storing box to move up, and at this moment worker pulls with hand Push plate is moved to the left, and when material storing box is moved to left end, can load onto new energy to material storing box at this time.
Because further including having the first rubber pad and the second rubber pad, the periphery of push plate is connected with first by way of bonding Rubber pad, card slot bottom are connected with the second rubber pad by way of bonding, so when worker pushes push plate, the first rubber pad The frictional force between worker and push plate will be increased, worker is made to be easier to push material storing box, the second rubber pad will make the second push rod and Material storing box mediate contact to protect the bottom of material storing box, and then extends the service life of material storing box.
Because further including having friction protrusion, friction protrusion is connected with by way of bonding at the top of pedal.So working as worker When with foot pedal, friction protrusion will increase the coefficient of friction of worker's sole and pedal, make foot be not easy to skid, to be more easier Pushes pedals, at the same it is more laborsaving.
(3) beneficial effect
Invention achieves the effects of fast storage new energy, while this storage bin can be carried when storing new energy New energy, and used when having reached low energy consumption and free of contamination purpose, and having carried without using electric power in the handling process Worker also just one, human resources are greatly saved.
Detailed description of the invention
Fig. 1 is the first schematic view of the front view of the invention.
Fig. 2 is the overlooking structure diagram of material storing box of the invention.
Fig. 3 is second of schematic view of the front view of the invention.
Fig. 4 is the third schematic view of the front view of the invention.
The label in accompanying drawing is: 1- cart, the first sliding rail of 2-, the first rack gear of 3-, 4- connecting rod, the second rack gear of 5-, 6- Two sliding rails, 7- support rod, 8- pedal, 9- guide sleeve, 10- connecting rod, 11- first through hole, the second sliding block of 12-, 13- supporting plate, 14- Two push rods, the second through-hole of 15-, the first push rod of 16-, 17- push plate, 18- feed inlet, 19- material storing box, 20- framework, 21- valve, 22- discharge nozzle, 23- third through-hole, 24- card slot, the first discharge port of 25-, the second discharge port of 26-, the first sliding block of 27-, 28- tooth Wheel, 29- handle, 30- lid, the first rubber pad of 31-, the second rubber pad of 32-, 33- friction protrusion.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
A kind of new energy fuel storage bin includes as shown in Figs 1-4 cart 1, the first sliding rail 2, the first rack gear 3, connection Bar 4, the second rack gear 5, the second sliding rail 6, support rod 7, pedal 8, guide sleeve 9, connecting rod 10, the second sliding block 12, supporting plate 13, second push away Bar 14, the first push rod 16, push plate 17, material storing box 19, framework 20, valve 21, discharge nozzle 22, the first sliding block 27, gear 28, handle 29 and lid 30;Handle 29 is connected in 1 right wall of cart by welding, 1 right wall of cart is provided with the second discharge port 26, pushes away 1 bottom left end of vehicle is connected with guide sleeve 9 by welding, and left and right side is by welding in 1 bottom of cart It is connected with support rod 7, first through hole 11 is provided on the support rod 7 of left, 7 top of support rod connects by bolted connection There are framework 20,20 right wall of framework and the contact of 1 inner right wall of cart, the first discharge port 25, the first discharging are provided in the right wall of framework 20 Mouth 25 and the second discharge port 26 are in same horizontal line, and the second through-hole 15, the top left of framework 20 are provided in the left wall of framework 20 Side is provided with feed inlet 18, and the bottom center of framework 20 is provided with card slot 24, and 24 bottom left of card slot and right side are provided with third through-hole 23, bottom is placed with material storing box 19 in framework 20, and discharge nozzle is connected with by way of flanged joint below 19 right wall of material storing box 22, discharge nozzle 22 is equipped with valve 21, is connected with the first push rod 16, the first push rod by welding in 19 left wall of material storing box 16 pass through the second through-hole, and 16 left end of the first push rod is connected with push plate 17 by welding, and the top of material storing box 19 passes through spiral shell The mode of line connection is connected with lid 30, and bottom passes through spiral shell in the cart 1 between the support rod 7 of left and the support rod 7 of right It tethers the mode connect and is connected with the first sliding rail 2 and the second sliding rail 6, the first sliding rail 2 is located at the right of the second sliding rail 6, and supporting plate 13 is put It sets at the top of the first sliding rail 2 and the second sliding rail 6,13 top left side of supporting plate and right side are connected with second by welding and push away Bar 14, the second push rod 14 pass through third through-hole 23, and slidingtype is connected with the first sliding block 27, the first sliding block 27 on the first sliding rail 2 Cooperate with the first sliding rail 2,27 left side of the first sliding block is connected with the first rack gear 3 by bolted connection, slides on the second sliding rail 6 Dynamic formula is connected with the second sliding block 12, the second sliding block 12 and the cooperation of the second sliding rail 6, is bolted on the right side of the second sliding block 12 Mode is connected with the second rack gear 5, and 12 front side of the second sliding block is connected with connecting rod 10 by welding, and connecting rod 10 sequentially passes through the One through-hole 11 and guide sleeve 9,10 left wall bottom end of connecting rod are connected with pedal 8 by welding, and gear 28 is welded by connecting rod 4 The bottom in cart 1 is connect, gear 28 can be rotated, and connecting rod 4 is between the first sliding rail 2 and the second sliding rail 6,3 He of the first rack gear Second rack gear 5 is engaged with gear 28 respectively.
It further include having the first rubber pad 31 and the second rubber pad 32, the periphery of push plate 17 is connected with the by way of bonding One rubber pad 31,24 bottom of card slot are connected with the second rubber pad 32 by way of bonding.
It further include having friction protrusion 33,8 top of pedal is connected with friction protrusion 33 by way of bonding.
The material of support rod 7 is Q235 steel.
The material of first push rod 16 and the second push rod 14 is Q235 steel.
Working principle: when new energy is stored into material storing box 19, and carries new energy, worker passes through 29 He of handle Cart 1 is pushed to material storing box 19 in the place of production new energy, and at this moment worker pulls push plate 17 to the left, and push plate 17 is pushed away by first Bar 16 drives material storing box 19 to be moved to the left.When material storing box 19 is moved to left end, worker opens lid 30, and worker can be new The energy is put into material storing box 19, and when material storing box 19 places full new energy, worker screws a lid on 30, closes material storing box 19, this When worker push push plate 17 to the right, push plate 17 drives material storing box 19 to move right by the first push rod 16.When worker obviously feels When being stuck in card slot 24 to material storing box 19, worker can push cart 1 by handle 29, to drive the material storing box for filling new energy 19 reach the place that use new energy.When cart 1 reaches the place that use new energy, worker steps on downwards pedal with foot 8, pedal 8 drives the second rack gear 5 to move down by connecting rod 10, and the second rack gear 5 is rotated counterclockwise with moving gear 28,28 band of gear Dynamic first rack gear 3 moves up, and the first rack gear 3 will push supporting plate 13 to move up.Supporting plate 13 drives 14 push card of the second push rod Material storing box 19 in slot 24 moves up, and at this moment the hand of worker will push to the right push plate 17, and push plate 17 will by the first push rod 16 Material storing box 19 is pushed to move right.When material storing box 19 is pushed to right end, the discharge nozzle 22 and valve 21 of material storing box 19 will be worn The first discharge port 25 and the second discharge port 26 are crossed, at this moment, worker opens valve 21, and new energy will be flowed out from discharge nozzle 22, at this time New energy can be put into place to be used.When the new energy in material storing box 19 is completed by the discharge of discharge nozzle 22, worker Valve 21 is shut, worker pulls push plate 17 to be moved to the left, and push plate 17 will drive material storing box 19 to be moved to the left, when material storing box 19 reaches When card slot 24, material storing box 19 will press the second push rod 14 and move down, and the second push rod 14 drives supporting plate 13, the first rack gear 3, gear 28 and second rack gear 5 move down reset.When to carry new energy again, worker steps on downwards pedal 8 with foot, and final second Push rod 14 will push material storing box 19 to move up, and at this moment worker pulls with hand push plate 17 and is moved to the left, when material storing box 19 is moved to When left end, new energy can be loaded onto material storing box 19 at this time.
Because further including having the first rubber pad 31 and the second rubber pad 32, the periphery of push plate 17 is connected by way of bonding There is the first rubber pad 31,24 bottom of card slot is connected with the second rubber pad 32 by way of bonding, so when worker pushes push plate When 17, the first rubber pad 31 will increase the frictional force between worker and push plate 17, and worker is made to be easier to push material storing box 19, and second Rubber pad 32 will make 19 mediate contact of the second push rod 14 and material storing box, to protect the bottom of material storing box 19, and then extend storing The service life of case 19.
Because further including having friction protrusion 33,8 top of pedal is connected with friction protrusion 33 by way of bonding.So working as When worker's foot pedal 8, friction protrusion 33 will increase the coefficient of friction of worker's sole and pedal 8, and foot is made to be not easy to skid, thus It is more easier pushes pedals 8, while more laborsaving.
The preferred embodiment of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art For, without departing from the inventive concept of the premise, several deformations can also be made, improves and substitutes, these belong to this hair Bright protection scope.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (5)

1. a kind of new energy fuel storage bin, which is characterized in that include cart (1), the first sliding rail (2), the first rack gear (3), Connecting rod (4), the second rack gear (5), the second sliding rail (6), support rod (7), pedal (8), guide sleeve (9), connecting rod (10), second are slided Block (12), supporting plate (13), the second push rod (14), the first push rod (16), push plate (17), material storing box (19), framework (20), valve (21), discharge nozzle (22), the first sliding block (27), gear (28), handle (29) and lid (30);Pass through weldering in cart (1) right wall The mode connect is connected with handle (29), and cart (1) right wall is provided with the second discharge port (26), and cart (1) bottom left end passes through welding Mode be connected with guide sleeve (9), left and right side is connected with support rod (7) by welding in cart (1) bottom, It is provided with first through hole (11) on the support rod (7) of left, is connected with framework by bolted connection at the top of support rod (7) (20), framework (20) right wall and cart (1) inner right wall contact, and are provided with the first discharge port (25) in the right wall of framework (20), first Discharge port (25) and the second discharge port (26) are in same horizontal line, and the second through-hole (15), frame are provided in the left wall of framework (20) The top left side of body (20) is provided with feed inlet (18), and the bottom center of framework (20) is provided with card slot (24), and card slot (24) bottom is left Side and right side are provided with third through-hole (23), and framework (20) interior bottom is placed with material storing box (19), below material storing box (19) right wall It is connected with by way of flanged joint discharge nozzle (22), discharge nozzle (22) is equipped with valve (21), in material storing box (19) left wall It is connected with by welding the first push rod (16), the first push rod (16) passes through the second through-hole, and the first push rod (16) left end is logical The mode for crossing welding is connected with push plate (17), and the mode being connected through a screw thread at the top of material storing box (19) is connected with lid (30), Cart (1) interior bottom between the support rod (7) of left and the support rod (7) of right is connected with by bolted connection One sliding rail (2) and the second sliding rail (6), the first sliding rail (2) are located at the right of the second sliding rail (6), and it is sliding that supporting plate (13) is placed on first The top of rail (2) and the second sliding rail (6), supporting plate (13) top left side and right side are connected with the second push rod by welding (14), the second push rod (14) passes through third through-hole (23), and slidingtype is connected with the first sliding block (27) on the first sliding rail (2), the One sliding block (27) and the first sliding rail (2) cooperation, the first sliding block (27) left side are connected with the first rack gear by bolted connection (3), slidingtype is connected with the second sliding block (12) on the second sliding rail (6), the second sliding block (12) and the second sliding rail (6) cooperation, the It is connected with by bolted connection the second rack gear (5) on the right side of two sliding blocks (12), passes through welding on front side of the second sliding block (12) Mode is connected with connecting rod (10), and connecting rod (10) sequentially passes through first through hole (11) and guide sleeve (9), and connecting rod (10) left wall bottom end is logical The mode for crossing welding is connected with pedal (8), and gear (28) is welded on cart (1) interior bottom by connecting rod (4), and gear (28) can Rotation, connecting rod (4) between the first sliding rail (2) and the second sliding rail (6), the first rack gear (3) and the second rack gear (5) respectively with Gear (28) engagement.
2. a kind of new energy fuel storage bin according to claim 1, which is characterized in that further include having the first rubber pad (31) and the second rubber pad (32), the periphery of push plate (17) are connected with the first rubber pad (31), card slot by way of bonding (24) bottom is connected with the second rubber pad (32) by way of bonding.
3. a kind of new energy fuel storage bin according to claim 1, which is characterized in that further include having friction protrusion (33), friction protrusion (33) are connected with by way of bonding at the top of pedal (8).
4. a kind of new energy fuel storage bin according to claim 1, which is characterized in that the material of support rod (7) is Q235 steel.
5. a kind of new energy fuel storage bin according to claim 1, which is characterized in that the first push rod (16) and second pushes away The material of bar (14) is Q235 steel.
CN201611026747.XA 2016-11-22 2016-11-22 A kind of new energy fuel storage bin Active CN106741068B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611026747.XA CN106741068B (en) 2016-11-22 2016-11-22 A kind of new energy fuel storage bin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611026747.XA CN106741068B (en) 2016-11-22 2016-11-22 A kind of new energy fuel storage bin

Publications (2)

Publication Number Publication Date
CN106741068A CN106741068A (en) 2017-05-31
CN106741068B true CN106741068B (en) 2018-12-04

Family

ID=58971240

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611026747.XA Active CN106741068B (en) 2016-11-22 2016-11-22 A kind of new energy fuel storage bin

Country Status (1)

Country Link
CN (1) CN106741068B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107891893B (en) * 2017-10-31 2019-06-18 海门茂发美术图案设计有限公司 A kind of lift truck carried for mold
CN109229191B (en) * 2018-10-08 2020-01-17 湖北倬晟建设工程有限公司 Improved building earthwork transportation device

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2129720Y (en) * 1992-09-12 1993-04-14 杨洪武 Hydraulic lift round barrel transport truck
CN100363219C (en) * 2002-02-07 2008-01-23 中国科学院寒区旱区环境与工程研究所 Multi-purpose hand cart for lifting and moving
KR100931044B1 (en) * 2007-12-14 2009-12-10 현대자동차주식회사 Conveyor for wheel chair ramps on buses
CN201989819U (en) * 2010-12-27 2011-09-28 天津滨海国际花卉科技园区股份有限公司 Single-roller type seedbed conveying trolley
CN203958232U (en) * 2014-05-14 2014-11-26 浙江凯迪恩彩色印刷有限公司 A kind of novel go-cart

Also Published As

Publication number Publication date
CN106741068A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN106741068B (en) A kind of new energy fuel storage bin
CN204750608U (en) Grain collection device
CN205455242U (en) Automatic feeding device
CN208070539U (en) A kind of oil tank detent mechanism for transporting petroleum
CN110834764A (en) Packing scale bag opening mechanism
CN201565492U (en) Vertical type slitter edge reeling machine
CN203428277U (en) Refractory brick raw material conveying device
CN202244979U (en) Draw arm type three-wheel environmental vehicle
CN206854515U (en) A kind of simple ladle body shaped device for Raw material pail processing
CN202072292U (en) Improved grain suction machine
CN109882322A (en) A kind of air filter for vehicle being convenient to clean
CN112718466B (en) Coal screening splitter with adjustable size
CN205186631U (en) Bagging -off baling press
CN202356251U (en) Automatic glue injection device
CN206314382U (en) Automatic spreading car provided with movable floor
CN215323434U (en) Binding machine
CN205204294U (en) Soundproof cotton waste recovery device
CN214243779U (en) Automatic canning equipment of preparation solution is eliminated to formaldehyde
CN206946515U (en) A kind of bent axle push rod drop type card-issuing device
CN107092936A (en) A kind of bent axle push rod drop type card-issuing device and its method of work
CN214356321U (en) Semitrailer turnover device
CN108613543B (en) Rice field rice retrieves dust removal drying device fast
CN202988030U (en) Dumper for dumping garbage can easily
CN209720553U (en) A kind of powder construction material holding vessel
CN216709823U (en) Bag feeding type packaging machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181024

Address after: 318001 room 627, A building, Grand Hyatt building, Jiaojiang District, Taizhou, Zhejiang.

Applicant after: Taizhou Taijie Chemical Technology Co., Ltd.

Address before: 312399 Cao E community, Cao E Street, Shangyu District, Shaoxing, Zhejiang

Applicant before: Ruan Chaying

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191205

Address after: Room 213, second floor, scientific research building, Dongting Lake Road, Gaoyou Economic Development Zone, Gaoyou City, Yangzhou City, Jiangsu Province

Patentee after: Yangzhou Guanke Technology Co., Ltd.

Address before: Room 627, Building A, Junyue Building, Jiaojiang District, Taizhou City, Zhejiang Province

Patentee before: Taizhou Taijie Chemical Technology Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211228

Address after: 225600 Jiangsu Jingwang New Energy Technology Co., Ltd., No. 99 Bosideng Avenue, Gaoyou Economic Development Zone, Yangzhou City, Jiangsu Province

Patentee after: Jiangsu Jingwang New Energy Technology Co.,Ltd.

Address before: Room 213, 2nd floor, scientific research building, Dongtinghu Road, Gaoyou Economic Development Zone, Gaoyou City, Yangzhou City, Jiangsu Province 225600

Patentee before: Yangzhou Guanke Technology Co.,Ltd.