CN106736077A CN201611236990.4A CN201611236990A CN106736077A CN 106736077 A CN106736077 A CN 106736077A CN 201611236990 A CN201611236990 A CN 201611236990A CN 106736077 A CN106736077 A CN 106736077A
Authority
CN
China
Prior art keywords
flange
steel pipe
plate
pipe post
coordinate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611236990.4A
Other languages
Chinese (zh)
Other versions
CN106736077B (en
Inventor
刘华青
许露
刘博�
曾倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd
Original Assignee
WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd filed Critical WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd
Priority to CN201611236990.4A priority Critical patent/CN106736077B/en
Publication of CN106736077A publication Critical patent/CN106736077A/en
Application granted granted Critical
Publication of CN106736077B publication Critical patent/CN106736077B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work

Landscapes

  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of steel pipe post flange coordinate location device and its localization method, it is related to coordinate setting technical field, including central plate, it is fixed on flange.Location-plate, it is fixed on the central plate, and two sides of location-plate are substantially coplanar with two sides of central plate, and location-plate is at least partially disposed at flange outside, the part that location-plate is located on the outside of flange is provided with least 3 not conllinear anchor points, and anchor point is provided with reflection plaster.Steel pipe post flange coordinate location device registration in the present invention and error is small.

Description

Steel pipe post flange coordinate location device and its localization method
Technical field
The present invention relates to coordinate setting technical field, and in particular to a kind of steel pipe post flange coordinate location device and Its localization method.
Background technology
In order to cost-effective, the manufacture of country's roller-coaster at present mainly combines domestic steel using external import roller coaster track Structure producer manufactures the mode of steel pipe post.Roller-coaster steel pipe post is particularly critical with the interface of track, that is, require steel pipe post Flange must with track flange hole position align, it is impossible to produce dislocation.The steel pipe post interface of this high accuracy high request Flange manufacture is the big bottleneck that roller-coaster recreation facility makes, and flange once produces dislocation, then goes live work high above the ground When, its difficulty is very huge.
According to conventional roller-coaster steel pipe post manufacturing experience, typically made a mark a little on flange surface, recycled Total powerstation carries out coordinate point location to mark point.Because flange blanking is irregular, and there is the error rule, therefore this kind is fixed The method error of position coordinate is very big.
The content of the invention
For defect present in prior art, it is an object of the invention to provide a kind of small steel pipe of registration error Column flange coordinate location device.
To achieve the above objectives, the present invention is adopted the technical scheme that:
A kind of steel pipe post flange coordinate location device, is positioned for docking port flange, including:
Central plate, it is fixed on the flange;
Location-plate, it is fixed on the central plate, two sides of the location-plate and two sides of the central plate Face is substantially coplanar, and the location-plate is at least partially disposed at the flange outside, and the location-plate is located at the interface method Part on the outside of orchid is provided with least 3 not conllinear anchor points, and the anchor point is provided with reflection plaster.
On the basis of above-mentioned technical proposal, the location-plate includes at least 3 stripe boards, and each described stripe board is provided with One anchor point.
On the basis of above-mentioned technical proposal, the location-plate includes 4 stripe boards, and 4 stripe boards are in cross It is fixed on the central plate.
On the basis of above-mentioned technical proposal, the steel pipe post flange coordinate location device also includes that first strengthens Gusset, the two ends of the first reinforcement gusset are fixed on two faces in the thickness of slab direction of the stripe board.
On the basis of above-mentioned technical proposal, the steel pipe post flange coordinate location device also includes that second strengthens Gusset, described second strengthens gusset in cross, and the second reinforcement gusset is fixed on the stripe board away from the interface On the face of flange.
On the basis of above-mentioned technical proposal, the central plate is annular.
On the basis of above-mentioned technical proposal, the anchor point is location hole, and the reflection plaster is arranged on the location hole Near one end of the flange.
At the same time, the present invention also provides a kind of registration error small localization method.
To achieve the above objectives, the present invention is adopted the technical scheme that:
A kind of method using above-mentioned steel pipe post flange coordinate location device positioning, the method includes following step Suddenly:
The steel pipe post flange coordinate location device is fixed on flange;
At least 3 design coordinates of not conllinear anchor point on Design Orientation plate;
Rectangular coordinate system in space XYZ is set up using the base plate of steel pipe post, the reading of the anchor point is read using total powerstation Take coordinate;
Compare the design coordinate and read coordinate, rotatable interface flange makes reading coordinate consistent with design coordinate;
Flange is welded on steel pipe post.
Compared with prior art, the advantage of the invention is that:
(1) steel pipe post flange coordinate location device of the invention includes location-plate, and location-plate is at least partially disposed at Flange outside.Because traditional approach is that anchor point is marked on flange, and the present invention is in flange periphery The external labeling anchor point of product, compares with traditional metering system, of the invention equivalent to the radius for expanding flange, so that meeting Reduce the error of measurement.
(2) due to that can not destroy the structure of flange, traditional approach can only rule on flange and mark point, and Anchor point of the invention is arranged in stripe board, and stripe board can be processed arbitrarily, and using the location hole conduct for processing After anchor point, its precision is also than the line high precision of traditional approach.
Brief description of the drawings
Fig. 1 be steel pipe post flange coordinate location device and steel pipe post in the present invention, flange assembling it is vertical Body figure;
Fig. 2 is the front view of steel pipe post flange coordinate location device in the present invention.
In figure:1- central plates, 2- location-plates, 21- location holes, 22- reflection plasters, 23- stripe boards, 3- first strengthens gusset, 4- second strengthens gusset, 5- flanges, 6- steel pipe posts.
Specific embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
Referring to shown in Fig. 1 and Fig. 2, the present invention provides a kind of steel pipe post flange coordinate location device, for docking Mouth flange 5 is positioned, and it includes central plate 1 and location-plate 2.
Central plate 1 is fixed on flange 5, and the present invention is provided with dowel hole on central plate 1, after insertion alignment pin Central plate 1 can be fixed on flange 5, in order to adapt to various sizes of flange 5, it is only necessary to change dowel hole .In addition in order to adapt to the shape of flange 5, the central plate 1 in the present invention is designed as annular.
Location-plate 2 is fixed on central plate 1, and two sides of location-plate 2 are substantially coplanar with two sides of central plate 1, That is central plate 1 and the face that flange 5 is in contact and a face relative with the face, and location-plate 2 it is corresponding two Individual face is substantially coplanar.Milling flat processing is carried out to two sides of location-plate 2 and two sides of central plate 1 in the present invention, its Flatness≤2.0mm.
Location-plate 2 is at least partially disposed at the outside of flange 5, location-plate 2 be located at the outside of flange 5 part be provided with to Few 3 not conllinear anchor points, are provided with reflection plaster 22, and total powerstation with the use of the seat that can measure anchor point on anchor point Mark.Determine a face according to 3 points, at least need to measure 3 coordinates of not conllinear anchor point in the present invention.
Location-plate 2 in the present invention includes at least 3 stripe boards 23, and each stripe board 23 is provided with an anchor point.Specifically , location-plate 2 is fixed on central plate 1 including 4 stripe boards, 23,4 stripe boards 23 in cross.In each stripe board 23 Anchor point is provided with the end in the outside of flange 5.Anchor point is the location hole processed in stripe board 23 in the present invention 21, the position of location hole 21 is from the center of flange 5 about 1m, a diameter of 30mm of location hole 21.Reflection plaster 22 is then arranged on Near the one end fits total station survey of flange 5, reflection plaster 22 can just be put to be put location hole 21 with counter, so that total powerstation can With preceding or measure after.
Because traditional approach is that anchor point is marked on flange 5, and the present invention be the circumferential area of flange 5 it External labeling anchor point, compares with traditional metering system, of the invention equivalent to the radius for expanding flange 5, so as to can subtract The error of small measurement.Further, since the structure of flange 5 can not be destroyed, traditional approach can only rule on flange 5 and do Mark point, and anchor point of the invention is arranged in stripe board 23, stripe board 23 can be processed arbitrarily, and use is processed Location hole as anchor point after, its precision is also than the line high precision of traditional approach.
In order to increase intensity, gusset 3 is strengthened present invention additionally comprises first, the two ends of the first reinforcement gusset 3 are fixed on two On the face in the thickness of slab direction of stripe board 23.In order to further increase intensity, gusset 4 is strengthened present invention additionally comprises second, second adds Strong gusset 4 is in cross, and the second reinforcement gusset 4 is fixed on stripe board 23 away from the face of flange 5.
The present invention also provides a kind of method using above-mentioned steel pipe post flange coordinate location device positioning, the method Comprise the following steps:
Steel pipe post flange coordinate location device is fixed on flange 5;
At least 3 design coordinates of not conllinear anchor point on Design Orientation plate 2;
Rectangular coordinate system in space XYZ is set up using the base plate of steel pipe post 6, the reading for reading anchor point using total powerstation is sat Mark;
Compare design coordinate and read coordinate, rotatable interface flange 5 makes reading coordinate consistent with design coordinate;
Flange 5 is welded on steel pipe post 6.
After flange 5 is welded on steel pipe post 6, complete to be docked with roller coaster track again as entirety.
The present invention is not limited to the above-described embodiments, for those skilled in the art, is not departing from On the premise of the principle of the invention, some improvements and modifications can also be made, these improvements and modifications are also considered as protection of the invention Within the scope of.The content not being described in detail in this specification belongs to prior art known to professional and technical personnel in the field.

Claims (8)

1. a kind of steel pipe post flange coordinate location device, is positioned for docking port flange (5), it is characterised in that Including:
Central plate (1), it is fixed on the flange (5);
Location-plate (2), it is fixed on the central plate (1), two sides and the central plate (1) of the location-plate (2) Two sides it is substantially coplanar, and the location-plate (2) be at least partially disposed at the flange (5) outside, the location-plate (2) part on the outside of the flange (5) is provided with least 3 not conllinear anchor points, and the anchor point is provided with instead Light pastes (22).
2. steel pipe post flange coordinate location device as claimed in claim 1, it is characterised in that:The location-plate (2) Including at least 3 stripe boards (23), each described stripe board (23) is provided with an anchor point.
3. steel pipe post flange coordinate location device as claimed in claim 2, it is characterised in that:The location-plate (2) Including 4 stripe boards (23), 4 stripe boards (23) are fixed on the central plate (1) in cross.
4. steel pipe post flange coordinate location device as claimed in claim 3, it is characterised in that:The steel pipe post connects Mouth flange coordinate location device also includes that first strengthens gusset (3), and the two ends of first reinforcement gusset (3) are fixed on two institutes On the face in the thickness of slab direction for stating stripe board (23).
5. the steel pipe post flange coordinate location device as described in claim 3 or 4, it is characterised in that:The steel pipe stands Post flange coordinate location device also includes that second strengthens gusset (4), and described second strengthens gusset (4) in cross, and institute State the second reinforcement gusset (4) and be fixed on the stripe board (23) away from the face of the flange (5).
6. steel pipe post flange coordinate location device as claimed in claim 1, it is characterised in that:The central plate (1) It is annular.
7. steel pipe post flange coordinate location device as claimed in claim 1, it is characterised in that:The anchor point is fixed Position hole (21), the reflection plaster (22) is arranged on the location hole (21) near one end of the flange (5).
8. the method that the steel pipe post flange coordinate location device described in a kind of utilization claim 1 is positioned, its feature exists In the method is comprised the following steps:
The steel pipe post flange coordinate location device is fixed on flange (5);
At least 3 design coordinates of not conllinear anchor point on Design Orientation plate (2);
Rectangular coordinate system in space XYZ is set up using the base plate of steel pipe post (6), the reading of the anchor point is read using total powerstation Coordinate;
Compare the design coordinate and read coordinate, rotatable interface flange (5) makes reading coordinate consistent with design coordinate;
Flange (5) is welded on steel pipe post (6).
CN201611236990.4A 2016-12-28 2016-12-28 Steel pipe post interface flange coordinate location device and its localization method Active CN106736077B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611236990.4A CN106736077B (en) 2016-12-28 2016-12-28 Steel pipe post interface flange coordinate location device and its localization method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611236990.4A CN106736077B (en) 2016-12-28 2016-12-28 Steel pipe post interface flange coordinate location device and its localization method

Publications (2)

Publication Number Publication Date
CN106736077A true CN106736077A (en) 2017-05-31
CN106736077B CN106736077B (en) 2019-02-26

Family

ID=58923021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611236990.4A Active CN106736077B (en) 2016-12-28 2016-12-28 Steel pipe post interface flange coordinate location device and its localization method

Country Status (1)

Country Link
CN (1) CN106736077B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109059774A (en) * 2018-10-19 2018-12-21 中交天津航道局有限公司 A kind of positioning device of dimensional component

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002286403A (en) * 2001-03-28 2002-10-03 Taku Seisakusho:Kk Testing device for steel pipe before lining
CN201850511U (en) * 2010-10-26 2011-06-01 广东冠粤路桥有限公司 Rapid stay cable sleeve lofting positioner
CN203286944U (en) * 2013-05-24 2013-11-13 上海外高桥造船有限公司 Tool for measuring center of circle
CN103673883A (en) * 2013-12-20 2014-03-26 沪东中华造船(集团)有限公司 Measuring tool and measuring method applied to boat pipe system flange center position
KR20150067429A (en) * 2013-12-10 2015-06-18 에스티엑스조선해양 주식회사 Adjusting pipes measuring apparatus method using 3 dimensional coordinate
CN204705292U (en) * 2015-06-24 2015-10-14 福州捷泰机电有限公司 A kind of detection architecture of flange pilot hole
CN105375097A (en) * 2015-12-02 2016-03-02 成都锦江电子系统工程有限公司 Large-scale paraboloid antenna surface operation angle control and loading measurement system
CN205111137U (en) * 2015-08-19 2016-03-30 纬泰机械(上海)有限公司 Flange welding and positioning device
CN205448996U (en) * 2016-03-08 2016-08-10 江南造船(集团)有限责任公司 Piping axiality detection device
CN206455319U (en) * 2016-12-28 2017-09-01 武汉武船重型装备工程有限责任公司 Steel pipe post flange coordinate location device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002286403A (en) * 2001-03-28 2002-10-03 Taku Seisakusho:Kk Testing device for steel pipe before lining
CN201850511U (en) * 2010-10-26 2011-06-01 广东冠粤路桥有限公司 Rapid stay cable sleeve lofting positioner
CN203286944U (en) * 2013-05-24 2013-11-13 上海外高桥造船有限公司 Tool for measuring center of circle
KR20150067429A (en) * 2013-12-10 2015-06-18 에스티엑스조선해양 주식회사 Adjusting pipes measuring apparatus method using 3 dimensional coordinate
CN103673883A (en) * 2013-12-20 2014-03-26 沪东中华造船(集团)有限公司 Measuring tool and measuring method applied to boat pipe system flange center position
CN204705292U (en) * 2015-06-24 2015-10-14 福州捷泰机电有限公司 A kind of detection architecture of flange pilot hole
CN205111137U (en) * 2015-08-19 2016-03-30 纬泰机械(上海)有限公司 Flange welding and positioning device
CN105375097A (en) * 2015-12-02 2016-03-02 成都锦江电子系统工程有限公司 Large-scale paraboloid antenna surface operation angle control and loading measurement system
CN205448996U (en) * 2016-03-08 2016-08-10 江南造船(集团)有限责任公司 Piping axiality detection device
CN206455319U (en) * 2016-12-28 2017-09-01 武汉武船重型装备工程有限责任公司 Steel pipe post flange coordinate location device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109059774A (en) * 2018-10-19 2018-12-21 中交天津航道局有限公司 A kind of positioning device of dimensional component

Also Published As

Publication number Publication date
CN106736077B (en) 2019-02-26

Similar Documents

Publication Publication Date Title
CN109612406B (en) Random detection method for ring splicing quality of splicing pipe pieces of shield tunnel
CN107871679A (en) A kind of motherboard to be cut, base plate preparation method and substrate cut accuracy checking method
CN106485749B (en) A kind of rectangular pins element rough localization method based on angle point
JP2008036918A5 (en)
CN102538646A (en) Tolerance test template for master node of ship hull and detection method thereof
CN106842838A (en) Alignment mark and substrate alignment method
CN104567763B (en) Steel structure detection method based on BIM (building information modeling) system
CN106736077A (en) Steel pipe post flange coordinate location device and its localization method
CN104931027B (en) A kind of projection line-putting method of decorative pattern
CN104596412A (en) Identification base for complex curved surface high-precision measuring and positioning
CN206455319U (en) Steel pipe post flange coordinate location device
CN205889917U (en) Formpiston location interfacing apparatus and fan blade mould
CN204988223U (en) Detection apparatus for steel member preparation size precision
CN106197283B (en) Coordinate recognizer, use method thereof and measurement system
CN109060799A (en) A kind of assembling line finished product detection determination method
CN107367249B (en) Prefabricated components assembling capacity detection method, method of adjustment and joining method
CN104567609B (en) The detection means and detection method of hole position distance on arc-shaped curved surface
CN107421512A (en) A kind of self-pierce riveting connection locator and localization method based on optical principle
CN205879076U (en) Simple and easy circumference detection frock of beating
CN107228657A (en) Pillar of electrification rail contacting net assembly parameter measuring system
CN209763977U (en) blast hole pore-forming quality detection device
CN104134005B (en) Presetting bit deviation determining method
US20150260515A1 (en) Method and apparatus for determining the distance of a light beam from a point on a surface of an object
CN208399893U (en) A kind of pcb board cursor printing equipment
CN109059889B (en) Application method of total station in special-shaped steel structure processing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant