CN106731255A - A kind of fixed structure of parallel combinations type spiral board demister - Google Patents

A kind of fixed structure of parallel combinations type spiral board demister Download PDF

Info

Publication number
CN106731255A
CN106731255A CN201611106403.XA CN201611106403A CN106731255A CN 106731255 A CN106731255 A CN 106731255A CN 201611106403 A CN201611106403 A CN 201611106403A CN 106731255 A CN106731255 A CN 106731255A
Authority
CN
China
Prior art keywords
base
rotational flow
flow plate
spiral board
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611106403.XA
Other languages
Chinese (zh)
Inventor
常立宏
丛永杰
李世刚
张玉增
柏春光
李树臣
胡静波
张修君
简键
王晓东
蒋松辉
岳峰
李志强
郭明春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HARBIN NO 3 POWER PLANT HUADIAN ENERGY CO Ltd
Shanghai Huolin Environmental Protection Engineering Equipment Co Ltd
HUADIAN ENERGY CO Ltd
Original Assignee
HARBIN NO 3 POWER PLANT HUADIAN ENERGY CO Ltd
Shanghai Huolin Environmental Protection Engineering Equipment Co Ltd
HUADIAN ENERGY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HARBIN NO 3 POWER PLANT HUADIAN ENERGY CO Ltd, Shanghai Huolin Environmental Protection Engineering Equipment Co Ltd, HUADIAN ENERGY CO Ltd filed Critical HARBIN NO 3 POWER PLANT HUADIAN ENERGY CO Ltd
Priority to CN201611106403.XA priority Critical patent/CN106731255A/en
Publication of CN106731255A publication Critical patent/CN106731255A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D45/00Separating dispersed particles from gases or vapours by gravity, inertia, or centrifugal forces
    • B01D45/12Separating dispersed particles from gases or vapours by gravity, inertia, or centrifugal forces by centrifugal forces
    • B01D45/16Separating dispersed particles from gases or vapours by gravity, inertia, or centrifugal forces by centrifugal forces generated by the winding course of the gas stream, the centrifugal forces being generated solely or partly by mechanical means, e.g. fixed swirl vanes

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Filtering Of Dispersed Particles In Gases (AREA)

Abstract

The present invention relates to a kind of fixed structure of parallel combinations type spiral board demister, belong to demister technical field.A kind of fixed structure of parallel combinations type spiral board demister, the parallel combinations type rotational flow plate defroster is arranged in a combination by some rotational flow plate defroster units, each rotational flow plate defroster unit includes the base of cylinder and parallelepiped, and spiral board is equipped with cylinder;Parallel in tower body support beam in large desulfurization tower to set up some support bars, some rotational flow plate defroster units are respectively across being fixed on adjacent two support bars, and the base of some rotational flow plate defroster units is in each other honeycomb arrangement.Present invention can be suitably applied in large-scale tower, assemble rapidly and efficiently, Stability Analysis of Structures.

Description

A kind of fixed structure of parallel combinations type spiral board demister
Technical field
The present invention relates to demister technical field, more particularly to a kind of fixed knot of parallel combinations type spiral board demister Structure.
Background technology
Rotational flow plate defroster is that, using the density contrast between gas-liquid, the centrifugal force produced by flow rotation makes drop (contain Dust) from air-flow separate, the computing formula of centrifugal force shows, the size of the certain dust of quality and centrifugal force suffered by droplet Inversely proportional with radius of turn, the more big then centrifugal force of radius is smaller, and separating effect is poorer.Illustrate the small spiral board of diameter than straight The big spiral board separative efficiency in footpath is high.
However, fume desulfurizing tower is all diameter from several meters to more than 20 meters of large-scale tower, this is unsuitable with eddy flow board diameter Excessive very contradiction, has promoted parallel combinations rotational flow plate defroster technology in large-scale or super-huge desulfuration absorbing tower at this stage Using being exactly briefly using multiple small-diameter unit rotational flow plate defroster parallel combinations (patent No.s in large-scale tower: ZL201220723758.4)。
The parallel combinations rotational flow plate defroster load mode for using at present has two kinds:First, made using stainless steel plate, will Several rotational flow plate defroster units are fixed in supporting plate circular hole, and supporting plate both played a supportive role, and also sealed.2nd, make Made of MODIFIED PP, by several or even hundreds of rotational flow plate defroster unit cylinders, each is fixed on and opens circle of parallelepiped On hole plate base, by parallelepiped flat base as cellular splicing is integral, large-scale tower edge exposed position is with blind Plate is sealed.Parallelepiped flat base is seated on the grid welded by stainless steel strip as cellular splicing is integral, overall Lived by large-scale tower internal loading beam load again.
Several rotational flow plate defroster units are fixed in supporting plate circular hole, due to being that stainless steel makes, structure Stabilization, but install complicated;And parallelepiped flat base is used as cellular splicing is integral, can be due to large-scale tower Interior operation dynamic pressure, causes cylinder large area lodging phenomenon often to occur.
The content of the invention
It is an object of the invention to regarding to the issue above, there is provided a kind of fixation of parallel combinations type spiral board demister Structure, is applicable in large-scale tower, assembles rapidly and efficiently, Stability Analysis of Structures.
The object of the present invention is achieved like this:
A kind of fixed structure of parallel combinations type spiral board demister, it is characterised in that the parallel combinations type eddy flow Plate demister is arranged in a combination by some rotational flow plate defroster units, each rotational flow plate defroster unit include cylinder with it is parallel The base of hexagon, is equipped with spiral board in cylinder;It is parallel in tower body support beam in large desulfurization tower to set up some Strut, some rotational flow plate defroster units are respectively across being fixed on adjacent two support bars, and some rotational flow plate defroster lists The base of unit is in each other honeycomb arrangement.
Wherein, the base center of the rotational flow plate defroster unit is provided with circular hole, and the circumference along circular hole on base is provided with One encloses the flanging perpendicular to base, and barrel jacket is mutually fixed outside flanging with flanging.
Wherein, the base and cylinder of the rotational flow plate defroster unit are made by MODIFIED PP material, and base and cylinder Between be fixed using the bolt of PP materials.
Wherein, the support bar is stainless steel square tube or carbon steel outer lining MODIFIED PP square tube.
Wherein, the circular hole inner side of the base of the rotational flow plate defroster unit is uniformly provided with six symmetrical fixing points, should When base is across on adjacent two support bars, the straight line that the fixing point that two of which is oppositely arranged is linked to be is located at two support bars The axis of symmetry on, remaining four fixing point is located at two both sides of support bar two-by-two respectively, and two positioned at the same side are solid The line of fixed point is parallel with support bar, will be located at the fixing point of base of the same side and close therewith respectively using two fixtures Support bar be fixed, and further using bolt base and support bar are fixed as one.
Wherein, the bolt is made up of PP materials.
Beneficial effects of the present invention are:The base and cylinder of rotational flow plate defroster unit used can be standardized, scale Production, production efficiency is high;Using the support bar of PP materials, the requirement to the levelness of support bar is reduced;Whole combined rotation The installation rate for flowing plate demister is fast.
Brief description of the drawings
Fig. 1 is the part-structure figure after parallel combinations type spiral board demister installation.
Fig. 2 is the attachment structure figure between rotational flow plate defroster unit and support bar.
Specific embodiment
With reference to specific embodiments and the drawings, the present invention is expanded on further.
As shown in Figure 1 with Figure 2, a kind of fixed structure of combined spiral board demister, the parallel combinations type rotation Stream plate demister is arranged in a combination by some rotational flow plate defroster units 1, and each rotational flow plate defroster unit 1 includes cylinder 11 With the base 12 of parallelepiped, base 12 and cylinder 11 are made by MODIFIED PP material, and spiral board, bottom are equipped with cylinder 11 12 centers of seat are provided with circular hole, and flanging of the circle perpendicular to base 12 is provided with along the circumference of circular hole on base 12, and cylinder 11 is enclosed within The outer bolt and the flanging of base 12 between using PP materials of the flanging of base 12 is fixed;Tower in large desulfurization tower Parallel in body support beam 2 to set up some support bars 3, some rotational flow plate defroster units 1 are respectively across being fixed on adjacent two branch On strut 3, and the base 12 of some rotational flow plate defroster units 1 is in each other honeycomb arrangement.
Support bar therein 3 can select stainless steel square tube, and reduce the levelness to support bar, preferably outside carbon steel Serve as a contrast the square tube of MODIFIED PP.
To make whole parallel combinations type spiral board demister quickly be assembled in large desulfurization tower, and Stability Analysis of Structures, Six symmetrical fixing points are uniformly provided with the inside of the circular hole of the base 12 of rotational flow plate defroster unit 1, the base 12 across When on adjacent two support bars 3, the straight line that the fixing point that two of which is oppositely arranged is linked to be is located at two symmetry axis of support bar 3 On line, remaining four fixing point is located at two both sides of support bar 3 two-by-two respectively, and two root anchor points positioned at the same side company Line is parallel with support bar 3, will be located at the fixing point and branch close therewith of the base 12 of the same side respectively using two fixtures Strut 3 is fixed, and further using bolt base 12 and support bar 3 is fixed as one.
This fixed structure so that the fixation of rotational flow plate defroster unit both has singulation, again can be under special circumstances Avoid the effect occurrence of large-area lodging problem because of dynamic pressure.
If by taking certain power plant 16.5m desulfurizing towers as an example, if a set of simultaneously using the grid installation that existing stainless steel strip makes Row combination rotational flow plate defroster, the requirement for horizontality to load beam is high, and otherwise grid out-of-flatness is difficult to Fast Installation a set of Parallel combinations rotational flow plate defroster, the general set-up time is 45 days.But, using the fixed structure in the present invention, to support bar Requirement for horizontality it is not high, i.e. the ability with self adaptation, installation rate is fast, and the general set-up time is less than 10 days.

Claims (6)

1. a kind of fixed structure of parallel combinations type spiral board demister, it is characterised in that the parallel combinations type spiral board Demister is arranged in a combination by some rotational flow plate defroster units (1), and each rotational flow plate defroster unit (1) is including cylinder (11) and parallelepiped base (12), is equipped with spiral board in cylinder (11);Tower body support in large desulfurization tower Parallel on beam (2) to set up some support bars (3), some rotational flow plate defroster units (1) are respectively across being fixed on adjacent two branch On strut (3), and the base (12) of some rotational flow plate defroster units (1) is in each other honeycomb arrangement.
2. a kind of fixed structure of parallel combinations type spiral board demister according to claim 1, it is characterised in that institute Base (12) center for stating rotational flow plate defroster unit (1) is provided with circular hole, and a circle is provided with along the circumference of circular hole on base (12) Perpendicular to the flanging of base (12), cylinder (11) is enclosed within outside flanging and is mutually fixed with flanging.
3. a kind of fixed structure of parallel combinations type spiral board demister according to claim 2, it is characterised in that institute The base (12) and cylinder (11) for stating rotational flow plate defroster unit (1) are made by MODIFIED PP material, and base (12) and cylinder (11) bolt between using PP materials is fixed.
4. a kind of fixed structure of parallel combinations type spiral board demister according to claim 1, it is characterised in that institute It is stainless steel square tube or carbon steel outer lining MODIFIED PP square tube to state support bar (3).
5. a kind of fixed structure of parallel combinations type spiral board demister according to claim 2, it is characterised in that institute The circular hole inner side for stating the base (12) of rotational flow plate defroster unit (1) is uniformly provided with six symmetrical fixing points, the base (12) During across on adjacent two support bars (3), the straight line that the fixing point that two of which is oppositely arranged is linked to be is located at two support bars (3) on the axis of symmetry, remaining four fixing point is located at two both sides of support bar (3) two-by-two respectively, and positioned at the same side The line of two root anchor points is parallel with support bar (3), and consolidating for base (12) of the same side will be located at respectively using two fixtures Fixed point and support bar (3) close therewith are fixed, and further using bolt are fixed as base (12) and support bar (3) Integrally.
6. a kind of fixed structure of parallel combinations type spiral board demister according to claim 5, it is characterised in that institute Bolt is stated to be made up of PP materials.
CN201611106403.XA 2016-12-05 2016-12-05 A kind of fixed structure of parallel combinations type spiral board demister Pending CN106731255A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611106403.XA CN106731255A (en) 2016-12-05 2016-12-05 A kind of fixed structure of parallel combinations type spiral board demister

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611106403.XA CN106731255A (en) 2016-12-05 2016-12-05 A kind of fixed structure of parallel combinations type spiral board demister

Publications (1)

Publication Number Publication Date
CN106731255A true CN106731255A (en) 2017-05-31

Family

ID=58878849

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611106403.XA Pending CN106731255A (en) 2016-12-05 2016-12-05 A kind of fixed structure of parallel combinations type spiral board demister

Country Status (1)

Country Link
CN (1) CN106731255A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205073794U (en) * 2015-10-09 2016-03-09 殷显伟 Combination spiral -flow type defogging dust arrester installation
CN206262256U (en) * 2016-12-05 2017-06-20 华电能源股份有限公司 A kind of fixed structure of parallel combinations type spiral board demister

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205073794U (en) * 2015-10-09 2016-03-09 殷显伟 Combination spiral -flow type defogging dust arrester installation
CN206262256U (en) * 2016-12-05 2017-06-20 华电能源股份有限公司 A kind of fixed structure of parallel combinations type spiral board demister

Similar Documents

Publication Publication Date Title
CN206262256U (en) A kind of fixed structure of parallel combinations type spiral board demister
JP2008045395A (en) Flangeless support structure
CN103255944B (en) Local double-layer spherical reticulated shell storage tank vault structure
EP3597840A1 (en) Modular installation and assembly set for a modular installation
CN203531493U (en) Heat-engine plant frame type non-metal combined chimney
CN104638381A (en) Spatial five-equal partition reflecting face unit of FAST (five-hundred-meter aperture spherical radio telescope)
CN102561787B (en) Anticorrosive composite chimney unit and chimney
CN106731255A (en) A kind of fixed structure of parallel combinations type spiral board demister
CN209254482U (en) A kind of energy-saving desulfurization mentions effect device
CN103790235B (en) the main frame structure assembly of integrated house
CN207980737U (en) A kind of rule stream packed bed rule stream phase change device
CN109853726B (en) Annular stretch-draw overall structure
DE102012009850A1 (en) Wind energy plant, has foundation, mast, nacelle, and vertically or horizontally rotatably mounted wind rotor, where vibration-resilient connection is provided between mast structure and foundation by large construction bottom plate
CN102716640B (en) Absorption tower
CN207090138U (en) A kind of novel oil inlet mouth device
CN112906104B (en) Calculation method for stable bearing capacity of ring beam of ring plate of steel silo
CN205975969U (en) Combination framework and connecting piece of rack and truss antarafacial
CN105290675B (en) A kind of cold separator welding equipment formwork structure of vapour and the cold separator of vapour
CN204563711U (en) Coal slurry screening plate column
CN102989267B (en) A kind of rule stream packed bed and its installation method
CN207478300U (en) A kind of adjustable type desulfurization synergistic mass transfer apparatus
CN201613127U (en) Inner member of fixed bed reactor for facilitating mass transfer
CN105525603B (en) A kind of method and device for reusing the balanced oil cylinder of vertical ship lift
CN108953469A (en) A kind of vibration absorber absorbing multi-direction high frequency high intensity vibration
CN105195007B (en) A kind of circulating fluid bed reactor inner member and its application

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination