CN106677229A - Pipe network system for treating frozen soil of tailings pond by combining drainage facility and construction method for pipe network system - Google Patents
Pipe network system for treating frozen soil of tailings pond by combining drainage facility and construction method for pipe network system Download PDFInfo
- Publication number
- CN106677229A CN106677229A CN201710104101.7A CN201710104101A CN106677229A CN 106677229 A CN106677229 A CN 106677229A CN 201710104101 A CN201710104101 A CN 201710104101A CN 106677229 A CN106677229 A CN 106677229A
- Authority
- CN
- China
- Prior art keywords
- pipe
- cross over
- network system
- dam
- frozen soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/10—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
- E02D31/14—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against frost heaves in soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention discloses a pipe network system for treating frozen soil of a tailings pond by combining a drainage facility and a construction method for the pipe network system. The pipe network system comprises water guide pipes, transverse drainage pipes and vertical communication pipes, wherein the end heads of the transverse drainage pipes extend out of the tailings pond to communicate with atmosphere; and the middle sections of the transverse drainage pipes communicate with a flood drainage facility of the tailings pond through the vertical communication pipes. The construction method for the pipe network system comprises the following steps of: starting to accumulate tailings and embedding the vertical communication pipes after a dam and the flood drainage facility are constructed at an initial stage of the tailings pond; embedding the first-grade water guide pipes and the transverse drainage pipes after accumulation elevation of the tailings is higher than dam top elevation of the dam at the initial stage, and selectively embedding inclined communication pipes; and increasing elevation and number of the water guide pipes, the vertical communication pipes, the transverse drainage pipes and the inclined communication pipes step by step with increase of accumulation elevation of the tailings until laying is completed. The pipe network system is simple in structure, is convenient to construct, is relatively low in cost, and can efficiently treat the frozen soil of the tailings pond.
Description
Technical field
The invention belongs to mill tailings storehouse field, more particularly to a kind of pipe network system for administering Tailings Dam frozen soil and its
Construction method.
Background technology
Frozen soil is referred to below zero degrees celsius, and the various rocks and soil containing ice.Frozen soil is related to the physics of soil, water, ice
Property is coupled, while being related to the heat conduction problem of air, frozen soil layer and bottom Rock And Soil.
The frozen soil phenomenon of Tailings Dam is inherently consistent with the frozen soil phenomenon of nature, has and freezes and melted
Journey, can all be divided into permanent frozen soil and frost zone, but there is also significant diversity:1) ground of nature is substantially solid
Fixed, and tailing dam beach face is constantly to rise, ice face rises to be carried out with beach face rising synchronous, and it is low that its rate of climb has
In frost zone depth, what is had exceeds well over frost zone depth;2) when Tailings Slurry is discharged on beach face, 4 DEG C of own temperature
~10 DEG C, in saturation, in beach face flowing time stage deposition, the bleeding in infiltration, into after frost zone further in subglacial
Deposition.
In general, seasonal frozen ground layer is interior then under the conditions of uncovered after the spring is warm all to melt in addition to Qinghai-Tibet Platean.
For Tailings Dam, uncovered condition is difficult to keep, because Tailings Dam general winter takes ore drawing under ice sheet, piles up mine tailing shape
Into frozen soil, and after spring warm defrosting, recover to disperse ore drawing before dam.Dispersion ore drawing is carried out before frozen soil layer does not melt completely, quite
In having added mine tailing coating on the frozen soil layer for not yet melting.At this moment general temperature is relatively low, and the low temperature of capped frozen soil layer is difficult
To conduct, original frozen state can only be kept, as tailings discharging continues to rise, increasing the buried depth of frozen soil layer becomes deep
Layer frost zone.In plane along certain direction continuous distribution, vertical direction receives seasonal effect for Disjunct distribution to deep frozen layer, embedding depth
Number of degrees rice is to tens of rice.Can be continuous along flowage line direction, or it is discontinuous.In the width in vertical flowage line direction
Degree, each Tailings Dam can different, with mine tailing granularity, to deposit the factor such as beach longitudinal gradient, saturation water level and gradient relevant.Deep layer
Frost zone is affected less by ambient temperature, and mine tailing is covered causes low temperature to be difficult to transfer out, so typically all maintaining freezing state.
Deep frozen layer is hard, and soil particle is cementing by ice sheet, but heat is melted.
The main harm of Tailings Dam deep layer frozen soil layer shows the following aspects:
1) tailing dam saturation line is caused to raise:The Tailings Dam higher for saturation, if saturation near initial stage dam crest
Higher or effusion, it is possible to create hard frozen soil.Because hard frozen soil bad hydraulic permeability is be close to waterproof, fill dam seepage water is hard
Frozen soil is intercepted, it is impossible to is continued extravasation formation and is choked water, causes dam slope saturation to rise.Deep frozen layer is located in fill dam, quite
In fluid-tight water barrier, when the seepage water that its top is come flow to this layer, intercepted by this frost zone, it is impossible to ooze under continuation, quilt
Compel to switch to horizontal seepage flow, until oozing under this frost zone downstream lateral edges ability, this is just greatly improved fill dam saturation water
Position.
2) dewatering effect of water seepage drainage facility is reduced:Due to deep frozen layer impermeable role, whether vertical row is oozed or level
Row is oozed, or early stage it is pre-buried or after the row that sets up ooze, all because being acted on by horizontal freezing layer water proof, be hardly formed vertical pumping
Funnel, is greatly lowered the dewatering effect of water seepage drainage facility.
3) stability of dam body is reduced:Saturation buried depth is the key factor for affecting tailing dam dam slide stabilization, and saturation is carried
The high stability for necessarily reducing dam body side slope.When especially deep frozen layer is near dam slope, dam slope can be caused to seep water for a long time natural pond
Poolization, frozen soil thaws and is likely to occur floating ice even Local Sliding.If dam seepage line dam crest effusion in the early stage, it is possible to create hard
Hard frozen soil, the spring warms up and comes interim, and the loose frozen soil in top melts fast, and ice crystal bleed causes top to carry out the water yield greatly, and now initial stage dam crest
Hard frozen soil melts slow and substantially impervious water, causes frozen soil upper pond level to rise fast, infiltration gradient increase, easily causes stream soil etc.
Seepage erosion, even results in dam body unstability.With mine tailing pile up absolute altitude rising, in storehouse deep frozen layer long-term high pressure,
Under heat effect, it is possible that melting, the frost zone intensity of thawing drastically reduces, away from free face thickness it is less under the conditions of can
Therefore dam body unstability can be caused.
4) impact of the frozen soil to Tailings Dam structures:The soil body, because water congeals into ice in soil, and is around migrated when freezing
The water for coming freezes to produce volumetric expansion, and body frost heaving can make drain pipe protuberance, disconnect even crack, and drain pipe both sides frost heave is uneven
Pipeline bending, deflection can be made when even.Body frost heaving is uneven to be caused Overflow Tower deflection or even collapses.Frozen soil intensity when melting
Reduce, big sedimentation and deformation can be produced, if structure base is in frozen soil layer, structures produce sedimentation and deformation, produce uneven
Even sedimentation can cause structures to incline, crack is even destroyed.
For the main harm of above Tailings Dam deep layer frozen soil layer, existing general counter-measure mainly includes:
1) ice period low water level operation:In order to mitigate the harm of frozen soil, Tailings Dam should carry out low water level operation before ice period.
Low water level operation has three big benefits:One is that dam seepage line water level can be made low, and loose frozen soil scope is big during frost;Two is hard jelly
Soil is away from dam slope, little to dam body seepage flow and stabilizing influence if forming deep frozen layer;Three is the storehouse for expanding winter subglacial ore drawing
Hold.
2) ice period take subglacial ore drawing:To prevent from depositing beach formation ore pulp Freezing block and floating ice layer, winter extremely frigid zones
Tailings Dam is using ore drawing and subglacial ore drawing under water.Subglacial ore drawing should also be as carrying out many mouthfuls of ore drawings, in case mine tailing is piled with stifled at one
The plug mouth of pipe, if necessary should also be in frost top layer punching ore drawing.
3) frozen soil just recovers ore drawing before dam after melting:Mine tailing covering is discharged to prevent frozen soil layer to be particularly hard frost zone
Deep frozen layer is formed, when warm frozen soil of annual spring starts to melt, does not rush to recover ore drawing before dam, should treat that hard frozen soil all melts
Recover ore drawing before dam after change again.The short Tailings Dam in deposition beach more should be thus, in case deep layer frozen soil layer harm.
Although after being processed by above-mentioned measure, can to a certain extent reduce Frozen soil problems, also necessarily affect
Mining production.Especially for the formation for preventing deep layer frozen soil layer, the measure of ore drawing before could recovering dam after frozen soil melts, so
The mine significantly underproduction is will result directly in, or even is stopped production.The area longer for ice period, frozen soil layer is relatively thick, the thawing time
It is corresponding longer, the underproduction or the off-time it is long, economic loss is often difficult to bear.
The content of the invention
The technical problem to be solved is to overcome the shortcomings of to be mentioned and defect in background above technology, there is provided a kind of
Simple structure, easy construction, cost is less, can efficiently administer the pipe network system of Tailings Dam frozen soil, and provides a kind of construction method.
To solve above-mentioned technical problem, technical scheme proposed by the present invention is:
A kind of combination water seepage drainage facility administers the pipe network system of Tailings Dam frozen soil, and the pipe network system includes being embedded in Tailings Dam
Aqueduct, horizontal drainage pipe and vertical cross over pipe, described aqueduct is provided with a plurality of along different elevations, and a plurality of aqueduct is extremely
It is few to connect with a horizontal drainage pipe;Extend Tailings Dam and atmosphere in the termination of described horizontal drainage pipe;Described horizontal stroke
It is connected with the flood discharge facility at Tailings Dam bottom by vertical cross over pipe to the stage casing of drainage pipe.
In the pipe network system of the invention described above, it is preferred that described a plurality of aqueduct is respectively from corresponding positioned at different
A plurality of horizontal drainage pipe connection at elevation, to form more ventilation passages.
In the pipe network system of the invention described above, it is preferred that described a plurality of horizontal drainage pipe is respectively by corresponding more
The vertical cross over pipe of bar is connected with the flood discharge facility, to ensure that whole pipe network system can send into the relative of more Tailings Dam bottoms of the reservior
High-temperature gas.
In the pipe network system of the invention described above, it is preferred that the described a plurality of horizontal drainage pipe arranged along different elevations passes through
Oblique cross over pipe is interconnected, and the oblique cross over pipe is at least connected with a vertical cross over pipe, bigger to form one
Gas flow loop passage, gas heat exchange area is bigger, and heat exchange is evenly.
In the pipe network system of the invention described above, it is preferred that the described a plurality of horizontal drainage pipe arranged along different elevations passes through
Oblique cross over pipe is interconnected, and the oblique cross over pipe keeps connecting with a plurality of vertical cross over pipe, so as to whole pipe network
System can be passed through the relatively-high temperature gas of more Tailings Dam bottoms of the reservior, and form a bigger gas channel, and gas heat exchange is more
Plus it is fully and uniform.
In the pipe network system of the invention described above, it is preferred that be correspondingly connected to the aqueduct of same horizontal drainage pipe and vertical
Cross over pipe intersects at same point with the horizontal drainage pipe, so that gas flow resistance is less, and it is convenient to construct.
In the pipe network system of the invention described above, it is preferred that be correspondingly connected to the aqueduct of same horizontal drainage pipe and vertical
Cross over pipe is intersected in the point of intersection of the horizontal drainage pipe and oblique cross over pipe, so that gas flow resistance is less, and constructs more
It is convenient.
In the pipe network system of the invention described above, it is preferred that the material of the oblique cross over pipe according to suffered structural load and
Ventilation is defined as being managed using PE;The material of the vertical cross over pipe is defined as adopting PE according to suffered structural load and ventilation
Pipe or concrete reinforced pipe;Diafiltration is evenly distributed with the aqueduct, horizontal drainage pipe, oblique cross over pipe and vertical cross over pipe logical
Pore, so that high-temperature gas uniformly penetrating accelerates the ablation of frozen soil in frozen soil layer.Aqueduct is opened in the pipe network system of the present invention
Hole, the general not perforate of conventional aqueduct and drainage pipe then perforate, this also has larger different from the present invention;Preferably, it is described
Not opening approach, or the percent opening of oblique cross over pipe and vertical cross over pipe can be also adopted on oblique cross over pipe and vertical cross over pipe
It is less than horizontal drainage pipe.Not perforate or perforate are less on oblique cross over pipe and vertical cross over pipe, are conducive to the High Temperature Gas of bottom
Body can as much as possible be transported to frozen soil layer, increase transfer of gas pressure and penetration, and the perforate on aqueduct is favourable
Accelerate the ablation of frozen soil in high-temperature gas uniformly penetrating to frozen soil layer.
Used as a total technology design, present invention also offers a kind of construction method of pipe network system, step is as follows:
1) after the flood discharge facility construction of tailings reservoir preliminary dam and bottom of the reservior is finished, start to pile up mine tailing and pre-buried vertical UNICOM
Pipe;
2) after it is higher than initial dam dam crest absolute altitude that mine tailing piles up absolute altitude, pre-buried first order aqueduct and horizontal drainage pipe, and
The horizontal drainage pipe for making the first order is just layed in frozen soil layer;Optionally pre-buried oblique cross over pipe;
3) with storehouse mine tailing pile up the rising of absolute altitude, aqueduct, vertical cross over pipe, horizontal drainage pipe and tiltedly are increased step by step
To the elevation and quantity of cross over pipe;Until completing the laying to whole pipe network system.
In the construction method of above-mentioned pipe network system, it is preferred that projection of the oblique cross over pipe on Tailings Dam vertical section
Linear or irregular curve, and horizontal drainage pipe at different levels is connected;The vertical cross over pipe is with horizontal drainage pipe in mine tailing
Projection on the cross section of storehouse is orthogonal thereto or oblique, and horizontal drainage pipe is connected with flood discharge facility;The horizontal drainage pipe laying
In with plane-parallel or incline certain angle plane in, and laterally drainage pipe is laid along the direction parallel to the axis of dam.
Compared with prior art, it is an advantage of the current invention that:
1) in ice period, because atmospheric temperature is relatively low, and air themperature is of a relatively high in the flood drainage system of bottom, the pipe network system
The presence of system, is conducive to improving the temperature of top layer mine tailing, slows down frozen soil and is formed, and reduces ice period frozen soil layer thickness, for some
Ice period shorter Tailings Dam, or even frozen soil layer can be eliminated.
2) after ice period terminates, frozen soil layer starts to melt, and bottom flood drainage system air can provide amount of heat, accelerates frozen soil
Melting layer, while can also accelerate the outer row of thawing water as the pipe network system in row's bleed-through road so that mine can take into account production
Benefit and Safety of Tailings Dam.
3) under certain conditions, such as ice period is long, produce the too big reason of pressure, and Tailings Dam does not wait until that frozen soil layer is complete
Ore drawing again after thawing, is now likely to form deep layer frozen soil layer, and then is converted into permanent freezing layer.After using the present invention, as long as
Possesses the pipe network system, the high-temperature gas in the flood drainage system of bottom can just be provided for a long term heat, be conducive to deep layer frozen soil layer
Melt, it is to avoid form permafrost.
4) present invention makes full use of the existing measures for draining leakage of Tailings Dam to build the pipe network system, easy construction, cost compared with
Little and effect is significant, with very high economic worth.
Description of the drawings
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are the present invention
Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can be with basis
These accompanying drawings obtain other accompanying drawings.
Fig. 1 is the vertical section schematic diagram that pipe network system shown in the embodiment of the present invention 1 is arranged in Tailings Dam.
Fig. 2 is the schematic cross section in Fig. 1 at A-A.
Fig. 3 is the vertical section schematic diagram that pipe network system shown in the embodiment of the present invention 2 is arranged in Tailings Dam.
Fig. 4 is the vertical section schematic diagram that pipe network system shown in the embodiment of the present invention 3 is arranged in Tailings Dam.
Marginal data
1st, initial dam;2nd, fill dam, 4, aqueduct;5th, deposit beach, 6, flood discharge facility;7th, frozen soil layer;10th, laterally row is oozed
Pipe;11st, oblique cross over pipe;12nd, vertical cross over pipe.
Specific embodiment
For the ease of understanding the present invention, more complete is made to the present invention below in conjunction with Figure of description and preferred embodiment
Face, meticulously describe, but protection scope of the present invention is not limited to embodiment in detail below.
It should be strongly noted that when a certain element, to be described as " be fixed on, be fixed in, be connected to or be communicated in " another
When on element, it can be directly fixed, affixed, connection or connect on another element, or by connecting in the middle of other
Fitting is indirectly fixed, affixed, connection or connection are on another element.
Unless otherwise defined, the implication that all technical terms used hereinafter are generally understood that with those skilled in the art
It is identical.Technical term used herein is intended merely to describe the purpose of specific embodiment, is not intended to limit the present invention
Protection domain.
Unless otherwise specified, various raw materials, reagent, instrument and equipment used in the present invention etc. can pass through city
Field is commercially available or can be prepared by existing method.
Embodiment 1
A kind of combination water seepage drainage facility as shown in Figure 1 and Figure 2 administers the pipe network system of Tailings Dam frozen soil, the pipe network system bag
Include aqueduct 4, horizontal drainage pipe 10, vertical cross over pipe 12 and the oblique cross over pipe 11 being embedded in Tailings Dam.The edge of aqueduct 4
Different elevations are provided with a plurality of, and connect from the corresponding a plurality of horizontal drainage pipe 10 at different elevations respectively, such as Fig. 2
Shown, Tailings Dam and atmosphere are extended in the termination of horizontal drainage pipe 10, a plurality of horizontal drainage pipe at different elevations
10 are interconnected by oblique cross over pipe 11, the horizontal drainage pipe 10 of vertical cross over pipe 12 connection bottom and Tailings Dam
Flood discharge facility 6.In the present embodiment, the aqueduct 4 and vertical cross over pipe 12 for being connected to same horizontal drainage pipe 10 is intersected in the horizontal stroke
To the point of intersection of drainage pipe 10 and oblique cross over pipe 11.
The construction procedure of the pipe network system in the present embodiment is as follows:
1) after the flood discharge facility 6 in tailings reservoir preliminary dam 1 and bottom of the reservior is built and finished, start to pile up mine tailing and pre-buried vertical
Siphunculus 12;
2) after it is higher than 1 dam crest absolute altitude of initial dam that mine tailing piles up absolute altitude, pre-buried first order aqueduct 4 and laterally drainage pipe
10, and the horizontal drainage pipe 10 of the first order is just layed in frozen soil layer 7;
3) with the rising of mine tailing accumulation absolute altitude in storehouse, aqueduct 4, horizontal drainage pipe 10 and oblique cross over pipe are increased step by step
11 elevation and quantity;Until completing the laying to whole pipe network system.
In the construction method of the present embodiment pipe network system, oblique cross over pipe 11 is managed with vertical cross over pipe 12 using PE, is led
Diafiltration passage, horizontal drainage pipe are evenly distributed with water pipe 4, horizontal drainage pipe 10, oblique cross over pipe 11 and vertical cross over pipe 12
10 are layed in the plane with plane-parallel, and laterally drainage pipe 10 is laid along the direction parallel to the axis of dam, oblique UNICOM
Linearly, vertical cross over pipe 12 is with horizontal drainage pipe 10 on Tailings Dam cross section for projection of the pipe 11 on Tailings Dam vertical section
Projection is orthogonal thereto.
In the present embodiment, a plurality of horizontal drainage pipe 10, a plurality of aqueduct 4, oblique cross over pipe 11 and vertical cross over pipe 12
Pipe network system is defined, in ice period, the air of the pipe network system connection lower temperature drains off floodwaters with the bottom with higher temperature
Air in system, is conducive to improving the temperature of top layer mine tailing, slows down frozen soil and is formed, and reduces ice period frozen soil layer thickness;Ice period
After end, frozen soil layer starts to melt, and bottom flood drainage system air can provide amount of heat, accelerates frozen soil melting layer, while the pipe
Net system is alternatively arranged as arranging bleed-through road, accelerates the outer row of thawing water so that mine can take into account productivity effect and Safety of Tailings Dam;
Additionally, if Tailings Dam possesses the pipe network system, the high-temperature gas in the flood drainage system of bottom can just be provided for a long term heat, be conducive to
The thawing of deep layer frozen soil layer, it is to avoid form permafrost.
Embodiment 2
A kind of combination water seepage drainage facility as shown in Figure 3 administers the pipe network system of Tailings Dam frozen soil, and the pipe network system includes burying
Aqueduct 4, horizontal drainage pipe 10 and vertical cross over pipe 12 in Tailings Dam.Aqueduct 4 be provided with along different elevations it is a plurality of,
And connect from the corresponding a plurality of horizontal drainage pipe 10 at different elevations respectively, the termination of horizontal drainage pipe 10 extends
Go out Tailings Dam and atmosphere, a plurality of horizontal drainage pipe 10 is respectively by corresponding a plurality of vertical cross over pipe 12 and Tailings Dam
Flood discharge facility 6 is connected.In the present embodiment, it is connected to the aqueduct 4 and vertical cross over pipe 12 of same horizontal drainage pipe 10 and is somebody's turn to do
Laterally drainage pipe 10 intersects at same point.
The construction procedure of the pipe network system in the present embodiment is as follows:
1) after the flood discharge facility 6 in tailings reservoir preliminary dam 1 and bottom of the reservior is built and finished, start to pile up mine tailing and pre-buried vertical
Siphunculus 12;
2) after it is higher than 1 dam crest absolute altitude of initial dam that mine tailing piles up absolute altitude, pre-buried first order aqueduct 4 and laterally drainage pipe
10, and the horizontal drainage pipe 10 of the first order is just layed in frozen soil layer 7;
3) with the rising of mine tailing accumulation absolute altitude in storehouse, aqueduct 4, horizontal drainage pipe 10 and vertical cross over pipe are increased step by step
12 elevation and quantity;Until completing the laying to whole pipe network system.
In the construction method of the present embodiment pipe network system, vertical cross over pipe 12 is managed using PE, aqueduct 4, horizontal drainage pipe
10 and vertical cross over pipe 12 on be evenly distributed with diafiltration passage, horizontal drainage pipe 10 is layed in the plane with plane-parallel,
And laterally drainage pipe 10 is laid along the direction parallel to the axis of dam, vertical cross over pipe 12 is cross-sectional in Tailings Dam with horizontal drainage pipe 10
Projection on face is orthogonal thereto.
In the present embodiment, a plurality of horizontal drainage pipe 10, a plurality of vertical cross over pipe 12 and a plurality of aqueduct 4 define pipe network
System, the air within ice period, the air and the bottom flood drainage system with higher temperature of the pipe network system connection lower temperature,
Be conducive to improving the temperature of top layer mine tailing, slow down frozen soil and formed, reduce ice period frozen soil layer thickness;After ice period terminates, frozen soil
Layer starts to melt, and bottom flood drainage system air can provide amount of heat, accelerates frozen soil melting layer, while the pipe network system can also be made
To arrange bleed-through road, accelerate the outer row of thawing water so that mine can take into account productivity effect and Safety of Tailings Dam;If additionally, mine tailing
Storehouse possesses the pipe network system, and the high-temperature gas in the flood drainage system of bottom can just be provided for a long term heat, be conducive to deep layer frozen soil layer
Thawing, it is to avoid formed permafrost.
Embodiment 3
A kind of combination water seepage drainage facility as shown in Figure 4 administers the pipe network system of Tailings Dam frozen soil, and the pipe network system includes burying
Aqueduct 4, horizontal drainage pipe 10, vertical cross over pipe 12 and oblique cross over pipe 11 in Tailings Dam.Aqueduct 4 is along difference
Elevation is provided with a plurality of, and connects from the corresponding a plurality of horizontal drainage pipe 10 at different elevations respectively, and laterally row is oozed
Tailings Dam and atmosphere are extended in the termination of pipe 10, and a plurality of horizontal drainage pipe 10 is interconnected by oblique cross over pipe 11, and
A plurality of horizontal drainage pipe 10 is connected respectively by corresponding a plurality of vertical cross over pipe 12 with the flood discharge facility 6 of Tailings Dam.This
In embodiment, be connected to same horizontal drainage pipe 10 aqueduct 4 and vertical cross over pipe 12 be intersected in the horizontal drainage pipe 10 with
The point of intersection of oblique cross over pipe 11.
The construction procedure of the pipe network system in the present embodiment is as follows:
1) after the flood discharge facility 6 in tailings reservoir preliminary dam 1 and bottom of the reservior is built and finished, start to pile up mine tailing and pre-buried vertical
Siphunculus 12;
2) after it is higher than 1 dam crest absolute altitude of initial dam that mine tailing piles up absolute altitude, pre-buried first order aqueduct 4 and laterally drainage pipe
10, and the horizontal drainage pipe 10 of the first order is just layed in frozen soil layer 7;
3) with the rising of mine tailing accumulation absolute altitude (referring mainly to fill dam 2) in storehouse, aqueduct 4, vertical UNICOM are increased step by step
The elevation and quantity of pipe 12, horizontal drainage pipe 10 and oblique cross over pipe 11;Until completing the laying to whole pipe network system.
In the construction method of the present embodiment pipe network system, oblique cross over pipe 11 is managed using PE, and vertical cross over pipe 12 adopts steel
Reinforced concrete pipe, on aqueduct 4, horizontal drainage pipe 10, oblique cross over pipe 11 and vertical cross over pipe 12 diafiltration ventilation is evenly distributed with
Hole (on oblique cross over pipe 11 and vertical cross over pipe 12 also can not perforate), horizontal drainage pipe 10 is layed in flat with plane-parallel
In face, and laterally drainage pipe 10 is laid along the direction parallel to the axis of dam, throwing of the oblique cross over pipe 11 on Tailings Dam vertical section
Linearly, projection of the vertical cross over pipe 12 with horizontal drainage pipe 10 on Tailings Dam cross section is orthogonal thereto for shadow.
In the present embodiment, a plurality of horizontal drainage pipe 10, a plurality of vertical cross over pipe 12, a plurality of aqueduct 4 and oblique UNICOM
Pipe 11 defines pipe network system, in ice period, the air of the pipe network system connection lower temperature and the bottom with higher temperature
Air in flood drainage system, is conducive to improving the temperature of top layer mine tailing, slows down frozen soil and is formed, and reduces ice period frozen soil layer thickness;Ice
After the jelly phase terminates, frozen soil layer starts to melt, and bottom flood drainage system air can provide amount of heat, accelerates frozen soil melting layer, while
The pipe network system is alternatively arranged as arranging bleed-through road, accelerates the outer row of thawing water so that mine can take into account productivity effect and Tailings Dam
Safety;Additionally, if Tailings Dam possesses the pipe network system, the high-temperature gas in the flood drainage system of bottom can just be provided for a long term heat,
Be conducive to the thawing of deep layer frozen soil layer, prevent from depositing the formation ore pulp Freezing block of beach 5 and floating ice layer, it is to avoid form permafrost.
Claims (10)
1. a kind of combination water seepage drainage facility administers the pipe network system of Tailings Dam frozen soil, and the pipe network system includes being embedded in Tailings Dam
Aqueduct (4), horizontal drainage pipe (10) and vertical cross over pipe (12), described aqueduct (4) be provided with along different elevations it is a plurality of,
It is characterized in that:A plurality of described aqueduct (4) is at least connected with a horizontal drainage pipe (10), described horizontal drainage pipe
(10) Tailings Dam and atmosphere are extended in termination, and the stage casing of described horizontal drainage pipe (10) passes through vertical cross over pipe (12)
It is connected with the flood discharge facility (6) at Tailings Dam bottom.
2. combination water seepage drainage facility according to claim 1 administers the pipe network system of Tailings Dam frozen soil, it is characterised in that:It is a plurality of
Described aqueduct (4) is connected respectively from the corresponding a plurality of horizontal drainage pipe (10) at different elevations.
3. combination water seepage drainage facility according to claim 2 administers the pipe network system of Tailings Dam frozen soil, it is characterised in that:It is described
A plurality of horizontal drainage pipe (10) be connected with the flood discharge facility (6) by corresponding a plurality of vertical cross over pipe (12) respectively
It is logical.
4. combination water seepage drainage facility according to claim 2 administers the pipe network system of Tailings Dam frozen soil, it is characterised in that:Along not
The described a plurality of horizontal drainage pipe (10) arranged with elevation is interconnected by oblique cross over pipe (11), the oblique cross over pipe
(11) at least it is connected with a vertical cross over pipe (12).
5. combination water seepage drainage facility according to claim 3 administers the pipe network system of Tailings Dam frozen soil, it is characterised in that:Along not
The described a plurality of horizontal drainage pipe (10) arranged with elevation is interconnected by oblique cross over pipe (11), described oblique cross over pipe
(11) keep connecting with described a plurality of vertical cross over pipe (12).
6. combination water seepage drainage facility according to claim 3 administers the pipe network system of Tailings Dam frozen soil, it is characterised in that:Correspondence
The aqueduct (4) and vertical cross over pipe (12) and the horizontal drainage pipe (10) for being connected to same horizontal drainage pipe (10) is intersected at together
A bit.
7. the combination water seepage drainage facility according to claim 4 or 5 administers the pipe network system of Tailings Dam frozen soil, it is characterised in that:
The aqueduct (4) and vertical cross over pipe (12) for being correspondingly connected to same horizontal drainage pipe (10) is intersected in the horizontal drainage pipe (10)
With the point of intersection of oblique cross over pipe (11).
8. the combination water seepage drainage facility according to any one of claim 4-6 administers the pipe network system of Tailings Dam frozen soil, and it is special
Levy and be:The material of the oblique cross over pipe (11) is managed using PE;The material of the vertical cross over pipe (12) is managed or steel using PE
Reinforced concrete pipe;It is uniform on the aqueduct (4), horizontal drainage pipe (10), oblique cross over pipe (11) and vertical cross over pipe (12)
It is furnished with diafiltration passage.
9. a kind of construction method of the pipe network system as any one of claim 1-8, it is characterised in that:Including following step
Suddenly:
1) after the flood discharge facility (6) in tailings reservoir preliminary dam (1) and bottom of the reservior is built and finished, start to pile up mine tailing and pre-buried vertical
Siphunculus (12);
2) after it is higher than initial dam (1) dam crest absolute altitude that mine tailing piles up absolute altitude, pre-buried first order aqueduct (4) and laterally drainage pipe
(10), and the horizontal drainage pipe (10) of the first order is made just to be layed in frozen soil layer (7);Optionally pre-buried oblique cross over pipe
(11);
3) with the rising of mine tailing accumulation absolute altitude in storehouse, aqueduct (4), vertical cross over pipe (12), horizontal drainage pipe are increased step by step
(10) and oblique cross over pipe (11) elevation and quantity;Until completing the laying to whole pipe network system.
10. construction method according to claim 9, it is characterised in that:The oblique cross over pipe (11) is in Tailings Dam vertical profile
Projection on face linearly or irregular curve, and horizontal drainage pipe (10) at different levels is connected;The vertical cross over pipe (12)
Or oblique orthogonal thereto with projection of the horizontal drainage pipe (10) on Tailings Dam cross section, and horizontal drainage pipe (10) is set with drainning off floodwaters
Apply (6) connection;The horizontal drainage pipe (10) is layed in plane-parallel or is inclined in the plane of an angle, and laterally row is oozed
Pipe (10) is laid along the direction parallel to the axis of dam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710104101.7A CN106677229B (en) | 2017-02-24 | 2017-02-24 | The pipe network system and its construction method of Tailings Dam frozen soil are administered in conjunction with water seepage drainage facility |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710104101.7A CN106677229B (en) | 2017-02-24 | 2017-02-24 | The pipe network system and its construction method of Tailings Dam frozen soil are administered in conjunction with water seepage drainage facility |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106677229A true CN106677229A (en) | 2017-05-17 |
CN106677229B CN106677229B (en) | 2018-09-28 |
Family
ID=58862753
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710104101.7A Active CN106677229B (en) | 2017-02-24 | 2017-02-24 | The pipe network system and its construction method of Tailings Dam frozen soil are administered in conjunction with water seepage drainage facility |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106677229B (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108104057A (en) * | 2017-12-14 | 2018-06-01 | 湖南中大经纬地热开发科技有限公司 | Self-cleaning heat exchange type tailing dam |
CN108104077A (en) * | 2017-12-14 | 2018-06-01 | 湖南中大经纬地热开发科技有限公司 | From derusting tailing dam drainage system |
CN108914879A (en) * | 2018-07-19 | 2018-11-30 | 兰州有色冶金设计研究院有限公司 | A kind of frame-type row infiltration system and method |
CN110158665A (en) * | 2019-04-03 | 2019-08-23 | 中节能大地环境修复有限公司 | Tailings Dam leachate collecting device and percolation liquid treating system |
CN110499814A (en) * | 2018-05-17 | 2019-11-26 | 南京梅山冶金发展有限公司 | The row for reducing saturation line of tailings pond buried depth seeps system layer method for arranging |
CN112575870A (en) * | 2019-09-29 | 2021-03-30 | 沈阳铝镁设计研究院有限公司 | Dam body seepage drainage facility arrangement structure for wet-method discharge tailing pond and construction method |
CN112982318A (en) * | 2021-03-11 | 2021-06-18 | 金建工程设计有限公司 | System combining bottom drainage and flood drainage facilities |
CN113882491A (en) * | 2021-10-14 | 2022-01-04 | 中钢集团马鞍山矿山研究总院股份有限公司 | Method for reducing infiltration line of tailing pond or phosphogypsum pond |
CN114427214A (en) * | 2022-03-07 | 2022-05-03 | 中冶长天国际工程有限责任公司 | Dam foundation reservoir bottom seepage-proofing paving structure and building method thereof |
CN114439090A (en) * | 2021-10-14 | 2022-05-06 | 中钢集团马鞍山矿山研究总院股份有限公司 | Interception, drainage and seepage structure for reducing seepage line of tailing pond or phosphogypsum pond |
CN117161636A (en) * | 2023-11-03 | 2023-12-05 | 矿冶科技集团有限公司 | Arrange and ooze nest of tubes system of processing |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1782280A3 (en) * | 1989-11-13 | 1992-12-15 | Чepeпobeцkoe Пpoизboдctbehhoe Oб'eдиhehиe "Ammoфoc" | Method of clearing slurry sump from pyrite cinders |
WO2014000069A2 (en) * | 2012-06-26 | 2014-01-03 | Manancial Projetos E Consultoria Ambiental Ltda. | Process of environmental recovery of inactive and exhausted mining areas, and use of mining and/or drilling residues in the environmental recovery of inactive and exhausted mining areas |
CN103615042A (en) * | 2013-11-28 | 2014-03-05 | 化工部长沙设计研究院 | Network type seepage discharging device in transverse direction, longitudinal direction and vertical direction |
CN103938658A (en) * | 2014-04-04 | 2014-07-23 | 同济大学 | Structure capable of avoiding cold damage to high-temperature and unstable freeze soil area tunnel portal side slope |
CN104213627A (en) * | 2014-09-04 | 2014-12-17 | 兰州有色冶金设计研究院有限公司 | Three-dimensional tailing pond seepage system and seepage method thereof |
CN206784452U (en) * | 2017-02-24 | 2017-12-22 | 中冶长天国际工程有限责任公司 | The pipe network system of Tailings Dam frozen soil is administered with reference to water seepage drainage facility |
-
2017
- 2017-02-24 CN CN201710104101.7A patent/CN106677229B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1782280A3 (en) * | 1989-11-13 | 1992-12-15 | Чepeпobeцkoe Пpoизboдctbehhoe Oб'eдиhehиe "Ammoфoc" | Method of clearing slurry sump from pyrite cinders |
WO2014000069A2 (en) * | 2012-06-26 | 2014-01-03 | Manancial Projetos E Consultoria Ambiental Ltda. | Process of environmental recovery of inactive and exhausted mining areas, and use of mining and/or drilling residues in the environmental recovery of inactive and exhausted mining areas |
CN103615042A (en) * | 2013-11-28 | 2014-03-05 | 化工部长沙设计研究院 | Network type seepage discharging device in transverse direction, longitudinal direction and vertical direction |
CN103938658A (en) * | 2014-04-04 | 2014-07-23 | 同济大学 | Structure capable of avoiding cold damage to high-temperature and unstable freeze soil area tunnel portal side slope |
CN104213627A (en) * | 2014-09-04 | 2014-12-17 | 兰州有色冶金设计研究院有限公司 | Three-dimensional tailing pond seepage system and seepage method thereof |
CN206784452U (en) * | 2017-02-24 | 2017-12-22 | 中冶长天国际工程有限责任公司 | The pipe network system of Tailings Dam frozen soil is administered with reference to water seepage drainage facility |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108104077A (en) * | 2017-12-14 | 2018-06-01 | 湖南中大经纬地热开发科技有限公司 | From derusting tailing dam drainage system |
CN108104057A (en) * | 2017-12-14 | 2018-06-01 | 湖南中大经纬地热开发科技有限公司 | Self-cleaning heat exchange type tailing dam |
CN110499814A (en) * | 2018-05-17 | 2019-11-26 | 南京梅山冶金发展有限公司 | The row for reducing saturation line of tailings pond buried depth seeps system layer method for arranging |
CN108914879A (en) * | 2018-07-19 | 2018-11-30 | 兰州有色冶金设计研究院有限公司 | A kind of frame-type row infiltration system and method |
CN110158665B (en) * | 2019-04-03 | 2024-03-01 | 中节能大地环境修复有限公司 | Percolate collecting device for tailing pond and percolate treatment system |
CN110158665A (en) * | 2019-04-03 | 2019-08-23 | 中节能大地环境修复有限公司 | Tailings Dam leachate collecting device and percolation liquid treating system |
CN112575870A (en) * | 2019-09-29 | 2021-03-30 | 沈阳铝镁设计研究院有限公司 | Dam body seepage drainage facility arrangement structure for wet-method discharge tailing pond and construction method |
CN112982318A (en) * | 2021-03-11 | 2021-06-18 | 金建工程设计有限公司 | System combining bottom drainage and flood drainage facilities |
CN114439090A (en) * | 2021-10-14 | 2022-05-06 | 中钢集团马鞍山矿山研究总院股份有限公司 | Interception, drainage and seepage structure for reducing seepage line of tailing pond or phosphogypsum pond |
CN113882491A (en) * | 2021-10-14 | 2022-01-04 | 中钢集团马鞍山矿山研究总院股份有限公司 | Method for reducing infiltration line of tailing pond or phosphogypsum pond |
CN114427214A (en) * | 2022-03-07 | 2022-05-03 | 中冶长天国际工程有限责任公司 | Dam foundation reservoir bottom seepage-proofing paving structure and building method thereof |
CN114427214B (en) * | 2022-03-07 | 2023-12-29 | 中冶长天国际工程有限责任公司 | Dam foundation reservoir bottom seepage-proofing paving structure and construction method thereof |
CN117161636A (en) * | 2023-11-03 | 2023-12-05 | 矿冶科技集团有限公司 | Arrange and ooze nest of tubes system of processing |
CN117161636B (en) * | 2023-11-03 | 2024-01-19 | 矿冶科技集团有限公司 | Arrange and ooze nest of tubes system of processing |
Also Published As
Publication number | Publication date |
---|---|
CN106677229B (en) | 2018-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106677229B (en) | The pipe network system and its construction method of Tailings Dam frozen soil are administered in conjunction with water seepage drainage facility | |
CN204023501U (en) | A remove dangerous and consolidate prevention of seepage processing structure for earth and rockfill dam | |
WO2008061415A1 (en) | A hydraulic sliding insertion panel and its using method | |
CN202483588U (en) | Self water-proof drainage system of tunnel lining | |
CN206419017U (en) | Shallow tunnel with big cross-section freezing underground excavation constructing structure | |
CN208701440U (en) | A kind of antifreeze drainage system of seasonal frost region side slope of embankment | |
CN206204901U (en) | A kind of accurate heating and anti-freezing anti-seepage channel | |
CN105297690A (en) | Fish passage facility for rock-fill dam and manufacturing method of fish passage facility | |
CN104652371A (en) | Overflow cemented rock-fill dam established based on old dam and construction method thereof | |
CN106592346A (en) | Head chute separated type ballastless track cutting bed structure for middle-strong salinized soil areas | |
CN205591075U (en) | Ecology structure of mating formation | |
CN205134303U (en) | Compound reinforced structure of soft base of ecological bamboo raft among road engineering of field | |
CN102425175B (en) | Reinforcement protective structure of large spoil disposal area in mountainous area | |
CN206784452U (en) | The pipe network system of Tailings Dam frozen soil is administered with reference to water seepage drainage facility | |
CN106149640B (en) | A method of it improving rock and permeates safety | |
CN206784355U (en) | For administering the pipe network system of frozen soil in Tailings Dam | |
CN105735206B (en) | The reparation structure and construction method of severe cold area morbid state concrete gravity dam | |
CN201099920Y (en) | Heat preservation collecting well | |
CN203229849U (en) | Highway excavation roadbed of road segment rich in ice, full of ice and containing soil-ice layer | |
CN205152914U (en) | A fish pass structure for rock -fill dam | |
CN207672344U (en) | Railway bed karez location pin-connected panel foundation stabilization construction | |
CN208167421U (en) | A kind of underground water cutting location Ballast track high-speed railway anti-freeze expansion road structure | |
CN106759232B (en) | Pipe network system and its construction method for administering frozen soil in Tailings Dam | |
CN102031742A (en) | roadbed longitudinal crack treatment method based on convex tenon type cement grouting geomembrane belt | |
CN205711985U (en) | The reparation structure of severe cold area morbid state concrete gravity dam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |