CN106655058A - Multi-dimensional snow and ice removal device of power network and application method thereof - Google Patents
Multi-dimensional snow and ice removal device of power network and application method thereof Download PDFInfo
- Publication number
- CN106655058A CN106655058A CN201611147959.3A CN201611147959A CN106655058A CN 106655058 A CN106655058 A CN 106655058A CN 201611147959 A CN201611147959 A CN 201611147959A CN 106655058 A CN106655058 A CN 106655058A
- Authority
- CN
- China
- Prior art keywords
- framework
- electrical network
- ice removal
- snow
- removes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/16—Devices for removing snow or ice from lines or cables
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The present invention relates to a multi-dimensional snow and ice removal device of a power network and an application method thereof, pertaining to the technical field of power maintenance equipment. The device includes a frame; an opening is arranged on one side of the frame and used for placing wires into the frame; two rollers are arranged in the frame, the middle surface of each roller is concave relative to both ends of the roller, so that the roller can be put on the wire to roll and drive the device to move while remaining stable; and two positions, on both sides of each roller, on the frame are both provided with arc hoops, wherein the arc hoops are linked with the frame via cylinders, one side of each arc hoop is a blade edge. The working method of the device comprises the steps of placing the wires under the rollers inside the frame from the opening, clamping the wires via the arc hoops by controlling the cylinders, moving the device and carrying out deicing operation by using the blade edges of the arc hoops. The multi-dimensional snow and ice removal device of the power network has the advantages of operation easiness, good effect for deicing, high adaptability(especially in a double-line condition), convenience for carrying and on-site installation, saving of manpower and material cost and reducing of the probability of accidental injuries to an operator.
Description
Technical field
The present invention relates to a kind of electrical network multidimensional snow removing ice removal and its application process, belong to electric power maintenance equipment and technology neck
Domain.
Background technology
With the popularization and development of power communication, the popularization area of national high pressure gauze constantly expands, and China is vast in territory,
Circuit passes through different geographical environments, is alternately affected by part territorial environment and the four seasons, and gauze can meet with low temperature and ice and snow day
Gas.
Prolonged low temperature and sleet can on the net form frost in high-voltage line, can cause to fall line after icing is serious, collapse, break
The failures such as line, cause the accidents such as tripping operation, power failure, not only cause equipment economic loss to national grid, the life for also giving people
Produce work to impact.
During generation low temperature ice disaster, power department can discharge manpower and materials and the circuit in disaster area is safeguarded and robbed
Repair, to minimize disaster impact before further seriously.
Deicing generally has the physics deicing mode different with chemical deicing, the disclosure of Chinese patent document 201520705008.8
A kind of deicing of high voltage wire device, scheme including walking mechanism front end is disposed with runout mechanism and hammer mechanism;Hammer machine
Structure includes that clip hits bar and adjusting gear rack, and adjusting gear rack two ends are respectively arranged with regulating bolt and unidirectional spring, unidirectional spring
The other end be arranged on clip strike bar on slide block be fixed together;Runout mechanism includes that the triangle with a leg connects
Bar, active wheel, support wheel and traction wheel;Active wheel is arranged on a drift angle of delta link, and active wheel connects with support wheel
Connect, support wheel is arranged at another drift angle of delta link, traction wheel is arranged on the leg end of delta link.China
Patent document 201620547889.X discloses a kind of towed deicing of high-voltage wires car, and deicing vehicle adopts storage battery power supply, walking
With driving Rear wheel suspension on high-tension bus-bar, the sprocket wheel connects direct current generator and cutter shaft and drives trailing wheel, the sprocket wheel recessed wheel
Between connected by chain, the sleeve bottom has magnet, and the upper tapered end is connected with upper boom, the upper boom and electromagnetism iron phase
Connect, and sleeve internal insulation into two mobile inner regions, the outer bar is fixed on outside sleeve.In currently available technology, deicing dress
Put mostly relatively complicated, ice removal is accommodated on electric wire, the quality of ice removal can increase the weight-bearing load of electrical network, and remove at present
It is directed to single grid line more ice device, if having split conductor or support between adjacent grid line, deicing operation may be hindered.
The content of the invention
For the deficiencies in the prior art, the present invention provides a kind of electrical network multidimensional snow removing ice removal.
The present invention also provides the application process of said apparatus.
Technical scheme is as follows:
A kind of electrical network multidimensional snow removing ice removal, including framework, framework is while be provided with opening, opening is electric wire to be placed into
In framework, two rollers are provided with framework, roller middle part surface is recessed in roller two ends so that roller can be positioned on electric wire and roll
Dynamic, driving device is walked and keeps certain and stablize, and the framework of roller both sides is provided with arc hoop, and arc hoop is by cylinder and frame
Frame is connected, and arc hoop side is sword side.At the roller that electric wire is placed in framework from opening, control cylinder makes arc hoop clip
On electric wire, mobile this device carries out anti-ice operation using the sword side of arc hoop.
According to currently preferred, framework is triangle-frame, and the cross section of framework is triangle.
It is further preferred that triangle is equilateral triangle.Maintain balance, operation stable with more preferable.
It is further preferred that triangle-frame does not set be arranged with one side of opening two rollers.The present invention is set to act on
In the deicing of two electric wires, and the structure of the present invention is utilized, the wire or support between usual two electric wires can't affect this to fill
The deicing operation put.
According to currently preferred, heating wire is provided with roller.Heating wire can tentatively melt on the electric wire with roller-contact
Ice and snow, aid in deicing.
According to currently preferred, guide post is provided with the outside of framework, the electrical network multidimensional snow removing ice removal also includes movement
Band and movable case, guide post is connected with movable case, and movable case is located on moving belt, and moving belt is connected with motor, and moving belt is located at
Between two neighboring electric power supporting tower, where Uneven road or massif are rugged, needing between the electric wire tower of deicing, by electricity
Transmission tower or other objects of reference arrange moving belt and movable case, are rotated by Motor drive moving belt, movable case movement are driven, so as to logical
Cross guide post and drive deicing operation;Or, framework outside is provided with guide post, the electrical network multidimensional snow removing ice removal also includes that movement is little
Car, guide post is connected with moving cart.Where road surface is relatively put down or be open, can be substituted using moving cart and build moving belt.
It is further preferred that guide post includes two connected loop bars.The scalable setting of loop bar, makes height adjustable.
It is further preferred that electrical network multidimensional snow removing ice removal also includes control device, control device by wire with
Cylinders.Cylinder can afterwards be controlled in place in electric wire by operating personnel promotes arc hoop to be stuck on electric wire.
According to currently preferred, each roller both sides is respectively provided with an arc hoop.Arc hoop is flexible by cylinder control, and two
Individual arc hoop can cover most of area of electric wire, add the contact surface of roller, and the electric wire for making has deicing action, Quan Fang in one week
Position deicing operation.
It is further preferred that arc hoop is located at framework inner side.The center of gravity for making whole device maintains framework inboard, beneficial to guarantor
Maintain an equal level weighing apparatus.
According to currently preferred, the electrical network multidimensional snow removing ice removal is also included except ice hammer, except ice hammer by cylinder with
Framework is connected.Increase except the ice on electric wire can be abolished a part by ice hammer in advance before the deicing of sword side, aid in deicing, make deicing
Effect is more preferable.
It is further preferred that except ice hammer is located at framework outside, cylinder is connected with control device.Make except ice hammer first acts on knot
Ice, acts on icing behind sword side, coordinate deicing.
According to currently preferred, framework is aluminum frame.The weight for alloing this device lighter completes deicing operation, together
When can ensure that certain intensity adapts to different environment.
A kind of electrical network multidimensional removes the snow the application process of ice removal, including step is as follows:
(1) electrical network multidimensional snow removing ice removal includes framework, and framework is provided with opening, and mobility framework makes electric wire enter by opening
In framework;
(2) place the wires under roller, control cylinder promotes arc hoop, makes arc hoop clip on electric wire;
(3) drive electrical network multidimensional snow removing ice removal to move along electric wire, carry out deicing operation.
According to currently preferred, in step (2), also include, by cylinder control except ice hammer is moved back and forth, act on knot
On ice.
The beneficial effects of the present invention is:
Technical scheme simple structure, it is easy to operate, make full use of the different structure of space utilization to freeze into
Row layering subjob, deicing effect is good, and installation weight is light, can reduce the secondary injury to electric wire.Strong adaptability, is suitable for difference
High-tension bus-bar environment, be specially adapted to two-wire, the attachment between two-wire does not interfere with the deicing operation of this device, is easy to carry
And in-site installation, install convenient, use manpower and material resources sparingly cost, reduces the unexpected injury probability of operating personnel.
Description of the drawings
Fig. 1 is deicer schematic front view of the present invention;
Fig. 2 is that deicer of the present invention is right regards schematic diagram;
Fig. 3 is deicer of the present invention and gauze line bar coordinating operation schematic diagram;
Wherein:1st, framework, 2, roller, 3, arc hoop, 3-1, sword side, 4, cylinder, 5, guide post, 6, moving belt, 7, mobile
Case, 8, right angle frame, 9, electric wire, 10, line bar.
Specific embodiment
Below by embodiment and combine accompanying drawing the present invention will be further described, but not limited to this.
As Figure 1-3.
Embodiment 1:
A kind of electrical network multidimensional snow removing ice removal, including framework, framework is while be provided with opening, opening is electric wire to be placed into
In framework, two rollers are provided with framework, roller middle part surface is recessed in roller two ends so that roller can be positioned on electric wire and roll
Dynamic, driving device is walked and keeps certain and stablize, and the framework of roller both sides is provided with arc hoop, and arc hoop is by cylinder and frame
Frame is connected, and arc hoop side is sword side.At the roller that electric wire is placed in framework from opening, control cylinder makes arc hoop clip
On electric wire, mobile this device carries out anti-ice operation using the sword side of arc hoop.
Framework is triangle-frame, and the cross section of framework is triangle.
Triangle-frame does not set and be arranged with one side of opening two rollers.The present invention is set to may act on removing for two electric wires
Ice, and the structure of the present invention is utilized, the wire or support between usual two electric wires can't affect the deicing operation of this device.
Framework is aluminum frame.The weight for alloing this device lighter completes deicing operation, while can ensure that certain
Intensity adapts to different environment.
Embodiment 2:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, triangle is equilateral three
It is angular.Maintain balance, operation stable with more preferable.
Embodiment 3:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, electric heating is provided with roller
Silk.Heating wire can tentatively melt the ice and snow on the electric wire with roller-contact, aid in deicing.
Embodiment 4:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, framework outside is provided with leads
To bar, the electrical network multidimensional snow removing ice removal also includes moving belt and movable case, and guide post is connected with movable case, and movable case is located at
On moving belt, moving belt is connected with motor, and moving belt is rugged in Uneven road or massif between two neighboring electric power supporting tower
Where rugged, needing to arrange moving belt and movable case between the electric wire tower of deicing, by electric wire tower or other objects of reference, by motor
Drive moving belt to rotate, drive movable case movement, so as to drive deicing operation by guide post.
Embodiment 5:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, framework outside is provided with leads
To bar, the electrical network multidimensional snow removing ice removal also includes moving cart, and guide post is connected with moving cart.Relatively put down or open on road surface
Where wealthy, can be substituted using moving cart and build moving belt.
Embodiment 6:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 4, except that, guide post includes two
Connected loop bar.The scalable setting of loop bar, makes height adjustable.
Embodiment 7:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, the electrical network multidimensional is removed
Snow and ice device also includes control device, and control device is by wire and cylinders.Can afterwards be controlled in place in electric wire by operating personnel
Cylinder processed promotes arc hoop to be stuck on electric wire.
Embodiment 8:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, each roller both sides is each
It is provided with an arc hoop.Arc hoop is flexible by cylinder control, and two arc hoops can cover most of area of electric wire, add roller
Contact surface, the electric wire for making has deicing action, comprehensive deicing operation for one week.
Located at framework inner side, the center of gravity for making whole device maintains framework inboard to arc hoop, beneficial to holding balance.
Embodiment 9:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 1, except that, the electrical network multidimensional is removed
Snow and ice device is also included except ice hammer, except ice hammer is connected by cylinder with framework, increases except ice hammer can in advance will before the deicing of sword side
Ice on electric wire abolishes a part, aids in deicing, makes deicing effect more preferable.
Embodiment 10:
A kind of electrical network multidimensional removes the snow ice removal, its structure with described in embodiment 9, except that, except ice hammer is located at framework
Outside, cylinder is connected with control device, as shown in Fig. 2 framework outside is provided with right angle frame, right angle frame one end is connected with framework, directly
The corner bracket other end passes through cylinder and is connected except ice hammer, freezes on the vertical plane below electric wire, and removes ice hammer positioned at horizontal plane
On so that except ice hammer can act perpendicularly to freeze, and except ice hammer first acts on icing, icing is acted on behind sword side, cooperation is removed
Ice, increases effect injury of the reduction to electric wire simultaneously.
Embodiment 11:
Electrical network multidimensional described in a kind of utilization embodiment 10 removes the snow the application process of ice removal, including step is as follows:
(1) electrical network multidimensional snow removing ice removal includes framework, and framework is provided with opening, and mobility framework makes electric wire enter by opening
In framework;
(2) place the wires under roller, control cylinder promotes arc hoop, makes arc hoop clip on electric wire;Step (2)
In, also include, by cylinder control except ice hammer is moved back and forth, act in icing;
(3) drive electrical network multidimensional snow removing ice removal to move along electric wire, carry out deicing operation.
Claims (10)
1. a kind of electrical network multidimensional removes the snow ice removal, it is characterised in that including framework, and framework is provided with while be provided with opening in framework
Two rollers, roller middle part surface is recessed in roller two ends, and the framework of roller both sides is provided with arc hoop, arc hoop by cylinder with
Framework is connected, and arc hoop side is sword side.
2. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that framework is triangle-frame, framework
Cross section is triangle;Preferably, triangle is equilateral triangle.
3. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that triangle-frame does not set one side of opening
On be arranged with two rollers;Preferably, it is provided with heating wire in roller.
4. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that framework outside is provided with guide post, institute
Stating electrical network multidimensional snow removing ice removal also includes moving belt and movable case, and guide post is connected with movable case, and movable case is located at moving belt
On, moving belt is connected with motor, and moving belt is between two neighboring electric power supporting tower;Or, framework outside is provided with guide post, institute
Stating electrical network multidimensional snow removing ice removal also includes moving cart, and guide post is connected with moving cart.
5. electrical network multidimensional according to claim 4 removes the snow ice removal, it is characterised in that guide post includes two connected sets
Bar.
6. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that the electrical network multidimensional removes the snow ice removal
Also include control device, control device is by wire and cylinders.
7. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that each roller both sides is respectively provided with one
Arc hoop;Preferably, arc hoop is located at framework inner side.
8. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that the electrical network multidimensional removes the snow ice removal
Also include except ice hammer, except ice hammer is connected by cylinder with framework;Preferably, except ice hammer is located at framework outside, cylinder and control dress
Put connected.
9. electrical network multidimensional according to claim 1 removes the snow ice removal, it is characterised in that framework is aluminum frame.
10. a kind of application process of electrical network multidimensional snow removing ice removal, including step is as follows:
(1) electrical network multidimensional snow removing ice removal includes framework, and framework is provided with opening, and mobility framework makes electric wire enter framework by opening
It is interior;
(2) place the wires under roller, control cylinder promotes arc hoop, makes arc hoop clip on electric wire;Preferably, step
(2) in, also include, by cylinder control except ice hammer is moved back and forth, act in icing;
(3) drive electrical network multidimensional snow removing ice removal to move along electric wire, carry out deicing operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611147959.3A CN106655058B (en) | 2016-12-13 | 2016-12-13 | Power grid multidimensional snow removing ice removal and its application process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611147959.3A CN106655058B (en) | 2016-12-13 | 2016-12-13 | Power grid multidimensional snow removing ice removal and its application process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106655058A true CN106655058A (en) | 2017-05-10 |
CN106655058B CN106655058B (en) | 2018-11-02 |
Family
ID=58825865
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611147959.3A Expired - Fee Related CN106655058B (en) | 2016-12-13 | 2016-12-13 | Power grid multidimensional snow removing ice removal and its application process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106655058B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114614430A (en) * | 2022-03-29 | 2022-06-10 | 国网河南省电力公司栾川县供电公司 | Electric wire snow removing equipment |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6373810A (en) * | 1986-09-17 | 1988-04-04 | 株式会社 木曽製作所 | Automatic applicator of snow-proof ring |
CN204886092U (en) * | 2015-09-07 | 2015-12-16 | 湖南大学 | High -voltage line removes ice structure |
CN105406398A (en) * | 2015-12-14 | 2016-03-16 | 国家电网公司 | Special frost remover for overhead line |
CN105811298A (en) * | 2016-03-11 | 2016-07-27 | 三峡大学 | High voltage transmission line press-bending deicing method and device |
-
2016
- 2016-12-13 CN CN201611147959.3A patent/CN106655058B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6373810A (en) * | 1986-09-17 | 1988-04-04 | 株式会社 木曽製作所 | Automatic applicator of snow-proof ring |
CN204886092U (en) * | 2015-09-07 | 2015-12-16 | 湖南大学 | High -voltage line removes ice structure |
CN105406398A (en) * | 2015-12-14 | 2016-03-16 | 国家电网公司 | Special frost remover for overhead line |
CN105811298A (en) * | 2016-03-11 | 2016-07-27 | 三峡大学 | High voltage transmission line press-bending deicing method and device |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114614430A (en) * | 2022-03-29 | 2022-06-10 | 国网河南省电力公司栾川县供电公司 | Electric wire snow removing equipment |
CN114614430B (en) * | 2022-03-29 | 2024-03-26 | 国网河南省电力公司栾川县供电公司 | Wire snow removing equipment |
Also Published As
Publication number | Publication date |
---|---|
CN106655058B (en) | 2018-11-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201887410U (en) | Knocking type high-tension wire deicer | |
CN204538627U (en) | A kind of transmission line deicer | |
CN103117525B (en) | A kind of built on stilts power transmission and distribution cable effectively power deicer | |
CN202535015U (en) | Deicer of high voltage line | |
CN201097435Y (en) | An ice eliminator for electric remote control high-voltage line | |
CN100486067C (en) | Electromotion remote control electric power overhead transmission line operating apparatus | |
CN115940064A (en) | Deicing device for power transmission line | |
CN106451294B (en) | A kind of power transmission line deicer | |
CN103094871A (en) | Anticing device of power transmission line and application method | |
CN206379705U (en) | One kind is applied in boisterous electric power maintenance annular machine | |
CN103928863A (en) | Electric power overhead line tractor | |
CN106655058A (en) | Multi-dimensional snow and ice removal device of power network and application method thereof | |
CN105356366B (en) | Overhead transmission line foreign body eliminating apparatus | |
CN210430869U (en) | High-voltage wire deicing aircraft | |
CN106786301B (en) | It is a kind of to apply in boisterous electric power maintenance annular machine and its application process | |
CN110424199A (en) | Power striker rail vehicle | |
CN113178830A (en) | Cable deicing device with anti-skidding function for power engineering | |
CN206379704U (en) | A kind of high pressure gauze deicer | |
CN106655057B (en) | A kind of high pressure gauze deicer and working method | |
CN104104048A (en) | Deicer | |
CN103277264B (en) | Large-scale fan blade tail bracket system | |
CN107062140A (en) | The two-way street lamp of express highway intelligent solar energy and its installation and application | |
CN105826891A (en) | Wire deicing device | |
CN103515910B (en) | A kind of high-voltage line deicer | |
CN210891421U (en) | Road emergency lighting device for smart city |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |