CN106643365A - Tunnel waste second lining blasting demolition and repairing construction method - Google Patents

Tunnel waste second lining blasting demolition and repairing construction method Download PDF

Info

Publication number
CN106643365A
CN106643365A CN201611143634.8A CN201611143634A CN106643365A CN 106643365 A CN106643365 A CN 106643365A CN 201611143634 A CN201611143634 A CN 201611143634A CN 106643365 A CN106643365 A CN 106643365A
Authority
CN
China
Prior art keywords
blasting
lining
pipe
concrete
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611143634.8A
Other languages
Chinese (zh)
Other versions
CN106643365B (en
Inventor
王志科
李野
刘百合
宋海丰
李向光
曹树强
刘福春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201611143634.8A priority Critical patent/CN106643365B/en
Publication of CN106643365A publication Critical patent/CN106643365A/en
Application granted granted Critical
Publication of CN106643365B publication Critical patent/CN106643365B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Engineering & Computer Science (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a tunnel waste second lining concrete blasting demolition and repairing construction method, which is invented for solving the problems that existing blasting can easily damage second lining concrete at a non-demolished section, and a repairing construction process is complicated. The method comprises the steps of slotting at a junction of a demolished section and a non-demolished section; dividing a second lining part to be demolished into a plurality of blasting sections; kerving at each blasting section; blasting from the middle part to two sides by utilizing a lateral freeing surface formed by kerving; kerving blasting for punching perpendicular holes along an inner wall of a tunnel, and circularly blasting for punching horizontal holes along an axial direction of the tunnel; intensively charging for kerving blasting, and charging layer by layer for circular blasting; adopting a non-electric detonating tube initiating system for initiating at the same time; repairing a second lining drainage system, processing a primary-branch fracture surface before paving, and after embedding a longitudinal plastic check well and a circumferential plastic check well, paving non-woven fabrics and a waterproof plate; adopting a trolley for secondary lining; installing an air vent hole and an injected hole; and dismantling a formwork for maintaining. The tunnel waste second lining concrete blasting demolition and repairing construction method provided by the invention has the advantages that the second lining concrete at the non-demolished section cannot be damaged, and the repairing construction speed is fast.

Description

The discarded two lining demolition blasting in tunnel and method for repairing and constructing
Technical field:
The present invention relates to the discarded two lining concrete in demolition blasting tunnel and method for repairing and constructing.
Background technology:
Often occurs the situation that two lining concrete need to remove because intensity is not enough during constructing tunnel, two lining concrete are torn open Except when should try one's best reduction to country rock and the disturbance of preliminary bracing.But current blasting construction method is to the non-two lining concrete for tearing section open Affect big, easily the non-two lining concrete for tearing section open are damaged, also need to carry out secondary reparation, both increased construction cost, affect again Duration.
The process for carrying out repairing construction to two lining concrete removal sections at present in addition is complicated, and speed is slow.
The content of the invention:
The technical problem to be solved is to provide one kind and the non-lining concrete of section two of tearing open will not be damaged, to removing section Repairing construction process is simple, and fireballing tunnel discarded two serves as a contrast demolition blasting and method for repairing and constructing.
What above-mentioned purpose was realized in:First the dismounting section side of section and non-dismounting section intersection is being removed using artificial Pneumatic pick is slotted, groove width 40cm, and groove depth is 30 ~ 35cm;
Two shirt portion position to be removed is divided into into several explosion sections, each explosion segment length is 12m;
The kerve of a wide 3m is first drawn in the middle of each explosion section, the length of the kerve is the girth that tunnel cross-section removes position;
The lateral free face formed using kerve, explosion is advanced from centre to both sides;
Kerf blasting beats upright opening along tunnel inner wall, and circulation propulsion explosion is axially fetched water flat hole along tunnel, and each circulation propulsion is about 3m;Several upright openings are beaten on tunnel inner wall at kerve(It is perpendicular with tunnel inner wall), in the tunnel inner wall of kerve both sides It is upper to beat several lateral apertures;
Kerf blasting parameter:Hole depth 0.30m, pitch-row 0.35m, single hole explosive payload 150g, unit consumption 2.0kg/m;
Circulation blasting parameter:Hole depth 0.35m, pitch-row 0.40m, single hole explosive payload 350g, unit consumption 1.5kg/m;
Kerf blasting concentrated charge, circulates explosion layered charge, is blocked using yellow mud;
From explosive:Explosive is emulsion;Detonator is non-electrical millisecond delay detonating detonator;
Blasting circuit:
In order to ensure safety standard is quick-fried, using nonel tube initiation system, volley detonation;The non-millisecond thunder of MS-7 sections is adopted in hole Pipe, adopts the non-millisecond detonator time delay of MS-3 sections outside hole, wherein constitute clusters per 2~10 on-electric detonators, per between group with one section Connection, forms cross duplicate network initiator and detonates;
Ensure good filling quality, forbid to be mingled with rubble in tamper during multiple-row blasting;
According to site test results, it is determined that suitable explosive payload, it is to avoid excess powder charge;
Repair two and serve as a contrast waterproof and water drainage system:
(1)To the process of a just section before laying:
A face at the beginning of labor cleaning and two lining joint areas after two linings are removed, then drop-over drain pipe and laying geotextiles and anti-again Water plate, to the artificial raggle of the lining construction joint of two ends two rubber fastening band and sealing rod are installed;
After old splash guard has been cleared up, the integrity of preliminary bracing is observed, if any damage, should in time clear up loosening portion around damage Point, and multiple spray is carried out, concrete surface smoothness is sprayed again should meet the requirement of D/L≤1/10(D is adjacent two salient point of preliminary bracing basal plane The depth for falling in;L is the distance between the adjacent salient point of basic unit, and L≤1m), then carry out the laying again of waterproof and water drainage system;
(2)Permeable blind pipe is arranged:
φ 50mm rings and φ 80mm longitudinal directions Permeable blind pipe, Permeable blind pipe material selection are set in the early stage between supporting and non-woven fabrics Mono-shell hole-punched bellows, ring φ 50mm and longitudinal direction φ 80mm blind pipe located at subsoil water compared with development at, ring blind pipe spacing is 10 Meter Yi Dao, longitudinal blind pipe is arranged at abutment wall foot, and sets abutment wall tapping pipe by subsoil water introducing hole medial sulcus every 5-10 rice, Ring and longitudinal blind pipe is asked directly to bend into tunnel lateral sulcus, the permeable french drain light and shade lining cutting section in longitudinal direction is respectively provided with and must not connect, indulges To blind pipe to be segmented excretion as principle, draining point slope point is preferably at expansion joint or subsiding crack, in case current are along seam infiltration;
(3)The laying of geotextiles, splash guard
After longitudinal direction, ring Permeable blind pipe are buried and finished, first lay and lay after non-woven fabrics splash guard, operation is first used in non-woven fabrics laying Single width non-woven fabrics are fixed to precalculated position by chassis, then non-woven fabrics are fixed on just spray concrete face with nailing, special fusible interlining Pad and nailing arrange in blossom type, and up and down molding is fixed for left and right, non-woven fabrics and the closely connected laying in spray concrete surface, should smooth out, without grand Corrugationless is played, non-woven fabrics lap width is not less than 50mm;
Single width splash guard is first fixed to precalculated position by splash guard laying with Mobile workbench, first eliminates the dust of waterproof plate surface, Again predetermined temperature is heated with Manual hot melting device, speed is welded on the special hot melt liner of fixed non-woven fabrics, splash guard overlap joint is wide Degree is more than 15cm, and using automatic double slit hot-melt welding machine, the effective width of wall scroll weld seam is not less than 15mm, and splash guard joint welding connects rear two Bar stays an air channel between stitching, and for air monitor welding quality is detected, the splash guard edge of broken-up laying should be reserved At least 20cm overlaps surplus;
Splash guard overlapping the slot should with movement joint, construction joint, country rock concentrate water outlet at etc. waterproof weak link stagger, distance should not be little In 50cm;
Non-woven fabrics, splash guard using laying " from top to bottom ", downward paving are laid to interior rail level absolute altitude from vault is symmetrical It is set as the domain;
Form concrete lining cutting:
Tunnel Second Lining is constructed using integral hydraulic lining trolley, and concrete is pumped into mould by delivery pump, in lining construction in time The pre-buried φ 20mm coating steel pipes of embedded backfill slip casting and the built-in fitting of other affiliated facilities, and in the pre-buried φ of vault midline position One, 42mm seamless steel pipes, use to the aerofluxuss in casting process;Construction technology is as follows:
(1)Chassis is in place:
It is mobile trolley used in place according to unwrapping wire position, chassis anti-skid device is arranged to chassis rail top after chassis is in place;
(2)Concreting:
Dismounting section two is served as a contrast and poured using C30 form concretes, when pouring arch wall concrete, is symmetrically poured from bottom to top, side Wall position concrete takes buried tube type to pour, and by the direct top pressure of hydraulic pump mould is entered, and extruding jacking type is poured;Poured using a point storehouse Fen Kou Build, arch first takes the formula of exiting to pour, and is finally bound with forced;Concrete attached vibrator and poker vibrator join Conjunction is made firm by ramming, it is ensured that inside concrete is closely knit, outer smooth, protects the pre- Grouting Pipe for being embedded in inside concrete, prevents its crooked With topple over, to guarantee two linings after backfill slip casting can be smoothed out;
(3)Steam vent and injected hole are installed:
1. lining trolley arch rod radial air vent:
Two ends and middle part respectively set a steam vent on lining trolley top panel, are connected using ring flange mode, and steam vent is simultaneous Do observation port and injected hole;
Radial direction exhaustor is connected by ring flange, and the top mouth of pipe holds out against with waterproof layer, makes waterproof layer closely connected with basal plane;
2. longitudinal exhaustor is installed with Grouting Pipe:
The longitudinal exhaustor in top adopts the colloid flexible pipe or pvc pipe of φ 20mm ~ φ 30mm, pipe shaft to lay blossom type benefit with Grouting Pipe Slurry hole, 2 ~ 3mm of aperture, longitudinal pitch≤30cm;
The longitudinal exhaustor in top is installed using pre- patch mode, fixed dot spacing≤80cm with Grouting Pipe;
(4)Form removal is conserved:
When side, arch concrete strength reach 8MPa when, can form removal, carry out watering maintenance after form removal in time, curing time is many In 14 days.
It is an advantage of the invention that:The non-lining concrete of section two of tearing open will not be damaged, to removing the letter of section repairing construction process Single, speed is fast, and construction cost is low, and quality is good.
Specific embodiment:
Slotted using artificial pneumatic pick in the dismounting section side for removing section and non-dismounting section intersection first, groove width 40cm, fluting is deep Spend for 30 ~ 35cm;
Two shirt portion position to be removed is divided into into several explosion sections, each explosion segment length is 12m;
The kerve of a wide 3m is first drawn in the middle of each explosion section, the length of the kerve is the girth that tunnel cross-section removes position;
The lateral free face formed using kerve, explosion is advanced from centre to both sides;
Kerf blasting beats upright opening along tunnel inner wall, and circulation propulsion explosion is axially fetched water flat hole along tunnel, and each circulation propulsion is about 3m;Several upright openings are beaten on tunnel inner wall at kerve(It is perpendicular with tunnel inner wall), in the tunnel inner wall of kerve both sides It is upper to beat several lateral apertures;
Kerf blasting parameter:Hole depth 0.30m, pitch-row 0.35m, single hole explosive payload 150g, unit consumption 2.0kg/m;
Circulation blasting parameter:Hole depth 0.35m, pitch-row 0.40m, single hole explosive payload 350g, unit consumption 1.5kg/m;
Kerf blasting concentrated charge, circulates explosion layered charge, is blocked using yellow mud;
From explosive:Explosive is emulsion;Detonator is non-electrical millisecond delay detonating detonator;
Blasting circuit:
In order to ensure safety standard is quick-fried, using nonel tube initiation system, volley detonation;MS-7 section non-electrical millisecond thunders are adopted in hole Pipe, adopts MS-3 section non-electric ms detonator time delays outside hole, wherein constitute clusters per 2~10 on-electric detonators, per between group with one Section connection, forms cross duplicate network initiator and detonates;
Ensure good filling quality, forbid to be mingled with rubble in tamper during multiple-row blasting;
According to site test results, it is determined that suitable explosive payload, it is to avoid excess powder charge;
Repair two and serve as a contrast waterproof and water drainage system:
(1)To the process of a just section before laying:
A face at the beginning of labor cleaning and two lining joint areas after two linings are removed, then drop-over drain pipe and laying geotextiles and anti-again Water plate, to the artificial raggle of the lining construction joint of two ends two rubber fastening band and sealing rod are installed;
After old splash guard has been cleared up, the integrity of preliminary bracing is observed, if any damage, should in time clear up loosening portion around damage Point, and multiple spray is carried out, concrete surface smoothness is sprayed again should meet the requirement of D/L≤1/10(D is adjacent two salient point of preliminary bracing basal plane The depth for falling in;L is the distance between the adjacent salient point of basic unit, and L≤1m), then carry out the laying again of waterproof and water drainage system;
(2)Permeable blind pipe is arranged:
φ 50mm rings and φ 80mm longitudinal directions Permeable blind pipe, Permeable blind pipe material selection are set in the early stage between supporting and non-woven fabrics Mono-shell hole-punched bellows, ring φ 50mm and longitudinal direction φ 80mm blind pipe located at subsoil water compared with development at, ring blind pipe spacing is 10 Meter Yi Dao, longitudinal blind pipe is arranged at abutment wall foot, and sets abutment wall tapping pipe by subsoil water introducing hole medial sulcus every 5-10 rice, Ring and longitudinal blind pipe is asked directly to bend into tunnel lateral sulcus, the permeable french drain light and shade lining cutting section in longitudinal direction is respectively provided with and must not connect, indulges To blind pipe to be segmented excretion as principle, draining point slope point is preferably at expansion joint or subsiding crack, in case current are along seam infiltration;
(3)The laying of geotextiles, splash guard
After longitudinal direction, ring Permeable blind pipe are buried and finished, first lay and lay after non-woven fabrics splash guard, operation is first used in non-woven fabrics laying Single width non-woven fabrics are fixed to precalculated position by chassis, then non-woven fabrics are fixed on just spray concrete face with nailing, special fusible interlining Pad and nailing arrange in blossom type, and up and down molding is fixed for left and right, non-woven fabrics and the closely connected laying in spray concrete surface, should smooth out, without grand Corrugationless is played, non-woven fabrics lap width is not less than 50mm;
Single width splash guard is first fixed to precalculated position by splash guard laying with Mobile workbench, first eliminates the dust of waterproof plate surface, Again predetermined temperature is heated with Manual hot melting device, speed is welded on the special hot melt liner of fixed non-woven fabrics, splash guard overlap joint is wide Degree is more than 15cm, and using automatic double slit hot-melt welding machine, the effective width of wall scroll weld seam is not less than 15mm, and splash guard joint welding connects rear two Bar stays an air channel between stitching, and for air monitor welding quality is detected, the splash guard edge of broken-up laying should be reserved At least 20cm overlaps surplus;
Splash guard overlapping the slot should with movement joint, construction joint, country rock concentrate water outlet at etc. waterproof weak link stagger, distance should not be little In 50cm;
Non-woven fabrics, splash guard using laying " from top to bottom ", downward paving are laid to interior rail level absolute altitude from vault is symmetrical It is set as the domain;
Form concrete lining cutting:
Tunnel Second Lining is constructed using integral hydraulic lining trolley, and concrete is pumped into mould by delivery pump, in lining construction in time The pre-buried φ 20mm coating steel pipes of embedded backfill slip casting and the built-in fitting of other affiliated facilities, and in the pre-buried φ of vault midline position One, 42mm seamless steel pipes, use to the aerofluxuss in casting process;Construction technology is as follows:
(1)Chassis is in place:
It is mobile trolley used in place according to unwrapping wire position, chassis anti-skid device is arranged to chassis rail top after chassis is in place;
(2)Concreting:
Dismounting section two is served as a contrast and poured using C30 form concretes, when pouring arch wall concrete, is symmetrically poured from bottom to top, side Wall position concrete takes buried tube type to pour, and by the direct top pressure of hydraulic pump mould is entered, and extruding jacking type is poured;Poured using a point storehouse Fen Kou Build, arch first takes the formula of exiting to pour, and is finally bound with forced;Concrete attached vibrator and poker vibrator join Conjunction is made firm by ramming, it is ensured that inside concrete is closely knit, outer smooth, protects the pre- Grouting Pipe for being embedded in inside concrete, prevents its crooked With topple over, to guarantee two linings after backfill slip casting can be smoothed out;
(3)Steam vent and injected hole are installed:
1. lining trolley arch rod radial air vent:
Two ends and middle part respectively set a steam vent on lining trolley top panel, are connected using ring flange mode, and steam vent is simultaneous Do observation port and injected hole;
Radial direction exhaustor is connected by ring flange, and the top mouth of pipe holds out against with waterproof layer, makes waterproof layer closely connected with basal plane;
2. longitudinal exhaustor is installed with Grouting Pipe:
The longitudinal exhaustor in top adopts the colloid flexible pipe or pvc pipe of φ 20mm ~ φ 30mm, pipe shaft to lay blossom type benefit with Grouting Pipe Slurry hole, 2 ~ 3mm of aperture, longitudinal pitch≤30cm;
The longitudinal exhaustor in top is installed using pre- patch mode, fixed dot spacing≤80cm with Grouting Pipe;
(4)Form removal is conserved:
When side, arch concrete strength reach 8MPa when, can form removal, carry out watering maintenance after form removal in time, curing time is many In 14 days.

Claims (1)

1. the discarded two lining demolition blasting in tunnel and method for repairing and constructing, is characterized in that:Removing section and non-dismounting section boundary first The dismounting section side at place is slotted using artificial pneumatic pick, groove width 40cm, and groove depth is 30 ~ 35cm;
Two shirt portion position to be removed is divided into into several explosion sections, each explosion segment length is 12m;
The kerve of a wide 3m is first drawn in the middle of each explosion section, the length of the kerve is the girth that tunnel cross-section removes position;
The lateral free face formed using kerve, explosion is advanced from centre to both sides;
Kerf blasting beats upright opening along tunnel inner wall, and circulation propulsion explosion is axially fetched water flat hole along tunnel, and each circulation propulsion is about 3m;Several upright openings are beaten on tunnel inner wall at kerve, several lateral apertures are beaten on the tunnel inner wall of kerve both sides;
Kerf blasting parameter:Hole depth 0.30m, pitch-row 0.35m, single hole explosive payload 150g, unit consumption 2.0kg/m;
Circulation blasting parameter:Hole depth 0.35m, pitch-row 0.40m, single hole explosive payload 350g, unit consumption 1.5kg/m;
Kerf blasting concentrated charge, circulates explosion layered charge, is blocked using yellow mud;
From explosive:Explosive is emulsion;Detonator is non-electrical millisecond delay detonating detonator;
Blasting circuit:
In order to ensure safety standard is quick-fried, using nonel tube initiation system, volley detonation;The non-millisecond thunder of MS-7 sections is adopted in hole Pipe, adopts the non-millisecond detonator time delay of MS-3 sections outside hole, wherein constitute clusters per 2~10 on-electric detonators, per between group with one section Connection, forms cross duplicate network initiator and detonates;
Ensure good filling quality, forbid to be mingled with rubble in tamper during multiple-row blasting;
According to site test results, it is determined that suitable explosive payload, it is to avoid excess powder charge;
Repair two and serve as a contrast waterproof and water drainage system:
(1)To the process of a just section before laying:
A face at the beginning of labor cleaning and two lining joint areas after two linings are removed, then drop-over drain pipe and laying geotextiles and anti-again Water plate, to the artificial raggle of the lining construction joint of two ends two rubber fastening band and sealing rod are installed;
After old splash guard has been cleared up, the integrity of preliminary bracing is observed, if any damage, should in time clear up loosening portion around damage Point, and multiple spray is carried out, concrete surface smoothness is sprayed again should meet the requirement of D/L≤1/10(D is adjacent two salient point of preliminary bracing basal plane The depth for falling in;L is the distance between the adjacent salient point of basic unit, and L≤1m), then carry out the laying again of waterproof and water drainage system;
(2)Permeable blind pipe is arranged:
φ 50mm rings and φ 80mm longitudinal directions Permeable blind pipe, Permeable blind pipe material selection are set in the early stage between supporting and non-woven fabrics Mono-shell hole-punched bellows, ring φ 50mm and longitudinal direction φ 80mm blind pipe located at subsoil water compared with development at, ring blind pipe spacing is 10 Meter Yi Dao, longitudinal blind pipe is arranged at abutment wall foot, and sets abutment wall tapping pipe by subsoil water introducing hole medial sulcus every 5-10 rice, Ring and longitudinal blind pipe is asked directly to bend into tunnel lateral sulcus, the permeable french drain light and shade lining cutting section in longitudinal direction is respectively provided with and must not connect, indulges To blind pipe to be segmented excretion as principle, draining point slope point is preferably at expansion joint or subsiding crack, in case current are along seam infiltration;
(3)The laying of geotextiles, splash guard
After longitudinal direction, ring Permeable blind pipe are buried and finished, first lay and lay after non-woven fabrics splash guard, operation is first used in non-woven fabrics laying Single width non-woven fabrics are fixed to precalculated position by chassis, then non-woven fabrics are fixed on just spray concrete face with nailing, special fusible interlining Pad and nailing arrange in blossom type, and up and down molding is fixed for left and right, non-woven fabrics and the closely connected laying in spray concrete surface, should smooth out, without grand Corrugationless is played, non-woven fabrics lap width is not less than 50mm;
Single width splash guard is first fixed to precalculated position by splash guard laying with Mobile workbench, first eliminates the dust of waterproof plate surface, Again predetermined temperature is heated with Manual hot melting device, speed is welded on the special hot melt liner of fixed non-woven fabrics, splash guard overlap joint is wide Degree is more than 15cm, and using automatic double slit hot-melt welding machine, the effective width of wall scroll weld seam is not less than 15mm, and splash guard joint welding connects rear two Bar stays an air channel between stitching, and for air monitor welding quality is detected, the splash guard edge of broken-up laying should be reserved At least 20cm overlaps surplus;
Splash guard overlapping the slot should with movement joint, construction joint, country rock concentrate water outlet at etc. waterproof weak link stagger, distance should not be little In 50cm;
Non-woven fabrics, splash guard using laying " from top to bottom ", downward paving are laid to interior rail level absolute altitude from vault is symmetrical It is set as the domain;
Form concrete lining cutting:
Tunnel Second Lining is constructed using integral hydraulic lining trolley, and concrete is pumped into mould by delivery pump, in lining construction in time The pre-buried φ 20mm coating steel pipes of embedded backfill slip casting and the built-in fitting of other affiliated facilities, and in the pre-buried φ of vault midline position One, 42mm seamless steel pipes, use to the aerofluxuss in casting process;Construction technology is as follows:
(1)Chassis is in place:
It is mobile trolley used in place according to unwrapping wire position, chassis anti-skid device is arranged to chassis rail top after chassis is in place;
(2)Concreting:
Dismounting section two is served as a contrast and poured using C30 form concretes, when pouring arch wall concrete, is symmetrically poured from bottom to top, side Wall position concrete takes buried tube type to pour, and by the direct top pressure of hydraulic pump mould is entered, and extruding jacking type is poured;Poured using a point storehouse Fen Kou Build, arch first takes the formula of exiting to pour, and is finally bound with forced;Concrete attached vibrator and poker vibrator join Conjunction is made firm by ramming, it is ensured that inside concrete is closely knit, outer smooth, protects the pre- Grouting Pipe for being embedded in inside concrete, prevents its crooked With topple over, to guarantee two linings after backfill slip casting can be smoothed out;
(3)Steam vent and injected hole are installed:
1. lining trolley arch rod radial air vent:
Two ends and middle part respectively set a steam vent on lining trolley top panel, are connected using ring flange mode, and steam vent is simultaneous Do observation port and injected hole;
Radial direction exhaustor is connected by ring flange, and the top mouth of pipe holds out against with waterproof layer, makes waterproof layer closely connected with basal plane;
2. longitudinal exhaustor is installed with Grouting Pipe:
The longitudinal exhaustor in top adopts the colloid flexible pipe or pvc pipe of φ 20mm ~ φ 30mm, pipe shaft to lay blossom type benefit with Grouting Pipe Slurry hole, 2 ~ 3mm of aperture, longitudinal pitch≤30cm;
The longitudinal exhaustor in top is installed using pre- patch mode, fixed dot spacing≤80cm with Grouting Pipe;
(4)Form removal is conserved:
When side, arch concrete strength reach 8MPa when, can form removal, carry out watering maintenance after form removal in time, curing time is many In 14 days.
CN201611143634.8A 2016-12-13 2016-12-13 Two lining demolition blastings and method for repairing and constructing are discarded in tunnel Active CN106643365B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611143634.8A CN106643365B (en) 2016-12-13 2016-12-13 Two lining demolition blastings and method for repairing and constructing are discarded in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611143634.8A CN106643365B (en) 2016-12-13 2016-12-13 Two lining demolition blastings and method for repairing and constructing are discarded in tunnel

Publications (2)

Publication Number Publication Date
CN106643365A true CN106643365A (en) 2017-05-10
CN106643365B CN106643365B (en) 2018-07-10

Family

ID=58824409

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611143634.8A Active CN106643365B (en) 2016-12-13 2016-12-13 Two lining demolition blastings and method for repairing and constructing are discarded in tunnel

Country Status (1)

Country Link
CN (1) CN106643365B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435549A (en) * 2017-08-14 2017-12-05 合肥卓立雅工程材料科技有限公司 A kind of tunnel applications geomembrane laying method
CN107587884A (en) * 2017-10-11 2018-01-16 中国葛洲坝集团第六工程有限公司 Tunnel double-lining concrete vault backfills grouting device
CN109026065A (en) * 2018-07-25 2018-12-18 中铁十六局集团有限公司 A kind of Tunnel Second Lining zero-fault construction method
CN109505629A (en) * 2018-12-29 2019-03-22 北京京水建设集团有限公司 Steel pipe behind fill concrete structure and construction method in a kind of tunnel
CN109853472A (en) * 2019-04-04 2019-06-07 无锡卡麦尔工程科技有限公司 A kind of river levee construction controlled permeability form lining
CN110410102A (en) * 2019-08-22 2019-11-05 西南交通大学 A kind of construction method for removing operation high-speed rail tunnel interlayer lining cutting
CN110487137A (en) * 2019-08-27 2019-11-22 山东科技大学 A kind of deep hole presplitting water coincidence blast charging structure and construction method
CN110593909A (en) * 2019-10-18 2019-12-20 中铁隧道局集团有限公司 Tunnel secondary lining dismounting and replacing construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202483588U (en) * 2012-01-12 2012-10-10 中国市政工程西北设计研究院有限公司 Self water-proof drainage system of tunnel lining
CN104989427A (en) * 2015-07-20 2015-10-21 舟山市智海技术开发有限公司 Tunnel construction lining amount determination device and construction method thereof
CN105019942A (en) * 2015-07-20 2015-11-04 甘肃路桥建设集团有限公司 Method for dismounting second-lined reinforced concrete in tunnel
CN105257320A (en) * 2015-10-29 2016-01-20 袁顺利 Tunnel waterproof structure and construction method
CN105781571A (en) * 2016-03-11 2016-07-20 中交第二公路工程局有限公司 Construction method for soft rock deformation tunnel lining support dismantling-replacing arch

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202483588U (en) * 2012-01-12 2012-10-10 中国市政工程西北设计研究院有限公司 Self water-proof drainage system of tunnel lining
CN104989427A (en) * 2015-07-20 2015-10-21 舟山市智海技术开发有限公司 Tunnel construction lining amount determination device and construction method thereof
CN105019942A (en) * 2015-07-20 2015-11-04 甘肃路桥建设集团有限公司 Method for dismounting second-lined reinforced concrete in tunnel
CN105257320A (en) * 2015-10-29 2016-01-20 袁顺利 Tunnel waterproof structure and construction method
CN105781571A (en) * 2016-03-11 2016-07-20 中交第二公路工程局有限公司 Construction method for soft rock deformation tunnel lining support dismantling-replacing arch

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435549A (en) * 2017-08-14 2017-12-05 合肥卓立雅工程材料科技有限公司 A kind of tunnel applications geomembrane laying method
CN107587884A (en) * 2017-10-11 2018-01-16 中国葛洲坝集团第六工程有限公司 Tunnel double-lining concrete vault backfills grouting device
CN107587884B (en) * 2017-10-11 2023-11-03 中国葛洲坝集团建设工程有限公司 Tunnel secondary lining concrete arch top backfill grouting device
CN109026065A (en) * 2018-07-25 2018-12-18 中铁十六局集团有限公司 A kind of Tunnel Second Lining zero-fault construction method
CN109505629A (en) * 2018-12-29 2019-03-22 北京京水建设集团有限公司 Steel pipe behind fill concrete structure and construction method in a kind of tunnel
CN109853472A (en) * 2019-04-04 2019-06-07 无锡卡麦尔工程科技有限公司 A kind of river levee construction controlled permeability form lining
CN110410102A (en) * 2019-08-22 2019-11-05 西南交通大学 A kind of construction method for removing operation high-speed rail tunnel interlayer lining cutting
CN110410102B (en) * 2019-08-22 2021-05-18 西南交通大学 Construction method for removing interlayer lining of operating high-speed rail tunnel
CN110487137A (en) * 2019-08-27 2019-11-22 山东科技大学 A kind of deep hole presplitting water coincidence blast charging structure and construction method
CN110487137B (en) * 2019-08-27 2021-07-23 山东科技大学 Deep hole pre-splitting water coupling blasting charging structure and construction method
CN110593909A (en) * 2019-10-18 2019-12-20 中铁隧道局集团有限公司 Tunnel secondary lining dismounting and replacing construction method

Also Published As

Publication number Publication date
CN106643365B (en) 2018-07-10

Similar Documents

Publication Publication Date Title
CN106643365A (en) Tunnel waste second lining blasting demolition and repairing construction method
CN108194136B (en) Lining construction method
CN110748359A (en) Tunnel water-proof and drainage construction process
CN111734457B (en) Construction method of tunnel water-drainage-preventing system
CN101864960A (en) Carst region double-arch road tunnel construction method
CN111287759B (en) Shallow-buried close-connection underground excavation tunnel construction method
CN106677803A (en) Structure and method for treating severe disengagement, cracking and other defects of tunnel lining
CN106050266A (en) Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN108643935A (en) The construction method in tunnel under rich water shallow embedding geology
CN107327308A (en) A kind of Railway Tunnel waterproof method
CN107587881A (en) A kind of composite lining structure and construction technology for permafrost tunnel
KR101415106B1 (en) The back feel grouting apparatus for upper part of tunnel
CN105951848A (en) Non-intermittent composite transfer structure for super-deep foundation pit support and construction method
CN109026026A (en) Under wear existing piping lane the multi-thread more arcading bored tunnel groups of big cross section construction method
CN108397200A (en) Formula construction method is done after metro station tunnel linkage segment structure
CN110593909A (en) Tunnel secondary lining dismounting and replacing construction method
CN113847050B (en) Construction method of ultra-long highway tunnel in lava mountain area
CN108505805A (en) Large-scale cast-in-place pond and its construction method are split in expansion reinforcing band control
CN103590841B (en) Supporting method for primary support of underground excavated chamber
CN216841801U (en) Shaft drainage system
CN109505612A (en) Big descending bored tunnel shield sky selection structure and construction technology
CN109403981A (en) The construction technology of subway shield shaft main structure
CN108361049A (en) A kind of tunnel waterproofing construction construction method
CN111594184A (en) Main hole excavating method for hole bias tunnel
CN115898469A (en) Tunnel secondary lining construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant