CN106638692A - Joint connecting mechanism of immersed tunnel - Google Patents

Joint connecting mechanism of immersed tunnel Download PDF

Info

Publication number
CN106638692A
CN106638692A CN201710016642.4A CN201710016642A CN106638692A CN 106638692 A CN106638692 A CN 106638692A CN 201710016642 A CN201710016642 A CN 201710016642A CN 106638692 A CN106638692 A CN 106638692A
Authority
CN
China
Prior art keywords
box
submerged tunnel
tunnel
pullover
box girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710016642.4A
Other languages
Chinese (zh)
Inventor
贺维国
范国刚
宋超业
张美琴
褚凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRTG Survey and Design Institute Co Ltd filed Critical CRTG Survey and Design Institute Co Ltd
Priority to CN201710016642.4A priority Critical patent/CN106638692A/en
Publication of CN106638692A publication Critical patent/CN106638692A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/067Floating tunnels; Submerged bridge-like tunnels, i.e. tunnels supported by piers or the like above the water-bed
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0001Rubbers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

The invention relates to a joint connecting mechanism of an immersed tunnel and belongs to the technical field of traffic. The joint connecting mechanism comprises an immersed tunnel box girder structure, a pile foundation, a spandrel girder, box girder end part pullover bases, rubber waterstops, pullover bolts and a cushion layer; the bottom of the immersed tunnel box girder structure is mutually matched with the spandrel girder; the bottom of the spandrel girder is provided with the pile foundation; two sides of the immersed tunnel box girder structure are provided with the box girder end part pullover bases; the rubber waterstops are embedded in the box girder end part pullover bases; the cushion layer is arranged between the two box girder end part pullover bases; the box girder end part pullover bases are positioned and fastened by virtue of the pullover bolts. The joint connecting mechanism of the immersed tunnel is low in construction difficulty, simple in process, high in construction speed and low in cost, is capable of avoiding problems existing in the prior art, and is beneficial to operation of underwater engineering.

Description

A kind of joint bindiny mechanism of submerged tunnel
Technical field
The present invention relates to a kind of joint bindiny mechanism of submerged tunnel, belongs to technical field of transportation.
Background technology
China is vast in territory, and seashore line length, river, river, lake and island are numerous, many using to environment, landscape shadow in recent years The little submerged tunnel mode of sound.Submerged tunnel joint waterproofing is one of key factor of whole engineering success or failure, conventional submerged tunnel All it is embedded in the soil layer below the bottom, tunnel cross-section is big, joint stress is complicated, joint waterproofing complex process, operation are more, construction Difficulty is big, long in time limit, cost is high.For under water the tunnel force modes without earthing differ completely with the tunnel for having earthing under water Sample, therefore its joint should not indiscriminately imitate earthing submerged tunnel joint connection manner.
The content of the invention
Present invention aims to the defect and deficiency of prior art, there is provided a kind of difficulty of construction is little, process is simple, Speed of application is fast, the joint bindiny mechanism of the submerged tunnel of low cost.
For achieving the above object, the technical solution used in the present invention is:It includes submerged tunnel box-beam structure, pile foundation, support Beam, box beam end drawing pedestal, rubber fastening band, drawing bolt, cushion;The bottom of described submerged tunnel box-beam structure Cooperate with joist;The bottom of described joist is provided with pile foundation;The both sides of described submerged tunnel box-beam structure are equipped with case Beam end drawing pedestal;Rubber fastening band is inlaid with described box beam end drawing pedestal;Two box beam end drawing pedestals Between be provided with cushion;And two box beam end drawing pedestals are positioned and fastened by drawing bolt.
Preferably, reserved drawing bolt hole on described box beam end drawing pedestal.
Preferably, described rubber fastening band is arranged on the inner side of reserved drawing bolt hole.
Preferably, the cross-sectional area of described submerged tunnel box-beam structure is more than or equal to 12 square metres.
Preferably, the bottom of described box beam end drawing pedestal cooperates with the bottom;The described water surface is under water , there is a certain distance at the top of tunnel box-beam structure between submerged tunnel box-beam structure and the water surface.
During present invention operation, tunnel line plane, vertical line type are fitted according to underwater topography and line requirements;According to Circuit is flat, vertical line type, and tunnel box-beam structure is divided into some sections, and every section of box beam length can be not less than 120m;Box beam is indirect Head nearby arranges pile foundation and supporting plate, and supporting plate top surface absolute altitude is identical with tunnel structure floor level;In construction pile foundation and supporting plate simultaneously, Prefabricated tunnel box beam;End drawing pedestal is simultaneously prefabricated with box beam, form overall;Waterstop is arranged on the outside of drawing pedestal; After box beam is lifted on underwater pile foundation, by drawing bolt prefabricated case beam drawing is connected to form tunnel.
After said structure, the present invention has the beneficial effect that:A kind of joint connection machine of submerged tunnel of the present invention Structure, difficulty of construction is little, process is simple, speed of application are fast, low cost, it is to avoid problems of the prior art, is conducive to water The operation of lower engineering.
Description of the drawings
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also To obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is the connection diagram of the present invention;
Fig. 2 is the A-A profiles of Fig. 1;
The schematic diagram of Fig. 3 raising middle flask beam end drawing pedestals of the present invention.
Description of reference numerals:
The 1- waters surface;2- is water-bed;3- submerged tunnel box-beam structures;4- pile foundations;5- joists;6- box beams end drawing pedestal;7- rubber Waterstop;8- drawing bolts;9- cushions.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention is further illustrated.
Referring to such as Fig. 1 -- shown in Fig. 3, this specific embodiment includes submerged tunnel box-beam structure 3, pile foundation 4, joist 5, case Beam end drawing pedestal 6, rubber fastening band 7, drawing bolt 8, cushion 9;The bottom of described submerged tunnel box-beam structure 3 Cooperate with joist 5;The bottom of described joist 55 is provided with pile foundation 4;The both sides of described submerged tunnel box-beam structure 3 are all provided with There is box beam end drawing pedestal 6;Rubber fastening band 7 is inlaid with described box beam end drawing pedestal 6;Draw two box beam ends Close and be provided with cushion 9 between pedestal 6;And two box beam end drawing pedestals 6 are positioned and fastened by drawing bolt 8;It is described Box beam end drawing pedestal 6 on reserve reserved drawing bolt hole;Described rubber fastening band 7 is arranged on reserved drawing bolt hole Inner side;The cross-sectional area of described submerged tunnel box-beam structure 3 is more than or equal to 12 square metres;Described box beam end drawing base The bottom of seat 6 cooperates with water-bed 2;The top of the described water surface 1 tunnel box-beam structure 3 under water, submerged tunnel box beam knot There is a certain distance between structure 3 and the water surface 1.
When this specific embodiment is operated:
1st, tunnel line plane, vertical line type are fitted according to underwater topography and line requirements.
2nd, according to circuit is flat, vertical line type, tunnel box-beam structure 3 is divided into some sections, every section of box beam length can not be little In 120m.
3rd, near joints arrange pile foundation 4 and supporting plate 5 between box beam, and the top surface absolute altitude of supporting plate 5 is identical with tunnel structure floor level.
4th, in construction pile foundation 4 and supporting plate 5 simultaneously, prefabricated tunnel box beam 3.
5th, it is end drawing pedestal 6 is simultaneously prefabricated with box beam 3, form overall.
6th, in the outside of drawing pedestal 3 arrangement waterstop.
7th, after box beam is lifted on underwater pile foundation, by drawing bolt 8 prefabricated case beam drawing is connected to form tunnel.
After said structure, this specific embodiment difficulty of construction is little, process is simple, speed of application fast, low cost, keeps away Exempt from problems of the prior art, be conducive to the operation of Underwater Engineering.
The above, only to illustrate technical scheme and unrestricted, those of ordinary skill in the art are to this Other modifications or equivalent that bright technical scheme is made, without departing from the spirit and scope of technical solution of the present invention, All should cover in the middle of scope of the presently claimed invention.

Claims (5)

1. the joint bindiny mechanism of a kind of submerged tunnel, it is characterised in that:It comprising submerged tunnel box-beam structure, pile foundation, joist, Box beam end drawing pedestal, rubber fastening band, drawing bolt, cushion;The bottom of described submerged tunnel box-beam structure with Joist cooperates;The bottom of described joist is provided with pile foundation;The both sides of described submerged tunnel box-beam structure are equipped with box beam End drawing pedestal;Rubber fastening band is inlaid with described box beam end drawing pedestal;Two box beam end drawing pedestals it Between be provided with cushion;And two box beam end drawing pedestals are positioned and fastened by drawing bolt.
2. the joint bindiny mechanism of a kind of submerged tunnel according to claim 1, it is characterised in that:Described box beam end Reserved drawing bolt hole on drawing pedestal.
3. the joint bindiny mechanism of a kind of submerged tunnel according to claim 1, it is characterised in that:Described rubber water-proof Band is arranged on the inner side of reserved drawing bolt hole.
4. the joint bindiny mechanism of a kind of submerged tunnel according to claim 1, it is characterised in that:Described submerged tunnel The cross-sectional area of box-beam structure is more than or equal to 12 square metres.
5. the joint bindiny mechanism of a kind of submerged tunnel according to claim 1, it is characterised in that:Described box beam end The bottom of drawing pedestal cooperates with the bottom;The top of described water surface tunnel box-beam structure under water.
CN201710016642.4A 2017-01-11 2017-01-11 Joint connecting mechanism of immersed tunnel Pending CN106638692A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710016642.4A CN106638692A (en) 2017-01-11 2017-01-11 Joint connecting mechanism of immersed tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710016642.4A CN106638692A (en) 2017-01-11 2017-01-11 Joint connecting mechanism of immersed tunnel

Publications (1)

Publication Number Publication Date
CN106638692A true CN106638692A (en) 2017-05-10

Family

ID=58843589

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710016642.4A Pending CN106638692A (en) 2017-01-11 2017-01-11 Joint connecting mechanism of immersed tunnel

Country Status (1)

Country Link
CN (1) CN106638692A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11323977A (en) * 1998-05-18 1999-11-26 Taisei Corp Water stop structure for underwater tunnel
JP2000045306A (en) * 1998-07-28 2000-02-15 Taisei Corp Launching tunnel directional controlling device
CN102561371A (en) * 2012-02-29 2012-07-11 中交一航局第五工程有限公司 Steel caisson enclosure structure at island-tunnel combination part
KR101355498B1 (en) * 2012-11-16 2014-01-29 한국해양과학기술원 Submerged tunnel module structure and construction method thereof using a reinforced concrete section with internally confined hollow
CN103912016A (en) * 2012-12-31 2014-07-09 中交一航局第二工程有限公司 Pipe joint tensioning crimping method
CN203924112U (en) * 2014-06-24 2014-11-05 刘小沙 Prefabricated pipe gallery
CN105908785A (en) * 2016-06-02 2016-08-31 中铁隧道集团二处有限公司 Sunken pipe butt joint GINA water stop belt longitudinal limiting pull rod device under high water difference condition

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11323977A (en) * 1998-05-18 1999-11-26 Taisei Corp Water stop structure for underwater tunnel
JP2000045306A (en) * 1998-07-28 2000-02-15 Taisei Corp Launching tunnel directional controlling device
CN102561371A (en) * 2012-02-29 2012-07-11 中交一航局第五工程有限公司 Steel caisson enclosure structure at island-tunnel combination part
KR101355498B1 (en) * 2012-11-16 2014-01-29 한국해양과학기술원 Submerged tunnel module structure and construction method thereof using a reinforced concrete section with internally confined hollow
CN103912016A (en) * 2012-12-31 2014-07-09 中交一航局第二工程有限公司 Pipe joint tensioning crimping method
CN203924112U (en) * 2014-06-24 2014-11-05 刘小沙 Prefabricated pipe gallery
CN105908785A (en) * 2016-06-02 2016-08-31 中铁隧道集团二处有限公司 Sunken pipe butt joint GINA water stop belt longitudinal limiting pull rod device under high water difference condition

Similar Documents

Publication Publication Date Title
CN102383443B (en) Connection structures between foundation pit support piles and outer walls of basement and construction method
CN105332417A (en) Method for constructing prefabricated steel frame composite structure with concrete wrapped outside
CN103866817A (en) Water intake pumping station
CN201567584U (en) Prefabricated construction reinforced concrete cushion cap foundation
CN207092107U (en) A kind of anti-subsidence structure using diaphram wall
CN202359566U (en) Cofferdam for deep-water soft soil foundation construction of bridge
CN210127485U (en) Concrete suction type caisson foundation and thin-wall pier stud connecting structure
CN104594360A (en) Composite double-row pile foundation pit supporting structure
CN106522263A (en) Construction method for wind power complete machine of structure composed of four barrel-type foundations and supported by concrete
CN201372441Y (en) Bonded and unbonded prestressed concrete basement structure
CN105421477A (en) Construction method for tower crane foundation
CN104060628A (en) Manufacturing method and structure for basement floor without crack, leakage and with oversized area
CN206233656U (en) Steel frame mill building structure
CN210529471U (en) Bridge package mound on urban rail transit cable
CN106638692A (en) Joint connecting mechanism of immersed tunnel
CN203531326U (en) Structure of ultra-large area basement terrace free of cracks and leakage
CN202430742U (en) Precast slab assembly soil retaining wall
CN210684719U (en) Unloading type single-row pile supporting structure
CN105040730B (en) Connection processing method for enclosure bored concrete pile and cellar structure floor slab in reversed foundation pit
CN209874039U (en) Basement deformation joint structure
CN207211170U (en) Steel cofferdam prestress anchoraging device
CN103397650B (en) A kind of large-scale steel cylinder cofferdam structure
CN112095665A (en) Water buoyancy balance construction method applied to subway upper cover
CN206655486U (en) A kind of elongated steel column temporary fixing structure
CN204510231U (en) A kind of Circular Pit is inverse makes retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190211

Address after: Room 2-3116, 88 Huanhan Road, Tianjin Free Trade Zone (Airport Economic Zone), Tianjin 300000

Applicant after: CHINA RAILWAY LIUYUAN GROUP Co.,Ltd.

Address before: 300000 Hebei Avenue, new Hongqiao, Hongqiao District, Tianjin City, No. 1

Applicant before: CHINA RAILWAY TUNNEL SURVEY & DESIGN INSTITUTE Co.,Ltd.

TA01 Transfer of patent application right
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170510

WD01 Invention patent application deemed withdrawn after publication