CN106638595A - Concrete prefabricated pile rapid sinking method - Google Patents

Concrete prefabricated pile rapid sinking method Download PDF

Info

Publication number
CN106638595A
CN106638595A CN201510711735.XA CN201510711735A CN106638595A CN 106638595 A CN106638595 A CN 106638595A CN 201510711735 A CN201510711735 A CN 201510711735A CN 106638595 A CN106638595 A CN 106638595A
Authority
CN
China
Prior art keywords
pile
sinking
end plate
prefabricated tubular
prefabricated pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510711735.XA
Other languages
Chinese (zh)
Inventor
梁建民
马光大
赵志飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mcc No13 Construction Co Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
Shanghai Mcc No13 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mcc No13 Construction Co Ltd filed Critical Shanghai Mcc No13 Construction Co Ltd
Priority to CN201510711735.XA priority Critical patent/CN106638595A/en
Publication of CN106638595A publication Critical patent/CN106638595A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the field of pile foundation construction, in particular to a concrete prefabricated pile rapid sinking method. The concrete prefabricated pile rapid sinking method includes the following steps: a step 1, machining a steel bar into a circular hoop, wherein the inner diameter of the circular loop is equal to the outer diameter of a prefabricated pile; a step 2, welding the circular loop on the outer periphery of the top of a pile head end plate of the prefabricated pile; a step 3, determining and rechecking a pile position, and performing pile sinking construction work; and a step 4, sinking a first joint of the prefabricated pile, and then connecting and sinking next joints of the prefabricated pile joint by joint till the pile head end plate reaches to a designed position, and completing pile sinking construction. The concrete prefabricated pile rapid sinking method can use local materials, is low in cost, is low in processing difficulty, has high operability, is good in pile sinking effect, and can greatly improve the pile sinking efficiency and quality.

Description

The quick pile sinking process of concrete precast pile
Technical field
The present invention relates to pile foundation construction field, the quick pile sinking process of specifically a kind of concrete precast pile.
Background technology
Pile foundation in skyscraper, bridge and port engineering using extremely wide, its have high capacity, good stability, settling amount little and it is uniform, be easy to the outstanding features such as mechanized construction, strong adaptability.
Then prefabricated tubular pile can be transported at stake position at the construction field (site) or prefabrication, then Jing hammer modes squeeze into stratum design attitude, i.e. piling construction.Pile driving method by hammer advantage is that equipment is simple, pile sinking speed is fast, low cost.However, when the layer of sand that soil property is harder, needs run through is thicker, pile sinking is extremely difficult, effect is reduced.At present frequently with the pile top that a steel plate processing is welded in pile crown position solving the above problems, but as Shen Ding exists《Engineering technology》(13rd phase in 2013)" brief talking the FAQs and countermeasure of the pile foundation construction " text delivered is pointed out, when stake sinkage does not reach design requirement, using large-tonnage pile frame and can adopt heavy hammer and low strike method pile sinking, and problem is that effect is still low, and it is damaged to easily cause pile crown.
The content of the invention
It is an object of the present invention to provide it is a kind of it is simple and practical, suitable for hard soil layer or the high-quality through operating modes such as layers of sand, the pile sinking process of high effect.
In order to achieve the above object, the present invention is realized in:
A kind of quick pile sinking process of concrete precast pile, comprises the steps,
Step 1, with one annular anchor ear of steel bar meter, the internal diameter of the annular anchor ear is equal with the stake external diameter of prefabricated tubular pile;
Step 2, by annular anchor ear full weld prefabricated tubular pile pile crown end plate top periphery;
Step 3, determine and check stake position, carry out piling construction operation;
After the completion of the first section pile sinking of step 4, prefabricated tubular pile, section by section simultaneously piling construction subsequently respectively saves prefabricated tubular pile for connection, and straight pile crown end plate reaches design attitude, completes piling construction.
The quick pile sinking process of described concrete precast pile, the diameter of reinforcing bar used by step 1 is not less than 18mm.
The quick pile sinking process of described concrete precast pile, before the pile crown end plate of prefabricated tubular pile pile top is equipped with.
This quick pile sinking process material therefor is easy to gather materials on the spot, with low cost;Process technology difficulty is low, after the full weld anchor ear of pile end plate periphery, foremost outside contacts the linear contact lay become between anchor ear and the soil body with the face between the soil body to original pile body, so greatly reduce frictional force of the pile body just between section and the soil body, so that suffered resistance is less when pile body is penetrating hard soil layer, through sandstone soil layer, thus it is with very strong operability;And pile sinking effect is good, can be good at improving pile sinking efficiency and quality.
Description of the drawings
Fig. 1 is the position view of anchor ear in this pile sinking process.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
As shown in figure 1, a kind of quick pile sinking process of concrete precast pile, comprises the steps,
Step 1, with one annular anchor ear 1 of steel bar meter, the internal diameter of the annular anchor ear 1 is equal with the stake external diameter of prefabricated tubular pile 2;
Step 2, by the full weld of annular anchor ear 1 prefabricated tubular pile 2 the top periphery of pile crown end plate 3;
Step 3, determine and check stake position, carry out piling construction operation;
After the completion of the first section pile sinking of step 4, prefabricated tubular pile 2, section by section simultaneously piling construction subsequently respectively saves prefabricated tubular pile for connection, until first segment pile crown end plate reaches design attitude, completes piling construction.
The quick pile sinking process of described concrete precast pile, the diameter of reinforcing bar used by step 1 is not less than 18mm.
The quick pile sinking process of described concrete precast pile, before the pile crown end plate 3 of prefabricated tubular pile 2 pile top is equipped with.
This quick pile sinking process material therefor is easy to gather materials on the spot, with low cost;Process technology difficulty is low, after the full weld anchor ear of pile end plate periphery, foremost outside contacts the linear contact lay become between anchor ear and the soil body with the face between the soil body to original pile body, so greatly reduce frictional force of the pile body just between section and the soil body, so that suffered resistance is less when pile body is penetrating hard soil layer, through sandstone soil layer, thus it is with very strong operability;And pile sinking effect is good, can be good at improving pile sinking efficiency and quality.

Claims (3)

1. a kind of quick pile sinking process of concrete precast pile, is characterized in that:Comprise the steps,
Step 1, with one annular anchor ear of steel bar meter, the internal diameter of the annular anchor ear is equal with the stake external diameter of prefabricated tubular pile;
Step 2, by annular anchor ear full weld prefabricated tubular pile pile crown end plate top periphery;
Step 3, determine and check stake position, carry out piling construction operation;
After the completion of the first section pile sinking of step 4, prefabricated tubular pile, section by section simultaneously piling construction subsequently respectively saves prefabricated tubular pile for connection, until pile crown end plate reaches design attitude, completes piling construction.
2. the quick pile sinking process of concrete precast pile according to claim 1, is characterized in that:The diameter of reinforcing bar used by step 1 is not less than 18mm.
3. the quick pile sinking process of concrete precast pile according to claim 1, is characterized in that:Pile top is equipped with before the pile crown end plate of prefabricated tubular pile.
CN201510711735.XA 2015-10-28 2015-10-28 Concrete prefabricated pile rapid sinking method Pending CN106638595A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510711735.XA CN106638595A (en) 2015-10-28 2015-10-28 Concrete prefabricated pile rapid sinking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510711735.XA CN106638595A (en) 2015-10-28 2015-10-28 Concrete prefabricated pile rapid sinking method

Publications (1)

Publication Number Publication Date
CN106638595A true CN106638595A (en) 2017-05-10

Family

ID=58815964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510711735.XA Pending CN106638595A (en) 2015-10-28 2015-10-28 Concrete prefabricated pile rapid sinking method

Country Status (1)

Country Link
CN (1) CN106638595A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000154540A (en) * 1998-09-18 2000-06-06 Sumitomo Metal Ind Ltd Bored pile, its work execution method, work execution device, and existing pile for bored pile
CN202577289U (en) * 2012-04-20 2012-12-05 中交第三航务工程局有限公司 Prestressed concrete pipe pile with easiness for pile sinking
CN103397632A (en) * 2013-08-06 2013-11-20 中国电力工程顾问集团华东电力设计院 PHC tubular pile and pile sinking method thereof
CN104452754A (en) * 2014-11-28 2015-03-25 中铁二十三局集团有限公司 Prestress concrete pipe pile construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000154540A (en) * 1998-09-18 2000-06-06 Sumitomo Metal Ind Ltd Bored pile, its work execution method, work execution device, and existing pile for bored pile
CN202577289U (en) * 2012-04-20 2012-12-05 中交第三航务工程局有限公司 Prestressed concrete pipe pile with easiness for pile sinking
CN103397632A (en) * 2013-08-06 2013-11-20 中国电力工程顾问集团华东电力设计院 PHC tubular pile and pile sinking method thereof
CN104452754A (en) * 2014-11-28 2015-03-25 中铁二十三局集团有限公司 Prestress concrete pipe pile construction method

Similar Documents

Publication Publication Date Title
CN205742241U (en) A kind of steel pipe perfusion prestressing force voltage stabilizing envelope stake device
CN111691420B (en) Construction method of PHC tubular pile
CN106337570B (en) Steel pipe grouting rapid reinforcement rod structure and construction method
CN205399418U (en) Sharp structure of stake that reinforcing PHC tubular pile pile sinking broke ground
CN102605785A (en) Prestressing pile sealing device for statically pressed piles of anchor bars
CN102251521A (en) Reinforced prestressed tubular pile and construction method thereof
CN104594343B (en) A kind of assembled stake and its construction method
CN210482760U (en) A steel bar sleeve grout connects overlap joint for assembled structure
CN208857811U (en) A kind of steel-pipe pile super-tonnage prestressing force envelope pilework
CN106638595A (en) Concrete prefabricated pile rapid sinking method
CN103572760A (en) Bored grouting pile whole pile length vibrating construction method and device
CN104343117A (en) Concrete pipe pile connector
CN204199543U (en) The full grouting connecting reinforcement sleeve of the variable cross section realized by technique for rolling
CN108999227A (en) A kind of ruggedized construction and its construction method on building basis
CN206158226U (en) Quick reinforced concrete column structure of steel pipe slip casting
CN203741835U (en) Pile tip structure for prefabricated pipe pile
CN204212153U (en) Assembled steel guard cylinder
CN103882859A (en) Original-state soil borrowing press-grouting concrete pile exerted by prestress and construction method thereof
CN206607586U (en) A kind of self-balancing grouting under pressure steel tube for soil-nail structure
CN106223334A (en) Broken pile repairing method and reinforcing structure thereof
CN202954356U (en) Concrete pile with connecting mechanism
CN207193965U (en) A kind of prestressed pipe pile end plate
CN205205826U (en) Tubular pile bottom slip casting device
CN204456096U (en) The shoe of rock steel pipe can be entered
CN204252127U (en) A kind of assembling stake

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510