CN106638324B - A kind of construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge - Google Patents
A kind of construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge Download PDFInfo
- Publication number
- CN106638324B CN106638324B CN201611262469.8A CN201611262469A CN106638324B CN 106638324 B CN106638324 B CN 106638324B CN 201611262469 A CN201611262469 A CN 201611262469A CN 106638324 B CN106638324 B CN 106638324B
- Authority
- CN
- China
- Prior art keywords
- box girder
- bridge
- prefabricated
- plate
- high performance
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/268—Composite concrete-metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种超高性能混凝土波形钢腹板组合箱梁桥的施工方法:首先按设计要求预制每跨箱梁的U形槽结构件;根据预制的U形槽结构件预制桥面中板;施工桥台、桥墩,将预制的U形槽结构件和桥面中板吊装就位,绑扎横向连接钢筋,浇筑横向湿接缝后形成完整的箱梁;施工下一个桥墩,将第二个箱梁吊装就位,相邻箱梁的波形钢腹板进行焊接,绑扎相邻箱梁间的纵向连接钢筋,浇筑相邻箱梁节段间的纵向湿接缝或现浇横梁,形成连续桥梁结构;待湿接缝混凝土达到设计强度值后,张拉顶板预应力钢束;重复上述步骤,完成多跨连续的桥梁结构。本发明箱梁自重轻、扭转畸变小、桥面板荷载分配能力好、施工架设方便,在大中跨径桥梁上具有广阔的应用前景。
This invention discloses a construction method for an ultra-high performance concrete corrugated steel web composite box girder bridge: First, U-shaped channel structural components for each span of the box girder are prefabricated according to design requirements; then, the bridge deck slab is prefabricated based on the prefabricated U-shaped channel structural components; the abutments and piers are constructed, and the prefabricated U-shaped channel structural components and bridge deck slabs are hoisted into place, transverse connecting reinforcement is tied, and transverse wet joints are poured to form a complete box girder; the next pier is constructed, the second box girder is hoisted into place, the corrugated steel webs of adjacent box girders are welded, longitudinal connecting reinforcement between adjacent box girders is tied, and longitudinal wet joints or cast-in-place crossbeams are poured between adjacent box girder segments to form a continuous bridge structure; after the wet joint concrete reaches the design strength value, the prestressed steel strands of the top slab are tensioned; the above steps are repeated to complete a multi-span continuous bridge structure. The box girder of this invention has a light self-weight, small torsional distortion, good load distribution capacity of the bridge deck, and is convenient for construction and erection, and has broad application prospects in medium and large span bridges.
Description
技术领域technical field
本发明涉及公路和城市道路桥梁技术,尤其是涉及一种超高性能混凝土波形钢腹板组合箱梁桥的施工方法。The invention relates to highway and urban road bridge technology, in particular to a construction method of an ultra-high performance concrete corrugated steel web composite box girder bridge.
背景技术Background technique
采用波形钢腹板代替传统混凝土箱梁的混凝土厚腹板,形成波形钢腹板箱梁,不仅结构的整体造型美观,同时避免了传统混凝土箱梁腹板开裂的问题,耐久性能好,故在大中跨度桥梁中得到了广泛应用。The corrugated steel web is used to replace the concrete thick web of the traditional concrete box girder to form a corrugated steel web box girder. Not only the overall shape of the structure is beautiful, but also the problem of cracking of the traditional concrete box girder web is avoided, and the durability is good. Widely used in large and medium span bridges.
与传统的混凝土箱梁相比,由于波形钢腹板箱梁断面的抗扭刚度和抗畸变刚度有所降低,所以波形钢腹板箱梁的宽度不宜太宽。一般而言,单箱单室的现浇混凝土箱梁或波形钢腹板组合箱梁最大宽度不超过5m,更宽的单箱箱梁要通过增加腹板数量形成单箱双室或单箱多室断面,或施加横向预应力钢束,以适应桥梁宽度的要求,避免桥面板受力过大,这样就导致出现梁体重量增加,施工难度增大,混凝土不易浇注等问题。Compared with the traditional concrete box girder, the width of the corrugated steel web box girder should not be too wide because the torsional stiffness and anti-distortion stiffness of the section of the corrugated steel web box girder are reduced. Generally speaking, the maximum width of a single-box single-chamber cast-in-situ concrete box girder or a corrugated steel web composite box girder does not exceed 5m, and a wider single-box box girder must be formed by increasing the number of webs to form a single box with double rooms or a single box with multiple Chamber section, or apply transverse prestressed steel beams to meet the requirements of bridge width and avoid excessive force on the bridge deck, which will lead to problems such as increased beam weight, increased construction difficulty, and difficult pouring of concrete.
UHPC(Ultra High Performance Concrete,超高性能混凝土)是一种高强度(抗拉强度大于7MPa、抗压强度大于150MPa)、高耐久性的新型混凝土材料。UHPC高性能的特点主要在于应力和拉应变的硬化,即产生类似于钢材拉应力屈服的行为,适当配筋的UHPC力学性能接近钢结构。在目前的水平上,已经显现出用于如桥梁这种重大结构工程中的优势,使得整体结构外观趋于轻巧,钢筋用量减少,某些工程甚至取消了钢筋。UHPC (Ultra High Performance Concrete) is a new type of concrete material with high strength (tensile strength greater than 7MPa, compressive strength greater than 150MPa) and high durability. The high performance of UHPC is mainly characterized by the hardening of stress and tensile strain, that is, the behavior similar to the yielding of steel under tensile stress, and the mechanical properties of UHPC with proper reinforcement are close to steel structures. At the current level, the advantages of being used in major structural projects such as bridges have been shown, making the appearance of the overall structure lighter, reducing the amount of steel bars, and some projects even cancel the steel bars.
采用UHPC材料,桥梁构件可减小结构尺寸,趋于纤细轻薄,从而降低自重,提高结构抵抗荷载的效率和增大桥梁的跨越能力,同时吊装、架设方便。因此,将传统波形钢腹板箱梁与超高性能混凝土(UHPC)结合,形成预应力超高性能混凝土波形钢腹板连续箱梁,对解决现有预应力混凝土连续箱梁桥腹板开裂和自重较大,施工复杂等难题具有重要意义。Using UHPC materials, bridge components can reduce the structural size and tend to be thinner and thinner, thereby reducing the self-weight, improving the efficiency of the structure to resist loads and increasing the spanning capacity of the bridge, and at the same time, it is convenient for hoisting and erection. Therefore, the traditional corrugated steel web box girder is combined with ultra-high performance concrete (UHPC) to form a prestressed UHPC continuous box girder with corrugated steel web, which is helpful to solve the problems of web cracking and cracking in existing prestressed concrete continuous box girder bridges The problems such as heavy weight and complex construction are of great significance.
发明内容Contents of the invention
本发明的目的在于提供一种超高性能混凝土波形钢腹板组合箱梁桥的施工方法,本发明的组合箱梁桥既具备传统波形钢腹板箱梁桥的优点,又有自重轻、桥面板荷载分配能力好、箱梁扭转畸变效应小等一系列优点,使单箱室桥面总宽度可达10m以上,且箱梁的主要构件均可在预制场内完成,现场施工作业少。The object of the present invention is to provide a construction method for an ultra-high performance concrete corrugated steel web composite box girder bridge. The composite box girder bridge of the present invention not only possesses the advantages of traditional corrugated steel web A series of advantages such as good load distribution capacity of the panel and small torsional distortion effect of the box girder make the total width of the bridge deck of a single box room more than 10m, and the main components of the box girder can be completed in the prefabricated field, with less on-site construction work.
为实现上述目的,本发明可采取下述技术方案:To achieve the above object, the present invention can take the following technical solutions:
本发明所述的超高性能混凝土波形钢腹板组合箱梁桥的施工方法包括下述步骤:The construction method of the ultra-high performance concrete corrugated steel web composite box girder bridge of the present invention comprises the following steps:
第一步,按桥梁设计要求,预制每跨箱梁的U形槽结构件:在预制场将波形钢腹板就位,并在其上、下翼缘上焊接栓钉连接件,然后在张拉台座上预定位置固定箱梁底板的预应力钢筋并张拉至设计值,再绑扎钢筋网,预埋顶板预应力管道,架设模板,浇注超高性能混凝土,预制包括桥面边板、箱梁底板、波形钢腹板、横隔板的U形槽结构件,其中桥面边板上预埋吊环;然后用蒸汽养护,48小时后拆模;The first step is to prefabricate the U-shaped channel structure of each span box girder according to the design requirements of the bridge: put the corrugated steel web in place in the prefabrication field, and weld the stud connectors on its upper and lower flanges, and then Fix the prestressed reinforcement of the bottom plate of the box girder at the predetermined position on the pedestal and stretch it to the design value, then bind the steel mesh, pre-bury the prestressed pipe on the roof, erect the formwork, pour ultra-high performance concrete, and prefabricate the side plate of the bridge deck and the box girder The bottom plate, corrugated steel web, and U-shaped groove structural parts of the transverse diaphragm, among which the suspension rings are pre-embedded on the side plate of the bridge deck; then cured with steam, and the formwork is removed after 48 hours;
第二步,根据第一步预制的U形槽结构件的桥面边板之间的距离预制桥面中板:绑扎钢筋网,预埋顶板预应力管道,架设模板,并在其上预埋吊环、横向连接钢筋、纵向连接钢筋,然后浇注超高性能混凝土,并用蒸汽养护,48小时后拆模;成型后的桥面中板总厚0.2m~0.5m,底部带有纵、横交错的T形加强肋;The second step is to prefabricate the middle plate of the bridge deck according to the distance between the bridge deck side plates of the U-shaped groove structural parts prefabricated in the first step: bind the steel mesh, pre-bury the prestressed pipe on the top plate, erect the formwork, and pre-bury it Hanging rings, horizontal connecting steel bars, and longitudinal connecting steel bars, then cast ultra-high performance concrete, cure with steam, and remove the formwork after 48 hours; T-shaped ribs;
第三步,施工桥台、桥墩,依次将预制的U形槽结构件和桥面中板吊装就位,绑扎横向连接钢筋,浇筑横向湿接缝后形成一个完整的箱梁;The third step is to construct the abutment and bridge piers, hoist the prefabricated U-shaped groove structural parts and the middle plate of the bridge deck in sequence, bind the horizontal connecting steel bars, and form a complete box girder after pouring the horizontal wet joints;
第四步,施工下一个桥墩,然后将第二个箱梁吊装就位,将相邻箱梁的波形钢腹板焊接为一体,并绑扎相邻箱梁之间的纵向连接钢筋,再浇筑相邻箱梁之间的纵向湿接缝或现浇横梁,形成连续的桥梁结构;待浇筑的混凝土达到设计强度值后,张拉穿设在顶板预应力管道中的预应力钢束;The fourth step is to construct the next pier, then hoist the second box girder into place, weld the corrugated steel webs of the adjacent box girders into one, bind the longitudinal connecting steel bars between adjacent box girders, and then pour the corresponding The longitudinal wet joints or cast-in-place beams between adjacent box girders form a continuous bridge structure; after the poured concrete reaches the design strength value, the prestressed steel strands installed in the roof prestressed pipe are stretched;
第五步,重复第四步,完成多跨连续的桥梁结构。In the fifth step, repeat the fourth step to complete the multi-span continuous bridge structure.
第一步预制每跨箱梁的U形槽结构件时,相邻两横隔板之间的间距小于5m。When prefabricating the U-shaped groove structural members of each span box girder in the first step, the distance between two adjacent diaphragms is less than 5m.
本发明施工方法与现有技术相比,其优点体现在:Compared with the prior art, the construction method of the present invention has the advantages of:
1)本发明采用超高性能混凝土材料(UHPC),构件在结构尺寸上趋于纤薄,自重较传统波形钢腹板箱梁降低约15-25%;1) The present invention adopts ultra-high performance concrete (UHPC), and the structural size of the members tends to be thinner, and the dead weight is about 15-25% lower than that of the traditional corrugated steel web box girder;
2)本发明的箱梁顶板(桥面中板)和箱梁底板采用超高性能混凝土材料制成,能充分利用UHPC的高抗拉、抗压特性;箱梁腹板采用波形钢腹板,能充分利用其优良的抗剪性能。2) The top plate of the box girder (middle plate of the bridge deck) and the bottom plate of the box girder of the present invention are made of ultra-high performance concrete materials, which can make full use of the high tensile and compressive properties of UHPC; the web of the box girder is made of corrugated steel web, Can make full use of its excellent shear performance.
3)本发明的箱梁顶板(桥面中板)采用了带T形矮纵肋和T形矮横肋的桥面板结构,承载效率比传统矩形截面箱梁顶板高,且荷载分配能力好,箱梁横向宽度可达到10m以上;3) The box girder roof (middle deck of the bridge deck) of the present invention adopts a bridge deck structure with T-shaped short longitudinal ribs and T-shaped short transverse ribs, and its load-bearing efficiency is higher than that of the traditional rectangular-section box girder roof, and its load distribution capacity is good. The transverse width of the box girder can reach more than 10m;
4)本发明在每跨箱梁内设置了较为密集的横隔板,使箱梁结构的整体性好,箱梁的扭转畸变效应小;4) In the present invention, relatively dense transverse diaphragms are arranged in each span of the box girder, so that the integrity of the box girder structure is good, and the torsional distortion effect of the box girder is small;
5)本发明的箱梁桥采用预制拼装的施工工艺,一方面由于采用超高性能混凝凝土材料,使箱梁的混凝土构件较为轻薄,便于吊装施工;另一方面,箱梁的主要构件(U形槽结构件和桥面中板)可在预制场内完成,现场模板和现浇施工作业量少,便于桥梁的快速架设;5) The box girder bridge of the present invention adopts the construction technology of prefabrication and assembly. On the one hand, due to the use of ultra-high performance concrete materials, the concrete members of the box girder are relatively light and thin, which is convenient for hoisting construction; on the other hand, the main components of the box girder (U-shaped groove structural parts and bridge deck middle plate) can be completed in the prefabricated field, with less on-site formwork and cast-in-place construction work, which is convenient for the rapid erection of the bridge;
6)本发明的箱梁底板预应力采用先张法预应力,比传统的后张法预应力波形钢腹板箱梁的现场钢束张拉作业量少,施工便捷。6) The prestressing of the box girder bottom plate of the present invention adopts the pretensioning method, which is less than the traditional post-tensioning prestressed corrugated steel web box girder on-site steel beam tensioning work, and the construction is convenient.
综上,本发明具有箱梁自重轻、扭转畸变小、桥面板的荷载分配能力好、施工架设方便等一系列优点。箱梁采用具有高耐久性的超高性能混凝土浇注,结构的耐久性好,尤其在大中跨径桥梁上具有广阔的应用前景。In summary, the present invention has a series of advantages such as light weight of the box girder, small torsional distortion, good load distribution capacity of the bridge deck, and convenient construction and erection. The box girder is poured with high-durability ultra-high-performance concrete, and the structure has good durability, especially in large and medium-span bridges, which has broad application prospects.
附图说明Description of drawings
图1是本发明预制的U形槽结构件的结构示意图。Fig. 1 is a schematic structural view of the prefabricated U-shaped groove structure of the present invention.
图2是本发明预制的桥面中板的结构图。Fig. 2 is a structural diagram of the prefabricated bridge deck middle plate of the present invention.
图3是图2的仰视图。FIG. 3 is a bottom view of FIG. 2 .
图4为就位一个箱梁的结构图。Figure 4 is a structural diagram of a box girder in place.
图5是图4中箱梁的纵向剖面图。Fig. 5 is a longitudinal sectional view of the box girder in Fig. 4 .
图6为就位2个箱梁的结构图。Figure 6 is a structural diagram of two box girders in place.
图7是图6的俯视结构图。FIG. 7 is a top structural view of FIG. 6 .
具体实施方式Detailed ways
本发明的超高性能混凝土波形钢腹板组合箱梁桥的施工方法包括下述步骤:The construction method of the ultra-high performance concrete corrugated steel web composite box girder bridge of the present invention comprises the following steps:
第一步,按桥梁设计要求,预制每跨箱梁的U形槽结构件:在预制场将两侧的波形钢腹板1.1、1.2就位,并在其上、下翼缘上焊接栓钉连接件2.1、2.2、2.3、2.4,然后在张拉台座上预定位置固定箱梁底板的先张预应力钢筋12,并张拉至设计值,再绑扎钢筋网,预埋顶板预应力管道13,架设模板,浇注超高性能混凝土,预制包括桥面边板3.1、3.2,箱梁底板4、波形钢腹板1.1、1.2、横隔板5的U形槽结构件,其中桥面边板3.1、3.2上分别预埋吊环6.1、6.2;然后用蒸汽养护,48小时后拆模,成型后的U形槽结构件如图1所示;其中每跨箱梁的两端均设置端板,箱梁内横隔板要设置的较为密集,一般情况下相邻两横隔板之间的间距小于5m,以保证箱梁的整体性,使其扭转畸变效应小;波形钢腹板1.1、1.2采用工字型波纹钢板;The first step is to prefabricate the U-shaped groove structural parts of each span box girder according to the bridge design requirements: place the corrugated steel webs 1.1 and 1.2 on both sides in the prefabrication field, and weld studs on the upper and lower flanges Connectors 2.1, 2.2, 2.3, 2.4, then fix the pre-tensioned prestressed reinforcement 12 of the bottom plate of the box girder at a predetermined position on the tensioning platform, and stretch it to the design value, then bind the reinforcement mesh, and pre-embed the roof prestressed pipe 13, Erect formwork, pour ultra-high-performance concrete, and prefabricate U-shaped groove structural parts including bridge deck side plates 3.1, 3.2, box girder bottom plate 4, corrugated steel webs 1.1, 1.2, and transverse diaphragm 5, of which bridge deck side plates 3.1, Embed rings 6.1 and 6.2 respectively on 3.2; then use steam to cure, and remove the mold after 48 hours. The inner diaphragms should be densely arranged. Generally, the distance between two adjacent diaphragms is less than 5m, so as to ensure the integrity of the box girder and reduce the effect of torsional distortion; the corrugated steel webs 1.1 and 1.2 adopt industrial Font corrugated steel plate;
第二步,根据第一步预制的U形槽结构件的桥面边板3.1、3.2之间的距离预制桥面中板7:绑扎钢筋网,架设模板,并在其上预埋吊环7.1、横向连接钢筋7.2、纵向连接钢筋7.3,然后浇注超高性能混凝土,并用蒸汽养护,48小时后拆模;成型后的桥面中板7总厚0.3m(根据桥梁宽度,可在0.2m~0.5m之间进行调整),底部带有纵、横交错的T形加强肋7.4(较矮),如图2、图3所示;The second step is to prefabricate the bridge deck middle plate 7 according to the distance between the bridge deck side plates 3.1 and 3.2 of the U-shaped groove structure prefabricated in the first step: bind the steel mesh, erect the formwork, and pre-embed the suspension ring 7.1, Horizontal connecting steel bar 7.2, vertical connecting steel bar 7.3, then pour ultra-high performance concrete, and steam curing, remove the formwork after 48 hours; the total thickness of the formed bridge deck middle plate 7 is 0.3m (according to the width of the bridge, it can be between 0.2m~0.5 m), the bottom has T-shaped stiffening ribs 7.4 (shorter) that intersect vertically and horizontally, as shown in Figure 2 and Figure 3;
第三步,施工桥台8、桥墩9,依次将预制的U形槽结构件和桥面中板7吊装就位,绑扎横向连接钢筋7.2,浇筑横向湿接缝10后形成一个完整的箱梁,如图4、图5所示;The third step is to construct the abutment 8 and the bridge pier 9, hoist the prefabricated U-shaped groove structural parts and the bridge deck mid-slab 7 in place in sequence, bind the transverse connecting steel bars 7.2, and pour the transverse wet joints 10 to form a complete box girder , as shown in Figure 4 and Figure 5;
第四步,施工下一个桥墩9,然后将第二个箱梁吊装就位,将相邻箱梁的波形钢腹板焊接为一体,并绑扎相邻箱梁之间的纵向连接钢筋7.3,再浇筑相邻箱梁之间的纵向湿接缝或现浇横梁11,形成连续的桥梁结构;待浇筑的混凝土达到设计强度值后,张拉穿设在顶板预应力管道13中的预应力钢束;如图6、图7所示;The fourth step is to construct the next pier 9, then hoist the second box girder into place, weld the corrugated steel webs of the adjacent box girders into one, and bind the longitudinal connecting steel bars 7.3 between adjacent box girders, and then Pouring the longitudinal wet joints or cast-in-place beams 11 between adjacent box girders to form a continuous bridge structure; after the concrete to be poured reaches the design strength value, stretch the prestressed steel strands in the roof prestressed pipe 13 ; As shown in Figure 6 and Figure 7;
第五步,重复第四步,完成多跨连续的桥梁结构,最后拆除模板,完成桥梁架设。The fifth step is to repeat the fourth step to complete the multi-span continuous bridge structure, and finally remove the formwork to complete the bridge erection.
Claims (2)
- A kind of 1. construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge, it is characterised in that:Including following steps Suddenly:The first step, it is prefabricated often across the U groove structure part of box beam by Bridge Design requirement:It is in precasting yard that Wavelike steel webplate is in place, And thereon, weld stud connector on lower flange, then the prestressing force of box beam bottom plate is fixed in precalculated position on stretching bed seat Reinforcing bar is simultaneously stretched to design load, then assembling reinforcement net, pre-buried top plate prestress pipe, sets up template, pours into a mould very-high performance coagulation Soil, it is prefabricated including bridge floor side plate, box beam bottom plate, Wavelike steel webplate, diaphragm plate U groove structure part, it is pre- wherein on bridge floor side plate Bury suspension ring;Then steam curing, form removal after 48 hours are used;Second step, according to plate in the distance between the prefabricated bridge floor side plate of U groove structure part of the first step prefabricated bridge floor:Colligation steel Muscle net, pre-buried top plate prestress pipe, template is set up, and in pre-buried suspension ring thereon, lateral connection reinforcing bar, longitudinally connected reinforcing bar, Then ultra-high performance concrete is poured into a mould, and with steam curing, form removal after 48 hours;Plate total thickness 0.2m in bridge floor after shaping ~ 0.5m, bottom is with longitudinal and transverse T-shaped ribs staggeredly;3rd step, construction abutment, bridge pier, successively lifts plate in prefabricated U groove structure part and bridge floor in place, colligation laterally connects Reinforcing bar is connect, a complete box beam is formed after pouring laterally wet seam;4th step, next bridge pier of constructing is then in place by second box beam lifting, and the Wavelike steel webplate of adjacent box beam is welded It is integrated, and the longitudinally connected reinforcing bar between the adjacent box beam of colligation, then pour the longitudinal wet joint or cast-in-place between adjacent box beam Crossbeam, form continuous bridge structure;After the concrete poured reaches design strength value, tensioning is located in top plate prestressed pipe Prestressed strand in road;5th step, the 4th step is repeated, complete the continuous bridge structure of multispan.
- 2. the construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge according to claim 1, its feature It is:The first step is prefabricated often when the U groove structure part of box beam, and 5m is smaller than between adjacent two diaphragm plate.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201611262469.8A CN106638324B (en) | 2016-12-30 | 2016-12-30 | A kind of construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201611262469.8A CN106638324B (en) | 2016-12-30 | 2016-12-30 | A kind of construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106638324A CN106638324A (en) | 2017-05-10 |
| CN106638324B true CN106638324B (en) | 2018-02-02 |
Family
ID=58837621
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201611262469.8A Active CN106638324B (en) | 2016-12-30 | 2016-12-30 | A kind of construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106638324B (en) |
Families Citing this family (16)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107675610B (en) * | 2017-10-29 | 2019-08-09 | 北京工业大学 | A Construction and Method of Segmental Connection of Prefabricated Assembled Bridge Piers |
| CN108824163A (en) * | 2018-07-05 | 2018-11-16 | 中国矿业大学(北京) | Wavelike steel webplate prestressing combined box beam bridge |
| CN109016127B (en) * | 2018-07-27 | 2020-07-24 | 中国十七冶集团有限公司 | Bridge arch box prefabrication production and transverse connection method thereof |
| CN109057148A (en) * | 2018-09-29 | 2018-12-21 | 中路杜拉国际工程股份有限公司 | Ultra-high performance concrete is without regular reinforcement Prestressed U type beam and its construction method |
| CN109208487A (en) * | 2018-10-24 | 2019-01-15 | 中铁第勘察设计院集团有限公司 | Railway ultra-high performance concrete box girder formwork and construction method |
| CN109898398A (en) * | 2019-03-15 | 2019-06-18 | 长沙理工大学 | A kind of fold-type UHPC top plate-corrugated steel web plate composite box girder bridge |
| CN109914216B (en) * | 2019-03-29 | 2024-04-16 | 湖南大学 | A prefabricated large-span ultra-high performance concrete box girder combined node and connection method thereof |
| CN110005429B (en) * | 2019-05-22 | 2024-09-13 | 河南省交通规划设计研究院股份有限公司 | Box-type roof structure at the fork of urban tunnel |
| CN110438879A (en) * | 2019-07-18 | 2019-11-12 | 广东冠粤路桥有限公司 | A kind of ultra-high performance concrete bridge structure and its construction method |
| CN110644349B (en) * | 2019-10-31 | 2024-10-29 | 山东省交通规划设计院集团有限公司 | Superstructure for wide box girder low tower cable-stayed bridge and construction method |
| CN111206489A (en) * | 2020-03-02 | 2020-05-29 | 甘肃省交通规划勘察设计院股份有限公司 | An assembled corrugated web steel box-UHPC composite girder bridge and construction method |
| CN111962472A (en) * | 2020-08-28 | 2020-11-20 | 华南理工大学 | An ultra-high performance concrete lightweight U-shaped aqueduct body |
| CN112081070A (en) * | 2020-08-28 | 2020-12-15 | 华南理工大学 | Design method of ultra-high performance concrete circular aqueduct and aqueduct |
| CN112942054B (en) * | 2021-04-13 | 2025-07-29 | 上海市城市建设设计研究总院(集团)有限公司 | Mixed-tensioning light prefabricated small box girder structure and construction method |
| CN113047161A (en) * | 2021-04-20 | 2021-06-29 | 湖南省交通规划勘察设计院有限公司 | Joint structure of NC-UHPC (numerical control-ultra high-performance polycarbonate) hybrid rigid frame bridge, hybrid rigid frame bridge and construction method of hybrid rigid frame bridge |
| CN117385747B (en) * | 2023-08-25 | 2026-02-06 | 湖南大学 | Standardized construction method for steel inner core-UHPC combined box girder |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2007040020A (en) * | 2005-08-04 | 2007-02-15 | Ps Mitsubishi Construction Co Ltd | Construction method for prestressed concrete box girder bridge |
| KR101067001B1 (en) * | 2011-02-17 | 2011-09-22 | 김찬수 | Slab construction method of steel box girder bridge using rebar |
| CN103669193B (en) * | 2014-01-13 | 2016-02-03 | 河南省交通规划设计研究院股份有限公司 | A kind of laterally assembled Wavelike steel webplate combination T beam and construction method |
| CN203755127U (en) * | 2014-03-10 | 2014-08-06 | 中交第三公路工程局有限公司 | Pre-stress high-performance concrete continuous box girder bridge |
| CN204370310U (en) * | 2014-12-19 | 2015-06-03 | 湖南明湘科技发展有限公司 | A kind of two dimension waveform steel and concrete combined bridge deck |
| CN104988844B (en) * | 2015-05-19 | 2016-08-24 | 河南省交通规划设计研究院股份有限公司 | Two times tensioning prestressing force assembled Wavelike steel webplate combination beam |
| CN105369729A (en) * | 2015-12-11 | 2016-03-02 | 河南省交通规划设计研究院股份有限公司 | External prestressing corrugated steel web T-shaped beam and construction method |
-
2016
- 2016-12-30 CN CN201611262469.8A patent/CN106638324B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN106638324A (en) | 2017-05-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106638324B (en) | A kind of construction method of ultra-high performance concrete corrugated steel web plate composite box girder bridge | |
| CN103696355B (en) | The light-duty combined bridge structure of a kind of superhigh tenacity concrete slab-girder steel | |
| CN109024225B (en) | Ultra-high performance concrete truss arch piece unit, truss arch piece bridge and construction method | |
| CN105839510B (en) | A kind of steel and ultra-high performance concrete composite continuous bridge structure and its construction method | |
| CN106758856B (en) | The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block | |
| CN203768784U (en) | Super toughness concrete plate-steel beam light combined bridge structure | |
| CN106894326B (en) | The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder | |
| CN103046463B (en) | Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof | |
| CN108824162A (en) | A kind of steel_concrete composite beam and its construction method using plain plate and corrugated sheet steel mixing web | |
| CN105803916B (en) | Light-duty combined box-type bent cap of steel and ultra-high performance concrete and preparation method thereof | |
| CN109440623B (en) | Temporary splicing structure of precast bridge of concrete segment | |
| CN104032668B (en) | Half-through steel purlin-Combined concrete continuous steel frame bridge | |
| CN102704406B (en) | Roadbed slab non-tensile stress construction method based on combined channel girder | |
| CN109024219B (en) | Prefabricated ultrahigh-performance concrete-common concrete combined beam bridge structure and construction method | |
| CN104762871A (en) | Prestressed concrete-steel tank beam bond beam continuous beam bridge | |
| CN112012091A (en) | UHPC-NC mixed box girder, large-span rigid frame bridge and construction method thereof | |
| CN113106845A (en) | Assembled tie bar rectangular steel tube concrete truss composite beam and construction method thereof | |
| CN108316120A (en) | It can rapidly-assembled precast bridge and its construction method | |
| CN207973983U (en) | It can rapidly-assembled precast bridge | |
| CN110331664B (en) | Steel-concrete mixed continuous box girder bridge deck joint structure and construction method thereof | |
| CN206408509U (en) | Ultra-high performance concrete corrugated steel web plate composite box girder | |
| CN110172927A (en) | The span centre of prestressed concrete continuous beam and continuous rigid frame closes up section constructing method | |
| CN113106846A (en) | Assembled type reinforced concrete-filled steel tube composite beam and construction method thereof | |
| CN113789711A (en) | NC-UHPC combined assembly type prestressed concrete box girder, construction method and bridge thereof | |
| CN113152784A (en) | Laminated beam and preparation method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 450003 Henan Province, Zhengzhou City, Zhongdong New District, No. 9 Zeyu Street Patentee after: Henan Zhonggong Design and Research Institute Group Co.,Ltd. Country or region after: China Patentee after: Li Feiran Address before: Longhai Road 27 450052 area in Henan city of Zhengzhou province No. 70 Patentee before: HENAN PROVINCIAL COMMUNICATIONS PLANNING & DESIGN INSTITUTE Co.,Ltd. Country or region before: China Patentee before: Li Feiran |