CN106625708A - Electric equipment transportation and clamping device capable of doing circular-arc-shaped motion - Google Patents

Electric equipment transportation and clamping device capable of doing circular-arc-shaped motion Download PDF

Info

Publication number
CN106625708A
CN106625708A CN201611223530.8A CN201611223530A CN106625708A CN 106625708 A CN106625708 A CN 106625708A CN 201611223530 A CN201611223530 A CN 201611223530A CN 106625708 A CN106625708 A CN 106625708A
Authority
CN
China
Prior art keywords
gear
rotating shaft
lock tube
clamping device
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611223530.8A
Other languages
Chinese (zh)
Other versions
CN106625708B (en
Inventor
李胜利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG JINYUAN INDUSTRIAL CO., LTD.
Original Assignee
Dongguan Shengrong Automation Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Shengrong Automation Technology Co Ltd filed Critical Dongguan Shengrong Automation Technology Co Ltd
Priority to CN201611223530.8A priority Critical patent/CN106625708B/en
Publication of CN106625708A publication Critical patent/CN106625708A/en
Application granted granted Critical
Publication of CN106625708B publication Critical patent/CN106625708B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25JMANIPULATORS; CHAMBERS PROVIDED WITH MANIPULATION DEVICES
    • B25J11/00Manipulators not otherwise provided for
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/74Feeding, transfer, or discharging devices of particular kinds or types
    • B65G47/90Devices for picking-up and depositing articles or materials

Abstract

The invention discloses an electric equipment transportation and clamping device capable of doing circular-arc-shaped motion. The electric equipment transportation and clamping device comprises a rotation mechanism mounted on a base plate, a support base mounted on the rotation mechanism and a clamping mechanism mounted on the support base. The base plate is mounted on an angle adjustment mechanism. The angle adjustment mechanism comprises three lifting rods movably connected with the bottom of the base plate. The rotation mechanism can drive the clamping mechanism to transport electric equipment in a rotation manner, the base plate can be inclined through the tree lifting rods, the rotation mechanism rotates on the inclined base plate, and the application range of the electric equipment transportation device is broadened.

Description

It is a kind of can circular movement power equipment transport clamping device
Technical field
The present invention relates to electrical equipment technical field, and in particular to a kind of conveying arrangement of power equipment.
Background technology
During electric power apparatus examination, transmission and transporting power equipment or maintenance tool, traditional power equipment are needed Robot for overhauling tends not to carry out transport operation, and the operation of electric power apparatus examination robotic manipulator is by regulation machine mostly Tool arm, rather than by adjusting the mode of manipulator, limited coverage area is often occurred during the adjustment of mechanical arm, and And when needing to occur circular arc operation trace, need to adjust the position of whole robot to realize operation, it is very inconvenient, while Automaticity is very low.
Authorization Notice No. for the U of CN 203875892 utility model disclose it is a kind of can circular movement power equipment Transport clamping device, is mainly made up of chassis, gear, clamping part, and the gear is located at chassis top, arranges on the chassis There are pushing meanss, the pushing meanss front end is connected with worm screw, and the worm screw engages with gear, the gear top is provided with folder Portion's support base is held, stationary gripping part pedestal, the clamping part end and fixed clamp are provided with the clamping part support base Portion's pedestal is connected.
The content of the invention
Technical problem solved by the invention:How the scope of application of power equipment conveying arrangement is increased.
To solve above-mentioned technical problem, the present invention provides following technical scheme:It is a kind of can circular movement power equipment Transport clamping device, including the rotating mechanism on chassis, the support base on rotating mechanism, installed in support base On clamping device;The chassis is arranged on angle adjusting mechanism, and angle adjusting mechanism includes three with tray bottom activity The elevating lever of connection.
By above-mentioned technical proposal, rotating mechanism can make clamping device transporting power equipment in a rotative pattern, and three lift The setting of bar, inclines can chassis, and rotating mechanism rotates on inclined chassis, increase the applicable model of power equipment conveying arrangement Enclose.Specifically, three elevating levers are circumferentially uniformly distributed, and an elevating lever rises, and another two elevating levers decline, and chassis is inclined Tiltedly, inclined angle is determined by the heave amplitude of three elevating levers.
The bottom on chassis opens up chute, and hinged block is sliding combined with chute, is hinged at the top of hinged block and elevating lever.Directly The elevating lever of line lifting orders about chassis inclination, while chassis OQ t bar rotates, has linear motion, hinged block concurrently Provide condition for above-mentioned linear motion with being slidably matched for chute.
The angle adjusting mechanism includes the change being articulated on basal disc, the base plate being fixed on basal disc and top board, pivot joint First rotating shaft, the second rotating shaft, the second auxiliary rotating shaft on top board, the 3rd rotating shaft, the 3rd auxiliary rotating shaft;First rotating shaft is provided with First gear, first rotating shaft is hollow, and the first elevating lever in three elevating levers is screwed onto in first rotating shaft;Second rotating shaft is provided with Second gear, the second rotary shaft hollow, the second elevating lever in three elevating levers is screwed onto in the second rotating shaft, second gear and second Equipment gear is engaged, and the second equipment gear is arranged in the second auxiliary rotating shaft;3rd rotating shaft is provided with the 3rd gear, the 3rd rotating shaft Hollow, the 3rd elevating lever in three elevating levers is screwed onto in the 3rd rotating shaft, and the 3rd gear is engaged with the 3rd equipment gear, and the 3rd Equipment gear is arranged in the 3rd auxiliary rotating shaft;Above-mentioned first gear, second gear, the second equipment gear, the 3rd gear, the 3rd Equipment gear is located between base plate and top board;Three elevating levers project upwards top board and are flexibly connected with tray bottom;The change Madial wall be provided with least one section tooth bar, it is above-mentioned first gear, second gear, the second equipment gear, the 3rd gear, the 3rd auxiliary Gear is helped to be located in change, first gear, the second equipment gear, the close change edge of the 3rd equipment gear, first gear, second Equipment gear, the core wheel line of the 3rd equipment gear deviate the rotation centerline of change.
By above-mentioned design, only to set one section of tooth bar on change madial wall as a example by, change rotates a circle, respectively with the first tooth Wheel, the second equipment gear, the 3rd equipment gear are engaged once.Jing after one section of rack drives, first gear is rotated forward, the second assist tooth Wheel and the 3rd equipment gear drive respectively second gear and the reversion of the 3rd gear.First gear drives first liter by first rotating shaft Drop bar rises, and second gear drives the second elevating lever to decline by the second rotating shaft, and the 3rd gear drives the 3rd by the 3rd rotating shaft Elevating lever declines, thus, chassis inclines.
First gear, the second equipment gear, the 3rd equipment gear are along change circumference to being uniformly distributed;On the madial wall of change It is provided with three sections of tooth bars, three sections of tooth bars are along change circumference to being uniformly distributed.Change rotates, three sections of tooth bars respectively with first gear, the Two equipment gears, the 3rd equipment gear are engaged simultaneously, improve the inclined efficiency in chassis and stability.
First through hole, the second through hole and third through-hole are opened up on the base plate, activity in first through hole is combined with the first lock Set, activity in the second through hole is combined with the second lock tube, and activity in third through-hole is combined with the 3rd lock tube;First through hole and the first lock The first spring is provided between set, second spring is provided between third through-hole and the second lock tube, between third through-hole and the 3rd lock tube It is provided with the 3rd spring;First lock tube is arranged the bottom of first rotating shaft, and the second lock tube is set in the bottom of the second auxiliary rotating shaft, and the 3rd Lock tube is set in the bottom of the 3rd auxiliary rotating shaft;First rotating shaft, the second auxiliary rotating shaft, the 3rd aid in the bottom of rotating shaft tapered Shape;The tapered shape in inner chamber middle part of the first lock tube, the intracavity bottom of the first lock tube is provided with pilot hole, and the side wall of pilot hole is provided with Guiding projection, on the first lifting bar side wall the gathering sill coordinated with guiding projection is opened up;Second lock tube and the 3rd lock tube The tapered shape of intracavity bottom;Transverse bar, the end of transverse bar are equipped with first lock tube, the second lock tube, the side wall of the 3rd lock tube Portion is provided with convex wedge;Release bar is provided with below arbitrary tooth bar, release bar is arranged on the madial wall of change, release bar Length be equal to arbitrary tooth bar length.
In above-mentioned design, fluted, the first lock tube, second is all provided with first through hole, the second through hole, third through-hole madial wall Projection is all provided with lock tube, the lateral wall of the 3rd lock tube, groove coordinates with projection, to the first lock tube, the second lock tube, the 3rd lock tube Guide effect is played in straight line lifting.
By above-mentioned design, so that one section of tooth bar on change madial wall is engaged with first gear as an example, in one section of tooth bar and Before the engagement of one gear, the release bar of change is contacted first with wedge, and pushes wedge, and wedge drives the first lock tube edge First through hole declines, and the cone-shaped middle part of the first lock tube inner chamber disengages with the cone-shaped bottom of first rotating shaft, first rotating shaft No longer braked by the first lock tube;Afterwards, one section of tooth bar is engaged with first gear, and in engagement process, release bar keeps pushing wedge The state of shape block.When one section of tooth bar departs from first gear after engagement, contact of the synchronous disengaging of release bar with wedge, the Under the elastic force of one spring, the first lock tube rises reset, and the first lock tube brakes first rotating shaft again.First rotating shaft is locked, and first Lifting is locked, and then improves the inclined precision and stability in chassis.Above-mentioned second lock tube braking second aids in rotating shaft, the 3rd lock Set braking the 3rd aids in the operation principle of rotating shaft to be same as the first lock tube braking first rotating shaft.
From unlike the second lock tube and the 3rd lock tube, the first lock tube is additionally provided with pilot hole, the lifting to the first elevating lever It is oriented to, i.e. the first lock tube has locking and the dual-use function being oriented to concurrently.
The madial wall of the change is provided with gear ring, and gear ring is engaged with the 4th gear, and the 4th gear is arranged on basal disc, the The gear of one Motor drive the 4th rotates, and the 4th gear is rotated by the driving change of engaging with gear ring.
The worm screw and the second of worm screw connection that the rotating mechanism is engaged including the worm gear being articulated on chassis with worm gear Motor, the second motor is arranged on chassis.Worm drive worm gear rotates, and worm gear drives support base and the rotation of clamping device thereon Turn.
The clamping device includes being fixed on the fixed folder portion on support base, the activity folder portion on expansion link, institute Expansion link is stated on the piston of cylinder or hydraulic cylinder, fixed folder portion opens up through hole, and the expansion link is through the through hole and gas The piston connection of cylinder or hydraulic cylinder.
Description of the drawings
Below in conjunction with the accompanying drawings the present invention is described further:
Fig. 1 be the present invention it is a kind of can circular movement power equipment transport clamping device structural representation;
Fig. 2 is the structural representation of angle adjusting mechanism 30 in Fig. 1;
Structural representations of the Fig. 3 for top board 34 in Fig. 2 after hiding;
Fig. 4 is enlarged drawing at A in Fig. 3;
Fig. 5 is enlarged drawing at B in Fig. 3;
Fig. 6 is the combining structure schematic diagram of the lock tube 71 of first rotating shaft 41 and first in Fig. 4;
Fig. 7 is the structural representation of the first lock tube 71 in Fig. 6.
Symbol description in figure:
10th, chassis;
20th, support base;
30th, angle adjusting mechanism;31st, basal disc;32nd, change;320th, tooth bar;321st, release bar;33rd, base plate;34th, top board;
41st, first rotating shaft;42nd, the second rotating shaft;420th, the second auxiliary rotating shaft;43rd, the 3rd rotating shaft;430th, the 3rd auxiliary turns Axle;
51st, first gear;52nd, second gear;520th, the second equipment gear;53rd, the 3rd gear;530th, the 3rd assist tooth Wheel;
61st, the first elevating lever;610th, gathering sill;62nd, the second elevating lever;63rd, the 3rd elevating lever;
71st, the first lock tube;710th, the inner chamber middle part of the first lock tube cone-shaped;711st, pilot hole;712nd, guiding projection;713、 Transverse bar;714th, wedge;72nd, the second lock tube;73rd, the 3rd lock tube;
81st, worm gear;82nd, worm screw;83rd, the second motor;84th, fixed folder portion;85th, expansion link;86th, activity folder portion.
Specific embodiment
Detailed description below is referring to figs. 1 to Fig. 7.
It is a kind of can circular movement power equipment transport clamping device, including the rotating mechanism on the chassis 10, Support base 20 on rotating mechanism, the clamping device on support base;The chassis is arranged on angular adjustment machine On structure 30, angle adjusting mechanism includes three elevating levers being flexibly connected with tray bottom.
The bottom on chassis 10 opens up chute, and hinged block is sliding combined with chute, is hinged at the top of hinged block and elevating lever.
The angle adjusting mechanism 30 includes the change 32 being articulated on basal disc 31, the base plate 33 being fixed on basal disc and top Plate 34, the first rotating shaft 41 being articulated on top board, the second rotating shaft 42, second aid in rotating shaft 420, the 3rd rotating shaft 43, the 3rd auxiliary Rotating shaft 430.
First rotating shaft is provided with first gear 51, and first rotating shaft is hollow, and the first elevating lever 61 in three elevating levers is spirally connected In first rotating shaft.
Second rotating shaft is provided with second gear 52, and the second rotary shaft hollow, the second elevating lever 62 in three elevating levers is spirally connected In the second rotating shaft, second gear is engaged with the second equipment gear 520, and the second equipment gear is arranged in the second auxiliary rotating shaft.
3rd rotating shaft is provided with the 3rd gear 53, and the 3rd rotary shaft hollow, the 3rd elevating lever 63 in three elevating levers is spirally connected In the 3rd rotating shaft, the 3rd gear is engaged with the 3rd equipment gear 530, and the 3rd equipment gear is arranged in the 3rd auxiliary rotating shaft.
Above-mentioned first gear, second gear, the second equipment gear, the 3rd gear, the 3rd equipment gear are located at base plate and top Between plate;Three elevating levers project upwards top board and are flexibly connected with the bottom of chassis 10.
The madial wall of the change is provided with three sections of tooth bars 320, above-mentioned first gear, second gear, the second equipment gear, 3rd gear, the 3rd equipment gear are located in change, first gear, the second equipment gear, the close change side of the 3rd equipment gear Edge, first gear, the second equipment gear, the core wheel line of the 3rd equipment gear deviate the rotation centerline of change.
First gear 51, the second equipment gear 520, the 3rd equipment gear 530 are along the circumference of change 32 to being uniformly distributed;Three sections Tooth bar is along change circumference to being uniformly distributed.
First through hole, the second through hole and third through-hole are opened up on the base plate 33, activity in first through hole is combined with first Lock tube 71, activity in the second through hole is combined with the second lock tube 72, and activity in third through-hole is combined with the 3rd lock tube 73;First through hole The first spring is provided between the first lock tube, second spring, third through-hole and the 3rd are provided between third through-hole and the second lock tube The 3rd spring is provided between lock tube.
First lock tube is arranged the bottom of first rotating shaft 41, and the second lock tube is set in the bottom of the second auxiliary rotating shaft 420, and the 3rd Lock tube is set in the bottom of the 3rd auxiliary rotating shaft 430;First rotating shaft, the second auxiliary rotating shaft, the bottom of the 3rd auxiliary rotating shaft are in Cone-shaped.
The 710 tapered shapes of inner chamber middle part of the first lock tube, the intracavity bottom of the first lock tube is provided with pilot hole 711, pilot hole Side wall be provided with guiding projection 712, open up on the side wall of first elevating lever 61 with guiding projection coordinate gathering sill 610; The tapered shape of intracavity bottom of the second lock tube and the 3rd lock tube.
Transverse bar 713 is equipped with first lock tube, the second lock tube, the side wall of the 3rd lock tube, the end of transverse bar is provided with Convex wedge 714.
Release bar 321 is provided with below arbitrary tooth bar, release bar is arranged on the madial wall of change 32, the length of release bar Equal to the length of arbitrary tooth bar.
The madial wall of the change 32 is provided with gear ring, and gear ring is engaged with the 4th gear, and the 4th gear is arranged on basal disc 31 On, the rotation of the gear of the first Motor drive the 4th.
Worm screw 82 and worm screw connection that the rotating mechanism is engaged including the worm gear 81 being articulated on chassis 10 with worm gear The second motor 83, the second motor be arranged on chassis on.
The clamping device includes the fixed folder portion 84 being fixed on support base 20, the activity folder on expansion link 85 Portion 86.
In practical operation, three elevating levers, the first elevating lever 61 rises, under the second elevating lever 62 and the 3rd elevating lever 63 Drop, or the first elevating lever declines, the second elevating lever and the 3rd elevating lever rise, and can make the skewed at any angle of chassis 10, rotates Mechanism rotates on inclined chassis 10, clamping device transporting power equipment or electric power tool under the driving of rotating mechanism.
Above content is only the better embodiment of the present invention, for one of ordinary skill in the art, according to the present invention Thought, will change in specific embodiments and applications, this specification content should not be construed as to this Bright restriction.

Claims (8)

1. it is a kind of can circular movement power equipment transport clamping device, including the rotating mechanism on chassis (10), Support base (20) on rotating mechanism, the clamping device on support base;It is characterized in that:Install on the chassis On angle adjusting mechanism (30), angle adjusting mechanism includes three elevating levers being flexibly connected with tray bottom.
2. it is as claimed in claim 1 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:Chassis (10) bottom opens up chute, and hinged block is sliding combined with chute, is hinged at the top of hinged block and elevating lever.
3. it is as claimed in claim 1 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:It is described Angle adjusting mechanism (30) includes the change (32) being articulated on basal disc (31), the base plate (33) being fixed on basal disc and top board (34), be articulated in first rotating shaft (41) on top board, the second rotating shaft (42), the second auxiliary rotating shaft (420), the 3rd rotating shaft (43), 3rd auxiliary rotating shaft (430);
First rotating shaft is provided with first gear (51), and first rotating shaft is hollow, and the first elevating lever (61) in three elevating levers is spirally connected In first rotating shaft;
Second rotating shaft is provided with second gear (52), and the second rotary shaft hollow, the second elevating lever (62) in three elevating levers is spirally connected In the second rotating shaft, second gear is engaged with the second equipment gear (520), and the second equipment gear is arranged on the second auxiliary rotating shaft On;
3rd rotating shaft is provided with the 3rd gear (53), and the 3rd rotary shaft hollow, the 3rd elevating lever (63) in three elevating levers is spirally connected In the 3rd rotating shaft, the 3rd gear is engaged with the 3rd equipment gear (530), and the 3rd equipment gear is arranged on the 3rd auxiliary rotating shaft On;
Above-mentioned first gear, second gear, the second equipment gear, the 3rd gear, the 3rd equipment gear be located at base plate and top board it Between;Three elevating levers project upwards top board and are flexibly connected with chassis (10) bottom;
The madial wall of the change is provided with least one section tooth bar (320), above-mentioned first gear, second gear, the second assist tooth Wheel, the 3rd gear, the 3rd equipment gear are located in change, first gear, the second equipment gear, the close change of the 3rd equipment gear Edge, first gear, the second equipment gear, the core wheel line of the 3rd equipment gear deviate the rotation centerline of change.
4. it is as claimed in claim 3 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:First Gear (51), the second equipment gear (520), the 3rd equipment gear (530) are along change (32) circumference to being uniformly distributed;Change it is interior Side wall is provided with three sections of tooth bars (320), and three sections of tooth bars are along change circumference to being uniformly distributed.
5. it is as claimed in claim 3 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:It is described First through hole, the second through hole and third through-hole are opened up on base plate (33), activity in first through hole is combined with the first lock tube (71), the Activity in two through holes is combined with the second lock tube (72), and activity in third through-hole is combined with the 3rd lock tube (73);First through hole and the The first spring is provided between one lock tube, second spring, third through-hole and the 3rd lock tube are provided between third through-hole and the second lock tube Between be provided with the 3rd spring;
First lock tube is arranged the bottom of first rotating shaft (41), and the second lock tube is set in the bottom of the second auxiliary rotating shaft (420), and the 3rd Lock tube is set in the bottom of the 3rd auxiliary rotating shaft (430);First rotating shaft, the second auxiliary rotating shaft, the 3rd aid in the bottom of rotating shaft equal Tapered shape;
The tapered shape of inner chamber middle part (710) of the first lock tube, the intracavity bottom of the first lock tube is provided with pilot hole (711), pilot hole Side wall be provided with guiding projection (712), open up on the wall of the first elevating lever (61) side with guiding projection coordinate gathering sill (610);The tapered shape of intracavity bottom of the second lock tube and the 3rd lock tube;
Transverse bar (713) is equipped with first lock tube, the second lock tube, the side wall of the 3rd lock tube, the end of transverse bar is provided with convex Wedge (714);
Release bar (321) is provided with below arbitrary tooth bar, release bar is arranged on the madial wall of change (32), the length of release bar Equal to the length of arbitrary tooth bar.
6. it is as claimed in claim 3 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:It is described The madial wall of change (32) is provided with gear ring, and gear ring is engaged with the 4th gear, and the 4th gear is arranged on basal disc (31), and first is electric Machine drives the rotation of the 4th gear.
7. it is as claimed in claim 1 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:It is described The worm screw (82) and the second of worm screw connection that rotating mechanism is engaged including the worm gear (81) being articulated on chassis (10) with worm gear Motor (83), the second motor is arranged on chassis.
8. it is as claimed in claim 1 it is a kind of can circular movement power equipment transport clamping device, it is characterised in that:It is described Clamping device includes being fixed on the fixed folder portion (84) on support base (20), the activity folder portion on expansion link (85) (86)。
CN201611223530.8A 2016-12-27 2016-12-27 It is a kind of can circular movement power equipment transport clamping device Expired - Fee Related CN106625708B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611223530.8A CN106625708B (en) 2016-12-27 2016-12-27 It is a kind of can circular movement power equipment transport clamping device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611223530.8A CN106625708B (en) 2016-12-27 2016-12-27 It is a kind of can circular movement power equipment transport clamping device

Publications (2)

Publication Number Publication Date
CN106625708A true CN106625708A (en) 2017-05-10
CN106625708B CN106625708B (en) 2018-10-30

Family

ID=58832846

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611223530.8A Expired - Fee Related CN106625708B (en) 2016-12-27 2016-12-27 It is a kind of can circular movement power equipment transport clamping device

Country Status (1)

Country Link
CN (1) CN106625708B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988233A (en) * 2017-05-28 2017-07-28 吴淑霞 A kind of automatic draw-out device of bridge pad
CN107697348A (en) * 2017-11-17 2018-02-16 郑州航空工业管理学院 Intelligent logistics sorting system based on Internet of Things
CN108455176A (en) * 2018-01-17 2018-08-28 卡斯纳(苏州)医疗设备有限公司 A kind of circulating conveyor of automatic dispensary
CN112489244A (en) * 2020-12-10 2021-03-12 河南威斯盾电子科技有限公司 Online real-time inspection mobile device
CN113654923A (en) * 2021-06-29 2021-11-16 湖南科技大学 Temperature-variable and angle-variable impact test control method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0222915A1 (en) * 1985-04-27 1987-05-27 Fanuc Ltd. Industrial robot
CN1745986A (en) * 2005-10-10 2006-03-15 燕山大学 Experimental platform of parallel mechanism with 3 and 4 freedom and adjustable 3-UPU
DE102009042014A1 (en) * 2009-09-21 2011-03-24 Dürr Systems GmbH Handling device for moving e.g. scanner for handling articles, has manipulator accommodated at carrier structure of parallel geometry unit, where powered movement axes are provided for displacing carrier structure relative to base
CN203717158U (en) * 2014-01-29 2014-07-16 华北电力大学(保定) Adiabatic compression air storage power generation system
CN203875892U (en) * 2014-05-08 2014-10-15 国家电网公司 Electrical equipment transporting and clamping device capable of doing arc motion
CN104626189A (en) * 2014-12-15 2015-05-20 深圳华强智能技术有限公司 Entertainment robot sphere three-freedom-degree parallel mechanism
US20150258682A1 (en) * 2014-03-13 2015-09-17 Brain Corporation Trainable modular robotic apparatus and methods

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0222915A1 (en) * 1985-04-27 1987-05-27 Fanuc Ltd. Industrial robot
CN1745986A (en) * 2005-10-10 2006-03-15 燕山大学 Experimental platform of parallel mechanism with 3 and 4 freedom and adjustable 3-UPU
DE102009042014A1 (en) * 2009-09-21 2011-03-24 Dürr Systems GmbH Handling device for moving e.g. scanner for handling articles, has manipulator accommodated at carrier structure of parallel geometry unit, where powered movement axes are provided for displacing carrier structure relative to base
CN203717158U (en) * 2014-01-29 2014-07-16 华北电力大学(保定) Adiabatic compression air storage power generation system
US20150258682A1 (en) * 2014-03-13 2015-09-17 Brain Corporation Trainable modular robotic apparatus and methods
CN203875892U (en) * 2014-05-08 2014-10-15 国家电网公司 Electrical equipment transporting and clamping device capable of doing arc motion
CN104626189A (en) * 2014-12-15 2015-05-20 深圳华强智能技术有限公司 Entertainment robot sphere three-freedom-degree parallel mechanism

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988233A (en) * 2017-05-28 2017-07-28 吴淑霞 A kind of automatic draw-out device of bridge pad
CN106988233B (en) * 2017-05-28 2019-04-26 湖南常德路桥建设集团有限公司 A kind of automatic draw-out device of bridge pad
CN107697348A (en) * 2017-11-17 2018-02-16 郑州航空工业管理学院 Intelligent logistics sorting system based on Internet of Things
CN108455176A (en) * 2018-01-17 2018-08-28 卡斯纳(苏州)医疗设备有限公司 A kind of circulating conveyor of automatic dispensary
CN112489244A (en) * 2020-12-10 2021-03-12 河南威斯盾电子科技有限公司 Online real-time inspection mobile device
CN113654923A (en) * 2021-06-29 2021-11-16 湖南科技大学 Temperature-variable and angle-variable impact test control method
CN113654923B (en) * 2021-06-29 2024-04-09 湖南科技大学 Impact test control method for changing temperature and angle

Also Published As

Publication number Publication date
CN106625708B (en) 2018-10-30

Similar Documents

Publication Publication Date Title
CN106625708A (en) Electric equipment transportation and clamping device capable of doing circular-arc-shaped motion
CN106142111B (en) Mechanical clamping jaw driving device
CN201792126U (en) Five-axis steel pipe intersecting line cutting machine
CN101954558B (en) Five-axis steel pipe intersecting line cutter
CN105127999B (en) One kind three translates rotating parallel device people's grasping and release device
CN206296719U (en) Possess self-feeding and the reclaimer device of upender
CN106274042B (en) A kind of thermoprinting machine
CN101983296A (en) Cylinder device
WO2015059757A1 (en) Work system
CN206296866U (en) Deflector roll arc surface repairs fixture
CN203092234U (en) Compact triaxial gyration positioner
CN206041286U (en) Aerify assembly fixture of cabinet
CN103143974A (en) Compact triaxial rotary positioner
CN204471070U (en) A kind of screw rod transmission transformational structure
CN101698268B (en) Friction type intersecting line cutting machine
WO2007141947A1 (en) Inter-element support mechanism, automatic tool changer with the inter-element support mechanism, conveying device, and actuator
CN212170132U (en) Be used for auto parts hollow tube fixture
CN105364506B (en) A kind of 4 universal clamp for cutting of benchmark
CN106877191A (en) A kind of power distribution cabinet for being easy to safeguard
CN206286831U (en) A kind of upset Digit Control Machine Tool of automatic intelligent
CN206359207U (en) A kind of power head
CN204035718U (en) Removable SERVO CONTROL numerical control tapping machine
CN206296867U (en) A kind of fixture for repairing deflector roll arc surface
CN206780249U (en) The cam spanner of the axle gantry machining center guide rail of bridge-type five correction installation
CN205798840U (en) A kind of two-wheel Knurling device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180824

Address after: 314000 188 Tea Garden Road, tanker town, Xiuzhou District, Jiaxing, Zhejiang

Applicant after: ZHEJIANG JINYUAN INDUSTRIAL CO., LTD.

Address before: 523000 2, 205, innovation and Technology Park, Songshan Lake high tech Industrial Development Zone, Dongguan, Guangdong, China, 205

Applicant before: Dongguan Sheng Rong Automation Technology Co., Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181030

Termination date: 20201227

CF01 Termination of patent right due to non-payment of annual fee