CN106611998A CN201510705953.2A CN201510705953A CN106611998A CN 106611998 A CN106611998 A CN 106611998A CN 201510705953 A CN201510705953 A CN 201510705953A CN 106611998 A CN106611998 A CN 106611998A
Authority
CN
China
Prior art keywords
circuit
input
switching
photoelectric isolating
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510705953.2A
Other languages
Chinese (zh)
Inventor
卡文艳
季晓刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Triumphant Energy-Saving Equipment Of Ningxia Fine Jade Co Ltd
Original Assignee
Triumphant Energy-Saving Equipment Of Ningxia Fine Jade Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Triumphant Energy-Saving Equipment Of Ningxia Fine Jade Co Ltd filed Critical Triumphant Energy-Saving Equipment Of Ningxia Fine Jade Co Ltd
Priority to CN201510705953.2A priority Critical patent/CN106611998A/en
Publication of CN106611998A publication Critical patent/CN106611998A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/005Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting using a power saving mode
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/061Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems for DC powered loads
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/068Electronic means for switching from one power supply to another power supply, e.g. to avoid parallel connection
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems

Landscapes

  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses an energy-saving power switching device which comprises an analog input circuit, a transformer isolation circuit, a zero-crossing comparison circuit, a 32-bit central processing unit, a switching signal input circuit, a photoelectric isolation circuit, a PLD logic device circuit, an action breaker circuit, a print and output circuit, a liquid crystal display, a keyboard input circuit, and a communication management circuit. The technology of real-time monitoring, judging and reliable processing of the 'interference electricity' of the system or real failure or voltage loss based on adaptive switch position and electrical parameter variation is one of the leading domestic technologies at present, and achieves the international requirements.

Description

A kind of energy-saving power switching arrangement
Technical field
The present invention relates to energy-saving power switching arrangement, and in particular to a kind of energy-saving power switching arrangement.
Background technology
Enterprise is used mostly and has power switchover device referred to as " prepared auto restart " (BZT) at present.Work as work When on and off switch non-protected trips, Backup Power Switch needs automatic closing;Automatic switching device of standby power supply, Used as the automaton for completing this function, which is for the safe operation of power system is in the production of enterprise Huge effect has been played, one of maximally effective automaton of can yet be regarded as at present, but backup auto-activating device is dynamic Make that the time is more long, be not suitable with the requirement that enterprise is improved to power safety and automatizationMainly Reason has five, and one is that device judges to start too late;Two be device start after by in-put of spare power supply when Between it is oversize;Three is phase place when can not accurately judge switch on opportunity;Four is that switching mode is single, is selected Property is poor;Five is excessive to the impact of whole electrical network when being switching, serious accident easily occurs, causes System is shaken, and causes system large-area power-cuts.Trace to its source, mainly the network of Industrial-Enterprises in China What construction featuress were determined, industrial undertaking's backup auto-activating device that always drop and mesolow transformer station use at present The backup auto-activating device operation principle of electricity grid substation is absolutely applied mechanically almost, not for industry enterprise The demand and technical characterstic of industry carries out principle, function, the expertness design of performance and exploitation but this Two diverse systems.
Further, since the present situation of China's power system, universal large and medium-sized enterprise faces often system and " shakes The puzzlement of electricity ", first and second system " shake electricity " cause when serious the large-area power failure of full factory or Operation equipment is paralysed.Economic loss is difficult to estimate that these problems annoying the Producer of enterprise and management Person, also the function innovation to backup auto-activating device propose urgent requirement, and urgent need wants a kind of brand-new dress Put to replace standby energy-saving power switching arrangement.
The content of the invention
The present invention is directed to the problems referred to above, there is provided a kind of energy-saving power switching arrangement.
The present invention the adopted technical scheme that solves the above problems is:A kind of power supply switching dress Put, process including analog input circuit, transformer isolation circuit, Zero-cross comparator circuit, 32 central authorities Device, on-off model input circuit, photoelectric isolating circuit, PLD logic device circuits, action breaker Circuit, print output circuit, liquid crystal display, input through keyboard circuit and telecommunication management circuit;Described 32 Position central processing unit connects Zero-cross comparator circuit, photoelectric isolating circuit, print output circuit, liquid respectively Brilliant display, input through keyboard circuit and telecommunication management circuit;The analog input circuit outfan connection is mutual Sensor isolation circuit;The transformer isolation circuit outfan connects Zero-cross comparator circuit;The switch Amount signal input circuit outfan connection photoelectric isolating circuit;The photoelectric isolating circuit outfan decibel 32 central processing units of connection and PLD logic device circuits;The PLD logic device circuits outfan Connecting moves breaker circuit;The action short-circuiting device circuit input/output terminal connects host computer.
Advantages of the present invention:
Device judges to start switching time soon, reaches 10ms;
Device will be the time of in-put of spare power supply fast after judging to start, within reaching 50ms;Except excessively breaking Device failure cause;
True detecting system phase place, accurately judges phase place during switch on opportunity;Utility power grid ensure Close a floodgate within 30 °;
Switching mode flexibly, is actually needed according to scene, and menu is various available, security reliability It is high;
It is little to the impact of whole electrical network during switching, be not in serious accident, anti-locking system concussion, System large-area power-cuts and " shaking electricity " is definitely avoided to affect;
The normal grid switching operation of artificial system is capable of achieving on device, tradition is fallen before being completely eliminated or avoiding The potential safety hazard that lock mode is brought, it is ensured that safe operation of electric network;
Existing automatic switching device of standby power supply or apparatus for fast switching are substituted completely, and wiring is simple, installation side Just;
Realize that safety automation switches, reach unattended, intelligent operation;
Multiple communication modes are changed with stipulations, can intervene rapidly the Internet, implement remote monitoring.
In addition to objects, features and advantages described above, also other purposes of the invention, Feature and advantage.Below with reference to figure, the present invention is further detailed explanation.
Description of the drawings
The accompanying drawing for constituting the part of the application is used for providing a further understanding of the present invention, the present invention Schematic description and description be used for explain the present invention, do not constitute inappropriate limitation of the present invention.
Fig. 1 is the structured flowchart of the embodiment of the present invention.
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, below in conjunction with accompanying drawing And embodiment, the present invention will be described in further detail.It should be appreciated that described herein concrete Embodiment only to explain the present invention, is not intended to limit the present invention.
With reference to Fig. 1, a kind of energy-saving power switching arrangement as shown in Figure 1, including analog input circuit, Transformer isolation circuit, Zero-cross comparator circuit, 32 central processing units, on-off model input circuit, Photoelectric isolating circuit, PLD logic device circuits, action breaker circuit, print output circuit, liquid crystal Display, input through keyboard circuit and telecommunication management circuit;32 central processing units connect zero passage respectively Comparison circuit, photoelectric isolating circuit, print output circuit, liquid crystal display, input through keyboard circuit and logical Fuse tube manages circuit;The analog input circuit outfan connects transformer isolation circuit;The transformer Isolation circuit outfan connects Zero-cross comparator circuit;The on-off model input circuit outfan connection Photoelectric isolating circuit;The photoelectric isolating circuit outfan decibel connects 32 central processing units and PLD Logic device circuit;The PLD logic device circuits outfan connecting moves breaker circuit;It is described Action short-circuiting device circuit input/output terminal connects host computer.
The device Starting mode and logic of the present invention:
1. line voltage distribution is started, device fact detection voltage variable quantity, when circuit three-phase voltage occur it is different Often or power supply, i.e. detection voltage are lost less than line voltage distribution setting valve and line current is less than excessively stream locking Value, starts blood pressure lowering logic.
2. low-frequency starting, device fact detection voltage and frequency variation, when circuit three-phase voltage occurs Exception also occurs declining with power supply, simultaneity factor frequency is lost, i.e., detection voltage is less than line electricity repoussage Definite value and frequency are less than system frequency setting valve and line current is less than excessively stream locking value, start blood pressure lowering and Frequency logic.
3. inverse probability is started, and when industrial system bus carries generator operation, electromotor is now born This bus major part load, user receive active from system.But when system loses power supply, electromotor Power transmission will be fallen to system, to prevent the system failure, device will start inverse probability.
4. the position of the switch starts, and when systems are functioning properly, closes bit switch because of working power and occurs suddenly During displacement, it is to ensure power supply reliability, device needs Backup Power Switch of closing, now the position of the switch Start.
5. trip protection is started, and the protection device on circuit is in this line of processing system external area error tripping Road working power, device play dynamic circuit connector stand-by power supply.
The device action mode of the present invention:
Device, can be according to the logical order being previously set to working power and standby electricity after correct startup Source switch carries out action, to ensure that system is safe and reliable.
1. switching in parallel
First close Backup Power Switch, after confirming that Backup Power Switch is closed, then divide the work and make on and off switch. In this course of action, system can short time cyclization.Parallel way is applied to normal condition similarly hereinafter display system Two power supplys between switching, can be used for inlet wire overhaul when artificial back brake or failure after recover manually. Parallel way is also divided into automated manner in parallel and semiautomatic fashion in parallel.Automated manner in parallel refers to device After combined floodgate, through time delay of adjusting, automatic tripping working power switch.Semiautomatic fashion in parallel is referred to Device is switched by manual tripping working power after combined floodgate.
Under specific to system list mother partition system wiring, as a example by being switched to 2DL from 1DL parallel connections, this When 3DL close position.After manual starting, if condition in parallel meets, device first closes 2DL switches, this When working power, two power supply cyclizations in short-term of stand-by power supply, Jing adjusts time delay (shunt tripping time delay) Device tripping 1DL again afterwards.
2. series connection switching
On and off switch is made in the first division of labor, after confirming that working power separates, then closes Backup Power Switch.Series connection Mode is applied to the automatic switchover of power supply in the case of accident and switch mis-jumping.
Under specific to system list mother partition system wiring, as a example by being switched to 2DL from 1DL parallel connections, this When 3DL close position.After manual starting, if condition in parallel meets, device elder generation tripping 1DL switches, so The 2DL that closes again afterwards is switched, and now working power, two power supplys of stand-by power supply do not have cyclization situation.
3. switch simultaneously
Device is sent out simultaneously and jumps working power switch and close Backup Power Switch order, is suitable for normal with system The use of falling load.With parallel connection switch logic.
The device implementation of the present invention:
Device implementation depends on accurate judgement and set-up mode of the device to system parameters, tool Body includes mode is implemented as described below:
1. quick-action switching
Quick-action switches to this device most advantage, is also that switching uses one of success rate highest switching mode, More than 80% is commonly reached, that is, be can guarantee that system safety, and it is larger not use the equipment such as electricity not to be subject to Impact and disturbance.
Wherein Rule of judgment:First:Line voltage distribution cannot be below system voltage 80% and more than;The Two:Bus is with voltage | dz | to be thrown " switching pressure reduction " within 20%;3rd:Bus and voltage to be thrown | dq | " switching angular difference " must be within 30 °.
Quick-action switching is entirely to switch the most fast combined floodgate mode of combined floodgate mode, wherein it is dynamic to complete whole switch Make the time in 100ms or so, it is ensured that the action message of stand-by power supply, it is ensured that the recovery of system electricity consumption.
2. same period tracking switching
If device loses quick-action switching machine meeting, device can proceed to rapidly same period tracking switching, to realize The best opportunity for restoring electricity, busbar voltage and treat that the asynchronous switch-on point between switching voltage is most important, Its opportunity for closing a floodgate point of its criterion device tracking attaches most importance to, around when switching the intrinsic combined floodgate being previously set Between be reference, select one " expected leading phase angle " as long as this " expected leading phase angle " is in device In the permission phase angle of setting, it is possible to which conjunction stand-by power supply order is sent out in the position for finding same period point, now right Electrical network impact is minimum, also will not be affected using electric load.
3. overbottom pressure switching
System voltage progressively reduces with handoff failure number of times, drops to about 30% in busbar voltage left The right side, now switch into overbottom pressure switching, but due to power off time it is long, not as this device first Switching mode.But can use in some particular systems, now switching does not have strict criterion, to system Also affect little.
4. safety delay switching
The safety delay switching of system, is for the supplement of overbottom pressure switching, now with stand-by power supply certainly A large amount of replacements of device are thrown, this kind of switching mode is also used, so this device is related to less.
The present invention provides a kind of full new firms power supply switching mode-power supply stable-switching device, leads to Cross and transformer station's (switchgear house) unmanned can be realized using the device, due to the short circuit, " rolling of external power grid Electricity ", air-drop etc. cause instantaneous or normal time service power outage, device automatic checkout system voltage, electricity The fact that stream, frequency, power variable quantity, the voltage of whole electricity system be unlikely to lose situation Under, safely and fast put into stand-by power supply or bus connection switch so that system reenters normal operating condition, So that whole electric power netting safe running.The development of Modern vacuum chopper, the time divide, closed a floodgate most soon may be used To reach 30-50ms, this realizes providing possibility, the safety of power system for stable-switching device of powering And reliability, it is desirable to peopleware and power supply unit automatization improve constantly, and depend merely on artificial operation difficult To be competent at, digital transformer substation has goed deep into enterprise, by from motion tracking, detection, judgement, execution Power supply stable-switching device coordinate other automatically-monitored softwares, really realize that transformer station (matches somebody with somebody Electric room) digitized, intellectuality, it is ensured that the safety and reliability of electrical network.
Device judges to start switching time soon, reaches 10ms;
Device will be the time of in-put of spare power supply fast after judging to start, within reaching 50ms;Except excessively breaking Device failure cause;
True detecting system phase place, accurately judges phase place during switch on opportunity;Utility power grid ensure Close a floodgate within 30 °;
Switching mode flexibly, is actually needed according to scene, and menu is various available, security reliability It is high;
It is little to the impact of whole electrical network during switching, be not in serious accident, anti-locking system concussion, System large-area power-cuts and " shaking electricity " is definitely avoided to affect;
The normal grid switching operation of artificial system is capable of achieving on device, tradition is fallen before being completely eliminated or avoiding The potential safety hazard that lock mode is brought, it is ensured that safe operation of electric network;
Existing automatic switching device of standby power supply or apparatus for fast switching are substituted completely, and wiring is simple, installation side Just;
Realize that safety automation switches, reach unattended, intelligent operation;
Multiple communication modes are changed with stipulations, can intervene rapidly the Internet, implement remote monitoring.
The self-adaptive switch position of the present invention and the variable quantity of electric parameter, for from system " the shaking electricity " of itself and real failure or decompression real-time monitoring, judgement reliable treatments, are current One of domestically leading technology, and reach international requirement.
Presently preferred embodiments of the present invention is the foregoing is only, it is not to limit the present invention, all at this Within bright spirit and principle, any modification, equivalent substitution and improvements made etc. should be included in Within protection scope of the present invention.

Claims (1)

1. a kind of energy-saving power switching arrangement, it is characterised in that including simulation input electricity Road, mutual inductance Device isolation circuit, Zero-cross comparator circuit, 32 central processing units, on-off model input electricity Road, photoelectric isolating circuit, PLD logic device circuits, action breaker circuit, printout Circuit, liquid crystal display, input through keyboard circuit and telecommunication management circuit;32 centres Reason device connects Zero-cross comparator circuit, photoelectric isolating circuit, print output circuit, liquid crystal respectively Show, input through keyboard circuit and telecommunication management circuit;The analog input circuit outfan connection is mutual Sensor isolation circuit;The transformer isolation circuit outfan connects Zero-cross comparator circuit;It is described On-off model input circuit outfan connects photoelectric isolating circuit;The photoelectric isolating circuit is defeated Go out to hold decibel to connect 32 central processing units and PLD logic device circuits;The PLD logics Device circuitry outfan connecting moves breaker circuit;The action short-circuiting device circuit input/defeated Go out end connection host computer.
CN201510705953.2A 2015-10-27 2015-10-27 Energy-saving power switching device Pending CN106611998A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510705953.2A CN106611998A (en) 2015-10-27 2015-10-27 Energy-saving power switching device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510705953.2A CN106611998A (en) 2015-10-27 2015-10-27 Energy-saving power switching device

Publications (1)

Publication Number Publication Date
CN106611998A true CN106611998A (en) 2017-05-03

Family

ID=58613989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510705953.2A Pending CN106611998A (en) 2015-10-27 2015-10-27 Energy-saving power switching device

Country Status (1)

Country Link
CN (1) CN106611998A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204068418U (en) * 2014-08-26 2014-12-31 西安博惠通用电气自动化有限公司 A kind of power supply source switching device

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204068418U (en) * 2014-08-26 2014-12-31 西安博惠通用电气自动化有限公司 A kind of power supply source switching device

Similar Documents

Publication Publication Date Title
US5442335A (en) Controller for controlling operation of at least one electrical load operating on an AC supply, and a method thereof
CN102088209A (en) Self-healing control method of distribution network
CN102290799B (en) Small-scale quick recovery method for power supply of power distribution network in open loop running
CN103138390A (en) Power distribution network fault handling method based on self-recovering control
CN104836330B (en) Backup auto-activating device bus PT three-phases broken string quick determination method and faulty action preventing method
CN111146755A (en) Feeder terminal and line protection device
CN203367963U (en) Intelligent endpoint power supply controller
CN104614642A (en) Small current grounding line selection method
CN105552908A (en) Self-healing control method of power distribution network
CN112421615A (en) Power distribution station self-healing control method and system based on intelligent breaker action
CN110912253B (en) Low-voltage intelligent spare power automatic switching system
CN210780230U (en) Switch device for switching high power from off-grid to grid-connected
CN105391038A (en) Area protection based intelligent terminal in power network and control method for intelligent terminal
CN103532221A (en) Spare-power automatic switching implementation method of lines under wiring and operating modes of self-adaptive 330kV substation
CN102694419B (en) Measurement and control integration management system
CN112421621A (en) Integrated intelligent distribution network operation monitoring cloud system based on 5G Internet of things
CN111555279A (en) Method for maintaining power utilization continuity based on intelligent unloading of three-level load
CN101924394A (en) Substation load stabilizing system and realizing method thereof
CN104821556A (en) Layered protecting configuration of outdoor low-voltage distribution area active compensation device and fault handling method
CN103378581A (en) AFCI comprehensive protecting device
CN204068418U (en) A kind of power supply source switching device
CN204068420U (en) A kind of power supply source switching device based on analog input circuit
CN114062973B (en) In-situ feeder automation reverse locking application method
CN106611998A (en) Energy-saving power switching device
Swathika et al. Communication assisted overcurrent protection of microgrid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170503