CN106600208A - Smart mobile phone application-based commercial concrete online scheduling management system - Google Patents
Smart mobile phone application-based commercial concrete online scheduling management system Download PDFInfo
- Publication number
- CN106600208A CN106600208A CN201610990328.1A CN201610990328A CN106600208A CN 106600208 A CN106600208 A CN 106600208A CN 201610990328 A CN201610990328 A CN 201610990328A CN 106600208 A CN106600208 A CN 106600208A
- Authority
- CN
- China
- Prior art keywords
- business
- concrete
- vehicle
- priority
- suppliers
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/101—Collaborative creation, e.g. joint development of products or services
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q30/00—Commerce
- G06Q30/06—Buying, selling or leasing transactions
- G06Q30/0601—Electronic shopping [e-shopping]
- G06Q30/0633—Lists, e.g. purchase orders, compilation or processing
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- Economics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Data Mining & Analysis (AREA)
- Tourism & Hospitality (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Accounting & Taxation (AREA)
- Finance (AREA)
- Development Economics (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a smart mobile phone application-based commercial concrete online scheduling management system. The system includes a commercial concrete enterprise management server, a construction end and a commercial concrete end; the commercial concrete enterprise management server comprises a smart scheduling module; the construction end comprises an order placement module; the commercial concrete end comprises an order module; and when associations are built among the commercial concrete end, the construction end and the commercial concrete enterprise management server, the commercial concrete enterprise management server carries out smart scheduling management. According to the smart mobile phone application-based commercial concrete online scheduling management system of the invention, vehicles, drivers and commercial concrete suppliers executed by orders are scheduled through the smart scheduling module, especially when the orders cannot be executed or the orders cannot be executed due to problems encountered in an execution process, the commercial concrete suppliers, vehicles and the drivers are scheduled through the smart scheduling module, and therefore, the further execution of the orders can be ensured immediately, and the benefits of the commercial concrete suppliers and construction units can be protected to the greatest extent; based on scheduling, the emergency response capability of the orders is improved, the execution efficiency of the orders is optimized, and the guarantee capability of key tasks is improved.
Description
Technical field
The present invention relates to a kind of business's concrete on-line scheduling management system based on smart mobile phone application.
Background technology
In the prior art, the order between Shang Tong suppliers and business concrete user beforehand through negotiation still by signing confession
Contract, business's concrete user is answered to propose business's concrete demand, Shang Tong suppliers arrange business's concrete order according to the demand of business concrete user, and carry out
Production, arranges vehicle that concrete and mortar are transported to into job site, due to Shang Tong suppliers, haulage vehicle and driver, applies
Work order position is more, if without dispatching management information system, the confusion in order fulfillment process will be caused, meanwhile, at least exist
Following problem:
(1)The level of informatization is not high, with the development of informationization technology, the intelligence degree more and more higher of information management, especially
It is that, with the popularization and application of smart mobile phone, intelligentized dispatching management information system has become main flow, and prior art is without fully profit
With existing information technology;
(2)Resource utilization is not high, for the management and running of vehicle, driver scientific can not be arranged, may cause to have
People hurry, somebody is not busy, and what is had is for motor vehicle more, and some vehicle use must be lacked, for driver and vehicle workload assurance not
It is balanced;
(3)Emergency disposal is indifferent, the problem in order fulfillment process is run into, it is impossible to which the very first time is carried out rationally effectively
Dispose, the contradictory problems between construction party and Shang Tong suppliers, loglstics enterprise may be caused to increase, also cause operating efficiency to drop
It is low.
Based on above reason, a kind of business's concrete on-line scheduling management system based on smart mobile phone application of invention is needed.
The content of the invention
One side according to embodiments of the present invention, there is provided a kind of business's concrete on-line scheduling pipe based on smart mobile phone application
Reason system, including:Business's concrete service for business management device, construction end and business's concrete end, it is characterised in that business's concrete service for business management
Device includes intelligent scheduling module, and the construction end includes the module that places an order, and business's concrete end includes order module;
The construction end places an order module after selecting Shang Tong suppliers, filling in business's concrete demand information, sends information to business's concrete
Service for business management device, business's concrete service for business management device sends above- mentioned information to the order module at business's concrete end, business's concrete end
Scheduling is carried out to business's concrete demand by order module, vehicle is sent, driver is sent, then above- mentioned information is sent to business's concrete enterprise
Industry management server, business's concrete service for business management device again sends the scheduling information at business's concrete end, vehicle and driver information to applying
Work end, associates so as to set up business's concrete end with construction end;
After association is set up between business's concrete end, construction end, business's concrete service for business management device, business's concrete service for business management device carries out intelligence
Can management and running;
The intelligent scheduling module includes to the production scheduling of all orders, vehicle driver's scheduling of logistics transportation:Business's concrete is supplied
Should degree of negotiating the transfer of, driver scheduling, vehicle scheduling;
Shang Tong suppliers scheduling is and/or the Shang Tong suppliers that current construction party is selected because current order cannot be performed
Because quantity on order is excessive or production capacity is limited or the not enough reason of driver vehicle, lead to not meet the order need of construction party
Ask, need other Shang Tong suppliers of scheduling to complete order taking responsibility;
The driver scheduling be because current order cannot be performed, and/or Shang Tong suppliers select driver due to task
Conflict cannot fulfil driving task, need dispatch other drivers complete driving task;
The vehicle scheduling is that, because current order cannot be performed, and/or vehicle is in the transportation of current order or transports
Because either objectively or subjectively reason leads to not perform transport task when will start, need to dispatch other vehicles and complete transport and appoint
Business.
In based on another embodiment of said system, the intelligent scheduling module is to Shang Tong suppliers, driver, vehicle
Scheduling be to be scheduled according to Shang Tong suppliers priority, driver's priority, vehicle priority;
Shang Tong suppliers priority is to carry out priority queueing to all Shang Tong suppliers relative to construction party, and queuing is leaned on
Front, priority is high, and the priority of scheduling is also high;
Driver's priority is that all drivers relative to construction party are carried out with priority queueing, is queued up forward, excellent
First level is high, and the priority of scheduling is also high;
The vehicle priority is that all vehicles relative to construction party are carried out with priority queueing, forward, priority of queuing up
Height, the priority of scheduling is also high.
Based in another embodiment of said system, the evaluation criterion of Shang Tong suppliers priority has:
Distance, the condition of road surface of distance construction side of Shang Tong suppliers job location;
The scope of the enterprise and production of Shang Tong suppliers, transport strength and current business's concrete production cycle, haul-cycle time;
After sale evaluation and service marking situation of the construction end to Shang Tong suppliers;
The enterprise qualification of Shang Tong suppliers;
The illegal violations record case of Shang Tong suppliers;
Registration class of the Shang Tong suppliers in register user.
In based on another embodiment of said system, the evaluation criterion of driver's priority has:
The current state of driver, the current state includes:Implementing driving task, etc. driving task to be performed, without appoint
Business;
Distance, the condition of road surface of driver's distance vehicle to be driven;
The same day cumulative operation time of driver;
Away from the time that last execution task terminates;
Driver violates the traffic regulations situation;
Average drive speed during the real-time driving task of driver.
In based on another embodiment of said system, the evaluation criterion of the vehicle priority has:
The current state of vehicle, the current state includes:Implementing transport task, etc. transport task to be performed, without task;
Vehicle condition, the vehicle condition includes:Well, fault-free, overhaul, scrap;
Whether vehicle has driver;
The distance of vehicle distances Shang Tong supplier and construction party job location, condition of road surface;
Vehicle day adds up operating range.
Based in another embodiment of said system, the intelligent scheduling module run into that the present situation places an order cannot
Perform or implementation procedure in encounter problems when cannot continue executing with, concrete supplier scheduling of entering to do business first selects highest priority
Shang Tong suppliers perform current order task, next carries out vehicle scheduling, selects the vehicle of highest priority, is finally driven
The person of sailing dispatches, and selects the driver of highest priority;
Described to dispatch buses when business's concrete material is loaded, next scheduled vehicle prepares to march into the arena, the intelligent scheduling module tool
There is time computing function, the filling material time of dispatching buses is next road institute elapsed time when marching into the arena of dispatching buses;
When cannot continue executing with when encountering problems in order fulfillment process, the order requeues;
Encountering problems to continue executing with the order fulfillment process refers to transport truck and driver from business's concrete
Suppliers transport business's concrete toward the construction site of construction party, and vehicle trouble, road service system, the event of business's concrete are run in transportation
Barrier causes business's concrete to be transported to construction site;
And/or,
After reaching construction site, because forwarding agent's concrete does not meet construction party requirement, not barcode scanning is received.
In based on another embodiment of said system, the intelligent scheduling module calls GPS module data, monitor in real time
The situation of logistics transportation, monitor in real time order implementation status.
Based on a kind of business's concrete on-line scheduling management system based on smart mobile phone application that the above embodiment of the present invention is provided,
Vehicle, driver and the Shang Tong suppliers performed to order by intelligent scheduling module is scheduled, particularly cannot in order
When encountering problems and cannot perform in execution or implementation procedure, can be by intelligent scheduling module rapidly to Shang Tong suppliers and Che
, driver be scheduled, the very first time guarantees that order is continued executing with, and at utmost maintains Shang Tong suppliers and unit in charge of construction
Interests, by scheduling, improve order emergency capability, optimize order execution efficiency, improve the guarantee energy of key task
Power.
Below by drawings and Examples, technical scheme is described in further detail.
Description of the drawings
Constitute the Description of Drawings embodiments of the invention of a part for specification, and together with description for explaining
The principle of the present invention.
Referring to the drawings, according to detailed description below, the present invention can be more clearly understood from, wherein:
Fig. 1 is structural representation of the present invention based on business's concrete on-line scheduling management system one embodiment of smart mobile phone application.
Specific embodiment
Describe the various exemplary embodiments of the present invention in detail now with reference to accompanying drawing.It should be noted that:Unless had in addition
Body illustrates that the part and the positioned opposite of step, numerical expression and numerical value for otherwise illustrating in these embodiments does not limit this
The scope of invention.
Simultaneously, it should be appreciated that for the ease of description, the size of the various pieces shown in accompanying drawing is not according to reality
Proportionate relationship draw.
It is below illustrative to the description only actually of at least one exemplary embodiment, never as to the present invention
And its any restriction applied or use.
For technology, method and apparatus may be not discussed in detail known to person of ordinary skill in the relevant, but suitable
In the case of, the technology, method and apparatus should be considered a part for specification.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi
It is defined in individual accompanying drawing, then it need not be further discussed in subsequent accompanying drawing.
Fig. 1 is structural representation of the present invention based on business's concrete on-line scheduling management system one embodiment of smart mobile phone application
Figure, as shown in figure 1, the embodiment is included based on business's concrete on-line scheduling management system of smart mobile phone application:Shang Tong enterprises manage
Reason server 1, construction end 2 and business's concrete end 3, it is characterised in that business's concrete service for business management device 1 includes intelligent scheduling module
11, the construction end 2 includes the module 21 that places an order, and business's concrete end 3 includes order module 31;
The construction end 2 places an order module 21 after selecting Shang Tong suppliers, filling in business's concrete demand information, sends information to business
Concrete service for business management device 1, business's concrete service for business management device 1 sends above- mentioned information to the order module 31 at business's concrete end 3, described
Business's concrete end 3 carries out scheduling by order module 31 to business's concrete demand, sends vehicle, sends driver, then sends out above- mentioned information
Business's concrete service for business management device 1 is delivered to, business's concrete service for business management device 1 is again by the scheduling information at business's concrete end 3, vehicle and driver
Information is sent to construction end 2, is associated with end 2 of constructing so as to set up business's concrete end 3;
After association is set up between business's concrete end 3, construction end 2, business's concrete service for business management device 1, business's concrete service for business management device 1 enters
Row intelligent scheduling is managed;
The production scheduling of 11 pairs of all orders of the intelligent scheduling module, vehicle driver's scheduling of logistics transportation include:Shang Tong
Supplier's scheduling, driver scheduling, vehicle scheduling;
Shang Tong suppliers scheduling is and/or the Shang Tong suppliers that current construction party is selected because current order cannot be performed
Because quantity on order is excessive or production capacity is limited or the not enough reason of driver vehicle, lead to not meet the order need of construction party
Ask, need other Shang Tong suppliers of scheduling to complete order taking responsibility;
The driver scheduling be because current order cannot be performed, and/or Shang Tong suppliers select driver due to task
Conflict cannot fulfil driving task, need dispatch other drivers complete driving task;
The vehicle scheduling is that, because current order cannot be performed, and/or vehicle is in the transportation of current order or transports
Because either objectively or subjectively reason leads to not perform transport task when will start, need to dispatch other vehicles and complete transport and appoint
Business.
Scheduling of the intelligent scheduling module 11 to Shang Tong suppliers, driver, vehicle is preferential according to Shang Tong suppliers
Level, driver's priority, vehicle priority are scheduled;
Shang Tong suppliers priority is to carry out priority queueing to all Shang Tong suppliers relative to construction party, and queuing is leaned on
Front, priority is high, and the priority of scheduling is also high;
Driver's priority is that all drivers relative to construction party are carried out with priority queueing, is queued up forward, excellent
First level is high, and the priority of scheduling is also high;
The vehicle priority is that all vehicles relative to construction party are carried out with priority queueing, forward, priority of queuing up
Height, the priority of scheduling is also high.
The evaluation criterion of Shang Tong suppliers priority has:
Distance, the condition of road surface of distance construction side of Shang Tong suppliers job location;
The scope of the enterprise and production of Shang Tong suppliers, transport strength and current business's concrete production cycle, haul-cycle time;
After sale evaluation and service marking situation of the construction end 2 to Shang Tong suppliers;
The enterprise qualification of Shang Tong suppliers;
The illegal violations record case of Shang Tong suppliers;
Registration class of the Shang Tong suppliers in register user.
The evaluation criterion of driver's priority has:
The current state of driver, the current state includes:Implementing driving task, etc. driving task to be performed, without appoint
Business;
Distance, the condition of road surface of driver's distance vehicle to be driven;
The same day cumulative operation time of driver;
Away from the time that last execution task terminates;
Driver violates the traffic regulations situation;
Average drive speed during the real-time driving task of driver.
The evaluation criterion of the vehicle priority has:
The current state of vehicle, the current state includes:Implementing transport task, etc. transport task to be performed, without task;
Vehicle condition, the vehicle condition includes:Well, fault-free, overhaul, scrap;
Whether vehicle has driver;
The distance of vehicle distances Shang Tong supplier and construction party job location, condition of road surface;
Vehicle day adds up operating range.
The intelligent scheduling module 11 run into the present situation place an order cannot perform or implementation procedure in encounter problems nothing
When method is continued executing with, concrete supplier scheduling of entering to do business first, the Shang Tong suppliers for selecting highest priority perform current order times
Business, next carries out vehicle scheduling, selects the vehicle of highest priority, finally carries out driver scheduling, selects highest priority
Driver;
Described to dispatch buses when business's concrete material is loaded, next scheduled vehicle prepares to march into the arena, the intelligent scheduling module 11
With Time Calculation function, the filling material time of dispatching buses is next when dispatching buses that road is consumed when marching into the arena
Between;
When cannot continue executing with when encountering problems in order fulfillment process, the order requeues;
Encountering problems to continue executing with the order fulfillment process refers to transport truck and driver from business's concrete
Suppliers transport business's concrete toward the construction site of construction party, and vehicle trouble, road service system, the event of business's concrete are run in transportation
Barrier causes business's concrete to be transported to construction site;
And/or,
After reaching construction site, because forwarding agent's concrete does not meet construction party requirement, not barcode scanning is received.
The intelligent scheduling module 11 calls GPS module data, the situation of monitor in real time logistics transportation, monitor in real time order
Implementation status.
Each embodiment is described by the way of progressive in this specification, and what each embodiment was stressed is and it
The difference of its embodiment, same or analogous part cross-reference between each embodiment.For system embodiment
For, it is substantially corresponding with embodiment of the method due to it, so description is fairly simple, portion of the related part referring to embodiment of the method
Defend oneself bright.
The method of the present invention and system may be achieved in many ways.For example, can by software, hardware, firmware or
Software, hardware, any combinations of firmware are realizing the method for the present invention and system.For said sequence the step of methods described
Merely to illustrate, order described in detail above is not limited to the step of the method for the present invention, it is special unless otherwise
Do not mentionlet alone bright.Additionally, in certain embodiments, also the present invention can be embodied as recording program in the recording medium, these programs
Including for realizing the machine readable instructions of the method according to the invention.Thus, the present invention also covers storage for performing basis
The recording medium of the program of the method for the present invention.
Description of the invention is given for the sake of example and description, and is not exhaustively or by the present invention
It is limited to disclosed form.Many modifications and variations are for the ordinary skill in the art obvious.Select and retouch
It is to more preferably illustrate the principle and practical application of the present invention, and one of ordinary skill in the art is managed to state embodiment
The present invention is solved so as to design the various embodiments with various modifications for being suitable to special-purpose.
Claims (7)
1. a kind of business's concrete on-line scheduling management system based on smart mobile phone application, including:Business's concrete service for business management device, construction
End, business's concrete end and haulage vehicle, it is characterised in that business's concrete service for business management device includes map data server, described
Construction end includes construction end map monitoring module, and business's concrete end includes business's concrete end map monitoring module, the haulage vehicle peace
Dress GPS terminal equipment;
The construction end sends order placement information to business's concrete service for business management device, and business's concrete service for business management device is by end of constructing
Order placement information is sent to business's concrete end of correspondence Shang Tong suppliers, and business's concrete end carries out scheduling, send vehicle, sends and drive to order
The person of sailing, then sends above- mentioned information to business's concrete service for business management device, and business's concrete service for business management device is again by the row at business's concrete end
Product information, vehicle and driver information are sent to construction end, are associated with end of constructing so as to set up business's concrete end;
The GPS terminal equipment is by business's concrete enterprise data server registration, GPS address informations being added to described
Diagram data server, is allowed to provide vehicle location service, and the map data server is by the monitoring of construction end map
Module and business's concrete end map monitoring module send the position of the location information of the GPS terminal equipment and monitor in real time vehicle.
2. system according to claim 1, it is characterised in that the intelligent scheduling module to Shang Tong suppliers, driver,
The scheduling of vehicle is scheduled according to Shang Tong suppliers priority, driver's priority, vehicle priority;
Shang Tong suppliers priority is to carry out priority queueing to all Shang Tong suppliers relative to construction party, and queuing is leaned on
Front, priority is high, and the priority of scheduling is also high;
Driver's priority is that all drivers relative to construction party are carried out with priority queueing, is queued up forward, excellent
First level is high, and the priority of scheduling is also high;
The vehicle priority is that all vehicles relative to construction party are carried out with priority queueing, forward, priority of queuing up
Height, the priority of scheduling is also high.
3. system according to claim 2, it is characterised in that the evaluation criterion of Shang Tong suppliers priority has:
Distance, the condition of road surface of distance construction side of Shang Tong suppliers job location;
The scope of the enterprise and production of Shang Tong suppliers, transport strength and current business's concrete production cycle, haul-cycle time;
After sale evaluation and service marking situation of the construction end to Shang Tong suppliers;
The enterprise qualification of Shang Tong suppliers;
The illegal violations record case of Shang Tong suppliers;
Registration class of the Shang Tong suppliers in register user.
4. system according to claim 2, it is characterised in that the evaluation criterion of driver's priority has:
The current state of driver, the current state includes:Implementing driving task, etc. driving task to be performed, without appoint
Business;
Distance, the condition of road surface of driver's distance vehicle to be driven;
The same day cumulative operation time of driver;
Away from the time that last execution task terminates;
Driver violates the traffic regulations situation;
Average drive speed during the real-time driving task of driver.
5. system according to claim 2, it is characterised in that the evaluation criterion of the vehicle priority has:
The current state of vehicle, the current state includes:Implementing transport task, etc. transport task to be performed, without task;
Vehicle condition, the vehicle condition includes:Well, fault-free, overhaul, scrap;
Whether vehicle has driver;
The distance of vehicle distances Shang Tong supplier and construction party job location, condition of road surface;
Vehicle day adds up operating range.
6. the system according to any one of claim 1-5, it is characterised in that the intelligent scheduling module is running into current shape
Condition place an order cannot perform or implementation procedure in encounter problems when cannot continue executing with, concrete supplier scheduling of entering to do business first, choosing
Select priority highest Shang Tong supplier and perform current order task, next carries out vehicle scheduling, select the car of highest priority
, driver scheduling is finally carried out, select the driver of highest priority;
Described to dispatch buses when business's concrete material is loaded, next scheduled vehicle prepares to march into the arena, the intelligent scheduling module tool
There is time computing function, the filling material time of dispatching buses is next road institute elapsed time when marching into the arena of dispatching buses;
When cannot continue executing with when encountering problems in order fulfillment process, the order requeues;
Encountering problems to continue executing with the order fulfillment process refers to transport truck and driver from business's concrete
Suppliers transport business's concrete toward the construction site of construction party, and vehicle trouble, road service system, the event of business's concrete are run in transportation
Barrier causes business's concrete to be transported to construction site;
And/or,
After reaching construction site, because forwarding agent's concrete does not meet construction party requirement, not barcode scanning is received.
7. the system according to any one of claim 1-5, it is characterised in that the intelligent scheduling module calls GPS module
Data, the situation of monitor in real time logistics transportation, monitor in real time order implementation status.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610990328.1A CN106600208A (en) | 2016-11-10 | 2016-11-10 | Smart mobile phone application-based commercial concrete online scheduling management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610990328.1A CN106600208A (en) | 2016-11-10 | 2016-11-10 | Smart mobile phone application-based commercial concrete online scheduling management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106600208A true CN106600208A (en) | 2017-04-26 |
Family
ID=58591104
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610990328.1A Pending CN106600208A (en) | 2016-11-10 | 2016-11-10 | Smart mobile phone application-based commercial concrete online scheduling management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106600208A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109299857A (en) * | 2018-08-28 | 2019-02-01 | 广州市惠邦信息科技有限公司 | Quotient's concrete intelligence clout rotary system |
CN109325824A (en) * | 2018-08-28 | 2019-02-12 | 广州市惠邦信息科技有限公司 | Quotient's concrete intelligence production method and system |
CN113011762A (en) * | 2021-03-29 | 2021-06-22 | 重庆市城投混凝土有限公司 | Scheduling system and method for concrete tank truck |
CN114549083A (en) * | 2022-03-02 | 2022-05-27 | 吴雨涵 | One-stop delivery system for commercial concrete |
CN116070880A (en) * | 2023-03-07 | 2023-05-05 | 智能网联汽车(山东)协同创新研究院有限公司 | Special dispatch system of transportation vehicle based on thing networking |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101652789A (en) * | 2007-02-12 | 2010-02-17 | 肖恩·奥沙利文 | Share transportation system and service network |
CN102185745A (en) * | 2011-04-22 | 2011-09-14 | 郭永平 | IOT (internet of things) service system |
CN104036359A (en) * | 2006-12-13 | 2014-09-10 | 克朗设备公司 | Fleet management system |
CN105894251A (en) * | 2016-04-01 | 2016-08-24 | 李翀 | Terminal and corresponding commercial concrete producing and shaping cooperative system |
-
2016
- 2016-11-10 CN CN201610990328.1A patent/CN106600208A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104036359A (en) * | 2006-12-13 | 2014-09-10 | 克朗设备公司 | Fleet management system |
CN101652789A (en) * | 2007-02-12 | 2010-02-17 | 肖恩·奥沙利文 | Share transportation system and service network |
CN102185745A (en) * | 2011-04-22 | 2011-09-14 | 郭永平 | IOT (internet of things) service system |
CN105894251A (en) * | 2016-04-01 | 2016-08-24 | 李翀 | Terminal and corresponding commercial concrete producing and shaping cooperative system |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109299857A (en) * | 2018-08-28 | 2019-02-01 | 广州市惠邦信息科技有限公司 | Quotient's concrete intelligence clout rotary system |
CN109325824A (en) * | 2018-08-28 | 2019-02-12 | 广州市惠邦信息科技有限公司 | Quotient's concrete intelligence production method and system |
CN113011762A (en) * | 2021-03-29 | 2021-06-22 | 重庆市城投混凝土有限公司 | Scheduling system and method for concrete tank truck |
CN114549083A (en) * | 2022-03-02 | 2022-05-27 | 吴雨涵 | One-stop delivery system for commercial concrete |
CN116070880A (en) * | 2023-03-07 | 2023-05-05 | 智能网联汽车(山东)协同创新研究院有限公司 | Special dispatch system of transportation vehicle based on thing networking |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106600208A (en) | Smart mobile phone application-based commercial concrete online scheduling management system | |
JP5857581B2 (en) | Vehicle allocation apparatus and vehicle allocation method | |
CN108062703A (en) | A kind of cargo managing method, system and platform | |
CN104809601B (en) | The mutual auxiliary system of express delivery based on electronic map | |
CN106570652A (en) | Commodity concrete electronic delivery order management system based on intelligent mobile phone application | |
CN107180326A (en) | One single intelligent shipping method of closed loop | |
Zhao et al. | Location management of cloud forklifts in finished product warehouse | |
GB2535719A (en) | Telephone call placement | |
CN107767683A (en) | A kind of road restricted driving reminding method and device | |
CN110135777A (en) | A kind of article conveyer method and device | |
Nesheli et al. | Real-time public transport operations: Library of control strategies | |
CN117436777A (en) | Multi-type intermodal method and system for intelligent logistics freight transportation | |
CN105280012A (en) | Bus dispatching system based on cloud computing | |
CN106570974B (en) | The online queue management system of quotient's concrete based on smart mobile phone application | |
CN109299857A (en) | Quotient's concrete intelligence clout rotary system | |
CN112085347A (en) | Digital allocation management system and method for container truck fleet | |
JP2021064231A (en) | Service system using autonomous traveling vehicle | |
CN114897428A (en) | Order processing method and device, electronic equipment and storage medium | |
CN112348537B (en) | Information processing method, device, electronic equipment and storage medium | |
CN110400004A (en) | The time limit method for early warning and device of railway goods | |
Bai et al. | Approximate dynamic programming for platoon coordination under hours-of-service regulations | |
CN114881692A (en) | Network appointment scheduling method and device, electronic equipment and storage medium | |
Prabhu et al. | Value stream mapping of truck operations: A case study | |
US11880801B2 (en) | Delivery system utilizing a secondary transportation service provider | |
CN115796494B (en) | Work order processing method and work order information display method for unmanned vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170426 |
|
WD01 | Invention patent application deemed withdrawn after publication |