CN106592590A - Construction equipment for carrier pile - Google Patents

Construction equipment for carrier pile Download PDF

Info

Publication number
CN106592590A
CN106592590A CN201611049685.4A CN201611049685A CN106592590A CN 106592590 A CN106592590 A CN 106592590A CN 201611049685 A CN201611049685 A CN 201611049685A CN 106592590 A CN106592590 A CN 106592590A
Authority
CN
China
Prior art keywords
penetration
pile
construction equipment
automatically
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611049685.4A
Other languages
Chinese (zh)
Inventor
王继忠
张连喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201611049685.4A priority Critical patent/CN106592590A/en
Publication of CN106592590A publication Critical patent/CN106592590A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/08Drop drivers with free-falling hammer
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/06Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers for observation while placing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention provides construction equipment for a carrier pile. The construction equipment comprises a pile support which is provided with a chassis and a support and a pounding system which is provided with a protection sleeve, a pounding hammer and a main winch, wherein the pounding hammer is hung and driven by the main winch to pound a bottom in a protection sleeve; and the construction equipment is characterized in that the equipment further comprises an automatic material filling device which can fill padding quantitatively into the protection sleeve for several times, an automatic pounding control device which controls the main winch to lift the pounding hammer automatically according to a preset height for pounding the padding and an automatic three-strike penetration detection device which can automatically detect and record a penetration value of the pounding hammer after each time of falling and pounding, so that during construction of the carrier pile, presetting, monitoring and recording of construction parameters and automatic constructing are realized. The construction equipment further comprises the automatic three-strike penetration detection device, one-strike penetration generated by the pounding hammer which falls freely at a certain height and strikes on soil or padding in a foundation can be automatically detected, and multi-strike penetration can be continuously detected, and data is recorded and output.

Description

A kind of construction equipment of carrier pile
Technical field
The application is related to field of civil engineering, and in particular to a kind of construction equipment of carrier pile.
Background technology
Carrier pile be quickly grow in recent years, a kind of widely used new pile-type, with bearing capacity is high, subject range Extensively, the advantages of cost economic, its be core mechanism be certain depth and scope under an end the soil body it is closely knit, casing is sunk in construction To designed elevation, inserts are put into into casing in batches, hammer compacting repeatedly into shape with post and form carrier, reach penetration requirement After be further filled with coagulation rammed earth, last Reperfu- sion concrete pile.Therefore, for the corollary equipment of carrier pile driving construction, which is main Ability and key control point, are how fast and easily to realize filler, compacting, measurement penetration.
And currently used for the corollary equipment of carrier pile driving construction, entirely artificial control operation, particularly in filler, ram The aspects such as real, measurement penetration, need several knack workmans to coordinate and complete jointly, and this present situation not only causes construction Cost increase, inefficiency etc. are negatively affected, and the construction quality to carrier pile is also easy to produce many adverse effects, specifically such as: 1st, by manually operating hoist engine to lift hammer ram, hammer ram falls away from accurately controlling, in some soil layers in higher sensitivity, Falling for hammer ram hammer out that casing is more into shape away from excessive easily causing, and causes the disturbance of the soil body, affects the quality and efficiency of pile;2nd, by people To filler in casing, this mode makes the falling away from accurately can not matching somebody with somebody of the quantity of each filler and hammer ram to the instruments such as work spade Close, when especially regular appearance filler is excessive, filler cannot excessively ram out casing into casing and cause casing to destroy, or Situations such as very few length for hammering out casing into shape of filler excessively causes the disturbance of the soil body, and for total amount of filler cannot be accomplished accurately Ground metering.3rd, the measurement of penetration is the major control index of carrier pile carrier, and is hit using the hand dipping three of people and passed through In-degree, has that metering precision is poor, the measurement time is longer, state quantity measurement, and the bearing capacity of stake is affected It is maximum.4th, artificial operation necessarily has the fatigue phase, particularly in filler, the operating process of compacting, easily causes industrial accident Or the generation of quality accident.
Therefore a kind of carrier pile construction equipment of automatization is researched and developed, it is real at aspects such as filler, compacting, measurement penetrations Existing mechanization, automatization are reduces costs, improve the needs of work efficiency, and accurately measure, tightly control, improve pile quality Needs.
The content of the invention
The present invention is proposed to solve the problems, such as above-mentioned, it is therefore intended that provide a kind of construction equipment of carrier pile, While improving construction quality, ensureing man-machine safety, construction cost is reduced.
For achieving the above object, the construction equipment of a kind of carrier pile of the invention, which includes pile frame and tamping system, institute The support that pile frame includes that horizontal chassis and relatively above-mentioned chassis erect is stated, the tamping system includes casing, hammer ram and is located at Main winch on chassis, the main winch pass through wire rope suspensioning and drive hammer ram to move up and down in the inside of casing, realize The soil body or filler of bottom are rammed;It is characterized in that:The construction equipment also includes automated packing device, rams automatically Filler gradation, quantitative is automatically filled in by control device, penetration self-operated measuring unit, the automated packing device In casing;Automatically the control device of ramming controls highly automated proposing of the main hoisting machine according to artificial default or Automatic Program calculating Hammer ram is risen, is coordinated with automated packing device and each filler is rammed;The penetration self-operated measuring unit is to ramming Hammering the pile penetration numerical value after whereabouts is rammed each time into shape carries out automatic measurement and records.
In above-mentioned construction equipment, also including chassis supports device or/and mobile rotary apparatuss, chassis supports device includes setting In the hydraulic pressure or mechanical lag of chassis surrounding, mobile rotation includes the one kind or several in hydraulic walking, crawler type, catheter type Kind.
In above-mentioned construction equipment, the top of casing can add vibration head or diesel hammer or hydraulic hammer depending on construction requirement, lead to Cross the drilling construction or quickening speed of fulfiling hole for adding that said apparatus realize stake.
In above-mentioned construction equipment, another secondary hoist engine on chassis, is additionally provided with, the secondary hoist engine passes through steel wire rope and pulley Group and drive casing rise or sink, so as to realize the drilling construction and cylinder-wall protecting of stake.
In above-mentioned construction equipment, also including controller, above-mentioned automated packing device, control device is rammed automatically, three is hit and is passed through In-degree self-operated measuring unit connects the controller by wired or wireless mode respectively, sets the number of automated packing by controller Amount and number of times, main winch lift the height of hammer ram, the standard figures of penetration, so as to realize that construction parameter is set Fixed, monitoring, record, and according to the construction of design parameter auto-control.
In above-mentioned construction equipment, automated packing device includes hopper, feed appliance, feed controller, is integral type or split Formula, feed controller control inlet amount by relay and gate, and the hopper needs to be located at construction equipment depending on construction In forward and backward, left and right multiple positions, after filling filler in hopper can many carrier piles of all promising policy construction needs.
In above-mentioned construction equipment, control device is rammed automatically on main winch, this rams control device automatically can Automatic lifting hammer ram, lifted loosen to after setting height automatically steel wire rope make hammer ram fall, ram in the completed after it is automatically right Steel wire rope is braked.
Above-mentioned control device of ramming automatically includes controlling respectively the brake lever and trip(ping) lever of main winch pneumatically or hydraulically Electromagnetic valve, pneumatically or hydraulically push rod, which easier can be reequiped to existing hoist engine
The above-mentioned pneumatically or hydraulically push rod rammed in control device automatically by the brake lever of fastening screw and main winch and from Close bar to be connected, can be by the brake lever and trip(ping) lever manually directly operated in main winch, so as to realize automatically, partly after unclamping screw Simple switching between either automatically or manually operating.
In above-mentioned construction equipment, penetration self-operated measuring unit can measure and record every blow pile penetration, Can measure and record the accumulated number of penetration, additionally it is possible to which whether the pile penetration after judgement once is no more than previous Pile penetration.
In above-mentioned construction equipment, penetration self-operated measuring unit is located on main hoisting machine, including located at main winch Little gear that the reel side gear wheel coaxial with reel is engaged with gear wheel, the magneto-electric rotary coding in little gear Device, the current transformer in main winch control chamber, the proximity switch located at main winch base, the above-mentioned electric current of connection are mutual The computing module or chip of sensor and proximity switch and encoder, the computing module or chip are in controller noted above;Master file When raising machine elevator, above-mentioned large and small pinion rotation is driven so as to pass through the rotation position of encoder recording reel;By elevator process In current step and vibrations judge steel wire rope from the lax moment for being changed into and tightening;Before being calculated by above-mentioned computing module or chip During elevator, steel wire rope is determined when time pile penetration from the lax reel rotation position difference for being changed into tightening the moment twice afterwards, is passed through The store function of computing module or chip calculates penetration accumulated number.The penetration self-operated measuring unit is to master file The number of drum turns acquisition precision for raising machine can reach 1/5000 circle, can reach below 1cm, enumerator to steel wire rope stroke recording precision Sampling period can reach 100KHz, time delay resolution about 1ms.
In above-mentioned construction equipment, the pile penetration result as measured by penetration self-operated measuring unit, to filling out automatically Expect device and ram automatically control device to be adjusted control, adjustment control is included in after ramming every time and judges penetration Whether set in advance desired value is reached, and such as reaching desired value no longer will ram;If miss the mark value, according to pile penetration As a result the amount of filler of automated packing device is increased or is reduced, or is improved or is reduced ramming automatically the height that control device lifts hammer ram Degree.
Above-mentioned construction equipment can be used in compaction pile of constructing, and when compacting pile construction is carried out, the construction equipment does not include shield Cylinder.Compaction pile typically tamps compacted rear form compound foundation using materials such as rubble, dregs, dirt in foundation soil body, is entering General detection blow pile penetration during row compacting pile construction.
For achieving the above object, present invention additionally comprises a kind of penetration self-operated measuring unit, it is characterised in that the dress Put can in carrier pile driving construction, automatic measurement hammer ram certain height and position free-falling impact in ground the soil body or Deformation numerical value produced by after filler, the i.e. blow pile penetration of hammer ram, and the device can continuously measure multi-hit pile penetration simultaneously Measurement data record that can be by measurement data or after being computed simultaneously is exported.
Above-mentioned penetration self-operated measuring unit, i.e., can measure and record every blow pile penetration, it is also possible to which measurement is simultaneously The accumulated number of record penetration, additionally it is possible to the which whether pile penetration after judgement once is not more than previous pile penetration.
Above-mentioned penetration self-operated measuring unit, on main hoisting machine, including located at main winch reel side with The little gear that the coaxial gear wheel of reel is engaged with gear wheel, the magneto-electric rotary encoder in little gear, located at master file The current transformer in machine control chamber, the proximity switch located at main winch base are raised, is connected above-mentioned current transformer and is close to The computing module or chip of switch and encoder;During main winch elevator, above-mentioned large and small pinion rotation is driven so as to pass through coding The rotation position of device recording reel;Judge that steel wire rope is changed into what is tightened from lax by the current step during elevator and vibrations Moment;Before and after being calculated by above-mentioned computing module or chip, steel wire rope is changed into tightening the volume at moment from lax during elevator twice Cylinder rotation position difference is determined when time pile penetration, by the store function calculating penetration accumulative total of computing module or chip Value.
The characteristics of of the invention and advantage are:
1. automatization is all improved in terms of filler, compacting, the feature of measurement penetration, so as to applying in carrier pile In work, that is, realize to the presetting of construction parameter, real-time monitoring, record at any time, and can be according to the parameter being pre-designed Auto-control is constructed.
2. automatization is improved in terms of the feature of filler and compacting, compare manual hand manipulation its precise degrees, match somebody with somebody Conjunction degree is obviously improved, the constructional difficulties that can avoid completely causing because filler is excessive or very few and heavy tamping energy is unstable etc., Quality problems.
3. automatic detection measurement penetration, it is little to compare manual hand manipulation its high precision, error, and passes through to be surveyed The pile penetration result of amount, rams to automated packing device and automatically control device and is adjusted control.
4. construction equipment low cost of manufacture, convenient transportation, and can in-situ reformation for existing carrier pile construction equipment Assembling.
5. compare existing construction equipment, the aspect such as the quality of construction, effect and speed has the lifting of highly significant, and energy Enough reduce by more than 80% labour expenses, construction cost is greatly reduced.
6. improve the safety of personnel and equipment.
Description of the drawings
Fig. 1 is that structure chart is faced in first preferred embodiment of the construction equipment of the present invention, and Fig. 2 is side block diagram;
Fig. 3 and Fig. 4 are that structure chart is faced in second and the 3rd preferred embodiment of the construction equipment of the present invention;
Fig. 5 is the controller and automated packing device of the construction equipment of the present invention and the control logic for ramming automatically control device Figure;
Fig. 6 is the part assembling drawing in the penetration self-operated measuring unit of the construction equipment of the present invention;
Fig. 7 is the penetration automatic measurement and automated packing device of the construction equipment of the present invention and rams automatically control device Control logic figure.
Specific embodiment
Below by way of the drawings and specific embodiments, the invention will be further described.
Fig. 1 is that structure chart is faced in first preferred embodiment of the construction equipment of the present invention, and Fig. 2 is side block diagram, As depicted in figs. 1 and 2, construction equipment includes pile frame and tamping system, and the pile frame includes horizontal chassis 1 and vertical Frame 2, the tamping system include casing 3, hammer ram 4 and located at the One On The Chassis main winch 5, the steel stretched out from main winch 5 Cord passes around the suspention hammer ram 4 of assembly pulley 8 on 2 top of support, and drives hammer ram 4 to move up and down in the inside of casing 3, realizes the bottom of to The soil body or filler in portion is rammed;The surrounding on chassis 1 is additionally provided with hydraulic pressure lower limb 9 for support equipment, is additionally provided with chassis 1 Slewing equipment 10 and running gear 11;The upper end of casing 3 is additionally provided with verticality control device 6, and the verticality control device 6 passes through Two horizontal arms in left and right are connected with the vertical guide rail on support 2 in draw-in groove mode;Another hoist engine 7 is additionally provided with chassis 1, is rolled up Raising machine 7 can drive casing 3 to rise or sink by rope and assembly pulley;Control chamber 19 and power distribution cabinet 20 are additionally provided with chassis 1; The construction equipment also includes the automated packing device located at 1 front end of chassis, and the automated packing device includes hopper 12, feed appliance 13 With feed controller 14, using relay and gate control inlet amount, the filler in hopper 12 is through charging for feed controller 14 Fall within feed appliance 13 and be fed device 13 to be invested in casing 3 after 14 gradation of controller, quantitative control;The construction equipment Also include ramming automatically control device 15 on main winch 5,5 automatic lifting hammer ram 4 of control main winch is high to setting Automatically loosening steel wire rope after degree is rammed 4 whereabouts filler of hammer ram, and automatically to steel wire rope system after ramming in the completed It is dynamic;The construction equipment also includes the penetration self-operated measuring unit 16 on main winch 5, and hammer ram is fallen each time Pile penetration after ramming carries out automatic measurement and records;The equipment also include controller 17, controller 17 respectively with feed control Device 14, ram automatically control device 15, penetration self-operated measuring unit 16 and connect.
Fig. 3 is that structure chart is faced in second preferred embodiment of the construction equipment of the present invention, as shown in figure 3, second Embodiment and one embodiment are that the difference of Fig. 1 is, the top of casing 3 is provided with for carrying out the mesopore vibration head of pore-forming 18。
Fig. 4 is that structure chart is faced in the 3rd preferred embodiment of the construction equipment of the present invention, as shown in figure 4, the 3rd Embodiment and one embodiment are that the difference of Fig. 1 is, not including casing 3.
Fig. 5 is controller and the automated packing device of the construction equipment of the present invention and rams automatically the control of control device and patrol Figure is collected, as shown in figure 5, by controller(PCL)Collection is rammed automatically proximity switch summation current transformer in control device, three is hit The input signal sent by magneto-electric rotary encoder in pile penetration self-operated measuring unit, and by controller(PCL)To automatic The gate relay of filler device, the electromagnetic valve rammed in control device automatically send output signal.
Fig. 6 be the present invention construction equipment penetration self-operated measuring unit in part assembling drawing, wherein Fig. 6 a For front view, Fig. 6 b are side view, as shown in fig. 6, gear wheel 21 is located at the reel side of main winch and coaxial with reel, it is little Gear 22 is engaged with gear wheel 21, and magneto-electric rotary encoder 23 is provided with little gear 22, during 5 hoisting rope of main winch, Gear wheel 21, little gear 22 is driven to rotate so as to pass through the rotation position of encoder recording reel.
Fig. 7 is the penetration automatic measurement and automated packing device of the construction equipment of the present invention and rams automatically control The control logic figure of device, as shown in fig. 7, calculating penetration according to sampling rotary encoder reading, and will calculate total Contrast judgement is carried out with desired value, miss the mark value then calculates the hammer lifting height and amount of filler rammed next time, and to automatic Filler device and automatic ramming device send control instruction, start elevator, filler afterwards and enter the next action cycle;Hit when three Pile penetration meets desired value, it is believed that rams, elevator and filler release.
The preferred embodiments of the present invention are the foregoing is only, the present invention is not limited to, for the skill of this area For art personnel, the present invention can have various modifications and variations.It is all within the spirit and principles in the present invention, made any repair Change, equivalent, improvement etc., be all contained within protection scope of the present invention.

Claims (16)

1. a kind of construction equipment of carrier pile, which includes pile frame and tamping system, and the pile frame includes horizontal chassis and phase The support erected to above-mentioned chassis, the tamping system include casing, hammer ram and the main winch on chassis, the master winch Machine passes through wire rope suspensioning and drives hammer ram to move up and down in the inside of casing, realizes ramming the soil body or filler of bottom Hit;It is characterized in that:The construction equipment also includes automated packing device, rams automatically control device, penetration and survey automatically Amount device, the automated packing device are automatically filled in filler gradation, quantitative in casing;It is described to ram automatically control dress The highly automated lifting hammer ram that the main hoisting machine of control is calculated according to artificial default or Automatic Program is put, is coordinated with automated packing device Each filler is rammed;The penetration self-operated measuring unit falls each time to hammer ram the pile penetration after ramming Numerical value carries out automatic measurement and records.
2. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that the construction equipment is also filled including chassis supports Put or/and mobile rotary apparatuss.
3. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that the top of casing depending on construction requirement can plus If vibration head or diesel hammer or hydraulic hammer.
4. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that another secondary elevator is additionally provided with chassis Machine, the secondary hoist engine drive casing to rise or sink by steel wire rope and assembly pulley.
5. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that the construction equipment also includes controller, on State automated packing device, control device, penetration self-operated measuring unit are rammed automatically respectively by wired or wireless parties Formula connects the controller, is hit by the quantity and number of times of controller setting automated packing, the height of main winch lifting hammer ram, three and is passed through The standard figures of in-degree, so as to realize the setting to construction parameter, monitoring, record, and according to design parameter auto-control Construction.
6. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that the automated packing device include hopper, Feed appliance, feed controller, are integral type or split type, and the feed controller controls charging by relay and gate Amount.
7. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that the control device of ramming automatically is located at master On hoist engine, this ram automatically control device can automatic lifting hammer ram, lifted loosen automatically steel wire rope to after setting height Make hammer ram fall, ram in the completed after automatically steel wire rope is braked.
8. the construction equipment of the carrier pile as described in claim 1 or 6, it is characterised in that described to ram automatically control device bag Include the brake lever and the pneumatically or hydraulically electromagnetic valve of trip(ping) lever of control main winch, pneumatically or hydraulically push rod respectively.
9. the construction equipment of the carrier pile as described in one of claim 1 or 7 or 8, it is characterised in that described to ram automatically control Pneumatically or hydraulically push rod in device is connected with the brake lever and trip(ping) lever of main winch by fastening screw, can after unclamping screw By the brake lever and trip(ping) lever that manually directly operate in main winch, cutting between automatic, semi-automatic or manual operation is realized Change.
10. the construction equipment of carrier pile as claimed in claim 1, it is characterised in that the penetration automatic measurement dress Put, it is also possible to measure and record the accumulated number of penetration, additionally it is possible to sentence Whether the pile penetration having no progeny once is not more than previous pile penetration.
The construction equipment of 11. carrier piles as described in claim 1 or 5 or 10, it is characterised in that the penetration is automatic Measurement apparatus are nibbled including the gear wheel coaxial with reel located at main winch reel side and gear wheel on main hoisting machine The little gear of conjunction, the magneto-electric rotary encoder in little gear, the current transformer in main winch control chamber, set The computing module or core of proximity switch, the above-mentioned current transformer of connection and proximity switch and encoder in main winch base Piece, the computing module or chip are in controller noted above;During main winch elevator, drive above-mentioned large and small pinion rotation so as to By the rotation position of encoder recording reel;Judge steel wire rope by lax change by the current step during elevator and vibrations For the moment tightened;Before and after being calculated by above-mentioned computing module or chip, steel wire rope is changed into tightening from lax during elevator twice The reel rotation position difference at moment determines when time pile penetration, calculates three by the store function of computing module or chip and hit injection Degree accumulated number.
The construction equipment of 12. carrier piles as claimed in claim 1, it is characterised in that filled by penetration automatic measurement Measured pile penetration result is put, control device is rammed to automated packing device and automatically and is adjusted control.
The construction equipment of 13. carrier piles as claimed in claim 1, it is characterised in that the construction equipment can be used in construction and squeeze Close stake, when compacting pile construction is carried out, the construction equipment does not include casing device.
14. a kind of penetration self-operated measuring units, it is characterised in that the device can be surveyed in carrier pile driving construction automatically Deformation numerical value of the amount hammer ram produced by after certain height and position free-falling impacts in the ground soil body or filler, i.e., The blow pile penetration of hammer ram, and the device can continuously measure multi-hit pile penetration can be by measurement data or after being computed Measurement data record is simultaneously exported.
15. penetration self-operated measuring units as claimed in claim 14, it is characterised in that the device can be measured simultaneously Record is per blow pile penetration, it is also possible to measure and record the accumulated number of penetration, additionally it is possible to the injection after judgement once Whether degree is not more than previous pile penetration.
The 16. penetration self-operated measuring units as described in claims 14 or 15, it is characterised in that the penetration Self-operated measuring unit is located on main hoisting machine, including the gear wheel coaxial with reel located at main winch reel side and canine tooth The little gear of wheel engagement, the magneto-electric rotary encoder in little gear, the Current Mutual Inductance in main winch control chamber Device, the proximity switch located at main winch base, the computing module for connecting above-mentioned current transformer and proximity switch and encoder Or chip;During main winch elevator, above-mentioned large and small pinion rotation is driven so as to pass through the rotation position of encoder recording reel; Judge that steel wire rope is changed into the moment tightened from lax by the current step during elevator and vibrations;By above-mentioned computing module Or chip calculate before and after twice during elevator steel wire rope is determined from the lax reel rotation position difference for being changed into tightening the moment ought Secondary pile penetration, calculates penetration accumulated number by the store function of computing module or chip.
CN201611049685.4A 2016-11-25 2016-11-25 Construction equipment for carrier pile Pending CN106592590A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611049685.4A CN106592590A (en) 2016-11-25 2016-11-25 Construction equipment for carrier pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611049685.4A CN106592590A (en) 2016-11-25 2016-11-25 Construction equipment for carrier pile

Publications (1)

Publication Number Publication Date
CN106592590A true CN106592590A (en) 2017-04-26

Family

ID=58593139

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611049685.4A Pending CN106592590A (en) 2016-11-25 2016-11-25 Construction equipment for carrier pile

Country Status (1)

Country Link
CN (1) CN106592590A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964955A (en) * 2017-11-28 2018-04-27 王继忠 A kind of self-operated measuring unit and method for automatic measurement for ramming pile penetration
CN113322928A (en) * 2021-06-15 2021-08-31 湖北波森特岩土工程有限公司 Multi-equipment efficient construction method for automatic non-soil-squeezing type carrier pile with pile body
CN113481962A (en) * 2021-08-13 2021-10-08 湖北波森特岩土工程有限公司 Method for automatically constructing deep dynamic compaction composite foundation
CN114991144A (en) * 2022-07-08 2022-09-02 邵良荣 Automatic construction equipment for carrier pile

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006097398A (en) * 2004-09-30 2006-04-13 Ube Concrete Kogyo Kk Depth measuring device for pile driver
CN201546244U (en) * 2009-11-27 2010-08-11 长安大学 Dynamic compaction depth detecting system based on photoelectric encoder
CN203475410U (en) * 2013-09-30 2014-03-12 石午江 Automatic-feeding automatic-compacting full-automatic heavy compactor
CN104563116A (en) * 2015-02-12 2015-04-29 王继忠 Construction equipment for automatically controlling tamping of heavy hammer
CN206289629U (en) * 2016-11-25 2017-06-30 王继忠 A kind of construction equipment of carrier pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006097398A (en) * 2004-09-30 2006-04-13 Ube Concrete Kogyo Kk Depth measuring device for pile driver
CN201546244U (en) * 2009-11-27 2010-08-11 长安大学 Dynamic compaction depth detecting system based on photoelectric encoder
CN203475410U (en) * 2013-09-30 2014-03-12 石午江 Automatic-feeding automatic-compacting full-automatic heavy compactor
CN104563116A (en) * 2015-02-12 2015-04-29 王继忠 Construction equipment for automatically controlling tamping of heavy hammer
CN206289629U (en) * 2016-11-25 2017-06-30 王继忠 A kind of construction equipment of carrier pile

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964955A (en) * 2017-11-28 2018-04-27 王继忠 A kind of self-operated measuring unit and method for automatic measurement for ramming pile penetration
CN113322928A (en) * 2021-06-15 2021-08-31 湖北波森特岩土工程有限公司 Multi-equipment efficient construction method for automatic non-soil-squeezing type carrier pile with pile body
CN113481962A (en) * 2021-08-13 2021-10-08 湖北波森特岩土工程有限公司 Method for automatically constructing deep dynamic compaction composite foundation
CN113481962B (en) * 2021-08-13 2022-07-15 邵良荣 Method for automatically constructing deep dynamic compaction composite foundation
CN114991144A (en) * 2022-07-08 2022-09-02 邵良荣 Automatic construction equipment for carrier pile
CN114991144B (en) * 2022-07-08 2023-12-08 邵良荣 Carrier pile automatic construction equipment

Similar Documents

Publication Publication Date Title
CN206289629U (en) A kind of construction equipment of carrier pile
CN106592590A (en) Construction equipment for carrier pile
CN106638596A (en) Construction equipment of carrier pile
US8821072B2 (en) Ground drilling method and apparatus
CN107461150A (en) A kind of piling machine for bridge construction
CN113322928B (en) Multi-equipment efficient construction method for automatic non-soil-squeezing type carrier pile with pile body
CN110428160A (en) A kind of digitlization construction management system, method and the dynamic compaction machinery of dynamic compaction machinery
CN104609326B (en) A kind of dynamic compaction machinery and its winding plant
CN110206054A (en) A kind of power transmission line safety zone basement process optimization method
CN213450269U (en) Rectangular slide-resistant pile mechanical construction device
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN201801867U (en) Automatic monitoring device for dynamic compaction
CN106769127A (en) System and method is excavated in the three-dimensional analog simulation experiment of three-dimensional loading
CN206298899U (en) A kind of construction equipment of carrier pile
CN204212143U (en) A kind of automatic soil compactor that self-feeding conveyer belt is housed
RU2011132467A (en) DEVICE AND METHOD FOR CHECKING THE DESIGN PARAMETER
CN206248485U (en) A kind of new indoor high frequency circulation impact dynamic consolidation experimental rig
CN207047829U (en) Modified vibrosinking pile construction equipment
CN206132133U (en) Ram quick -witted construction operation parameters acquisition system by force
CN215888187U (en) Dynamic compaction foundation ramming settlement measuring system
CN214401726U (en) Ramming point arrangement device for collapsible loess foundation
CN113188513B (en) Intelligent measurement and analysis system of high-speed hydraulic tamper
CN114411683B (en) Method for improving ramming settlement measurement precision
CN217980279U (en) Accurate measuring device for ramming settlement of dynamic compactor
CN107542080B (en) Recording method for compacted graded broken stone pile driving construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426

RJ01 Rejection of invention patent application after publication