CN106570569A - Measuring and collecting work intelligent management system and measuring and collecting method thereof - Google Patents
Measuring and collecting work intelligent management system and measuring and collecting method thereof Download PDFInfo
- Publication number
- CN106570569A CN106570569A CN201610998326.7A CN201610998326A CN106570569A CN 106570569 A CN106570569 A CN 106570569A CN 201610998326 A CN201610998326 A CN 201610998326A CN 106570569 A CN106570569 A CN 106570569A
- Authority
- CN
- China
- Prior art keywords
- module
- management system
- data
- intelligent management
- login
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/24—Querying
- G06F16/245—Query processing
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/24—Querying
- G06F16/245—Query processing
- G06F16/2458—Special types of queries, e.g. statistical queries, fuzzy queries or distributed queries
- G06F16/2462—Approximate or statistical queries
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
Abstract
The invention provides a measuring and collecting work intelligent management system comprising a system login module, a field data collecting module, a field data upload module, a field problem input module, a field problem analysis module, a dispatch list generation module, a dispatch list output module, a field problem feedback module, a data statistical analysis module, a report statistics module and a data inquiring module. The invention also comprises a measuring and collecting method of the measuring and collecting work intelligent management system. The historical records can be inquired through keywords, and inquiring can be specified to the responsible person so as to solve the inconvenience caused by a paper work record sheet.
Description
Technical field
The present invention relates to measure acquisition technique field, specifically a kind of metering collecting work intelligent management system and its
Metering acquisition method.
Background technology
Metering (collection) device scene defect elimination workload is big, wide, and some cell (unit) metering (collection) problems are frequent
Appearance is difficult to count, finds, regularly all kinds of working reports, data statistics excessively repeat, loaded down with trivial details, papery work on the spot record
It is not easy to preserve, searches, and system is unable to self-perfection.
The content of the invention
It is an object of the invention to provide a kind of metering collecting work intelligent management system and its metering acquisition method, are used for
Solve data statistics in existing metering collecting work excessively repeat, it is loaded down with trivial details, responsibility confirms trouble, system cannot self-perfection ask
Topic.
The present invention solves its technical problem and is adopted the technical scheme that:Metering collecting work intelligent management system, it is special
Levying is, including
For logging in the system login module of gage work intelligent management system;With,
For the on-site data gathering module of collection site data;With,
For to transmission module in the field data of field data typing management system;With,
For the site problems input module to site problems input system;With,
For the site problems analysis module being analyzed to the site problems of typing;With,
For generating the job order generation module of job order;With,
For job order to be printed the job order output module to be checked with scene;With,
For site problems to be fed back the site problems feedback module so as to sophisticated systems data bank;With,
For statistic analysis record, and judge certain problem in certain place data statistic analysis mould that Jing often occurs
Block;With,
For screening and derive the report form statistics module of the quantity of a certain work and details in certain period;With,
For checking, retrieving the data inquiry module of the content of history work sheet.
Further, described system login module is provided with logon rights, including level login and general login;It is senior
Log in and logged in by job number and password for administrative staff, typically log in for common staff by job number and password
Logged in;Level login is different with the general authority for logging in, and the authority of level login is more than the general authority for logging in.
Further, the condition of described job order generation module work is under the system of level login.
Further, described field data includes field image or scene photograph.
Further, described site problems input module is input into by keyword;
Described site problems analysis module is analyzed by keyword to site problems, and staff is confirmed.
Further, the content of work sheet includes working time, job site, action, staff, work
Outfit, change card or change the situation of table.
Further, described data inquiry module inquiry data are inquired about using keyword.
The metering acquisition method of metering collecting work intelligent management system, using metering collecting work intelligent management system,
It is characterized in that, specifically include following steps:
Step 1), metering collecting work intelligent management system is logged in by the general login of system login module;
Step 2), by transmission module in on-site data gathering module, field data and site problems input module by scene
The image data and key to the issue word for going wrong is entered into management system;
Step 3), metering collecting work intelligent management system is logged in by the level login of system login module;
Step 4), system the image data of problem and key to the issue word are analyzed by site problems analysis module,
Confirmed after confirmation;
Step 5), by job order generation module confirm generate job order;
Step 6), metering collecting work intelligent management system is logged in by the general login of system login module;
Step 7), site problems are carried out being entered into management system by site problems feedback module, management system will be existing
The result that the result of field case study module analysis is fed back with site problems feedback module is compared, anti-with live feedback module
The result of feedback is defined, and carries out sophisticated systems data bank;
Step 8), the content of data statistic analysis module statistical analysis job order, and judge what which area easily occurs
The problem of kind, and the number of times for going wrong;
Step 9), if desired for query history logging, inquired about by keyword by data inquiry module.
The invention has the beneficial effects as follows:Metering collecting work intelligent management system and its metering collection side that the present invention is provided
Method, using having logon rights system login module, different grades of staff has different logon rights, and higher grade
Logon rights are more.
The present invention carries out site problems by the collection of field data to be entered into management system first, again asks at scene
Topic is analyzed, and is confirmed after relevant staff's confirmation, generates job order.Staff rescues to scene
Afterwards, problem is fed back to again management system, management system is contrasted the result of analysis with the result of feedback, and to feed back
Result be defined, progressively voluntarily improve data bank, whole system realizes problem analysis, solve problem and self-perfection data bank
One systematized operation.
The present invention can carry out query history record by keyword, can solve papery logging specific to person liable
The inconvenience that single tape is come.
Description of the drawings
Fig. 1 is the functions of modules figure of the present invention.
Specific embodiment
As shown in figure 1, metering collecting work intelligent management system, including
For logging in the system login module of gage work intelligent management system;With,
For the on-site data gathering module of collection site data;With,
For to transmission module in the field data of field data typing management system;With,
For the site problems input module to site problems input system;With,
For the site problems analysis module being analyzed to the site problems of typing;With,
For generating the job order generation module of job order;With,
For job order to be printed the job order output module to be checked with scene;With,
For site problems to be fed back the site problems feedback module so as to sophisticated systems data bank;With,
For statistic analysis record, and judge certain problem in certain place data statistic analysis mould that Jing often occurs
Block;With,
For screening and derive the report form statistics module of the quantity of a certain work and details in certain period;With,
For checking, retrieving the data inquiry module of the content of history work sheet.
System login module is provided with logon rights, including level login and general login;Level login is used for custodian
Member is logged in by job number and password, is typically logged in and is logged in by job number and password for common staff;It is senior
Login is different with the general authority for logging in, and the authority of level login is more than the authority of general login.
The condition of job order generation module work is under the system of level login.
Field data includes field image or scene photograph.
Site problems input module is input into by keyword;
Described site problems analysis module is analyzed by keyword to site problems, and staff is confirmed.
The content of work sheet include the working time, job site, action, staff, work outfit,
Change card or change the situation of table.
Data inquiry module inquiry data are inquired about using keyword.
The metering acquisition method of metering collecting work intelligent management system, using metering collecting work intelligent management system,
Specifically include following steps:
Step 1), metering collecting work intelligent management system is logged in by the general login of system login module;
Step 2), by transmission module in on-site data gathering module, field data and site problems input module by scene
The image data and key to the issue word for going wrong is entered into management system;
Step 3), metering collecting work intelligent management system is logged in by the level login of system login module;
Step 4), system the image data of problem and key to the issue word are analyzed by site problems analysis module,
Confirmed after confirmation;
Step 5), by job order generation module confirm generate job order;
Step 6), metering collecting work intelligent management system is logged in by the general login of system login module;
Step 7), site problems are carried out being entered into management system by site problems feedback module, management system will be existing
The result that the result of field case study module analysis is fed back with site problems feedback module is compared, anti-with live feedback module
The result of feedback is defined, and carries out sophisticated systems data bank;
Step 8), the content of data statistic analysis module statistical analysis job order, and judge what which area easily occurs
The problem of kind, and the number of times for going wrong;
Step 9), if desired for query history logging, inquired about by keyword by data inquiry module.
The present invention is not limited only to above-mentioned steps flow process, above-mentioned simply one of embodiments of the invention.
Although the above-mentioned accompanying drawing that combines is described to the specific embodiment of the present invention, not to present invention protection model
The restriction enclosed, on the basis of technical scheme, those skilled in the art do by need not paying creative work
The various modifications for going out or deformation are still within protection scope of the present invention.
Claims (8)
1. collecting work intelligent management system is measured, be it is characterized in that, including
For logging in the system login module of gage work intelligent management system;With,
For the on-site data gathering module of collection site data;With,
For to transmission module in the field data of field data typing management system;With,
For the site problems input module to site problems input system;With,
For the site problems analysis module being analyzed to the site problems of typing;With,
For generating the job order generation module of job order;With,
For job order to be printed the job order output module to be checked with scene;With,
For site problems to be fed back the site problems feedback module so as to sophisticated systems data bank;With,
For statistic analysis record, and judge certain problem in certain place data statistic analysis module that Jing often occurs;
With,
For screening and derive the report form statistics module of the quantity of a certain work and details in certain period;With for checking, retrieving
The data inquiry module of the content of history work sheet.
2. metering collecting work intelligent management system according to claim 1, is characterized in that, described system login module
It is provided with logon rights, including level login and general login;Level login is carried out for administrative staff by job number and password
Log in, typically log in and logged in by job number and password for common staff;Level login and the general authority for logging in
Difference, the authority of level login is more than the general authority for logging in.
3. metering collecting work intelligent management system according to claim 2, is characterized in that, described job order generates mould
The condition of block work is under the system of level login.
4. metering collecting work intelligent management system according to claim 1, is characterized in that, described field data includes
Field image or scene photograph.
5. metering collecting work intelligent management system according to claim 1, is characterized in that, described site problems input
Module is input into by keyword;
Described site problems analysis module is analyzed by keyword to site problems, and staff is confirmed.
6. metering collecting work intelligent management system according to claim 1, is characterized in that, the content bag of work sheet
Include the working time, job site, action, staff, work outfit, change card or change the situation of table.
7. metering collecting work intelligent management system according to claim 1, is characterized in that, described data inquiry module
Inquiry data are inquired about using keyword.
8. the metering acquisition method of collecting work intelligent management system is measured, using the meter described in claim 1-6 any one
Amount collecting work intelligent management system, is characterized in that, specifically include following steps:
Step 1), metering collecting work intelligent management system is logged in by the general login of system login module;
Step 2), by transmission module in on-site data gathering module, field data and site problems input module by scene appearance
The image data and key to the issue word of problem is entered into management system;
Step 3), metering collecting work intelligent management system is logged in by the level login of system login module;
Step 4), system the image data of problem and key to the issue word are analyzed by site problems analysis module, check
Confirmed after errorless;
Step 5), by job order generation module confirm generate job order;
Step 6), metering collecting work intelligent management system is logged in by the general login of system login module;
Step 7), site problems are carried out by site problems feedback module be entered into management system, management system asks at scene
The result that the result of topic analysis module analysis is fed back with site problems feedback module is compared, and is fed back with live feedback module
As a result it is defined, carries out sophisticated systems data bank;
Step 8), the content of data statistic analysis module statistical analysis job order, and judge which kind of which area easily occurs and ask
Topic, and the number of times for going wrong;
Step 9), if desired for query history logging, inquired about by keyword by data inquiry module.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610998326.7A CN106570569A (en) | 2016-11-11 | 2016-11-11 | Measuring and collecting work intelligent management system and measuring and collecting method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610998326.7A CN106570569A (en) | 2016-11-11 | 2016-11-11 | Measuring and collecting work intelligent management system and measuring and collecting method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106570569A true CN106570569A (en) | 2017-04-19 |
Family
ID=58541791
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610998326.7A Pending CN106570569A (en) | 2016-11-11 | 2016-11-11 | Measuring and collecting work intelligent management system and measuring and collecting method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106570569A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109849527A (en) * | 2019-01-22 | 2019-06-07 | 广东铭钰科技股份有限公司 | A kind of automatic signaling method and system of laser machine |
CN110096421A (en) * | 2019-04-30 | 2019-08-06 | 中国人民解放军海军大连舰艇学院 | A kind of acquisition and management system of communication data |
CN110689259A (en) * | 2019-09-25 | 2020-01-14 | 云南电力技术有限责任公司 | Power system statistic digital detection management system |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104182840A (en) * | 2014-08-26 | 2014-12-03 | 国家电网公司 | Electric marketing metering mobile application system and work method thereof |
CN104377817A (en) * | 2014-11-11 | 2015-02-25 | 国家电网公司 | Operation and maintenance integrated on-site work information collecting system of transformer substation |
CN104517194A (en) * | 2014-12-30 | 2015-04-15 | 国家电网公司 | Power operation-maintenance dispatching list generating method based on dynamic planning |
CN105260841A (en) * | 2015-10-16 | 2016-01-20 | 国网甘肃省电力公司天水供电公司 | Auditing system for power distribution network fault emergency repair receipt |
CN105373870A (en) * | 2014-08-26 | 2016-03-02 | 国家电网公司 | Power check mobile application system for power marketing and working method thereof |
CN105825337A (en) * | 2016-03-17 | 2016-08-03 | 国网安徽省电力公司信息通信分公司 | Intelligent inspection system for 500KV substation communication device |
CN106504117A (en) * | 2016-10-31 | 2017-03-15 | 国家电网公司 | Electric power outdoor operation system |
-
2016
- 2016-11-11 CN CN201610998326.7A patent/CN106570569A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104182840A (en) * | 2014-08-26 | 2014-12-03 | 国家电网公司 | Electric marketing metering mobile application system and work method thereof |
CN105373870A (en) * | 2014-08-26 | 2016-03-02 | 国家电网公司 | Power check mobile application system for power marketing and working method thereof |
CN104377817A (en) * | 2014-11-11 | 2015-02-25 | 国家电网公司 | Operation and maintenance integrated on-site work information collecting system of transformer substation |
CN104517194A (en) * | 2014-12-30 | 2015-04-15 | 国家电网公司 | Power operation-maintenance dispatching list generating method based on dynamic planning |
CN105260841A (en) * | 2015-10-16 | 2016-01-20 | 国网甘肃省电力公司天水供电公司 | Auditing system for power distribution network fault emergency repair receipt |
CN105825337A (en) * | 2016-03-17 | 2016-08-03 | 国网安徽省电力公司信息通信分公司 | Intelligent inspection system for 500KV substation communication device |
CN106504117A (en) * | 2016-10-31 | 2017-03-15 | 国家电网公司 | Electric power outdoor operation system |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109849527A (en) * | 2019-01-22 | 2019-06-07 | 广东铭钰科技股份有限公司 | A kind of automatic signaling method and system of laser machine |
CN110096421A (en) * | 2019-04-30 | 2019-08-06 | 中国人民解放军海军大连舰艇学院 | A kind of acquisition and management system of communication data |
CN110689259A (en) * | 2019-09-25 | 2020-01-14 | 云南电力技术有限责任公司 | Power system statistic digital detection management system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100437514C (en) | Bank main machine pressure testing method and tester | |
CN110505102B (en) | Power information communication fusion monitoring and service standardization management platform system and method | |
CN1894652B (en) | Automatic monitoring and statistical analysis of dynamic process metrics to expose meaningful changes | |
CN107330080B (en) | Data processing method and device and computer equipment applying same | |
CN106570569A (en) | Measuring and collecting work intelligent management system and measuring and collecting method thereof | |
CN105260841A (en) | Auditing system for power distribution network fault emergency repair receipt | |
CN105069178A (en) | Experimental data acquisition and analysis system and method | |
CN104104734A (en) | Log analysis method and device | |
CN105137215B (en) | Medical equipment cost-benefit wireless monitoring analysis system and medical equipment cost-benefit wireless monitoring analysis method | |
CN101996364A (en) | Method for modifying labor time standard and labor time standard management system | |
CN108171421A (en) | A kind of road surface O&M disposal efficiency and method for evaluating quality towards urban transportation smart machine system O&M | |
CN102650875A (en) | Inspection system, management server, inspection apparatus and method for managing inspection data | |
CN106484059A (en) | A kind of server radiating regulation and control method, apparatus and system | |
CN109522318A (en) | A kind of data quality management method and system | |
CN101840545A (en) | Integrated system and method for test detection, management and monitoring | |
CN112561289A (en) | Energy performance integrated verification method in energy management system authentication | |
CN104714429A (en) | Coal sample experiment data acquisition and analysis system and method | |
CN104281523A (en) | Demand testability analysis method and system | |
CN109032904A (en) | Monitored, management server and data acquisition, analysis method and management system | |
CN105427030B (en) | A kind of differentiation processing method of early warning information and system | |
CN103268329A (en) | Plasma display screen manufacturing process data mining system | |
CN206931114U (en) | A kind of architecture engineering material Stores Management System | |
CN106559262A (en) | A kind of area fault alarm method and system | |
CN110175196A (en) | A kind of bill of materials problem statistical method and device | |
CN109508966A (en) | A kind of archives of city construction business integrated management method Internet-based and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170419 |
|
RJ01 | Rejection of invention patent application after publication |