CN106567393A - Collapsible loess deep foundation pit support construction method - Google Patents

Collapsible loess deep foundation pit support construction method Download PDF

Info

Publication number
CN106567393A
CN106567393A CN201610971354.XA CN201610971354A CN106567393A CN 106567393 A CN106567393 A CN 106567393A CN 201610971354 A CN201610971354 A CN 201610971354A CN 106567393 A CN106567393 A CN 106567393A
Authority
CN
China
Prior art keywords
wall
soil
foundation pit
slope
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610971354.XA
Other languages
Chinese (zh)
Inventor
袁银书
王丽梅
王安鑫
张振禹
朱建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Civil Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201610971354.XA priority Critical patent/CN106567393A/en
Publication of CN106567393A publication Critical patent/CN106567393A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

The invention discloses a collapsible loess deep foundation pit support construction method. The method comprises the following steps: (1) a working well deep foundation pit is excavated to a first layer of depth in a layered manner under the geological conditions of collapsible loess and opaque loess; (2) an anchor rod engineering drilling machine is adopted to drill out multiple drilling holes on a slope wall of a first layer of foundation pit according to preset hole positions; (3) an air compressor is used for driving an impacter to drive a soil nail steel pipe in each drilling hole; (4) after concrete is primarily sprayed on the slope wall of the first layer of foundation pit, a reinforcement net is mounted; and the reinforcement net extends to the ground of the top of the foundation pit; (5) slurry is injected in pipe holes of the soil nail steel pipes through pressure; (6) a concrete surface layer is sprayed on the reinforcement net; (7) multiple horizontal drainage pipes are inserted in the slope wall of the first layer of foundation pit at intervals; and (8) the steps are repeated. The method forms soil and nail compound bodies to prominently improve the overall slope stability and the slope overload bearing capacity.

Description

A kind of collapsible loess deep foundation pit supporting construction method
Technical field
The present invention relates to a kind of pattern foundation pit supporting structure, more particularly to a kind of high installation accuracy deep foundation pit supporting construction of collapsible loess Method.
Background technology
Collapsible loess is distributed widely in China northeast, northwest, Central China and East China some areas.Collapsible loess is divided into again Self-weight collapsible and non-self centred graph, i.e., under the effect of upper overburden layer weight stress, or in weight stress and add Under stress collective effect, there is notable additional deformation because of the structural deterioration of soil after immersion and be referred to as settlement by soaking.Collapsible loess exists Under native state, with many macroscopic spaces, and the tubular space formed due to biological agent is often accompanied, it is natural to cut open Face is in vertical joint, with mobile and densification the ability of certain opposing.It in the dry state, because soil property has vertical direction The small pipeline of distribution, can almost keep vertical side slope.But after it receives water enchroachment (invasion) wet, the rapid disintegrate destruction of framing structure of soil is produced Serious differential settlement.
1st, the Chinese patent of Application No. CN201520056572.1 discloses " a kind of multilamellar soil nail wall deep foundation pit support ", Including body of wall and the soil body, ground floor soil nail wall is provided with the soil body, is arranged on the design work face of ground floor soil nail wall Soil nailing, the ground floor soil nail wall bottom is provided with platform, and the platform is arranged with second layer soil nail wall, in second layer soil nailing Soil nailing is set on the design work face of wall.The presence of platform changes the distribution of soil pressure after wall, changes local stress Strain regime, increases the coefficient of stability of the soil body;The soil body below platform is both slopes and the drag area of higher level's soil body, can be with Reduce the deformation of higher level's soil body;The track of soil body progressive failure after wall is changed, soil deformation is reduced to surrounding building Coverage.This patent disclosed that a kind of multilamellar soil nail wall deep foundation pit support, and be provided with platform.It is not suitable for settlement by soaking Canal in Loess Area, it is easily wrong during the installation process of soil nailing and slip casting for the geologic structure of the collapsible loess of given area Position.
2nd, the Chinese patent of Application No. CN201620058771.0 discloses " a kind of supporting construction for deep basal pit ", Including the soil body around deep basal pit, the side wall of the soil body is provided with from described to deep basal pit slanted floor Cheng Po in the soil body The slope protection pile that soil body top is vertically squeezed into downwards near the position of the side wall of the soil body, the side wall along the soil body is provided with soil nailing Wall bar-mat reinforcement, the side wall along the soil body is inserted with obliquely many soil nailings into the soil body, and the soil nailing stretches out the soil body Side wall part by fixture and the soil nail wall bar-mat reinforcement fixed strain, spray coagulation on the soil nail wall bar-mat reinforcement Soil forms concrete soil nail wall.Beneficial effect is simple structure, safety, economy, the applying for cobble rationally and suitable for foundation soil Work environment.This patent disclosed that a kind of is the construction environment of cobble suitable for foundation soil, and be provided with slope protection pile.It is uncomfortable For Collapsible Loess District, for the geologic structure of the collapsible loess of given area, the installation process of soil nailing and slip casting Easily misplace in journey.
3rd, the Chinese patent of Application No. CN201520916760.7 discloses a kind of " supporting knot for soft soil foundation pit Structure ", includes:Foundation ditch bottom, reinforced mesh, foundation ditch top and stress soil nailing, also include:Advanced soil nailing, reinforcement soil nailing, iron wire and add Strong reinforcing bar;Its reinforced mesh surface is injected with concrete layer, and reinforced mesh top is connected with foundation ditch top, bottom and foundation ditch bottom phase Even;In the embedded reinforced mesh of its advanced soil nailing vertical direction, in the oblique embedded reinforced mesh of stress soil nailing, reinforcement soil nailing level side To in embedded reinforced mesh, this patent disclosed that it is a kind of suitable for foundation soil for weak soil construction environment.Weak soil and settlement by soaking Loess geologic structure differs greatly.Collapsible Loess District is not suitable for, for the geology knot of the collapsible loess of given area Structure, easily misplaces during the installation process of soil nailing and slip casting.
The content of the invention
It is an object of the invention to overcome the deficiencies in the prior art, there is provided one kind significantly improves side slope stability in the large and holds The collapsible loess deep foundation pit supporting construction method of the ability overloaded by side slope.
A kind of collapsible loess deep foundation pit supporting construction method of the present invention, comprises the following steps:
(1) stage excavation is adopted to the active well deep basal pit under the conditions of collapsible loess, silty loess geology, is first excavated to First layer depth;
(2) multiple drillings are got out according to predetermined hole position on the slope wall of ground floor foundation ditch using anchor bolt works rig;
(3) impacter is driven to squeeze into a soil nailing steel pipe, described soil nailing in each drilling using air compressor Steel pipe includes body, and in each body a cone segments are fixedly arranged at the front end with, and is provided with the tube wall of described body multiple Slurry outlet in quincuncial arrangement, the diameter of described slurry outlet adopts 8~10mm, in the pipe near each pulp hole site A reinforcing bar is welded with along soil nailing steel pipe axis direction on the outer wall of body, the cuff welding on the outer wall of described body afterbody There are rectangular ribs, and multiple axis are welded with the outer wall of the body on front side of rectangular ribs and put down with body axis Capable locking muscle, multiple described locking muscle along body outer wall circumferencial direction uniformly at intervals, in the length side of described body Multiple locating supports are installed upwards, 120 degree are spaced simultaneously along pipe on body circumferencial direction between two adjacent locating supports The length direction of body is crisscross arranged, and described multiple locating supports adopt a few shape structures;
(4) bar-mat reinforcement is installed after first pneumatically placed concrete on the slope wall of ground floor foundation ditch, described bar-mat reinforcement extends to foundation ditch The ground at top, and stretch out the side slope 0.4~0.5m of line at the top of foundation ditch;
(5) to slip casing by pressure in the pore of soil nailing steel pipe, slip casting is divided into twice, and the interval of slip casting twice 24h, Stress control exists 0.5~2.0MPa, the fullness coefficient that slurry is injected into hole is more than 1;
(6) multiple pneumatically placed concrete surface layer is conserved to design thickness, then watering, covering and heat insulating on described bar-mat reinforcement;
(7) interval intubating length is 3~6m and diameter is not less than 50mm in the slope wall of described ground floor foundation ditch Stretch out concrete topping in multiple horizontal drain pipes, the outer end of described horizontal drain pipe;
(8) repeat the above steps (1)-(7), until layering completes active well deep pit digging.
The inventive method does not account for or accounts for less separate operaton time, efficiency of construction with excavation of foundation pit successively excavation section by section operation Height, takes cycle is short.The locating support of soil nailing steel pipe, it is ensured that centre of the steel pipe in drilling.Prop up the water at armour layer back Drainpipes discharge freely for flat raft, and the hydrops after gunite concrete surface layer are discharged in time, plays the self-stable function of the soil body, makes side slope Displacement and deformation obtain constrained.The locating support of soil nailing steel pipe, makes soil nail wall deform very little in itself, to adjacent buildings shadow Ring little.The ability for form soil nailing complex, significantly improving side slope stability in the large and bear side slope overload.This method is by intensive Soil nailing group, the soil body in situ, gunite concrete surface layer and the necessary waterproof system composition support system that are reinforced, it is common with the soil body With load is undertaken, play restrained deformation.And locating support ensures centre of the soil nailing steel pipe in drilling, support The free-flowing of serosity during construction without prejudice to slip casting.
Description of the drawings
Fig. 1 is the signal that a kind of soil nailing steel pipe of collapsible loess deep foundation pit supporting construction method of the present invention squeezes into the soil body Figure;
Fig. 2 is the structural representation of the partial cross section of the soil nailing steel pipe that Fig. 1 is adopted;
Fig. 3 is the side view of the structure shown in Fig. 2.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention is described in detail with specific embodiment.
The inventive method is applied under the conditions of the Northwest's collapsible loess, silty loess geology, deep foundation pit slope height The side slope protection engineering of no more than 15m.
As shown in drawings a kind of collapsible loess deep foundation pit supporting construction method of the present invention, comprises the following steps:
(1) stage excavation is adopted to the active well deep basal pit under the conditions of collapsible loess, silty loess geology, is first excavated to First layer depth;
(2) multiple drillings 6 are got out according to predetermined hole position on the slope wall of ground floor foundation ditch using anchor bolt works rig;
(3) impacter is driven to squeeze into a soil nailing steel pipe 1 in each drilling using air compressor.Described soil nailing Steel pipe 1 is improvement on an existing structure, and described soil nailing steel pipe 1 includes body, and in each body one is fixedly arranged at the front end with Individual cone segments, are provided with multiple slurry outlets 3 in quincuncial arrangement on the tube wall of described body, the diameter of described slurry outlet Using 8~10mm.One is welded with the outer wall near the body of each pulp hole site along the axis direction of soil nailing steel pipe 1 Root reinforcing bar 2, grogs blocking slurry outlet when preventing from breaking pipe.Cuff is welded with rectangular ribs on the outer wall of described body afterbody 7, and the locking muscle of multiple axis and body diameter parallel is welded with the outer wall of the body near the front side of rectangular ribs 7 8, multiple described locking muscle 8 along body outer wall circumferencial direction uniformly at intervals.Install on the length direction of described body There are multiple locating supports, 120 degree and along the length of body are spaced on body circumferencial direction between two adjacent locating supports Direction is crisscross arranged, and described multiple locating supports adopt a few shape structures 5, so can ensure that central part of the steel pipe in drilling Position.
Preferably being spaced staggeredly spacing of the two adjacent locating supports of 120 degree of settings on the length direction of body is 2~3m.Spatial skeleton can be so arranged in, formation can improve the compound soil body of in-situ soil intensity, rigidity and stability.
(4) bar-mat reinforcement 9 is installed after first pneumatically placed concrete on the slope wall of ground floor foundation ditch, described bar-mat reinforcement extends to foundation ditch The ground at top, and stretch out the side slope 0.4~0.5m of line at the top of foundation ditch.
(5) to slip casing by pressure in the pore of soil nailing steel pipe 1, slip casting is divided into twice, the interval of slip casting twice 24h, Stress control In 0.5~2.0MPa, the fullness coefficient that slurry is injected into hole is more than 1;
(6) multiple pneumatically placed concrete surface layer is conserved to design thickness, then watering, covering and heat insulating on described bar-mat reinforcement;
(7) interval intubating length is 3~6m and diameter is not less than 50mm in the slope wall of described ground floor foundation ditch Concrete topping is stretched out in multiple horizontal drain pipes, the outer end of described horizontal drain pipe, so as to by after gunite concrete surface layer Hydrops are discharged.Preferred multiple horizontal drainage tube pitch are 2~2.5m, so prevent loess from meeting the givey hidden danger of water electrode, and Soil layer bearing capacity is improved, foundation ditch safety and stability is protected.
(8) repeat the above steps (1)-(7), until layering completes active well deep pit digging.
Embodiment 1
(1) stage excavation is adopted to the active well deep basal pit under the conditions of collapsible loess, silty loess geology, is first excavated to First layer depth;
(2) multiple drillings 6 are got out according to predetermined hole position on the slope wall of ground floor foundation ditch using anchor bolt works rig;
(3) impacter is driven to squeeze into a soil nailing steel pipe 1 in each drilling using air compressor.Described soil nailing Steel pipe 1 is improvement on an existing structure, and described soil nailing steel pipe 1 includes body, and in each body one is fixedly arranged at the front end with Individual cone segments, are provided with multiple slurry outlets 3 in quincuncial arrangement on the tube wall of described body, the diameter of described slurry outlet Using 8mm.A steel is welded with the outer wall near the body of each pulp hole site along the axis direction of soil nailing steel pipe 1 Muscle 2, grogs blocking slurry outlet when preventing from breaking pipe.Cuff is welded with rectangular ribs 7 on the outer wall of described body afterbody, and And the locking muscle 8 of multiple axis and body diameter parallel is welded with the outer wall of the body near the front side of rectangular ribs 7, it is many Individual described locking muscle 8 along body outer wall circumferencial direction uniformly at intervals.It is provided with the length direction of described body many Individual locating support, is spaced on body circumferencial direction 120 degree and along the length direction of body between two adjacent locating supports It is crisscross arranged, described multiple locating supports adopt a few shape structures 5.Two adjacent locating supports of the 120 degree of settings in interval exist Staggeredly spacing on the length direction of body is 2m.
(4) bar-mat reinforcement 9 is installed after first pneumatically placed concrete on the slope wall of ground floor foundation ditch, described bar-mat reinforcement extends to foundation ditch The ground at top, and stretch out the side slope line 0.4m at the top of foundation ditch.
(5) to slip casing by pressure in the pore of soil nailing steel pipe 1, slip casting is divided into twice, the interval of slip casting twice 24h, Stress control In 1MPa, the fullness coefficient that slurry is injected into hole is more than 1;
(6) multiple pneumatically placed concrete surface layer is conserved to design thickness, then watering, covering and heat insulating on described bar-mat reinforcement;
(7) multiple levels that intubating length is 5m and a diameter of 52mm are spaced in the slope wall of described ground floor foundation ditch Concrete topping is stretched out in drain pipe, the outer end of described horizontal drain pipe, so that the hydrops after gunite concrete surface layer are discharged. Multiple horizontal drainage tube pitch are 2m.
(8) repeat the above steps (1)-(7), until layering completes active well deep pit digging.
After testing:120 degree of locating support is spaced on the soil nailing steel pipe installed in the soil body and body circumferencial direction, its row Arrange into spatial skeleton, it is ensured that centre of the steel pipe in drilling, and formed and can improve in-situ soil intensity, rigidity and stability The compound soil body, intensive soil nailing group, reinforcement, locking muscle, the soil body in situ being reinforced, gunite concrete surface layer and necessary anti- Water system constitutes support system, with soil body shared load, plays restrained deformation collapsible loess.Low cost, saves Economic benefit 1% or so.
Embodiment 2
(1) stage excavation is adopted to the active well deep basal pit under the conditions of collapsible loess, silty loess geology, is first excavated to First layer depth;
(2) multiple drillings 6 are got out according to predetermined hole position on the slope wall of ground floor foundation ditch using anchor bolt works rig;
(3) impacter is driven to squeeze into a soil nailing steel pipe 1 in each drilling using air compressor.Described soil nailing Steel pipe 1 is improvement on an existing structure, and described soil nailing steel pipe 1 includes body, and in each body one is fixedly arranged at the front end with Individual cone segments, are provided with multiple slurry outlets 3 in quincuncial arrangement on the tube wall of described body, the diameter of described slurry outlet Using 10mm.One is welded with the outer wall near the body of each pulp hole site along the axis direction of soil nailing steel pipe 1 Reinforcing bar 2, grogs blocking slurry outlet when preventing from breaking pipe.Cuff is welded with rectangular ribs 7 on the outer wall of described body afterbody, And the locking muscle 8 of multiple axis and body diameter parallel is welded with the outer wall of the body near the front side of rectangular ribs 7, Multiple described locking muscle 8 along body outer wall circumferencial direction uniformly at intervals.It is provided with the length direction of described body Multiple locating supports, are spaced on body circumferencial direction 120 degree and along the length side of body between two adjacent locating supports To being crisscross arranged, described multiple locating supports adopt a few shape structures 5.Two adjacent locating supports of the 120 degree of settings in interval Staggeredly spacing on the length direction of body is 2.5m.
(4) bar-mat reinforcement 9 is installed after first pneumatically placed concrete on the slope wall of ground floor foundation ditch, described bar-mat reinforcement extends to foundation ditch The ground at top, and stretch out the side slope line 0.5m at the top of foundation ditch.
(5) to slip casing by pressure in the pore of soil nailing steel pipe 1, slip casting is divided into twice, the interval of slip casting twice 24h, Stress control In 0.5MPa, the fullness coefficient that slurry is injected into hole is more than 1;
(6) multiple pneumatically placed concrete surface layer is conserved to design thickness, then watering, covering and heat insulating on described bar-mat reinforcement;
(7) multiple levels that intubating length is 3m and a diameter of 50mm are spaced in the slope wall of described ground floor foundation ditch Concrete topping is stretched out in drain pipe, the outer end of described horizontal drain pipe, so that the hydrops after gunite concrete surface layer are discharged. Multiple horizontal drainage tube pitch are 2.5m.
(8) repeat the above steps (1)-(7), until layering completes active well deep pit digging.
After testing:120 degree of locating support is spaced on the soil nailing steel pipe installed in the soil body and body circumferencial direction, its row Arrange into spatial skeleton, it is ensured that centre of the steel pipe in drilling, and formed and can improve in-situ soil intensity, rigidity and stability The compound soil body, is by intensive soil nailing group, reinforcement, the soil body in situ, gunite concrete surface layer and necessity for locking muscle, being reinforced Waterproof system composition support system, with soil body shared load, play restrained deformation collapsible loess.Low cost, Save economic benefit 1% or so.
Embodiment 3
(1) stage excavation is adopted to the active well deep basal pit under the conditions of collapsible loess, silty loess geology, is first excavated to First layer depth;
(2) multiple drillings 6 are got out according to predetermined hole position on the slope wall of ground floor foundation ditch using anchor bolt works rig;
(3) impacter is driven to squeeze into a soil nailing steel pipe 1 in each drilling using air compressor.Described soil nailing Steel pipe 1 is improvement on an existing structure, and described soil nailing steel pipe 1 includes body, and in each body one is fixedly arranged at the front end with Individual cone segments, are provided with multiple slurry outlets 3 in quincuncial arrangement on the tube wall of described body, the diameter of described slurry outlet Using 9mm.A steel is welded with the outer wall near the body of each pulp hole site along the axis direction of soil nailing steel pipe 1 Muscle 2, grogs blocking slurry outlet when preventing from breaking pipe.Cuff is welded with rectangular ribs 7 on the outer wall of described body afterbody, and And the locking muscle 8 of multiple axis and body diameter parallel is welded with the outer wall of the body near the front side of rectangular ribs 7, it is many Individual described locking muscle 8 along body outer wall circumferencial direction uniformly at intervals.It is provided with the length direction of described body many Individual locating support, is spaced on body circumferencial direction 120 degree and along the length direction of body between two adjacent locating supports It is crisscross arranged, described multiple locating supports adopt a few shape structures 5.Two adjacent locating supports of the 120 degree of settings in interval exist Staggeredly spacing on the length direction of body is 3m.
(4) bar-mat reinforcement 9 is installed after first pneumatically placed concrete on the slope wall of ground floor foundation ditch, described bar-mat reinforcement extends to foundation ditch The ground at top, and stretch out the side slope line 0.45m at the top of foundation ditch.
(5) to slip casing by pressure in the pore of soil nailing steel pipe 1, slip casting is divided into twice, the interval of slip casting twice 24h, Stress control In 2MPa, the fullness coefficient that slurry is injected into hole is more than 1;
(6) multiple pneumatically placed concrete surface layer is conserved to design thickness, then watering, covering and heat insulating on described bar-mat reinforcement;
(7) multiple levels that intubating length is 6m and a diameter of 50mm are spaced in the slope wall of described ground floor foundation ditch Concrete topping is stretched out in drain pipe, the outer end of described horizontal drain pipe, so that the hydrops after gunite concrete surface layer are discharged. Multiple horizontal drainage tube pitch are 2.3m.
(8) repeat the above steps (1)-(7), until layering completes active well deep pit digging.
After testing:120 degree of locating support is spaced on the soil nailing steel pipe installed in the soil body and body circumferencial direction, its row Arrange into spatial skeleton, it is ensured that centre of the steel pipe in drilling, and formed and can improve in-situ soil intensity, rigidity and stability The compound soil body, is by intensive soil nailing group, reinforcement, the soil body in situ, gunite concrete surface layer and necessity for locking muscle, being reinforced Waterproof system composition support system, with soil body shared load, play restrained deformation collapsible loess.Low cost, Save economic benefit 1% or so.

Claims (3)

1. a kind of collapsible loess deep foundation pit supporting construction method, it is characterised in that comprise the following steps:
(1) stage excavation is adopted to the active well deep basal pit under the conditions of collapsible loess, silty loess geology, is first excavated to first Layer depth;
(2) multiple drillings are got out according to predetermined hole position on the slope wall of ground floor foundation ditch using anchor bolt works rig;
(3) impacter is driven to squeeze into a soil nailing steel pipe, described soil nailing steel pipe in each drilling using air compressor Including body, a cone segments are fixedly arranged at the front end with each body, are provided with the tube wall of described body multiple in prunus mume (sieb.) sieb.et zucc. The slurry outlet of flower-shape arrangement, the diameter of described slurry outlet adopts 8~10mm, in the body near each pulp hole site A reinforcing bar is welded with along soil nailing steel pipe axis direction on outer wall, cuff is welded with square on the outer wall of described body afterbody Shape reinforcement, and multiple axis are welded with the outer wall of the body on front side of rectangular ribs with body diameter parallel Locking muscle, multiple described locking muscle along body outer wall circumferencial direction uniformly at intervals, on the length direction of described body Multiple locating supports are installed, 120 degree and along body are spaced on body circumferencial direction between two adjacent locating supports Length direction is crisscross arranged, and described multiple locating supports adopt a few shape structures;
(4) bar-mat reinforcement is installed on the slope wall of ground floor foundation ditch, described bar-mat reinforcement extends to foundation ditch top after first pneumatically placed concrete Ground, and stretch out the side slope 0.4~0.5m of line at the top of foundation ditch;
(5) to slip casing by pressure in the pore of soil nailing steel pipe, slip casting is divided into twice, the interval of slip casting twice 24h, and Stress control is 0.5 ~2.0MPa, the fullness coefficient that slurry is injected into hole is more than 1;
(6) multiple pneumatically placed concrete surface layer is conserved to design thickness, then watering, covering and heat insulating on described bar-mat reinforcement;
(7) interval intubating length is 3~6m and diameter is multiple not less than 50mm in the slope wall of described ground floor foundation ditch Stretch out concrete topping in horizontal drain pipe, the outer end of described horizontal drain pipe;
(8) repeat the above steps (1)-(7), until layering completes active well deep pit digging.
2. collapsible loess deep foundation pit supporting construction method according to claim 1, it is characterised in that:120 degree of interval sets Staggeredly spacing of the two adjacent locating supports put on the length direction of body is 2~3m.
3. the collapsible loess deep foundation pit supporting construction method according to claims 1 or 2, it is characterised in that:Described Multiple horizontal drainage tube pitch are 2~2.5m.
CN201610971354.XA 2016-11-04 2016-11-04 Collapsible loess deep foundation pit support construction method Pending CN106567393A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610971354.XA CN106567393A (en) 2016-11-04 2016-11-04 Collapsible loess deep foundation pit support construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610971354.XA CN106567393A (en) 2016-11-04 2016-11-04 Collapsible loess deep foundation pit support construction method

Publications (1)

Publication Number Publication Date
CN106567393A true CN106567393A (en) 2017-04-19

Family

ID=58541618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610971354.XA Pending CN106567393A (en) 2016-11-04 2016-11-04 Collapsible loess deep foundation pit support construction method

Country Status (1)

Country Link
CN (1) CN106567393A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459058A (en) * 2020-12-07 2021-03-09 中建八局第四建设有限公司 Echelon pressurizing grouting anchor rod and construction method thereof
CN113605402A (en) * 2021-07-26 2021-11-05 江苏银洲建设集团有限公司 Deep foundation pit support water stop system and construction method thereof
CN113718768A (en) * 2021-09-02 2021-11-30 王冲 Honeycomb soil nail soil body reinforcing accessory for improving slope stability
CN114059559A (en) * 2021-12-16 2022-02-18 陕西建工第十三建设有限公司 Collapsible loess area foundation pit excavation supporting structure and process thereof
CN114277830A (en) * 2022-01-21 2022-04-05 中国建筑第八工程局有限公司 Construction process of raft foundation of oversized equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1540107A (en) * 2003-04-26 2004-10-27 曾宪明 Operation method for supportins soft border by using earth slope nails
WO2006074145A1 (en) * 2005-01-03 2006-07-13 Geoject, Inc. Grout injecting/structure anchoring system
CN101748741A (en) * 2009-12-18 2010-06-23 中冶交通工程技术有限公司 Construction method of concrete supporting structure
CN102660948A (en) * 2012-05-30 2012-09-12 甘肃省建设投资(控股)集团总公司 Steel tube locked anchor rod construction method
CN203716146U (en) * 2013-12-11 2014-07-16 甘肃省建设投资(控股)集团总公司 Orientation steel pipe locking single prestress anchor rope

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1540107A (en) * 2003-04-26 2004-10-27 曾宪明 Operation method for supportins soft border by using earth slope nails
WO2006074145A1 (en) * 2005-01-03 2006-07-13 Geoject, Inc. Grout injecting/structure anchoring system
CN101748741A (en) * 2009-12-18 2010-06-23 中冶交通工程技术有限公司 Construction method of concrete supporting structure
CN102660948A (en) * 2012-05-30 2012-09-12 甘肃省建设投资(控股)集团总公司 Steel tube locked anchor rod construction method
CN203716146U (en) * 2013-12-11 2014-07-16 甘肃省建设投资(控股)集团总公司 Orientation steel pipe locking single prestress anchor rope

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
韩建刚主编: "《土力学与基础工程》", 31 August 2014 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459058A (en) * 2020-12-07 2021-03-09 中建八局第四建设有限公司 Echelon pressurizing grouting anchor rod and construction method thereof
CN113605402A (en) * 2021-07-26 2021-11-05 江苏银洲建设集团有限公司 Deep foundation pit support water stop system and construction method thereof
CN113605402B (en) * 2021-07-26 2023-02-21 江苏银洲建设集团有限公司 Deep foundation pit support water stop system and construction method thereof
CN113718768A (en) * 2021-09-02 2021-11-30 王冲 Honeycomb soil nail soil body reinforcing accessory for improving slope stability
CN114059559A (en) * 2021-12-16 2022-02-18 陕西建工第十三建设有限公司 Collapsible loess area foundation pit excavation supporting structure and process thereof
CN114277830A (en) * 2022-01-21 2022-04-05 中国建筑第八工程局有限公司 Construction process of raft foundation of oversized equipment

Similar Documents

Publication Publication Date Title
CN106567393A (en) Collapsible loess deep foundation pit support construction method
CN105089061B (en) Ultra-deep foundation pit supporting method
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN105672240B (en) Inclining destruction type Dangerous Rock Body administering method
CN108035361A (en) A kind of advanced support supporting construction and its construction method
CN104818711A (en) Anti-liquefaction three-dimensional drainage rigid pile and construction method thereof
CN106759376A (en) Anchored Sheet Pile Wall for Excavation system and its construction method for closing on existing underground structure
CN102330436B (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN204825928U (en) Excavation supporting
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN204780990U (en) Combined type retaining wall structure
CN112854260B (en) Ecological concrete rock-soil slope protection structure and construction method
CN102220764B (en) Construction method of deep foundation pit bracing system
CN201077988Y (en) Hidden beam-column type prestressing force earth nail wall
CN204898684U (en) Super dark excavation supporting system
CN215629929U (en) Novel site operation structure of anti-floating anchor rod
CN103711123B (en) The construction method of bamboo joint type mortar pile
CN205934947U (en) Dark foundation pit dewatering tubular well structure
CN206337564U (en) A kind of soil nailing steel pipe support device
CN209923935U (en) Co-location combined pile wall supporting structure in upper-soft and lower-hard stratum
CN110258584B (en) Foundation pit side slope soil nailing pipe wall enclosure structure and construction method
CN114032928A (en) Soil nailing wall construction method for pre-reinforcing slope rock-soil mass
CN207700198U (en) A kind of advanced support supporting construction
CN202298627U (en) Foundation pit supporting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170419