CN106555599A - 浅埋暗挖法隧道超前小导管施工方法 - Google Patents
浅埋暗挖法隧道超前小导管施工方法 Download PDFInfo
- Publication number
- CN106555599A CN106555599A CN201611043959.9A CN201611043959A CN106555599A CN 106555599 A CN106555599 A CN 106555599A CN 201611043959 A CN201611043959 A CN 201611043959A CN 106555599 A CN106555599 A CN 106555599A
- Authority
- CN
- China
- Prior art keywords
- ductule
- sleeve pipe
- advanced tubule
- arch
- bow member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 36
- 210000005239 tubule Anatomy 0.000 title claims abstract description 25
- 238000009933 burial Methods 0.000 title claims abstract description 14
- 239000004567 concrete Substances 0.000 claims abstract description 21
- 238000009412 basement excavation Methods 0.000 claims abstract description 10
- 239000011378 shotcrete Substances 0.000 claims abstract description 10
- 238000007789 sealing Methods 0.000 claims abstract description 4
- 238000005507 spraying Methods 0.000 claims abstract description 3
- 230000035945 sensitivity Effects 0.000 claims description 6
- 238000007569 slipcasting Methods 0.000 claims description 3
- 239000002689 soil Substances 0.000 abstract description 9
- 238000000034 method Methods 0.000 abstract description 8
- 238000010586 diagram Methods 0.000 description 4
- 239000011435 rock Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明涉及一种浅埋暗挖法隧道超前小导管施工方法,其步骤为:(1)隧道拱部开挖完成后首先在拱顶临空面喷射薄层早强混凝土约束层;(2)拱顶初喷混凝土完成后架设拱架,同时在拱部按设计小导管环距及打设角度预留套管,套管内径略大于小导管外径,并与拱架绑扎固定,两端做好封口措施;(3)拱架与套管安装完毕后进行拱部初支喷射混凝土施工,同时对掌子面喷射薄层早强混凝土约束层;(4)在喷射混凝土形成强度,下榀土方开挖之前,通过预留的套管打设小导管。本发明通过增加辅助措施,将小导管调整至初支混凝土封闭后打设,加快了初支封闭速度,保证了小导管的打设精度,同时极大减轻了在小导管打设过程中拱顶与开挖面土体受扰掉块或滑落情况。
Description
技术领域
本发明涉及一种浅埋暗挖法隧道超前小导管施工方法,尤其是一咱适用于高灵敏度松散地层浅埋暗挖法隧道的施工。
背景技术
超前小导管是浅埋暗挖隧道初支施工阶段的一种辅助施工措施,传统做法为:隧道拱部土方开挖完成后架设拱架,而后沿拱顶环向打设小导管,小导管尾部与拱架焊接,而后进行初支混凝土喷射施工,形成以拱架为基础,悬臂作用的超前支护措施。
传统小导管打设工艺,先打设小导管后进行初支喷射混凝土施工,特别是在松散地层中,会延长初支封闭时间而增大开挖面的失稳风险。另外,小导管常采用气压式凿岩机振动顶插工艺,对土层的扰动较大,特别是在高灵敏度松散地层中,采用传统小导管打设工艺,会导致拱顶与掌子面土层受扰发生局部掉块或滑落情况,轻则造成界面超挖增加施工成本,重则会导致拱顶或掌子面失稳坍塌,因此,在高灵敏度松散地层施工浅埋暗挖法隧道,需对超前小导管传统打设技术构建辅助措施进行工序调整与优化。
发明内容
本发明提供一种浅埋暗挖法隧道超前小导管施工方法,适用于高灵敏度松散地层施工浅埋暗挖法隧道,采用超前小导管传统施工方法时打设精度差、打设过程中临空面局部土体掉块或滑落等工况。
本发明的技术方案是:一种浅埋暗挖法隧道超前小导管的施工方法,用于高灵敏度松散地层,其步骤为:
1.隧道拱部开挖完成后首先在拱顶临空面喷射薄层早强混凝土约束层;
2、拱顶混凝土约束层完成后架设拱架,同时在拱部按设计超前小导管环距及打设角度预留套管,且套管内径大于超前小导管外径,并与拱架绑扎固定,两端做好封口措施;
3、拱架与套管安装完毕后进行拱部初支喷射混凝土施工,同时对掌子面喷射薄层早强混凝土约束层;
4、在喷射混凝土形成强度,下榀土方开挖之前,通过预留的套管打设超前小导管。注浆前,在小导管尾端安装止浆塞,防止浆液沿超前小导管与套管间空隙外溢。
本发明的有益效果是:
1、通过在拱架安装时预留套管,将小导管调整至初支混凝土封闭后打设,加快了初支封闭速度,同时预留套管对小导管打设起定位导向作用,保证了小导管环距、角度等打设精度。
2、小导管打设前,通过对开挖临空面土体增设薄层喷砼工序形成约束措施,极大减轻了在小导管打设过程中临空面土体受扰掉块或滑落情况。
在高灵敏度松散地层施工浅埋暗挖法隧道,本发明较传统小导管打设工艺,加快了初支封闭速度,保证了小导管的打设精度,极大减轻了在小导管打设过程中拱顶与开挖面土体受扰掉块或滑落情况,便于施工成本与施工风险的控制。
附图说明
图1为本发明的施工方法中的第一步骤示意图;
图2为本发明的施工方法中的第二步骤示意图;
图3为本发明的施工方法中的第三步骤示意图;
图4为本发明的施工方法中的第四步骤示意图。
具体实施方式
下面结合附图与实施例对本发明作进一步说明。
如图1至图4所示,本发明的浅埋暗挖法隧道超前小导管施工方法,用于高灵敏度松散地层,其步骤如下:
(1)隧道拱部开挖完成后首先在拱顶1临空面喷射薄层早强混凝土约束层2(3cm-5cm厚),见图1。
(2)拱顶混凝土约束层2完成后架设拱架4,同时在拱部按设计超前小导管3环距及打设角度预留套管5(可选用PVC材质)。套管5内径略大于超前小导管3外径。套管5与拱架绑扎固定,两端做好封口措施,见图2。
(3)拱架4与套管3安装完毕后进行拱部初支喷射混凝土6施工,同时对掌子面喷射薄层早强混凝土约束层7(3cm-5cm厚),见图3。
(4)在喷射混凝土形成强度,下榀土方开挖之前,通过预留的套管5打设超前小导管3,见图4。注浆前,在超前小导管3尾端安装止浆塞,防止浆液沿超前小导管3与套管5间空隙外溢。
本发明应用实施实例:
乌鲁木市轨道交通一号线工程三工站—宣仁墩站区间采取浅埋暗挖法施工,拱部120°打设φ25钢管(t=3mm,L=3m)作为超前支护措施,小导管环距0.35m,纵距1.5m(隔榀打设),外插角11°~17°。暗挖隧道施工地层为砂卵石地层,其结构松散,对施工扰动反应灵敏,是一种典型的力学结构不稳定地层。施工之初,采取传统小导管打设工艺,因地层卵石所占比例大,小导管打设精度极难控制,另一方面,因地层对施工扰动反应灵敏,在小导管采用气压式凿岩机振动斜向上顶插施工过程中,时常发生拱顶或开挖面土体掉块或滑落情况,增大了施工成本与施工风险。
采取本发明后,加快了初支封闭速度,保证了小导管的打设精度,极大减轻了在小导管打设过程中拱顶与开挖面土体受扰掉块或滑落情况,节约了施工成本,降低了施工风险,为工程带来良好的益处。
Claims (2)
1.一种浅埋暗挖法隧道超前小导管施工方法,用于高灵敏度松散地层,其步骤为:
1)隧道拱部开挖完成后首先在拱顶(1)临空面喷射薄层早强混凝土约束层(2);
2)拱顶混凝土约束层(2)完成后架设拱架(4),同时在拱部按设计超前小导管(3)环距及打设角度预留套管(5),套管(5)内径大于超前小导管(3)外径,并与拱架(4)绑扎固定,两端做好封口措施;
3)拱架(4)与套管(5)安装完毕后进行拱部初支喷射混凝土(6)施工,同时对掌子面喷射薄层早强混凝土约束层(7);
4)在喷射混凝土形成强度,下榀土方开挖之前,通过预留的套管(5)打设超前小导管(3)。
2.根据权利要求1所述的浅埋暗挖法隧道超前小导管施工方法,其特征在于:注浆前,在超前小导管(3)尾端安装止浆塞,防止浆液沿超前小导管(3)与套管(5)间空隙外溢。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611043959.9A CN106555599A (zh) | 2016-11-24 | 2016-11-24 | 浅埋暗挖法隧道超前小导管施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611043959.9A CN106555599A (zh) | 2016-11-24 | 2016-11-24 | 浅埋暗挖法隧道超前小导管施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106555599A true CN106555599A (zh) | 2017-04-05 |
Family
ID=58444437
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611043959.9A Pending CN106555599A (zh) | 2016-11-24 | 2016-11-24 | 浅埋暗挖法隧道超前小导管施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106555599A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109139048A (zh) * | 2018-09-04 | 2019-01-04 | 中铁十二局集团有限公司 | 一种超前小导管注浆结构及其施工方法 |
CN111648823A (zh) * | 2020-05-22 | 2020-09-11 | 中交二航局第二工程有限公司 | 适用于断层破碎带隧道的坍塌处理方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101614125A (zh) * | 2009-07-23 | 2009-12-30 | 中铁九局集团有限公司 | V级围岩隧道施工方法 |
CN102305091A (zh) * | 2011-08-25 | 2012-01-04 | 中铁十六局集团有限公司 | 一种硬岩大断面隧道施工的支撑结构及其施工方法 |
CN103410528A (zh) * | 2013-08-29 | 2013-11-27 | 中南大学 | 一种隧道衬砌结构及施工方法 |
CN104453946A (zh) * | 2014-11-19 | 2015-03-25 | 北京首尔工程技术有限公司 | 一种软弱围岩隧道修建的超前加固施工方法 |
CN104989410A (zh) * | 2015-07-13 | 2015-10-21 | 中铁十九局集团第二工程有限公司 | 浅埋暗挖隧道地表限沉防塌施工方法 |
-
2016
- 2016-11-24 CN CN201611043959.9A patent/CN106555599A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101614125A (zh) * | 2009-07-23 | 2009-12-30 | 中铁九局集团有限公司 | V级围岩隧道施工方法 |
CN102305091A (zh) * | 2011-08-25 | 2012-01-04 | 中铁十六局集团有限公司 | 一种硬岩大断面隧道施工的支撑结构及其施工方法 |
CN103410528A (zh) * | 2013-08-29 | 2013-11-27 | 中南大学 | 一种隧道衬砌结构及施工方法 |
CN104453946A (zh) * | 2014-11-19 | 2015-03-25 | 北京首尔工程技术有限公司 | 一种软弱围岩隧道修建的超前加固施工方法 |
CN104989410A (zh) * | 2015-07-13 | 2015-10-21 | 中铁十九局集团第二工程有限公司 | 浅埋暗挖隧道地表限沉防塌施工方法 |
Non-Patent Citations (2)
Title |
---|
周鑫元等: "九景高速公路隧道工程的质量监控", 《公路》 * |
李光耀: "小导管注浆在富水大粒径砂卵石地层中的应用", 《山西建筑》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109139048A (zh) * | 2018-09-04 | 2019-01-04 | 中铁十二局集团有限公司 | 一种超前小导管注浆结构及其施工方法 |
CN109139048B (zh) * | 2018-09-04 | 2020-05-15 | 中铁十二局集团有限公司 | 一种超前小导管注浆结构及其施工方法 |
CN111648823A (zh) * | 2020-05-22 | 2020-09-11 | 中交二航局第二工程有限公司 | 适用于断层破碎带隧道的坍塌处理方法 |
CN111648823B (zh) * | 2020-05-22 | 2021-08-03 | 中交二航局第二工程有限公司 | 适用于断层破碎带隧道的坍塌处理方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102493822B (zh) | 一种通过富水断层影响带的隧道的帷幕注浆施工方法 | |
CN102287195B (zh) | 浅埋暗挖大跨度隧道下穿既有高速铁路施工方法 | |
CN107218045B (zh) | 岩质地层暗挖地铁车站出入口暗挖段的快速施工方法 | |
CN103993892A (zh) | 一种用于软弱破碎不均匀地层隧道施工的支护方法 | |
CN102155234B (zh) | 非对称的小间距隧道开挖施工方法 | |
CN103835729A (zh) | 深部长距离巷道围岩地面预注浆加固工艺 | |
CN101701646B (zh) | 地下管道的泥水平衡式拉管施工方法 | |
CN103016027B (zh) | 一种软弱、破碎复杂地质条件下隧道或巷道掘进方法 | |
CN104389618A (zh) | 一种连拱隧道洞身无室大管棚支护施工方法 | |
CN105298499A (zh) | 一种深竖井反井钻机开挖偏移处理方法 | |
CN105041322A (zh) | 顶管机进出洞的加固方法及加固系统 | |
WO2010058933A3 (ko) | 터널굴착공법 | |
CN203847129U (zh) | 一种用于软弱破碎不均匀地层隧道施工的支护装置 | |
CN102678126A (zh) | 山岭隧道软弱围岩破碎带或浅埋偏压地段的开挖方法 | |
CN106837411B (zh) | 一种深埋盾构隧道充填注浆的布置结构及方法 | |
CN208965598U (zh) | 灌浆帷幕与地下洞室相交部位的防渗处理结构 | |
CN105041327B (zh) | 暗挖隧道反挖盾构接收方法 | |
CN107575237A (zh) | 一种暗挖法与盾构法相结合建造地铁车站的施工方法 | |
CN102733390B (zh) | 一种地下废弃锚索/锚杆的拆除方法 | |
CN105909262B (zh) | 一种暗挖隧道掘进方法 | |
CN106555599A (zh) | 浅埋暗挖法隧道超前小导管施工方法 | |
CN108915702B (zh) | 一种圆形小断面隧道内盾构接收方法 | |
CN103216265B (zh) | 一种高应力巷道围岩变形控制方法 | |
CN101358529A (zh) | 短导管及短导管固砂剂加固施工工艺 | |
CN211115996U (zh) | 上软下硬地层盾构法与矿山法交界处隧道段洞内加固结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170405 |
|