CN106555399A - A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method - Google Patents
A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method Download PDFInfo
- Publication number
- CN106555399A CN106555399A CN201710058536.2A CN201710058536A CN106555399A CN 106555399 A CN106555399 A CN 106555399A CN 201710058536 A CN201710058536 A CN 201710058536A CN 106555399 A CN106555399 A CN 106555399A
- Authority
- CN
- China
- Prior art keywords
- anchor rod
- slip casting
- steel pipe
- carbonate rock
- rock area
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/10—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
- E02D31/12—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method, including steel pipe and anti-float anchor rod, fix and extend in injected hole side by side by colligation with steel pipe for anti-float anchor rod, and steel pipe extend in injected hole and is provided with sieve aperture on one section.The present invention is tied up in fixed implantation bolt grouting hole by the steel pipe with sieve aperture and Pulling-Resistant Anchor Rod, draining pressure release is carried out by sieve aperture during slip casting, effectively reduce grouting pressure, reduce slip casting difficulty, slip casting is faster, especially secondary grouting effect more preferably, efficiently solves the problems, such as carbonate rock area as hydraulic pressure is high, anti-float anchor rod grouting difficulty, the present invention also have simple structure, low cost, it is easy to operate the characteristics of.
Description
Technical field
The present invention relates to a kind of Pulling-Resistant Anchor Rod slip casting drainage arrangement of carbonate rock area in the case of having artesian head and
Its construction method, belongs to bolt grouting technical field.
Background technology
In recent years, with the large-scale development of the underground space, increasing problem along with underground engineering development and
Produce, wherein underground structure is because the example that water buoyancy is damaged is no lack of minority.Some engineerings in work progress, due to which
The top number of plies is few, and dead load is often insufficiently resistant to the buoyancy of underground water generation, occurs in that basement bottom board is large-area and opens
Split, heave;The underground structure of some engineerings integrally floats, and causes serious economic loss.Therefore, anti-floating problem one
It is directly the problem of project planner's attention.
For the Anti-floating design of basement bottom board, in engineering, common method for designing has ballast method (as increased base plate thickness
Or overlying soil thickness) anti-floating, uplift pile anti-floating, anti-float anchor rod anti-floating etc..When arranging anti-float anchor rod, anchor pole is by high pressure injection
Slurry is fixed in basic following ground, is anchored in basis, and the withdrawal resistance under water buoyancy effect is provided to basement, anti-with other
Floating measure is compared, fast because having the advantages that low cost, the strong adaptability to site soil layers, speed of application, anti-in basement at present
It is widely used in float meter.However, in carbonate rock area, due to special karst landform, underground storage is big
The underground water of amount, level of ground water are higher so that as hydraulic pressure is big when anti-float anchor rod slip casting is anchored, and slurries are not yet able to do in time solidification just
Lifted by water pressure, it is final to increase the successful difficulty of slip casting, even result in slip casting failure.
The content of the invention
The technical problem to be solved in the present invention is:There is provided a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its
Construction method, solves the problems, such as carbonate rock area as hydraulic pressure is high, anti-float anchor rod grouting difficulty.
The technical scheme that the present invention takes is:A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement, including steel pipe
With anti-float anchor rod, fix and extend in injected hole side by side by colligation with steel pipe for anti-float anchor rod, and steel pipe is extend into one section in injected hole
On be provided with sieve aperture.
Preferably, above-mentioned outer diameter of steel pipes is 20-40 millimeters.
Preferably, above-mentioned sieve aperture spreads all over and stretches into one section of steel pipe pipe shaft of injected hole, screen-aperture 8-10 millimeters.
Preferably, above-mentioned sieve aperture is 300-600 millimeters along length of steel pipe direction pitch of holes.
Preferably, interlaced arrangement between above-mentioned sieve aperture tandem.
A kind of construction method of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement, the method are comprised the following steps:
Step one, after artesian water water level in foundation ditch is evacuated to below the bottom of hole, surveying and locating positions the position of injected hole, and performs
Mark;
Step 2, is drilled to injected hole mark downward vertically using rig, is drilled into specified drilling depth;
Step 3, the good steel pipe of colligation side by side and anti-float anchor rod are put in injected hole;
Step 4, carries out high-pressure slip-casting to drilling.
Beneficial effects of the present invention:Compared with prior art, the present invention is tied up by the steel pipe with sieve aperture and Pulling-Resistant Anchor Rod
In fixed implantation bolt grouting hole, draining pressure release is carried out by sieve aperture during slip casting, grouting pressure is effectively reduced, slip casting is reduced difficult
Degree, faster, especially secondary grouting effect more preferably, efficiently solves carbonate rock area as hydraulic pressure is high, anti-float anchor rod for slip casting
The problem of grouting difficulty, the present invention also have simple structure, low cost, it is easy to operate the characteristics of.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the overlooking the structure diagram of Fig. 1;
Fig. 3 is the steel-tube construction schematic diagram of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment is described further to the present invention.
Embodiment 1:As shown in Figure 1-Figure 3, a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement, including steel pipe 1
With anti-float anchor rod 2, fix and extend in injected hole 4 side by side by steel wire by colligation with steel pipe 1 for anti-float anchor rod 2, and steel pipe 1 extend into
Sieve aperture 3 is provided with 4 interior one sections of injected hole.
Preferably, 1 external diameter of above-mentioned steel pipe be 20-40 millimeters, 2 a diameter of 28 millimeters of anti-float anchor rod, disclosure satisfy that pressure release will
Ask.
Preferably, above-mentioned sieve aperture 3 spreads all over and stretches into 4 one sections of 1 pipe shafts of steel pipe of injected hole, 3 aperture 8-10 millimeters of sieve aperture, Neng Gouman
Sufficient pressure release requires, and avoids grouting serous fluid that the problem that pressure release effect becomes is caused by sieve aperture.
Preferably, above-mentioned sieve aperture 3 is 300-600 millimeters along 1 length direction pitch of holes of steel pipe, disclosure satisfy that pressure release requirement.
Preferably, interlaced arrangement between 3 tandem of above-mentioned sieve aperture, pressure release effect are more preferable.
Embodiment 2:A kind of construction method of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement, the method includes following
Step:
Step one, after artesian water water level 6 in foundation ditch is evacuated to below the bottom of hole, surveying and locating positions the position of injected hole 4, and makees
It is good to mark;
Step 2, is drilled to 4 mark of injected hole downward vertically using rig, is drilled into designated depth, and aperture is
130mm;
Anti-float anchor rod 2 of 1 pipe of steel of the 25mm side by side of steel wire bundle with a diameter of 28 millimeters is put into injected hole 4 by step 3
It is interior;
Step 4, carries out high-pressure slip-casting to injected hole 4, after the completion of slip casting, does not extract steel pipe, be allowed to together with anti-float anchor rod into
Anchor, resists withdrawal resistance jointly.
The above, the only specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, any
Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained
Cover within protection scope of the present invention, therefore, protection scope of the present invention should be defined by the scope of the claims.
Claims (6)
1. a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement, it is characterised in that:Including steel pipe(1)With anti-float anchor rod
(2), anti-float anchor rod(2)With steel pipe(1)Colligation side by side is fixed and extend into injected hole(4)It is interior, steel pipe(1)It extend into injected hole
(4)Sieve aperture is provided with interior one section(3).
2. a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement according to claim 1, it is characterised in that:Steel pipe
(1)External diameter is 20-40 millimeters.
3. a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement according to claim 2, it is characterised in that:Sieve aperture
(3)Spread all over and stretch into one section of steel pipe of injected hole(1)Pipe shaft, sieve aperture(3)Aperture 8-10 millimeters.
4. a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement according to claim 1, it is characterised in that:Sieve aperture
(3)Along steel pipe(1)Length direction pitch of holes is 300-600 millimeters.
5. a kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement according to claim 1, it is characterised in that:Sieve aperture
(3)Interlaced arrangement between tandem.
6. the construction party according to a kind of arbitrary described carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement of claim 1-5
Method, it is characterised in that:The method is comprised the following steps:
Step one, after artesian water water level in foundation ditch is evacuated to below the bottom of hole, surveying and locating positions the position of injected hole, and performs
Mark;
Step 2, is drilled to injected hole mark downward vertically using rig, is drilled into specified drilling depth;
Step 3, the good steel pipe of colligation side by side and anti-float anchor rod are put in injected hole;
Step 4, carries out high-pressure slip-casting to drilling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710058536.2A CN106555399A (en) | 2017-01-23 | 2017-01-23 | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710058536.2A CN106555399A (en) | 2017-01-23 | 2017-01-23 | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106555399A true CN106555399A (en) | 2017-04-05 |
Family
ID=58446434
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710058536.2A Pending CN106555399A (en) | 2017-01-23 | 2017-01-23 | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106555399A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106930294A (en) * | 2017-04-26 | 2017-07-07 | 辽宁有色基础工程公司 | A kind of bedrock fracture artesian area grouting method |
CN113445471A (en) * | 2021-06-10 | 2021-09-28 | 中国水利水电第九工程局有限公司 | Dam abutment waterproof curtain consolidation grouting construction process |
CN114718643A (en) * | 2022-05-10 | 2022-07-08 | 山东科技大学 | Water diversion method for rock burst mine construction anchor cable grouting hole |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2006074145A1 (en) * | 2005-01-03 | 2006-07-13 | Geoject, Inc. | Grout injecting/structure anchoring system |
CN201050062Y (en) * | 2007-06-26 | 2008-04-23 | 北京建工一建工程建设有限公司 | Sand bed soil reinforcing piece |
CN201132957Y (en) * | 2007-12-05 | 2008-10-15 | 中国水电顾问集团中南勘测设计研究院 | Roof bolt |
CN102660948A (en) * | 2012-05-30 | 2012-09-12 | 甘肃省建设投资(控股)集团总公司 | Steel tube locked anchor rod construction method |
CN104805837A (en) * | 2014-01-24 | 2015-07-29 | 河南理工大学 | Tube seam grouting combined anchor rod body |
CN206448270U (en) * | 2017-01-23 | 2017-08-29 | 贵州正业工程技术投资有限公司 | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement |
-
2017
- 2017-01-23 CN CN201710058536.2A patent/CN106555399A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2006074145A1 (en) * | 2005-01-03 | 2006-07-13 | Geoject, Inc. | Grout injecting/structure anchoring system |
CN201050062Y (en) * | 2007-06-26 | 2008-04-23 | 北京建工一建工程建设有限公司 | Sand bed soil reinforcing piece |
CN201132957Y (en) * | 2007-12-05 | 2008-10-15 | 中国水电顾问集团中南勘测设计研究院 | Roof bolt |
CN102660948A (en) * | 2012-05-30 | 2012-09-12 | 甘肃省建设投资(控股)集团总公司 | Steel tube locked anchor rod construction method |
CN104805837A (en) * | 2014-01-24 | 2015-07-29 | 河南理工大学 | Tube seam grouting combined anchor rod body |
CN206448270U (en) * | 2017-01-23 | 2017-08-29 | 贵州正业工程技术投资有限公司 | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106930294A (en) * | 2017-04-26 | 2017-07-07 | 辽宁有色基础工程公司 | A kind of bedrock fracture artesian area grouting method |
CN113445471A (en) * | 2021-06-10 | 2021-09-28 | 中国水利水电第九工程局有限公司 | Dam abutment waterproof curtain consolidation grouting construction process |
CN114718643A (en) * | 2022-05-10 | 2022-07-08 | 山东科技大学 | Water diversion method for rock burst mine construction anchor cable grouting hole |
CN114718643B (en) * | 2022-05-10 | 2022-11-04 | 山东科技大学 | Water diversion method for rock burst mine construction anchor cable grouting hole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111827274B (en) | High-strength grouting method for marine wind power weakly-weathered bedrock single-pile socketed foundation | |
CN101545462B (en) | A steel-concrete combined weight type offshore wind fan foundation structure | |
CN204370469U (en) | A kind of drilled pile long leg jacket offshore wind turbine foundation | |
CN104389318B (en) | Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof | |
CN202039382U (en) | Ribbing seabed suction anchor | |
CN103510528A (en) | Blind trench water discharging structure used for underground structure up-floating prevention | |
CN104805854A (en) | Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment | |
CN201713812U (en) | Underwater drilling pile foundation protective cylinder | |
CN101539118B (en) | Passive antiscour base of basic structure of gravity-type offshore wind turbine | |
CN105780806A (en) | Offshore wind turbine foundation for long-leg jacket of drilling piles and construction method of offshore wind turbine foundation | |
CN102296629B (en) | Tower-drum structure suitable for ocean engineering and installation method thereof | |
CN106555399A (en) | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement and its construction method | |
CN105862906A (en) | Offshore wind power plant draught fan single pile foundation and construction method | |
CN101701459B (en) | Method for processing soft soil foundation of intertidal belt to form construction working face | |
CN103572770B (en) | A kind of stake case hydraulic structures and construction method thereof | |
CN105569062A (en) | Dewatering method implemented through permeation, weakening and emission reduction | |
CN206448270U (en) | A kind of carbonate rock area Pulling-Resistant Anchor Rod slip casting drainage arrangement | |
CN206052761U (en) | A kind of marine wind electric field single-pile foundation | |
CN201502065U (en) | Anchor rod joint excavation compound basis | |
CN204282390U (en) | For the steel concrete-steel structure mixing gravity type foundation of offshore wind farm | |
CN203977417U (en) | Ribs built-in steel casing for a kind of pile of deep water pile foundation | |
CN206015511U (en) | One implant post steel pipe column | |
CN102146669B (en) | Movable/fixed man-made island cylindrical foundation | |
CN210636421U (en) | Underwater hollowing defect repairing device for navigation wall pile foundation of ship lock on gravel layer foundation | |
CN204435321U (en) | A kind of steam power station water intaking open channel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170405 |