CN106548290A - A kind of urban area development decision-making supports system and method - Google Patents
A kind of urban area development decision-making supports system and method Download PDFInfo
- Publication number
- CN106548290A CN106548290A CN201610979648.7A CN201610979648A CN106548290A CN 106548290 A CN106548290 A CN 106548290A CN 201610979648 A CN201610979648 A CN 201610979648A CN 106548290 A CN106548290 A CN 106548290A
- Authority
- CN
- China
- Prior art keywords
- data
- programme
- gis
- urban area
- decision
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000011161 development Methods 0.000 title claims abstract description 61
- 238000000034 method Methods 0.000 title claims abstract description 44
- 230000008569 process Effects 0.000 claims abstract description 22
- 230000000712 assembly Effects 0.000 claims abstract description 7
- 238000000429 assembly Methods 0.000 claims abstract description 7
- 230000005540 biological transmission Effects 0.000 claims abstract description 4
- 239000002689 soil Substances 0.000 claims description 16
- 238000010276 construction Methods 0.000 claims description 10
- 238000009432 framing Methods 0.000 claims description 5
- 238000004321 preservation Methods 0.000 claims description 5
- 206010016256 fatigue Diseases 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 14
- 238000013461 design Methods 0.000 description 7
- 238000012986 modification Methods 0.000 description 6
- 230000004048 modification Effects 0.000 description 6
- 239000000203 mixture Substances 0.000 description 4
- 230000008859 change Effects 0.000 description 3
- 238000009472 formulation Methods 0.000 description 3
- 238000004364 calculation method Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000008676 import Effects 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 238000010835 comparative analysis Methods 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000009795 derivation Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000032696 parturition Effects 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Educational Administration (AREA)
- General Business, Economics & Management (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of urban area development decision-making supports system and method, including:Transmission module in basic data, for uploading GIS data and item base data;GIS process assembly modules, for setting up programme according to basic data and while generating with reference to figure;For the GIS assignment of GIS data in revised planning scheme, while programme and being adjusted according to the adjustment of GIS assignment correspondence with reference to figure;For preserving programme;Finance measuring and calculating module, for configuring relation and financial measure formula between the data list structure needed in financial calculating process, table, and GIS process assemblies module is associated to obtain automatically its GIS assignment, calculated by financial measure formula, generated financial statement corresponding with programme;Programme contrast module, contrasts to its financial statement for choosing multiple programmes kept, provides support for decision-making.The present invention makes that whole operation flow is smooth, human cost is low, output is flexible and efficient, can provide strong twelve Earthly Branches for decision-making and hold.
Description
Technical field
The present invention relates to urban area development field, more particularly to a kind of urban area development decision-making support system and side
Method.
Background technology
In urban area development field, Multiple factors affect overall project output.Different plot residing for detailed programs, no
With the land price difference in plot, removal number, compensation standard etc., and project start building time, construction period, in the construction period
The ratio between investments in each year, all can bring the impact of complexity to the income of overall project.
Additionally, bank rate change, inflation index, the fluctuation and change of all kinds of Land Estate Prices, and affect project income
Key factor.
Need to set up finance model, calculated the above-mentioned factor of each scheme included comprehensively and analyzed, drawn
The financial statement of the program.
In urban area, development field finally determines a set of development plan, comprising planning and designing, solution formulation and adjustment, side
The financial statement output of case, multiple steps such as various dimensions comparative analysis between different schemes, finally therefrom choose optimal case, there is provided
Decision support.The software systems for supporting are not provided for whole process in industry at present, need to use stand alone software in different steps
The work of stages respectively is completed, is such as charted using ArcGis softwares in the planning and designing stage, in solution formulation and adjusting stage
Using the manual operations of Office softwares, the financial measuring and calculating stage is calculated using Excel softwares, then using Word, Excel etc.
Instrument writes various forms.
All kinds of corrupt practices creep in for this working method:
Firstly, since each software independent operating, the input and output of each step are unable to the coordinating and unifying, and operation flow needs big
The human input of amount.Such as a certain purpose property value is have modified in the project setting stage, this modification cannot be automatically reflected in previous
In the design of individual step (i.e. planning and designing), ArcGis softwares are can only enter by manually changing corresponding value item by item.And scheme is adjusted
It is whole be the operation of the ArcGis softwares for frequently, thus bringing be also frequently.
Secondly, each software is powerful in the art, and ArcGis softwares carry out charting, Excel carries out computing, Word is compiled
System report etc..But the limitation of each software is similarly projected, respective result, figure, text, data separating can only be each exported.
And in real work, have many scenes to need the result of multiple softwares outputs above to combine, intuitively embody to decision-making
Person.As scheme compile and edit after produce it is each dimension, very more than calculating data, need to be shown with reference to planning chart, now
Can only put into a large amount of manpowers carry out charting, work of tabulating.
3rd, typing amount is big, error error rate is high.As full-service flow process carries out work using different software in different phase
Make, the variation that either step occurs, its structure for producing will be manually entered in another software, thus bring hard work
Amount, and inevitably error, mistake.
As can be seen here, related tool software is developed in above-mentioned existing urban area, it is clear that still suffered from inconvenience and defect, and
Urgently it is further improved.How to found that a kind of operation flow is smooth, human cost is low, export flexible and efficient new city
City region development decision-making supports system and method, becomes current urgent problem.
The content of the invention
The technical problem to be solved in the present invention is to provide that a kind of operation flow is smooth, human cost is low, output is flexible and efficient
New urban area development decision-making support system and method so as to provide strong twelve Earthly Branches for decision-making and hold.
To solve above-mentioned technical problem, the present invention is adopted the following technical scheme that:
A kind of urban area development decision-making supports system, including:
Transmission module in basic data, for uploading GIS data and item base data.
GIS process assembly modules, including programme and with reference to figure generate submodule, adjustment submodule and programme protect
Submodule is deposited, wherein:Programme and submodule is generated with reference to figure, for setting up programme according to basic data and giving birth to simultaneously
Into with reference to figure;Adjustment submodule, for the GIS assignment of GIS data in revised planning scheme, while programme and with reference to figure life
Into the programme in submodule and with reference to figure, according to the adjustment of GIS assignment, correspondence is adjusted;Programme preserves submodule, uses
In the programme that preservation is adjusted.
Finance measuring and calculating module, surveys for configuring relation and finance between the data list structure needed in financial calculating process, table
Formula is calculated, and GIS process assemblies module is associated to obtain automatically its GIS assignment, calculated by financial measure formula, generate
Financial statement corresponding with programme.
Programme contrast module, contrasts to its financial statement for choosing multiple programmes kept, is
Decision-making provides support.
Further, the item base data adopt txt, xlsx, xls or dbf form;Accordingly, also including project
Basic data correction verification module, does not meet data that form specifies and is pointed out for returning.
Further, the adjustment submodule, for bringing automatically the graphic operation mode of data with mouse drag, program into
The GIS assignment of parameters in revised planning scheme;The mouse drag and program are brought automatically data into and are specially:In planning side
Number list is shown on the graphic interface of case, is clicked in programme with mouse and data is directly dragged to after the figure spot of assignment
Numerically, program automatically saves this corresponding numerical value of operation to the correspondence of list;Or reversely pulled by mouse.
Further, the finance measuring and calculating module is configured or in web interface by uploading excel finance model files
Directly adjustment configures finance model at end.
Further, the programme includes the reallocation of land, roading, supporting planning, real estate projects planning;It is described
It is public by specifying certain entry value or the new finance of web interface end adjustment configuration in upload excel finance model files to calculate with reference to figure
The output valve of formula, associates the different picture of output from the map of programme.
Further, it is described with reference to figure include following distribution map in it is various:Allocation of landownership and land use right distribution map, earth clearance cost
Intensity distribution, tax revenue potential distribution figure, construction cost are thrown in distribution map, soil unit price distribution map, soil total price distribution map, landing
Distribution map, integrated cost distribution map, comprehensive value distribution map, comprehensive input and output distribution map.
Further, the generating mode of the plurality of programme kept also includes:According to the side being previously generated
New departure is saved as, and/or uploads again basic data covering original basis data after case modification, generate new departure.
Further, the programme contrast module, the key index chosen in financial statement are contrasted.
Further, also including development progress display module, for owning in the framing dynamic demonstration arbitrary disposition time period
The development progress of project, and/or the accumulative development progress of project in arbitrary year is checked, and/or check that the year is ongoing
Project development progress.
Further, also including data download module, the data download module be used for provide scheme GIS data download,
Each scheme financial statement is downloaded and contrast of multiple-schemes report is downloaded.
A kind of urban area development decision-making supports method, comprises the steps:
Upload GIS data and item base data;Data according to uploading are set up programme and while are generated with reference to figure;
The GIS assignment of GIS data in revised planning scheme, at the same programme and with reference to figure according to the adjustment of GIS assignment correspondence adjust
It is whole;The programme that preservation is adjusted;Close between data list structure that finance measuring and calculating part is needed in configuring financial calculating process, table
System and financial measure formula, and dynamic acquisition GIS assignment, are calculated by financial measure formula, are generated corresponding with programme
Financial statement;Choose multiple programmes kept to contrast its financial statement, support is provided for decision-making.
Further, the item base data adopt txt, xlsx, xls or dbf form;By format check, return
Do not meet data that form specifies and pointed out.
Further, brought into mouse drag, program automatically every in the graphic operation mode revised planning scheme of data
The GIS assignment of parameter;The mouse drag and program are brought automatically data into and are specially:It is above-listed in the graphic interface of programme
There is number list, the correspondence for data list being directly dragged to after the figure spot of assignment in programme is clicked on numerically with mouse,
Program automatically saves this corresponding numerical value of operation;Or reversely pulled by mouse.
Further, the finance measuring and calculating part is configured or in web interface by uploading excel finance model files
Directly adjustment configures finance model at end.
Further, the programme includes the reallocation of land, roading, supporting planning, real estate projects planning;It is described
It is public by specifying certain entry value or the new finance of web interface end adjustment configuration in upload excel finance model files to calculate with reference to figure
The output valve of formula, associates the different picture of output from the map of programme.
Further, it is described with reference to figure include following distribution map in it is various:Allocation of landownership and land use right distribution map, earth clearance cost
Intensity distribution, tax revenue potential distribution figure, construction cost are thrown in distribution map, soil unit price distribution map, soil total price distribution map, landing
Distribution map, integrated cost distribution map, comprehensive value distribution map, comprehensive input and output distribution map.
Further, the generating mode of the plurality of programme kept also includes:According to the side being previously generated
New departure is saved as, and/or uploads again basic data covering original basis data after case modification, generate new departure.
Further, the key index chosen in financial statement is contrasted.
Further, also show that all items opens in the framing dynamic demonstration arbitrary disposition time period including development progress
The progress of sending out, and/or the accumulative development progress of project in arbitrary year is checked, and/or check the annual ongoing project development
Progress.
Further, also download including data, there is provided scheme GIS data is downloaded, each scheme financial statement is downloaded and multi-party
Case comparison report is downloaded.
At least there is advantages below by adopting above-mentioned technical proposal, the present invention:
1st, built-in GIS process assemblies, operating personnel can carry out planning design work without the need for grasping professional GIS software.
2nd, graphic operation mode:In the way of mouse drag, program bring data into automatically, design work is greatly simplified
Make.
3rd, generate with reference to figure in real time:According to all kinds of with reference to figure of typing parameter generation, it is to judge current planning and designing step
Maximally effective reference frame is provided.
4th, configurableization of finance measuring and calculating module:The excel finance model files put up can be uploaded, or in web circle
Flexible configuration is carried out relation, financial measure formula etc. between data list structure, table on face, different enterprises, disparity items are answered
With with greatly compatibility.
5th, the data of financial Calculating model prepare:The assignment carried out to GIS is greatly reduced automatically into finance measuring and calculating module
The workload of data inputting.
6th, contrast of multiple-schemes:Adjust key index as needed at any time, generate different types of form.
7th, whole operation flow is smooth, human cost is low, output is flexible and efficient, provides for decision-making and effectively supports.
Description of the drawings
Above-mentioned is only the general introduction of technical solution of the present invention, in order to better understand the technological means of the present invention, below
With reference to accompanying drawing, the present invention is described in further detail with specific embodiment.
Fig. 1 is that a kind of urban area development decision-making of the invention supports system module composition figure;
Fig. 2 is that a kind of urban area development decision-making of the invention supports method overall flow figure;
Fig. 3 is programme adjustment schematic flow sheet;
Fig. 4 is system program main interface schematic diagram;
Fig. 5 is that basic data uploads schematic diagram;
Fig. 6 is that basic data derives schematic diagram;
Fig. 7 is newly-built project schematic diagram;
Fig. 8 is based on the newly-built schematic diagram of existing program;
Fig. 9 is introduced into scheme schematic diagram;
Figure 10 is export plan schematic diagram;
Figure 11 is reallocation of land adjustment schematic diagram;
Figure 12 is roading adjustment schematic diagram;
Figure 13 is supporting planning and adjusting schematic diagram;
Figure 14 is real estate planning and adjusting schematic diagram;
Figure 15 is allocation of landownership and land use right distribution reference figure;
Figure 16 is development progress demonstration schematic diagram;
Figure 17 is scheme comparison's figure.
Specific embodiment
The present invention disconnects for the planning and designing stage picture and text link that several standalone tool softwares in industry are present, adjustment rule
Draw and operate that loaded down with trivial details and interface is directly perceived, finance measuring and calculating phase data typing workload is heavy, error error rate is higher etc. using existing
Shape, is analyzed and comprehensively designs with reference to industry requirement, and exploitation devises a kind of new urban area development decision-making and supports system
And method.
As shown in figure 1, a kind of urban area development decision-making of the present invention supports system, including:
Transmission module 100 in basic data, for uploading GIS data and item base data (txt/xlsx/xls/dbf etc.
Multiple format).
GIS process assemblies module 200, including programme (reallocation of land, roading, supporting planning, real estate projects rule
Draw) and submodule 201, adjustment submodule 202 and programme preservation submodule 203 are generated with reference to figure, wherein:Programme and
Submodule 201 is generated with reference to figure, for programme being set up according to basic data and while being generated with reference to figure;Adjustment submodule
202, for the GIS assignment of GIS data in revised planning scheme, while programme and generating in submodule 201 with reference to figure
Programme and with reference to figure according to the adjustment of GIS assignment correspondence adjust;Programme preserves submodule 203, adjusts for preserving
Whole good programme.
Finance measuring and calculating module 300, for configuring relation and finance between the data list structure needed in financial calculating process, table
Measure formula, and the adjustment submodule 202 in GIS process assemblies module 200 is associated to obtain automatically its GIS assignment, by wealth
Business measure formula is calculated, and generates financial statement corresponding with programme.
Programme contrast module 400, contrasts to its financial statement for choosing multiple programmes kept,
Support is provided for decision-making.
Said system has following major function:
1st, built-in GIS process assemblies:The concrete operations of planning design work are incorporated on system interface.
2nd, generate with reference to figure in real time:The assignment carried out to GIS, can generate which in addition by operation rule set in advance
His reference pattern, shows immediately operator, the adjustment direction of next step is determined for which.10 kinds of this programme offer is different types of
With reference to figure, (allocation of landownership and land use right distribution map, earth clearance cost profile, soil unit price distribution map, soil total price distribution map, landing are thrown
Intensity distribution, tax revenue potential distribution figure, construction cost distribution map, integrated cost distribution map, comprehensive value distribution map, comprehensive throwing
Enter output distribution map) it is for reference.Above-mentioned is both the output of project setting with reference to figure, and provides reference for adjustment next time.
Operator's Adjusted Option, calculated after, control output result (includes with reference to figure and finance results of measuring), adjustment side again
Case ... is so repeated multiple times, finally determines scheme.
3rd, finance measuring and calculating module:According to the difference of business, the data list structure that needs in flexible configuration finance calculating process,
Relation and financial measure formula between table, the assignment carried out to GIS, automatically into finance measuring and calculating module, is next step measuring and calculating work
Prepare.
4th, contrast of multiple-schemes:Can continuously generate multiple schemes, and the complicated financial statement of synchronism output each scheme, it is to determine
Plan provides support.
In the adjustment submodule of said system, can using most directly, easily graphic operation mode (such as mouse drag and
Program brings data mode automatically into), " mouse drag ", " program is brought into automatically " they are the mode of operation of same operation and follow-up knot
Really:Conventional operation mode is that a certain figure spot arranges time value, needs first to click on the figure spot, then manually enters year in certain text box
Number value is chosen in drop-down menu.Mouse drag is referred to lists year column table on the graphic interface of programme, with
Left mouse button is directly dragged on the specified time after the figure spot of assignment in clicking on programme, and program automatically saves this operation
Corresponding time value.Above-mentioned mouse drag can also reverse operating, directly will be dragged in the figure spot for treating assignment in the time.To scheme
Shape mode of operation provides the GIS assignment adjustment to each GIS data in programme, greatly simplifies design work.
Finance measuring and calculating module in said system, can be configured or in web by uploading excel finance model files
Interface edge directly adjusts configuration finance model (carrying out flexible configuration to relation, financial measure formula etc. between data list structure, table).
Accordingly, specified certain entry value uploaded in excel finance model files can be passed through with reference to figure or the adjustment configuration of web interface end is new
The output valve of financial measure formula, associates the different picture of output from the map of programme.
The generating mode of the multiple programmes kept in said system is except generating according to the basic data for uploading
New departure, also includes:According to save as after the scheme modifying being previously generated new departure and again upload basic data cover
Lid original basis data, generate new departure.
Programme contrast module in said system, it is right to be carried out according to the key index in setting financial statement
Than key index can also be adjusted as needed at any time, exported different types of form, provided strong support for decision-making.
Said system also includes development progress display module, can be with all items in the framing dynamic demonstration arbitrary disposition time period
Purpose development progress, checks the accumulative development progress of project in arbitrary year, checks the annual ongoing project development progress.
Said system also includes data download module, and data download module is used to provide the download of scheme GIS data, each scheme
Financial statement is downloaded and contrast of multiple-schemes report is downloaded.
If Fig. 2 is that a kind of urban area development decision-making of the invention supports method overall flow figure;Fig. 3 is programme adjustment
Schematic flow sheet;With said system accordingly, coordinate shown in Fig. 2, a kind of urban area development decision-making of the present invention supports method,
Comprise the steps:
Upload data based on GIS data and item base data (multiple format such as txt/xlsx/xls/dbf);
Programme is set up according to basic data and while is generated with reference to figure;
The GIS assignment (geographical position, sequential etc.) of GIS data in revised planning scheme, while programme and with reference to figure
It is corresponding according to the adjustment of GIS assignment to adjust;
The programme that preservation is adjusted;
Finance measuring and calculating part, according to business difference, between the data list structure needed in flexible configuration finance calculating process, table
Relation and financial measure formula (uploading excel finance models file or in web terminal flexible configuration finance model), and obtain automatically
Its GIS assignment, is calculated by financial measure formula, generates financial statement corresponding with programme;(not shown in figure,
In programme, revised planning solution processes are generated, correspondence is generated);
Choose multiple programmes kept to contrast its financial statement, support is provided for decision-making, may be used also in addition
To carry out data download.
Specifically, it is divided into following components:
1st, basic data is uploaded
System requirements must upload basic data first.Basic data is made up of two parts:1st, GIS data;2nd, project base
Plinth data (multiple format such as txt/xlsx/xls/dbf).This two parts data has strict form regulation, and program is to data
Verified, not meeting the data that form specifies will be retired, and program carries out clear, clear and definite prompting simultaneously.
2nd, generate scheme
(1) according to the basic data for uploading, a key generates scheme.
(2), while generating scheme, supporting generation 10 is with reference to figure.
(3) there are four planning charts in scheme, adjust the parameters of element on the diagram respectively.
(4) after adjusting one or more parameter, implement calculation function, 10 update with reference to figure, parameter are checked for operator
The effect of configuration, to continue adjusting parameter.
3rd, finance measuring and calculating
(1) difference according to business, relation and wealth between the data list structure needed in flexible configuration finance calculating process, table
Business measure formula.
(2) after parameters being adjusted in scheme, implement calculation function, generate finance measuring and calculating report and check for operator.
(3) when whole parameter adjustments are finished, program sizing exports multinomial financial statement.
4th, generate new departure
Operator can select various ways, generate new departure:
(1) according to the basic data for having uploaded, generate new departure.
(2) according to the scheme for having generated, after modification, save as new departure.
(3) basic data (covering former data) is uploaded again, new departure is generated.
5th, contrast of multiple-schemes
After generating multiple designs, contrast of multiple-schemes can be carried out.
(1) the several key indexs for contrast are determined.
(2) select from existing scheme it is multiple, or all, generate comparison report.
(3) many parts of comparison reports can be continuously generated from multiple angles.
6th, data are downloaded
Program provides all kinds data and downloads.
(1) each scheme GIS data is downloaded.
(2) each scheme finance results of measuring (detailed account) is downloaded.
(3) contrast of multiple-schemes report is downloaded.
Below from concrete application angle, the present invention will be described in detail:
As shown in figure 4, for the present invention system program main interface;Program function includes:Basic data is uploaded, is derived;Side
Case is newly-built, import, derive;Project setting;Scheme comparison.
In data manipulation, basic data is uploaded as shown in figure 5, basic data includes GIS data and item base data
(multiple format such as txt/xlsx/xls/dbf).Scheme is set up after basic data is uploaded, as shown in fig. 6, can be according to selection
Scheme derives Excel data and map datum, may be selected which data derived.
In scheme operation, newly-built project is as shown in fig. 7, fill in Scenario Name, description on the page as shown in 7 figures -->
Click on " establishment scheme ", can be with as shown in figure 8, being based on existing scheme, generation new departure selects scheme to be referred to, fills out
Write Scenario Name, description -->Click on " establishment scheme ";Also can be with as shown in figure 9, import plan, clicks on " browsing " and selects to want
The scheme of importing, fills in new departure title (must fill out) and new departure explanation (optional), clicks on " importing ".When prompting importing finish by
" it is determined that " success.Also can also as illustrated in fig. 10, export plan selects to want derived scheme, clicks on " browsing " and selects derived
Path, clicks on " derivation ".When prompting " scheme is derived successfully " is derived successfully.
In project setting, planning and adjusting part therein includes:
(1) reallocation of land adjustment, as shown in figure 11, to soil " development progress " and the base in " selling progress " and each plot
Plinth information is adjusted.
(2) roading adjustment, as shown in figure 12, is adjusted to " construction progress " and essential information of road.
(3) supporting planning and adjusting, as shown in figure 13, the adjustment to supporting " construction progress " and essential information.
(4) real estate planning and adjusting, as shown in figure 14, is carried out to " construction progress ", " managing sale situation " and essential information
Adjustment.
In project setting, it is adjusted according to the planning to four planning figure layers, is shown with reference on figure at 10 after computing
Show different data, there is provided personnel refer at any time to solution formulation, carry out the project setting of next step.With reference to the landright in figure
Category distribution map as shown in figure 15, its be it is original to soil belonging to Regional Distribution displaying, xx villages etc. belonging to example block soil.Levy
Ground removal cost distribution map, is the displaying figure layer to each exploitation plot removal cost.Soil unit price distribution map, is to each exploitation ground
The displaying figure layer of the land values in block unit area.Soil total price distribution map, is to developing the soil in the block gross area of various places
The displaying figure layer of value.Intensity distribution is thrown in landing, mainly the actual input of administration assets.
Furthermore it is also possible to provide development progress demo function as shown in figure 16, such as program is entered according to the change of setting option
Row is calculated, it is possible to specify the time period of several years after starting from certain year, annual development progress is connected in asymptotic color mode
Extend existing.Program can playing pictures automatically, it is also possible to specifically checking in a certain year.
On scheme comparison, as different schemes has different financial datas and business indicator.Program is to multiple schemes
The contrast of these indexs is carried out, is used for managerial decision.Operate as shown in figure 17,2 sides are at least selected in scheme list
Case --->Click on " contrast scheme " to show such as comparing result between the scheme in diagram page.
In sum, entirely operation flow is smooth, human cost is low, output is flexible and efficient for the present invention, can provide for decision-making
Effectively support.
The above, is only presently preferred embodiments of the present invention, not makees any pro forma restriction to the present invention, this
Art personnel make a little simple modification, equivalent variations or modification using the technology contents of the disclosure above, all fall within this
In bright protection domain.
Claims (20)
1. a kind of urban area development decision-making supports system, it is characterised in that include:
Transmission module in basic data, for uploading GIS data and item base data;
GIS process assembly modules, including programme and with reference to figure generate submodule, adjustment submodule and programme preserve son
Module, wherein:
Programme and submodule is generated with reference to figure, for setting up programme according to basic data and simultaneously generation is with reference to figure;
Adjustment submodule, for the GIS assignment of GIS data in revised planning scheme, while programme and sub with reference to figure generation
Programme in module and correspondence is adjusted according to the adjustment of GIS assignment with reference to figure;
Programme preserves submodule, for preserving the programme adjusted;
Finance measuring and calculating module, it is public for configuring relation and finance measuring and calculating between the data list structure needed in financial calculating process, table
Formula, and GIS process assemblies module is associated to obtain automatically its GIS assignment, calculated by financial measure formula, generate and advise
Draw the corresponding financial statement of scheme;
Programme contrast module, contrasts to its financial statement for choosing multiple programmes kept, is decision-making
There is provided and support.
2. urban area development decision-making according to claim 1 supports system, it is characterised in that the item base data
Using txt, xlsx, xls or dbf form;Accordingly, also including item base data check module, for return be not inconsistent it is qualified
Data that formula specifies simultaneously are pointed out.
3. urban area development decision-making according to claim 1 supports system, it is characterised in that the adjustment submodule,
For bringing automatically the GIS assignment of parameters in the graphic operation mode revised planning scheme of data with mouse drag, program into;
The mouse drag and program are brought automatically data into and are specially:Numerical value row are shown on the graphic interface of programme
Table, clicks on the correspondence for being directly dragged to data list after the figure spot of assignment in programme numerically with mouse, and program is automatic
Preserve this corresponding numerical value of operation;Or reversely pulled by mouse.
4. urban area development decision-making according to claim 1 supports system, it is characterised in that the finance measuring and calculating module
Configured by upload excel finance model files or configuration finance model is directly adjusted at web interface end.
5. urban area development decision-making according to claim 4 supports system, it is characterised in that the programme includes
The reallocation of land, roading, supporting planning, real estate projects planning;It is described to upload excel finance model text by specifying with reference to figure
The output valve of the new finance measure formula of certain entry value or web interface end adjustment configuration in part, is associated with the map of programme defeated
Go out different pictures.
6. urban area development decision-making according to claim 5 supports system, it is characterised in that it is described with reference to figure include as
It is various in lower distribution map:Allocation of landownership and land use right distribution map, earth clearance cost profile, soil unit price distribution map, soil total price point
Intensity distribution, tax revenue potential distribution figure, construction cost distribution map, integrated cost distribution map, comprehensive value point are thrown in Butut, landing
Butut, comprehensive input and output distribution map.
7. urban area development decision-making according to claim 1 supports system, it is characterised in that the plurality of to keep
The generating mode of programme also includes:According to saving as new departure after the scheme modifying being previously generated, and/or go up again
Pass basic data and cover original basis data, generate new departure.
8. urban area development decision-making according to claim 1 supports system, it is characterised in that the programme contrast
Module, the key index chosen in financial statement are contrasted.
9. urban area development decision-making according to claim 1 supports system, it is characterised in that also including development progress exhibition
Show module, for the development progress of all items in the framing dynamic demonstration arbitrary disposition time period, and/or check arbitrary year
Project adds up development progress, and/or checks the annual ongoing project development progress.
10. urban area development decision-making according to claim 1 supports system, it is characterised in that also download including data
Module, the data download module are used to provide the download of scheme GIS data, the download of each scheme financial statement and contrast of multiple-schemes report
Accuse and download.
A kind of 11. urban area development decision-makings support method, it is characterised in that comprise the steps:
Upload GIS data and item base data;
Data according to uploading are set up programme and while are generated with reference to figure;
The GIS assignment of GIS data in revised planning scheme, while programme and right according to the adjustment of GIS assignment with reference to figure
Should adjust;
The programme that preservation is adjusted;
Relation and financial measure formula between data list structure that finance measuring and calculating part is needed in configuring financial calculating process, table, and
It is dynamic to obtain GIS assignment, calculated by financial measure formula, generated financial statement corresponding with programme;
Choose multiple programmes kept to contrast its financial statement, support is provided for decision-making.
12. urban area development decision-makings according to claim 11 support method, it is characterised in that the item base number
According to using txt, xlsx, xls or dbf form;By format check, return and do not meet data that form specifies and pointed out.
13. urban area development decision-makings according to claim 11 support method, it is characterised in that with mouse drag, journey
Sequence brings the GIS assignment of parameters in the graphic operation mode revised planning scheme of data automatically into;
The mouse drag and program are brought automatically data into and are specially:Numerical value row are shown on the graphic interface of programme
Table, clicks on the correspondence for being directly dragged to data list after the figure spot of assignment in programme numerically with mouse, and program is automatic
Preserve this corresponding numerical value of operation;Or reversely pulled by mouse.
14. urban area development decision-makings according to claim 11 support method, it is characterised in that the financial measuring and calculating portion
Divide configured by upload excel finance model files or configuration finance model is directly adjusted at web interface end.
15. urban area development decision-makings according to claim 14 support method, it is characterised in that the programme bag
Include the reallocation of land, roading, supporting planning, real estate projects planning;It is described to upload excel finance model by specifying with reference to figure
The output valve of the new finance measure formula of certain entry value or web interface end adjustment configuration in file, is associated with the map of programme
The different picture of output.
16. urban area development decision-makings according to claim 15 support method, it is characterised in that described to include with reference to figure
It is various in following distribution map:Allocation of landownership and land use right distribution map, earth clearance cost profile, soil unit price distribution map, soil total price
Intensity distribution, tax revenue potential distribution figure, construction cost distribution map, integrated cost distribution map, comprehensive value are thrown in distribution map, landing
Distribution map, comprehensive input and output distribution map.
17. urban area development decision-makings according to claim 11 support method, it is characterised in that the plurality of to keep
The generating mode of programme also include:According to saving as new departure after the scheme modifying being previously generated, and/or again
Upload basic data and cover original basis data, generate new departure.
18. urban area development decision-makings according to claim 11 support method, it is characterised in that choose in financial statement
Key index contrasted.
19. urban area development decision-makings according to claim 11 support method, it is characterised in that also including development progress
Show, the development progress of all items in the framing dynamic demonstration arbitrary disposition time period, and/or check that the project in arbitrary year is tired out
Meter development progress, and/or check the annual ongoing project development progress.
20. urban area development decision-makings according to claim 11 support method, it is characterised in that also including under data
Carry, there is provided scheme GIS data is downloaded, each scheme financial statement is downloaded and contrast of multiple-schemes report is downloaded.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610979648.7A CN106548290A (en) | 2016-11-08 | 2016-11-08 | A kind of urban area development decision-making supports system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610979648.7A CN106548290A (en) | 2016-11-08 | 2016-11-08 | A kind of urban area development decision-making supports system and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106548290A true CN106548290A (en) | 2017-03-29 |
Family
ID=58394743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610979648.7A Pending CN106548290A (en) | 2016-11-08 | 2016-11-08 | A kind of urban area development decision-making supports system and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106548290A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107622353A (en) * | 2017-09-27 | 2018-01-23 | 合肥博力生产力促进中心有限公司 | A kind of Enterprise Project technical scheme layout regulator control system based on information analysis |
CN108665192A (en) * | 2018-07-02 | 2018-10-16 | 深圳市诺信连接科技有限责任公司 | A kind of roadside greening management platform and method |
CN110889794A (en) * | 2019-09-30 | 2020-03-17 | 成都市市政工程设计研究院 | Statistical method for municipal road land acquisition houses |
CN113379231A (en) * | 2021-06-08 | 2021-09-10 | 深圳市城市产业发展集团有限公司 | Full-period digital measuring model, device, storage medium and electronic equipment for district development construction fund |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103020290A (en) * | 2012-05-07 | 2013-04-03 | 山东电力集团公司青岛供电公司 | Power grid information verifying method and system |
CN103150680A (en) * | 2013-03-25 | 2013-06-12 | 东南大学 | Automatic layout method for urban development land with best road accessibility |
CN105279711A (en) * | 2015-05-29 | 2016-01-27 | 南京市规划局 | Construction project planning and site selection system and method |
CN105488728A (en) * | 2015-12-11 | 2016-04-13 | 中国烟草总公司广东省公司 | Tobacco field infrastructure management system based on geographic information system technique |
-
2016
- 2016-11-08 CN CN201610979648.7A patent/CN106548290A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103020290A (en) * | 2012-05-07 | 2013-04-03 | 山东电力集团公司青岛供电公司 | Power grid information verifying method and system |
CN103150680A (en) * | 2013-03-25 | 2013-06-12 | 东南大学 | Automatic layout method for urban development land with best road accessibility |
CN105279711A (en) * | 2015-05-29 | 2016-01-27 | 南京市规划局 | Construction project planning and site selection system and method |
CN105488728A (en) * | 2015-12-11 | 2016-04-13 | 中国烟草总公司广东省公司 | Tobacco field infrastructure management system based on geographic information system technique |
Non-Patent Citations (2)
Title |
---|
KAZETOTORI: "想给一个input赋值一个JS拖动事件", 《百度知道》 * |
张进洁: "基于3DGIS的规划支持系统研究", 《硕士学位论文》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107622353A (en) * | 2017-09-27 | 2018-01-23 | 合肥博力生产力促进中心有限公司 | A kind of Enterprise Project technical scheme layout regulator control system based on information analysis |
CN108665192A (en) * | 2018-07-02 | 2018-10-16 | 深圳市诺信连接科技有限责任公司 | A kind of roadside greening management platform and method |
CN110889794A (en) * | 2019-09-30 | 2020-03-17 | 成都市市政工程设计研究院 | Statistical method for municipal road land acquisition houses |
CN113379231A (en) * | 2021-06-08 | 2021-09-10 | 深圳市城市产业发展集团有限公司 | Full-period digital measuring model, device, storage medium and electronic equipment for district development construction fund |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20210219660A1 (en) | Footwear Designing Tool | |
US9024952B2 (en) | Discovering and configuring representations of data via an insight taxonomy | |
US20120116835A1 (en) | Hybrid task board and critical path method based project management application interface | |
CN106548290A (en) | A kind of urban area development decision-making supports system and method | |
Cliburn et al. | Design and evaluation of a decision support system in a water balance application | |
US10289671B2 (en) | Graphically displaying selected data sources within a grid | |
US20090070158A1 (en) | Method apparatus and system for visualization of probabilistic models | |
US20070205276A1 (en) | Visualization confirmation of price zoning display | |
US20080086716A1 (en) | Method and apparatus for information display with intermediate datasource access | |
US20120226626A1 (en) | System and method for creating business intelligence dashboard mockups | |
US20180174243A1 (en) | Systems, methods and apparatus for enhanced navigation in preparation of an electronic tax return | |
CN113255302A (en) | Method for operating tissue architecture diagram, computer device and computer storage medium | |
CN110264548A (en) | A kind of attributive character information space analysis method of land data | |
JP2006259940A (en) | Statistical information presentation device | |
US11094096B2 (en) | Enhancement layers for data visualization | |
US20070103490A1 (en) | Automatic element substitution in vector-based illustrations | |
CN106898247A (en) | A kind of quick geology drawing methods of layer position modification | |
WO2012033715A1 (en) | Methods and systems for stylized map generation | |
CN116719521A (en) | Demonstrator model editing method and system and configuration software system | |
US11373256B2 (en) | Editing and representing property values for a digital map | |
McLean et al. | The ‘Ike Wai Hawai ‘i groundwater recharge tool | |
Yori et al. | Mastering Autodesk Revit 2020 | |
US11263791B2 (en) | System and method for generation of an interactive color workspace | |
DE102005004386A1 (en) | Method and apparatus for analyzing an electromagnetic wave, and computer product | |
US20070174792A1 (en) | Graphic subselection in a computer aided design |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170329 |