CN106545117A - A kind of public utility Integral ceiling and its construction method - Google Patents
A kind of public utility Integral ceiling and its construction method Download PDFInfo
- Publication number
- CN106545117A CN106545117A CN201610339026.8A CN201610339026A CN106545117A CN 106545117 A CN106545117 A CN 106545117A CN 201610339026 A CN201610339026 A CN 201610339026A CN 106545117 A CN106545117 A CN 106545117A
- Authority
- CN
- China
- Prior art keywords
- air
- water
- integral ceiling
- electricity
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/006—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation with means for hanging lighting fixtures or other appliances to the framework of the ceiling
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
- E04B9/20—Means for suspending the supporting construction adjustable
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Duct Arrangements (AREA)
Abstract
A kind of public utility Integral ceiling, including bearing unit (100), functional unit and interface unit, air-conditioning air main (6) are mounted horizontally structural member and pass through and be supported on Horizontal mounting arrangements part;The air-conditioning air main (6) is including inverted U-shaped body passageways (6.1), on inverted U-shaped body passageways two bottom sides side, outwards turnover has horizontal lock portion (6.2), in horizontal lock portion, integral middle forms vertically portion (6.3), the horizontal lock portion is capping sticking department (6.4) in vertically portion right part, the horizontal lock portion is decorative panel sticking department (6.5) in vertically portion left part, bottom (8) is fastened in capping sticking department (6.4), clamping Decorative hanging board (7) is connected with the both sides vertically portion of U-shaped body passageways (6.1), the clamping decorative panel (7) is provided through groove below bottom buckling parts, Horizontal structural members cross described through groove.By the structure that cooperate of the air-conditioning air main with Horizontal mounting arrangements part, the public utility Integral ceiling, ensure that Integral ceiling can accomplish that floor height is minimum, accomplishes convenient to install and maintain by the combination of the structure design and functional column of water, electricity and gas integrated frame.
Description
Technical field
The invention belongs to furred ceiling technical field, and in particular to a kind of public utility Integral ceiling and its construction method.
Background technology
It is the development trend of furred ceiling industry, referred to as Integral ceiling that furred ceiling is integrated with electrical equipment.Integral ceiling is by sheet material and electrical equipment collection
Conjunction is formed, and modularity is the characteristics of Integral ceiling is most prominent, and Integral ceiling is typically by heating module, lighting module, ventilation module
Arbitrarily assembled with modular form with the material such as metal aluminum-pinch, dismounting facility, type are various.Computer floor and data processing experiment
Room, hospital and government organs commence business and are increasingly dependent on the multiple data handling equipment arrange in which.Reasonable employment water, electricity,
Warm, air, increasingly becomes the functional requirement of Integral ceiling.Meanwhile, the furred ceiling for reducing height is also the shape that client enjoys a lot
Formula.
At present Integral ceiling is connected to complete keel frame structure using lightgage steel joist and triangular keel mostly, in addition it is also necessary in frame
The facilities such as water pipe, cable, airduct are installed on frame, this structure installation procedure is complicated, and stability is inadequate.
A kind of integrated suspended ceiling device is designed, the integrated basic demand of water, electricity, gas, heat has both been met, has also been met floor height highly minimum
Require, simple structure location and installation is convenient, is the difficult problem of designer really.
The content of the invention
For the problem that above-mentioned prior art is present, the present invention provides a kind of public utility Integral ceiling and its construction method.
The present invention is achieved in that a kind of public utility Integral ceiling, including including bearing unit, functional unit and interface unit,
The bearing unit includes Horizontal mounting arrangements part, phase with vertical installation part and some overall heavy burden parts, Horizontal mounting arrangements part
Crossover node is connected the phase with vertical installation part, and the overall heavy burden part adjustable ground is fixedly connected the phase with vertical installation part,
The overall heavy burden part is fastened on house top board;The functional unit includes with wind module, fire alarm module and electricity-water-gas module,
The functional unit is fixed on the top of bearing unit, and Integral ceiling connecting interface unit is worn under the functional unit;It is described to use wind
Module includes air-conditioning air main, and the air-conditioning air main is passed through and is supported on by the Horizontal mounting arrangements part of other direction and is horizontally mounted
On structural member;The air-conditioning air main includes inverted U-shaped body passageways, and on inverted U-shaped body passageways two bottom sides side, outwards turnover has
Horizontal lock portion, in horizontal lock portion, integral middle forms vertically portion, and the horizontal lock portion is on the right side of vertically portion
Part is capping sticking department, and the horizontal lock portion is decorative panel sticking department in vertically portion left part, and bottom is fastened on envelope
On lid sticking department, clamping Decorative hanging board is connected with the both sides vertically portion of U-shaped body passageways, the clamping decorative panel is the bottom of at
Groove is provided through below lid buckling parts, Horizontal structural members cross described through groove.
Further, in the top margin both sides of U-shaped body passageways, outwards turnover has top fixed part, and top fixed part is fixed on house top
Portion, the floor height of Integral ceiling are equal to the height of the air-conditioning air main.
Further, the cross section of the clamping Decorative hanging board is lay flat on one's back Z-shaped, including integrally formed upper Access Division, lower card
Socket part and opposite joint portion, the clamping Decorative hanging board in the left side and the clamping Decorative hanging board on right side are docked and are locked with fixture in opposite joint portion
Fixed, the size of the inverted U-shaped body passageways of the air-conditioning air main is not limited by the crossover node size of Horizontal mounting arrangements part,
The air-conditioning air main substitutes a Horizontal mounting arrangements part, is passed through and is supported on level by the Horizontal mounting arrangements part of other direction
In mounting structure.
Further, the clamping Decorative hanging board includes integrally formed upper Access Division, lower Access Division and opposite joint portion, when the card in left side
When connecing the clamping Decorative hanging board on Decorative hanging board and right side and being connected to the both sides of U-shaped body passageways, the distance between described lower Access Division
Mesh width when intersecting equal to Horizontal structural members, is connected with decorative cover between the lower Access Division of the lower Access Division and right side in left side
Plate.
Further, the electricity-water-gas module includes forceful electric power module, light current module, upper water module and gas module.
Further, also including water, electricity and gas integrated frame, water, electricity and gas integrated frame is mountain font main body, is division board in the middle of the font main body of mountain,
Electric bridge portion is provided with the side of division board, is provided with the opposite side of division board that water pipe installs portion additional and trachea installs portion, water, electricity and gas one additional
Frame is fixed on bearing unit, and the electricity-water-gas module is fixed on the water, electricity and gas integrated frame.
Further, on the bearing unit, an avris is fixed with the first water, electricity and gas integrated frame, is fixed with the second water power in another avris
Gas integrated frame, the forceful electric power module are arranged on the first water, electricity and gas integrated frame, and high tension cable is located in spool, and high tension cable connects
Junction box is connect, under the junction box outlet wiring, Integral ceiling linkage function post, functional column lower accepting water electric terminal is worn;It is described weak
Electric module is arranged on the second water, electricity and gas integrated frame, and type low-voltage cable is located in the spool of the second water, electricity and gas integrated frame, low-voltage cable
Connection junction box, wears Integral ceiling connection suspension type electric-appliance interface module under the junction box outlet wiring.
Further, the fire alarm module includes that water under high pressure is responsible for, and the water under high pressure supervisor is separately positioned on the both sides of air-conditioning air main
Close wall side bearing unit on, the other scion grafting of water under high pressure supervisor goes out water under high pressure arm, and the water under high pressure arm passes through Integral ceiling
Connection fire-fighting spraying head and functional column.
Further, the wind module includes fresh air structure, air discharge structure and air-conditioner wind structure, the fresh air air main of fresh air structure
It is directly anchored on bearing unit, and connects fresh air terminal by Integral ceiling is worn under arm;The air draft air main one of air discharge structure
End connects air draft terminal by Integral ceiling is worn under vertical arm, and the other end is discharged to outside house through body of wall by air exhaust branch pipe.
A kind of construction method of the public utility Integral ceiling, comprises the steps:
1) support unit construction, the corner first direction fixed interval in house arrange the first positioning supporting part, solid in second direction
Determine the second positioning supporting part of interval setting, second positioning supporting part is than the low certain distance of the height of the first positioning supporting part;
2) first level structural member is installed, by many first level structural members parallel equidistant positioning correspondence first in a first direction
On positioning supporting part;
Wherein, the installation of air-conditioning air main, by first positioning supporting part air-conditioning air main installed therein;
3) the second Horizontal structural members are installed, and are equidistantly positioned at vertical with first direction the by many second Horizontal structural members parallel
On second positioning supporting part in two directions, during installation, the second Horizontal structural members cross the air-conditioning air main;In first level structure
Part and the second Horizontal structural members infall install fixed knot;
4) installation of vertical junction component, installs phase with vertical installation part at the multiple fixed knots of the vertical wall surrounding in house, described vertical
Overall heavy burden part is fixedly connected at the top of mounting structure, at least 3 swell fixtures are fixed on floor through the slotted mount holes;
5) Dingan County fills ceiling height really, when being fixed to minimum constructive height installation, by the top of the inverted U-shaped body passageways of air-conditioning air main
Portion is held out against at the top of house, is fixed at the top of house through the bolt hole of top fixed part with expansion bolt;
Or, when scalable Integral ceiling is highly installed, not by fixed, rotation at the top of the top fixed part of air-conditioning air main and house
The top nut of phase with vertical installation part, carries out adjustable range labelling on the screw rod of overall heavy burden part, adjusts all overall heavy burdens
The screw rod of part screws position in nut to sustained height labelling;
6) interface unit is connected to functional unit by the hollow space installation function unit between house top board and Horizontal structural members
On;
7) remove the support unit.
The present invention realizes the problem of Integral ceiling by following technical spirit:Guarantee can accomplish that floor height is minimum while integrated.
(1) structure design of air-conditioning air main, it is ensured that can integrate with Horizontal mounting arrangements part, while the water under high pressure of fire alarm
A pipe point both sides are arranged symmetrically, it is ensured that the balance of Horizontal mounting arrangements part;
(2) design of adjustable Horizontal mounting arrangements part, the overall supporting part of Horizontal mounting arrangements part is adjustable with vertical junction component
Formula is designed.
Air-conditioning air main and Horizontal mounting arrangements part be it is integrated, Horizontal mounting arrangements part through below body passageways through groove simultaneously
It is supported on the lower section of air-conditioning air main.
In addition, roof will be clung at the top of air-conditioning air main, then the height of Integral ceiling is exactly the height of air-conditioning air main, can
To accomplish the minimum floor height of Integral ceiling.
(3) combination of the structure design and functional column of water, electricity and gas integrated frame, dividing plate by electricity with water, edge of drawing last breath, water, electricity and gas integrated frame
Be integrated with water, electricity it is gentle, this integrated installation be easy to and functional column combination, it is convenient to install and maintain;
The public utility Integral ceiling, integrated level are high, by air-conditioning air main and the structure for cooperating of Horizontal mounting arrangements part
Design ensure that Integral ceiling can accomplish that floor height is minimum, accomplish peace by the combination of the structure design and functional column of water, electricity and gas integrated frame
Fill easy to maintenance.
Description of the drawings
Fig. 1 is the main sectional view of public utility Integral ceiling of the present invention;
Fig. 2 is the IV1 of public utility Integral ceiling of the present invention:8 partial enlarged views;
Fig. 3 a) for air-conditioning air main first embodiment cross-sectional view;
Fig. 3 b) for air-conditioning air main second embodiment cross-sectional view.
Specific embodiment
Embodiments of the invention are elaborated below in conjunction with accompanying drawing, but be not limited to the scope of the present invention.
As shown in figure 1, a kind of integrated suspended ceiling device, including bearing unit 100, functional unit, interface unit, the load-bearing list
Unit 100 includes some overall heavy burden parts 1 and Horizontal mounting arrangements part 2, phase with vertical installation part 3, the Horizontal mounting arrangements part
Including first level structural member 2.1 and the second Horizontal structural members 2.2, the corner first direction fixed interval in house first are arranged
First positioning supporting part, arranges the second positioning supporting part in second direction fixed interval, and second positioning supporting part is more fixed than first
The low certain distance of height of position support member, by many first level structural members 2.1 parallel equidistant positioning correspondence in a first direction
On positioning supporting part, then the second party vertical with first direction is equidistantly positioned at by many second Horizontal structural members 2.2 parallel
To corresponding support member on, be provided with fixed knot 2.3 in first level structural member 2.1 and 2.2 infall of the second Horizontal structural members,
Phase with vertical installation part 3 is provided with the multiple fixed knots of vertical wall surrounding, is fixedly connected at the top of the phase with vertical installation part 3 whole
Body heavy burden part 1, the overall heavy burden part 1 include threaded shank 1.1 and fixed cap 1.2, and the fixed cap is provided with least 3
Slotted mount holes, at least 3 swell fixtures 1.3 are fixed on floor through the slotted mount holes, and the slotted mount holes set
Cross flute profile is counted into, arbitrarily can adjust to ensure that installation dimension is accurate in the range of both horizontally and vertically 30-80 millimeters.
The functional unit includes with wind module, fire alarm module, electricity-water-gas module, and the electricity-water-gas module includes forceful electric power module, weak
Electric module, upper water module and gas module, the wind module include fresh air structure, air discharge structure and air-conditioner wind structure.
The interface unit includes functional column, suspension type electric-appliance interface module, air draft terminal interface.
The fresh air air main 4 of fresh air structure is directly anchored on bearing unit, and connects fresh air end by Integral ceiling is worn under arm
End.5 one end of air draft air main of air discharge structure connects air draft terminal 18 by Integral ceiling is worn under vertical arm, and the other end passes through
Air exhaust branch pipe 5.1 is discharged to outside house through body of wall.The air draft terminal 18 includes universal draft hood, atomic absorption cover or ventilation
Cabinet.
In order to reduce the height of Integral ceiling as far as possible, the structure with Horizontal structural members one of air-conditioning air main, the main wind are devised
The cross section of pipe such as Fig. 3 a) and Fig. 3 b) shown in, air-conditioning air main 6 includes inverted U-shaped body passageways 6.1, logical in inverted U-shaped main body
Outwards turnover has horizontal lock portion 6.2 on road two bottom sides side, and in horizontal lock portion, integral middle forms vertically portion 6.3, institute
It is capping sticking department 6.4 that horizontal lock portion is stated in vertically portion right part, and the horizontal lock portion is on the left of vertically portion
Part is decorative panel sticking department 6.5.
Inverted U-shaped body passageways 6.1 are formed in one part, lower openings;It is further preferred that inverted U-shaped body passageways 6.1 are dress
Accessory, transverse slat and two risers, two riser both sides are outwards transferred, and turning point is fixedly connected to form inverted U-shaped body passageways with transverse slat,
Turning point is provided with the top fixed part 6.6 being fixedly connected with roof.
Bottom 8 is fastened on capping sticking department, such air-conditioning air main has reformed into the closed channel that can be divulged information.In U-shaped main body
The both sides decorative panel sticking department of passage 6.1 is respectively arranged with clamping Decorative hanging board 7, and the cross section of the clamping Decorative hanging board 7 is
What is laid flat on one's back is Z-shaped, including integrally formed upper Access Division 7.1 and lower Access Division 7.2 and opposite joint portion 7.3, the card in the left side
The clamping Decorative hanging board for connecing Decorative hanging board and right side is docked and is locked with fixture in opposite joint portion.
Such as Fig. 3 b) shown in, the clamping decorative panel 7 be provided with below bottom buckling parts Horizontal structural members through groove, when main wind
Pipe substitutes Horizontal structural members when installing, and the Horizontal structural members of another vertical direction cross described through groove, the Horizontal structural members
Distance from top bottom 8 lower surface 5-10mm.The width of the air main is not limited by the sizing grid of Horizontal structural members, its
Size freely sets.
It is further preferred that such as Fig. 3 a) shown in be air main cross section another embodiment, the clamping Decorative hanging board 7 wraps
The opposite joint portion for including integrally formed upper Access Division 7.1, lower Access Division 7.2 and being integrally attached between Access Division and lower Access Division
7.3, when the clamping Decorative hanging board in left side and the clamping Decorative hanging board on right side are connected to the both sides of U-shaped body passageways 6, it is described under
The distance between Access Division 7.2 is exactly equal to mesh width when Horizontal structural members intersect, under the clamping Decorative hanging board in left side
Decoration panel, the opposite joint portion of the clamping Decorative hanging board are connected between the lower Access Division of the clamping Decorative hanging board on Access Division and right side
The opposite joint portion of the clamping Decorative hanging board adjacent with right side is fixed.At this moment the grid when width of air main is Horizontal structural members intersection is long
Degree, the height H of air main determine the height of Integral ceiling.
The side of the length direction of the U-shaped body passageways of air-conditioning main air duct is provided with least 2 branch air duct installing ports, installs main air duct
Afterwards, branch air duct can be connected on the branch air duct installing port, and the other end connection of the branch air duct is inlaid on decoration panel
Air diffuser.
The installation of minimum constructive height is fixed to, when mounted, the top of the U-shaped body passageways 6.1 of air-conditioning air main is held out against in house
Top, the air main occupy the position of a Horizontal structural members, solid through the bolt hole of top fixed part 6.6 with expansion bolt
It is scheduled at the top of house.
The installation of scalable Integral ceiling height, when mounted, will not be solid at the top of the top fixed part 6.6 and house of air-conditioning air main
It is fixed, the top nut of phase with vertical installation part is rotated, the screw rod of overall heavy burden part screws the position i.e. scalable in nut, from
And the distance at the top of Horizontal mounting arrangements part and house is the height also scalable of Integral ceiling.
After main air duct is installed, the hollow space between house top board and Horizontal structural members is the space for installing other modules.
The fire alarm module includes water under high pressure supervisor 16, and the water under high pressure supervisor is separately positioned on leaning on for the both sides of air-conditioning air main 6
On the bearing unit on nearly wall side, water under high pressure is responsible for 16 side scion graftings and goes out water under high pressure arm, and the water under high pressure arm connects through Integral ceiling
Connect fire-fighting spraying head 9 and functional column 10.
As shown in Fig. 2 also including water, electricity and gas integrated frame 11, water, electricity and gas integrated frame 11 is mountain font main body, in the middle of the font main body of mountain
For division board 11.1, electric bridge portion 11.2 is provided with the side of division board, be provided with water pipe in the opposite side of division board and install portion 11.3 additional
Portion 11.4 is installed additional with trachea.Water, electricity and gas integrated frame is fixed on bearing unit.The division board 11.1 is formed of an electrically insulating material.
Water pipe installs portion 11.3 additional includes multiple water pipe clips;Trachea installs portion 11.4 additional includes multiple trachea clips.Electric bridge portion is installed with point
Line box, junction box connection spool 11.6, wears Integral ceiling linkage function post 10 under spool 11.6.
On the bearing unit, an avris is fixed with the first water, electricity and gas integrated frame 12, is fixed with the second water, electricity and gas one in another avris
Frame 13.
The forceful electric power module is arranged on the first water, electricity and gas integrated frame 12, and high tension cable is located in the spool, and high tension cable connects
Junction box is connect, under the junction box outlet wiring, Integral ceiling linkage function post 10 is worn.Functional column lower accepting water electric terminal.
The light current module is arranged on the second water, electricity and gas integrated frame 13, and type low-voltage cable is located in the spool of the second water, electricity and gas integrated frame
In, low-voltage cable connection junction box wears Integral ceiling connection suspension type electric-appliance interface module 14 under the junction box outlet wiring.
Meanwhile, water arm 15 is fixed with the water pipe of the first water, electricity and gas integrated frame or the second water, electricity and gas integrated frame installs portion additional,
Gas Pipe is fixed on the first water, electricity and gas integrated frame or the trachea of the second water, electricity and gas integrated frame is installed additional in portion, wears under water pipe and Gas Pipe
Integral ceiling linkage function post, or under water pipe and Gas Pipe, wear Integral ceiling connection suspension type electric-appliance interface module.
The public utility Integral ceiling, integrated level are high, by air-conditioning air main and the structure for cooperating of Horizontal mounting arrangements part
Design ensure that Integral ceiling can accomplish that floor height is minimum, accomplish peace by the combination of the structure design and functional column of water, electricity and gas integrated frame
Fill easy to maintenance.
Claims (10)
1. a kind of public utility Integral ceiling, including including bearing unit (100), functional unit and interface unit, the load-bearing
Unit (100) includes Horizontal mounting arrangements part (2), phase with vertical installation part (3) and some overall heavy burden parts (1), level
The crossover node of mounting structure is connected the phase with vertical installation part (3), it is characterised in that
Overall heavy burden part (1) adjustable ground is fixedly connected the phase with vertical installation part (3), the overall heavy burden part fastening
To on house top board;
The functional unit includes that with wind module, fire alarm module and electricity-water-gas module the functional unit is fixed on bearing unit
(100) top, wears Integral ceiling connecting interface unit under the functional unit;
The wind module includes air-conditioning air main (6), and the air-conditioning air main (6) is mounted horizontally structural member and passes through and support
On Horizontal mounting arrangements part;
The air-conditioning air main (6) includes inverted U-shaped body passageways (6.1), outwards turns on inverted U-shaped body passageways two bottom sides side
Folding has horizontal lock portion (6.2), and in horizontal lock portion, integral middle forms vertically portion (6.3), the horizontal lock portion
In vertically portion, right part is capping sticking department (6.4), and the horizontal lock portion is decoration in vertically portion left part
Plate sticking department (6.5), bottom (8) are fastened in capping sticking department (6.4), are hung down in the both sides of U-shaped body passageways (6.1)
Straight sticking department is connected with clamping Decorative hanging board (7), and the clamping decorative panel (7) is provided through groove below bottom buckling parts,
Horizontal structural members cross described through groove.
2. a kind of public utility Integral ceiling according to claim 1, it is characterised in that in the top margin of U-shaped body passageways
Outwards turnover has top fixed part (6.6) for both sides, and top fixed part (6.6) is fixed at the top of house, floor height of Integral ceiling etc.
In the height (H) of the air-conditioning air main (6).
3. a kind of public utility Integral ceiling according to claim 1, it is characterised in that the clamping Decorative hanging board (7)
Cross section be lay flat on one's back Z-shaped, including integrally formed upper Access Division (7.1), lower Access Division (7.2) and opposite joint portion (7.3),
The clamping Decorative hanging board in the left side and the clamping Decorative hanging board on right side are docked and are locked with fixture, the air-conditioning master in opposite joint portion
The size of the inverted U-shaped body passageways (6.1) of airduct (6) is not limited by the crossover node size of Horizontal mounting arrangements part, institute
State air-conditioning air main and substitute a Horizontal mounting arrangements part, passed through by the Horizontal mounting arrangements part of other direction and be supported on level peace
On assembling structure part.
4. a kind of public utility Integral ceiling according to claim 1, it is characterised in that the clamping Decorative hanging board (7)
Including integrally formed upper Access Division (7.1), lower Access Division (7.2) and opposite joint portion (7.3), when the clamping Decorative hanging board in left side
When being connected to the both sides of U-shaped body passageways (6) with the clamping Decorative hanging board on right side, between the lower Access Division (7.2) away from
From mesh width when intersecting equal to Horizontal structural members, decoration is connected between the lower Access Division of the lower Access Division and right side in left side
Panel.
5. a kind of public utility Integral ceiling according to claim 1, it is characterised in that the electricity-water-gas module includes by force
Electric module, light current module, upper water module and gas module.
6. a kind of public utility Integral ceiling according to claim 5, it is characterised in that also including water, electricity and gas integrated frame (11),
Water, electricity and gas integrated frame (11) is mountain font main body, is division board (11.1), is provided with the side of division board in the middle of the font main body of mountain
Electric bridge portion (11.2), is provided with the opposite side of division board that water pipe installs portion (11.3) additional and trachea installs portion (11.4), water, electricity and gas additional
Integrated frame is fixed on bearing unit, and the electricity-water-gas module is fixed on the water, electricity and gas integrated frame (11).
7. a kind of public utility Integral ceiling according to claim 6 a, it is characterised in that avris on the bearing unit
The first water, electricity and gas integrated frame (12) is fixed with, and the second water, electricity and gas integrated frame (13), the forceful electric power module is fixed with another avris
On the first water, electricity and gas integrated frame (12), high tension cable is located in spool, high tension cable connection junction box, described point
Integral ceiling linkage function post (10), functional column lower accepting water electric terminal are worn under line box outlet wiring;The light current module is arranged on
On second water, electricity and gas integrated frame (13), type low-voltage cable is located in the spool of the second water, electricity and gas integrated frame, low-voltage cable connection point
Line box, wears Integral ceiling connection suspension type electric-appliance interface module (14) under the junction box outlet wiring.
8. a kind of public utility Integral ceiling according to claim 1, it is characterised in that the fire alarm module includes high pressure
Water is responsible for (16), and the water under high pressure supervisor is separately positioned on the bearing unit on the close wall side of the both sides of air-conditioning air main (6),
The other scion grafting of water under high pressure supervisor (16) goes out water under high pressure arm, and the water under high pressure arm is through Integral ceiling connection fire-fighting spraying head (9)
With functional column (10).
9. a kind of public utility Integral ceiling top according to claim 7, it is characterised in that the wind module includes newly
Wind structure, air discharge structure, the fresh air air main (4) of fresh air structure are directly anchored on bearing unit, and by wearing collection under arm
Connect fresh air terminal into furred ceiling;Air draft air main (5) one end of air discharge structure connects air draft by Integral ceiling is worn under vertical arm
Terminal (18), the other end are discharged to outside house through body of wall by air exhaust branch pipe (5.1).
10. a kind of construction method of the public utility Integral ceiling as described in claim 1-9 is arbitrary, it is characterised in that
Comprise the steps:
1) support unit construction, the corner first direction fixed interval in house arrange the first positioning supporting part, solid in second direction
Determine the second positioning supporting part of interval setting, second positioning supporting part is than the low certain distance of the height of the first positioning supporting part;
2) first level structural member is installed, and equidistant is positioned many first level structural members (2.1) parallel in a first direction
On the first positioning supporting part of correspondence;
Wherein, the installation of air-conditioning air main, by first positioning supporting part air-conditioning air main (6) installed therein;
3) the second Horizontal structural members are installed, and are equidistantly positioned at many second Horizontal structural members (2.2) parallel and first direction
On second positioning supporting part of vertical second direction, during installation, the second Horizontal structural members (2.2) cross the air-conditioning air main (6);
Fixed knot (2.3) is installed in first level structural member (2.1) and the second Horizontal structural members (2.2) infall;
4) installation of vertical junction component, installs phase with vertical installation part (3) at the multiple fixed knots of the vertical wall surrounding in house, described
Overall heavy burden part (1) is fixedly connected at the top of phase with vertical installation part (3), at least 3 swell fixtures (1.3) are through the groove
Shape installing hole is fixed on floor;
5) Dingan County fills ceiling height really, when being fixed to minimum constructive height installation, by the inverted U-shaped body passageways (6.1) of air-conditioning air main
Top hold out against at the top of house, be fixed at the top of house through the bolt hole of top fixed part (6.6) with expansion bolt;
Or, when scalable Integral ceiling is highly installed, will not be solid at the top of the top fixed part (6.6) of air-conditioning air main and house
It is fixed, the top nut of phase with vertical installation part is rotated, adjustable range labelling is carried out on the screw rod of overall heavy burden part, adjust all
The screw rod of overall heavy burden part screws position in nut to sustained height labelling;
6) interface unit is connected to functional unit by the hollow space installation function unit between house top board and Horizontal structural members
On;
7) remove the support unit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610339026.8A CN106545117B (en) | 2016-05-19 | 2016-05-19 | A kind of public utility Integral ceiling and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610339026.8A CN106545117B (en) | 2016-05-19 | 2016-05-19 | A kind of public utility Integral ceiling and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106545117A true CN106545117A (en) | 2017-03-29 |
CN106545117B CN106545117B (en) | 2019-07-09 |
Family
ID=58364938
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610339026.8A Active CN106545117B (en) | 2016-05-19 | 2016-05-19 | A kind of public utility Integral ceiling and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106545117B (en) |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108590012A (en) * | 2018-06-01 | 2018-09-28 | 北京亚都新风净化工程技术有限公司 | A kind of furred ceiling overhaul of the equipments panel connector |
CN109750783A (en) * | 2018-12-29 | 2019-05-14 | 天津永利达盛实验室设备有限公司 | A kind of physical and chemical raw laboratory integration Lift-on/Lift-off System |
WO2019218170A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Method for construction of suspended ceiling system |
WO2019218212A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Suspended ceiling system having separated water pipe and electrical cable |
WO2019218209A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe and high-voltage cable installed therein |
WO2019218182A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage cable installed therein |
WO2019218211A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage and low-voltage cables installed therein |
WO2019218228A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage and low-voltage cables installed therein |
WO2019218238A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe and high-voltage cable installed therein |
WO2019218253A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Suspended ceiling system having separated water pipe and electrical cable |
WO2019218233A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Construction method for house having water pipe separate from main structure |
CN110499861A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN110499860A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN111148882A (en) * | 2018-05-16 | 2020-05-12 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with water pipe and weak current electric wire |
CN111576715A (en) * | 2020-05-21 | 2020-08-25 | 武汉市研华智造环保科技有限公司 | Triangular keel of electric wire constraint structure |
WO2020252199A1 (en) * | 2019-06-12 | 2020-12-17 | Overcast Innovations Llc | Utility connection systems, splines, and associated methods |
CN112313384A (en) * | 2018-05-16 | 2021-02-02 | 增城市碧桂园物业发展有限公司 | Suspended ceiling |
CN112313383A (en) * | 2018-05-16 | 2021-02-02 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with water pipe and weak current electric wire |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0570295A1 (en) * | 1992-05-13 | 1993-11-18 | Guy Hosteing | Profiles for supporting and tensioning a false ceiling or wall |
JPH06213487A (en) * | 1992-12-17 | 1994-08-02 | Internatl Business Mach Corp <Ibm> | Plenum module device |
JP2006299778A (en) * | 2005-04-22 | 2006-11-02 | Matsushita Denko Bath & Life Kk | Joining structure of ceiling panel and wall panel |
CN102261151A (en) * | 2011-05-10 | 2011-11-30 | 北京建工博海建设有限公司 | Bar-type air outlet, silencing plenum box and grille lamp combined suspended ceiling and construction method thereof |
CN203547001U (en) * | 2013-09-26 | 2014-04-16 | 陈正义 | Integration belt |
CN204081193U (en) * | 2014-09-24 | 2015-01-07 | 邹建林 | A kind of Integral ceiling wind outlet unit and installation of ceiling component |
CN205777006U (en) * | 2016-05-19 | 2016-12-07 | 武汉科贝科技股份有限公司 | A kind of public utility Integral ceiling |
-
2016
- 2016-05-19 CN CN201610339026.8A patent/CN106545117B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0570295A1 (en) * | 1992-05-13 | 1993-11-18 | Guy Hosteing | Profiles for supporting and tensioning a false ceiling or wall |
JPH06213487A (en) * | 1992-12-17 | 1994-08-02 | Internatl Business Mach Corp <Ibm> | Plenum module device |
JP2006299778A (en) * | 2005-04-22 | 2006-11-02 | Matsushita Denko Bath & Life Kk | Joining structure of ceiling panel and wall panel |
CN102261151A (en) * | 2011-05-10 | 2011-11-30 | 北京建工博海建设有限公司 | Bar-type air outlet, silencing plenum box and grille lamp combined suspended ceiling and construction method thereof |
CN203547001U (en) * | 2013-09-26 | 2014-04-16 | 陈正义 | Integration belt |
CN204081193U (en) * | 2014-09-24 | 2015-01-07 | 邹建林 | A kind of Integral ceiling wind outlet unit and installation of ceiling component |
CN205777006U (en) * | 2016-05-19 | 2016-12-07 | 武汉科贝科技股份有限公司 | A kind of public utility Integral ceiling |
Cited By (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110499860A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN112313384A (en) * | 2018-05-16 | 2021-02-02 | 增城市碧桂园物业发展有限公司 | Suspended ceiling |
WO2019218170A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Method for construction of suspended ceiling system |
WO2019218212A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Suspended ceiling system having separated water pipe and electrical cable |
WO2019218209A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe and high-voltage cable installed therein |
WO2019218182A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage cable installed therein |
WO2019218211A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage and low-voltage cables installed therein |
WO2019218228A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage and low-voltage cables installed therein |
WO2019218238A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe and high-voltage cable installed therein |
WO2019218253A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Suspended ceiling system having separated water pipe and electrical cable |
WO2019218233A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Construction method for house having water pipe separate from main structure |
CN112313383A (en) * | 2018-05-16 | 2021-02-02 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with water pipe and weak current electric wire |
CN111148882A (en) * | 2018-05-16 | 2020-05-12 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with water pipe and weak current electric wire |
CN110730849A (en) * | 2018-05-16 | 2020-01-24 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with water pipes and strong-current electric wires |
CN110499861A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN111164267A (en) * | 2018-05-16 | 2020-05-15 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with water pipes and strong-current electric wires |
CN112236569A (en) * | 2018-05-16 | 2021-01-15 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with strong current and weak current wires |
CN112218991A (en) * | 2018-05-16 | 2021-01-12 | 增城市碧桂园物业发展有限公司 | Ceiling system provided with strong current and weak current wires |
CN112189075A (en) * | 2018-05-16 | 2021-01-05 | 东莞市碧桂园房地产开发有限公司 | Construction method of house with water pipe and main body structure separated |
CN108590012A (en) * | 2018-06-01 | 2018-09-28 | 北京亚都新风净化工程技术有限公司 | A kind of furred ceiling overhaul of the equipments panel connector |
CN109750783A (en) * | 2018-12-29 | 2019-05-14 | 天津永利达盛实验室设备有限公司 | A kind of physical and chemical raw laboratory integration Lift-on/Lift-off System |
WO2020252199A1 (en) * | 2019-06-12 | 2020-12-17 | Overcast Innovations Llc | Utility connection systems, splines, and associated methods |
US12070639B2 (en) | 2019-06-12 | 2024-08-27 | Overcast Innovations Llc | Utility connection systems, splines, and associated methods |
CN111576715A (en) * | 2020-05-21 | 2020-08-25 | 武汉市研华智造环保科技有限公司 | Triangular keel of electric wire constraint structure |
Also Published As
Publication number | Publication date |
---|---|
CN106545117B (en) | 2019-07-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106545117A (en) | A kind of public utility Integral ceiling and its construction method | |
US7952022B2 (en) | Dual access luminaire junction box | |
CN102041864A (en) | Support keel of integrated ceiling, unit buckle, electrical appliance module and installation method thereof | |
EA013848B1 (en) | Display for public use | |
CN111321838B (en) | Heat insulation building suspended ceiling with ventilation effect | |
CN209100786U (en) | A kind of rail traffic non-packed repairs suspension and support integration system of standing | |
CN205777006U (en) | A kind of public utility Integral ceiling | |
US20150159824A1 (en) | Assemblies and methods for mounting electrical fixtures to suspended ceilings | |
CN112554425A (en) | Fall-level ceiling connecting piece capable of being installed rapidly, ceiling system and installation method | |
CN112411859A (en) | Modular furred ceiling keel structure for interior decoration | |
CN106381976B (en) | The installation system and installation method of metal 3 D stereo decorative panel | |
CN210263600U (en) | Suspended ceiling mounting structure | |
CN202899393U (en) | Unit assembly type suspended ceiling connection structure | |
CN212001863U (en) | Passageway furred ceiling mounting structure | |
CN206099216U (en) | Automatic change regulator cubicle | |
CN206041258U (en) | Equipment distribution box | |
CN206467866U (en) | A kind of electric appliance installing structure of Integral ceiling | |
CN108130974B (en) | Top wall integrated partition structure capable of freely partitioning indoor space | |
CN106553658B (en) | A kind of seat pencil routing method used for rail vehicle and wire structures | |
CN205807324U (en) | LED lamp panel surface frame | |
CN206174256U (en) | Corridor passageway furred ceiling | |
CN216865672U (en) | Suspended ceiling assembling structure | |
CN205806958U (en) | A kind of LED lamp panel surface frame | |
CN219261486U (en) | House integrated furred ceiling convenient to dismantle | |
CN209277453U (en) | A kind of metal finishing box furred ceiling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: An integrated suspended ceiling for public facilities and its construction method Effective date of registration: 20230420 Granted publication date: 20190709 Pledgee: Bank of China Limited Ezhou branch Pledgor: WUHAN KEBEI TECHNOLOGY CO.,LTD. Registration number: Y2023420000168 |