CN106524776A - Method for blowing out submerged arc furnace for long time to protect electrode - Google Patents
Method for blowing out submerged arc furnace for long time to protect electrode Download PDFInfo
- Publication number
- CN106524776A CN106524776A CN201610909848.5A CN201610909848A CN106524776A CN 106524776 A CN106524776 A CN 106524776A CN 201610909848 A CN201610909848 A CN 201610909848A CN 106524776 A CN106524776 A CN 106524776A
- Authority
- CN
- China
- Prior art keywords
- electrode
- time
- power failure
- star
- hours
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F27—FURNACES; KILNS; OVENS; RETORTS
- F27D—DETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
- F27D19/00—Arrangements of controlling devices
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F27—FURNACES; KILNS; OVENS; RETORTS
- F27D—DETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
- F27D11/00—Arrangement of elements for electric heating in or on furnaces
- F27D11/08—Heating by electric discharge, e.g. arc discharge
- F27D11/10—Disposition of electrodes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Furnace Details (AREA)
- Discharge Heating (AREA)
Abstract
The invention discloses a method for blowing out a submerged arc furnace for a long time to protect an electrode. The method comprises the following steps of: controlling electrode length and an electrode position before power failure; and after power failure, carrying out operations such as thermal insulation, anti-oxidization work and regulation on a power supply system after power transmission on the electrode. On one hand, electrode hard breakage probability caused by furnace long-time blowout is reduced, so that positive effects are brought for cost decreasing and benefit increasing of enterprises; on the other hand, unnecessary workload of staff is reduced by reducing electrode hard breakage times, so that safety risks are reduced.
Description
Technical field
The present invention relates to ore smelting technical field, more particularly to a kind of side of mineral hot furnace long-time protection of boiler during shutdown period electrode
Method.
Background technology
Easily there is electrode hard broken accident to blowing out more than 8 hours electrodes in power transmission recovery process in tradition.Cause blowing out and
The rising of production cost.To preventing the pre- of electrode hard broken accident to prevent and kill off outside the management that intensifier electrode is pasted(It is dust-proof), mainly take two
Individual measure:One is to select optimum electrode paste formula, and another is to reduce heat to stop.The electrode paste of self-baking electrode during baking,
Because the binding agent after coking is intended to shrink, and the solid material filled is stable at such a temperature.The difference of these physical propertys
Material internal is not caused to produce thermal stress:Solid particle is subject to compression stress, and the binding agent after coking is stretched stress.
My 25MW ferrosilicon mineral hot furnace 2014 of unit two, long-time blowing out rear electrode in 2015 respectively it is hard it is disconnected 28 times, 20
Secondary, 4,750,000 yuan of direct economic loss is produced a very large impact to the benefit of company.
The content of the invention
A kind of method of mineral hot furnace long-time protection of boiler during shutdown period electrode, comprises the following steps:
Step one:To electrode length, the control of electrode position before having a power failure:According to the length of repair time, in advance to Electrode Fluctuation
Amount is controlled and consumption of electrode is short;The natural perpendicularity of adjustment electrode is carried out;Electrode Pressure Slipping Volume stop after, electrode transfer to
Between 500mm-800mm;
Step 2:Electrode is carried out being incubated after power failure, anti-oxidation work:Supplement furnace charge and increase charge level in stove, while will with furnace charge
Electrode is buried;Brasses discharge is adjusted to the 1/3 of normal brasses discharge;Increase the height of paste column;Per phase electrode decentralization 200-
300mm;
Step 3:Power supply system is adjusted after power transmission:Power off time adopted the direct power transmission of corner connection within 8 hours;Power failure 8
When between hour to 24 hours, mode power transmission is connect using star, star connects 1/2 control of the firing electrodes time by actual furnace outage time,
Switch to corner connection roasting after stable;When having a power failure more than 24 hours, mode power transmission is connect using star, star connects the firing electrodes time by actually stopping
1/2 to 1/3 control of stove time, switchs to corner connection roasting after stablizing.
Beneficial effects of the present invention:On the one hand reduce because long-time blowing out causes the probability of electrode hard breakage, be that this drops in company
Potentiation, reduces cost bring positive role, and the number of times on the other hand reducing electrode hard breakage reduces the unnecessary workload of worker, drop
Lower security risk.
Specific embodiment:
A kind of method of mineral hot furnace long-time protection of boiler during shutdown period electrode, comprises the following steps:
Step one:To electrode length, the control of electrode position before having a power failure:According to the length of repair time, in advance to Electrode Fluctuation
Amount is controlled and by consumption of electrode short to mitigate the impact that electrode is conducted oneself with dignity;It is adjusted for electrode deflection, it is ensured that electricity
The natural perpendicularity of pole, prevents electrode from causing electrode hard breakage because deflection produces reciprocal active force;After Electrode Pressure Slipping Volume stops,
Electrode is transferred between 500mm-800mm, reduces the naked leakage area of electrode, anti-oxidation;In the 4th stove ferrum level-lowering after rolling
To below furnace shell 300mm, it is that shutdown maintenance is ready;
Step 2:Electrode is carried out being incubated after power failure, anti-oxidation work:Supplement furnace charge and increase in stove charge level to reduce stove interior temperature
Degree, while buried electrode with furnace charge;Brasses discharge is adjusted to the 1/3 of normal brasses discharge, reduces the thermal loss of electrode;
Increase the height of paste column to improve the consistency of firing electrodes;Electrode oxygen in recovery process is prevented per phase electrode decentralization 200-300mm
Change;
Step 3:Power supply system is adjusted after power transmission:
1. power off time is within 8 hours;
1.1 power off times in principle can be with the direct power transmission of corner connection within 8 hours.Mode is connect using star more than 8 hours in principle
Power transmission.
Three-phase electrode naked leakage part is all buried after power transmission by 1.2 as far as possible, anti-oxidation.
If without hipocratic face after 1.3 power transmissions, principle whether go up lift electrode.
2nd, have a power failure more than 8 hours, less than 24 hours;
2.1 have a power failure more than 8 hours, by the way of star picks electricity
2.2 shutdown maintenances are less than 24 hours, and star connects 1/2 control of the firing electrodes time by actual furnace outage time.Star picks electricity
Roasting time is controlled within the 1/2 of actual furnace outage time, when electrode load rises to Y1 levels or basically reaches the invariable power stage(Three
Phase electrode secondary side voltage is constant current in 129-177, is invariable power during 177-216)When, stop after stablizing more than 20 minutes
Stove prepares star and switches through corner connection work, into corner connection firing stage.
3rd, the long-time blowing out having a power failure more than 24 hours;
3.1 have a power failure more than 24 hours, by the way of star picks electricity;
More than 24 hours, star connect 1/2 to 1/3 control of the firing electrodes time by actual furnace outage time to 3.2 shutdown maintenances, specifically
With reference to furnace outage time, general star connect the time less than 30 hours.Star picks electric roasting time control the 1/ of actual furnace outage time
Within 2, when electrode load rises to Y1 levels or the invariable power stage is basically reached(Three-phase electrode secondary side voltage in 129-177 is
Constant current, is invariable power during 177-216)When, blowing out after stablizing more than 20 minutes prepares star and switches through corner connection work, into corner connection
Firing stage.
Since the method shield electrode was used from 2016, during in March, 2016-August, monthly count more than 8 hours
Draw maintenance and electrode hard broken accident does not occur, my company 3# ferrosilicon mineral hot furnace is because electrical network, transformer fault blowing out are more than 140 hours
More than, there is no accident of breaking firmly in electrode yet.
Claims (1)
1. a kind of method of mineral hot furnace long-time protection of boiler during shutdown period electrode, it is characterised in that comprise the following steps:
Step one:To electrode length, the control of electrode position before having a power failure:According to the length of repair time, in advance to Electrode Fluctuation
Amount is controlled and consumption of electrode is short;The natural perpendicularity of adjustment electrode;Electrode Pressure Slipping Volume stop after, electrode transfer to
Between 500mm-800mm;
Step 2:Electrode is carried out being incubated after power failure, anti-oxidation work:Supplement furnace charge and increase charge level in stove, while will with furnace charge
Electrode is buried;Brasses discharge is adjusted to the 1/3 of normal brasses discharge;Increase the height of paste column;Electrode transfers 200-300mm;
Step 3:Power supply system is adjusted after power transmission:Power off time adopted the direct power transmission of corner connection within 8 hours;Power failure 8
When between hour to 24 hours, mode power transmission is connect using star, star connects 1/2 control of the firing electrodes time by actual furnace outage time,
Switch to corner connection roasting after stable;When having a power failure more than 24 hours, mode power transmission is connect using star, star connects the firing electrodes time by actually stopping
1/2 to 1/3 control of stove time, switchs to corner connection roasting after stablizing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610909848.5A CN106524776B (en) | 2016-10-19 | 2016-10-19 | A kind of method of mineral hot furnace long-time protection of boiler during shutdown period electrode |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610909848.5A CN106524776B (en) | 2016-10-19 | 2016-10-19 | A kind of method of mineral hot furnace long-time protection of boiler during shutdown period electrode |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106524776A true CN106524776A (en) | 2017-03-22 |
CN106524776B CN106524776B (en) | 2019-03-08 |
Family
ID=58332995
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610909848.5A Active CN106524776B (en) | 2016-10-19 | 2016-10-19 | A kind of method of mineral hot furnace long-time protection of boiler during shutdown period electrode |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106524776B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110553511A (en) * | 2019-09-10 | 2019-12-10 | 石横特钢集团有限公司 | Method for preventing electrode from being hard broken in peak avoiding production of submerged arc furnace |
CN113108607A (en) * | 2021-04-15 | 2021-07-13 | 嘉峪关宏电铁合金有限责任公司 | Quick repairing process for lining of silicomanganese ore heating furnace with super furnace age |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS635673B2 (en) * | 1984-09-28 | 1988-02-04 | Nippon Mining Co | |
CN201326032Y (en) * | 2008-12-11 | 2009-10-14 | 上海森和投资有限公司 | Silicon core electrode for polysilicon reducing furnace |
CN201666933U (en) * | 2010-04-20 | 2010-12-08 | 宝山钢铁股份有限公司 | Electrode insulation detecting device for three-phase AC electric arc furnace |
-
2016
- 2016-10-19 CN CN201610909848.5A patent/CN106524776B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS635673B2 (en) * | 1984-09-28 | 1988-02-04 | Nippon Mining Co | |
CN201326032Y (en) * | 2008-12-11 | 2009-10-14 | 上海森和投资有限公司 | Silicon core electrode for polysilicon reducing furnace |
CN201666933U (en) * | 2010-04-20 | 2010-12-08 | 宝山钢铁股份有限公司 | Electrode insulation detecting device for three-phase AC electric arc furnace |
Non-Patent Citations (3)
Title |
---|
李宏志等: "《热停炉电极硬断原因的分析与预防》", 《铁合金》 * |
王光胜等: "《角接快速电极焙烧法的实践》", 《铁合金》 * |
黄海胜等: "《12 .5MVA电炉自焙电极的维护管理与事故探讨》", 《铁合金》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110553511A (en) * | 2019-09-10 | 2019-12-10 | 石横特钢集团有限公司 | Method for preventing electrode from being hard broken in peak avoiding production of submerged arc furnace |
CN113108607A (en) * | 2021-04-15 | 2021-07-13 | 嘉峪关宏电铁合金有限责任公司 | Quick repairing process for lining of silicomanganese ore heating furnace with super furnace age |
Also Published As
Publication number | Publication date |
---|---|
CN106524776B (en) | 2019-03-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205231835U (en) | Structure for large -scale thermal power factory unit high pressure service power each other is being equipped with | |
CN102222893B (en) | A kind of fast failure demand limiter based on current-carrying isolator | |
CN203504285U (en) | UPS integrated power supply | |
CN101552462A (en) | Black-start method | |
CN106524776A (en) | Method for blowing out submerged arc furnace for long time to protect electrode | |
CN205489506U (en) | Thunder and lightning protection circuit for high voltage direct current power supply system | |
CN208521887U (en) | A kind of electronic fuse switch equipped with arc extinguishing structure | |
CN208781801U (en) | A kind of safety-type fuse | |
CN204100290U (en) | A kind of high-energy electronic igniter circuit | |
CN204332866U (en) | A kind of safety device for high-voltage power equipment being provided with shell fragment | |
CN208285234U (en) | A kind of high-power rectifying device, direct current change poles system and a kind of direct current smelting furnace | |
CN104505313B (en) | It is provided with the safety device for high-voltage power equipment of shell fragment | |
CN207542021U (en) | A kind of dropproof formula arrester | |
CN207338959U (en) | A kind of novel high-pressure incoming line cabinet | |
CN205489034U (en) | Block terminal device of oven | |
CN204376423U (en) | A kind of switch combination for quick deciliter of micro-grid connection point | |
CN209183494U (en) | A kind of highly-safe high-tension fuse structure | |
CN204633240U (en) | A kind of LF stove water-cooled cable anchor ear | |
CN202127247U (en) | Discharge device for capacitor | |
CN204332867U (en) | A kind of safety device for high-voltage power equipment | |
CN202792929U (en) | Full-automatic high-temperature tunnel type sintering kiln | |
CN204204782U (en) | Electricapparatus fuse | |
CN102110554B (en) | Protective device for high-voltage power equipment | |
CN204012734U (en) | A kind of 10kV pole-mounted reactive compensation device | |
CN203387184U (en) | Submerged arc furnace transformer device with series compensation devices |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |