Test method and system of automobile controller Download PDF

Info

Publication number
CN106502235B
CN106502235B CN201610929458.4A CN201610929458A CN106502235B CN 106502235 B CN106502235 B CN 106502235B CN 201610929458 A CN201610929458 A CN 201610929458A CN 106502235 B CN106502235 B CN 106502235B
Authority
CN
China
Prior art keywords
test
client
task
test task
establishing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610929458.4A
Other languages
Chinese (zh)
Other versions
CN106502235A (en
Inventor
陈慧勃
代康伟
黄颍华
张俊
张玉盼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Electric Vehicle Co Ltd
Original Assignee
Beijing Electric Vehicle Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Electric Vehicle Co Ltd filed Critical Beijing Electric Vehicle Co Ltd
Priority to CN201610929458.4A priority Critical patent/CN106502235B/en
Publication of CN106502235A publication Critical patent/CN106502235A/en
Application granted granted Critical
Publication of CN106502235B publication Critical patent/CN106502235B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B23/00Testing or monitoring of control systems or parts thereof
    • G05B23/02Electric testing or monitoring

Abstract

The invention provides a method and a system for testing an automobile controller, wherein the method comprises the following steps: acquiring a test task establishing instruction from a first role user in a client, establishing a test task according to the test task establishing instruction, and distributing the test task to a second role user in the client; acquiring a test case creating operation from a second role user in a client, and creating a test case in the test task according to the test case creating operation; and controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client. The scheme improves the convenience in the automobile test work and improves the efficiency for the test work of testers.

Description

Test method and system of automobile controller
Technical Field
The invention relates to the technical field of device testing, in particular to a testing method and a testing system of an automobile controller.
Background
The automobile controller is an important part in the production, manufacture and use of automobiles, and the quality of the performance of the automobile controller has great direct influence on the overall performance of the automobile. In order to ensure that the functions and the operation and use conditions of the automobile controller are good, the automobile controller needs to be tested to detect whether the automobile controller has problems or not so as to ensure the good performance of the overall design. In the testing process, particularly hardware-in-the-loop (HIL) testing, a tester usually needs to stay in a laboratory for a long time to establish, execute and track a testing task and manage and monitor testing equipment, task allocation and testing communication are realized by oral communication of all responsibility personnel, remote control testing cannot be realized, the problem that the tracking of the testing problem cannot achieve real-time performance, testing cannot be performed without a laboratory environment, the problem that management work such as testing process approval consumes a long period and the like, time is consumed, and testing efficiency is seriously influenced exists.
Disclosure of Invention
The embodiment of the invention provides a test method and a test system for an automobile controller, and aims to solve the problems that remote control test cannot be realized, test problem tracking cannot be realized in real time, test work cannot be executed without a laboratory environment, management work such as test flow approval consumes a long period, and test efficiency is influenced in the prior art.
In order to solve the technical problem, the embodiment of the invention adopts the following technical scheme:
in one aspect, an embodiment of the present invention provides a method for testing an automobile controller, including:
acquiring a test task establishing instruction from a first role user in a client, establishing a test task according to the test task establishing instruction, and distributing the test task to a second role user in the client;
acquiring a test case creating operation from a second role user in a client, and creating a test case in the test task according to the test case creating operation;
and controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client.
Optionally, the step of establishing a test task according to the test task establishment instruction includes:
according to the test task establishing instruction, obtaining a test type and test time;
determining target test equipment according to the test type, the test time and the current running state of the test equipment;
and establishing a test task comprising the test type, the test time and the target test equipment.
Optionally, the step of establishing a test task according to the test task establishment instruction further includes:
pushing the obtained display information to the client to display the information at the client;
the display information includes: the test type, the test time, the current running state of the test equipment and the determined target test equipment.
Optionally, when the test task is assigned to a second role user in the client, the test method further includes:
and sending a notification message to the second role user through an instant communication channel.
Optionally, the step of controlling the test device to execute the test task according to the test case includes:
acquiring the priority of the test task;
and controlling the test equipment to execute the test task according to the test case and the priority of the test task.
Optionally, when the test result is fed back to the client, the test method further includes:
and feeding back the question item in the test result to the first role user in the client through an instant communication channel.
Optionally, before the step of obtaining a test task establishment instruction from a first persona user in a client and establishing a test task according to the test task establishment instruction, the test method further includes:
acquiring a test task application request from a third role user in a client;
and sending a notification message of the test task application to the first role user in the client according to the test task application request.
Optionally, after the step of feeding back the question item in the test result to the first persona user in the client through an instant communication channel, the test method further includes:
acquiring a question item distribution instruction of the first role user from a client;
and distributing the question item to the third triangular color user in the client according to the question item distribution instruction.
On the other hand, an embodiment of the present invention further provides a test system for an automobile controller, including:
the system comprises a test task establishing and distributing module, a test task establishing and distributing module and a test task distributing module, wherein the test task establishing and distributing module is used for acquiring a test task establishing instruction from a first role user in a client, establishing a test task according to the test task establishing instruction and distributing the test task to a second role user in the client;
the test case creating module is used for acquiring a test case creating operation from a second role user in the client, and creating a test case in the test task according to the test case creating operation;
and the test execution and feedback module is used for controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client.
Optionally, the test task creating and distributing module includes:
the obtaining submodule is used for establishing an instruction according to the test task and obtaining a test type and test time;
the determining submodule is used for determining target test equipment according to the test type, the test time and the current running state of the test equipment;
and the establishing submodule is used for establishing a test task containing the test type, the test time and the target test equipment.
Optionally, the test task creating and distributing module further includes:
the pushing submodule is used for pushing the obtained display information to the client so as to display the information at the client;
the display information includes: the test type, the test time, the current running state of the test equipment and the determined target test equipment.
Optionally, when the test task is assigned to a second role user in the client, the test system further includes:
and the first sending module is used for sending a notification message to the second role user through an instant communication channel.
Optionally, the test execution and feedback module includes:
the obtaining submodule is used for obtaining the priority of the test task;
and the execution submodule is used for controlling the test equipment to execute the test task according to the test case and the priority of the test task.
Optionally, when the test result is fed back to the client, the test system further includes:
and the feedback module is used for feeding back the question items in the test results to the first role user in the client through an instant communication channel.
Optionally, the test system further comprises:
the first acquisition module is used for acquiring a test task application request from a third role user in the client;
and the second sending module is used for sending a notification message of the test task application to the first role user in the client according to the test task application request.
Optionally, the test system further comprises:
the second acquisition module is used for acquiring a question item distribution instruction of the first role user from the client;
and the distribution module is used for distributing the question item to the third triangle users in the client according to the question item distribution instruction.
One or more embodiments of the present invention have the following advantageous effects:
according to the embodiment of the invention, a test task is established according to an obtained test task establishment instruction from a first role user in a client, and the test task is distributed to a second role user in the client; acquiring a test case creating operation from a second role user in a client, and creating a test case in the test task; controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client; can realize long-range automatic HIL test to automobile controller, realize remote automatic test, carry out propelling movement and distribution of task between different role users, through the operation of the different users of customer end, make automobile controller's test task's implementation process, operating personnel need not confine to the laboratory, can make HIL test work more high-efficient, the tester time is more free, the testing device utilization ratio is higher, the convenience in the automobile test work has been improved, for tester test work raises the efficiency.
Drawings
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
FIG. 1 is a flow chart illustrating a testing method of an automobile controller according to a first embodiment of the present invention;
fig. 2 is a block diagram showing a test system of an automobile controller according to a first embodiment of the present invention;
fig. 3 is a block diagram showing an overall schematic diagram of a test system of an automobile controller according to an embodiment of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
First embodiment
The embodiment of the invention provides a method for testing an automobile controller, which is shown in fig. 1 and 3 and comprises the following steps:
step 101: the method comprises the steps of obtaining a test task establishing instruction from a first role user in a client, establishing a test task according to the test task establishing instruction, and distributing the test task to a second role user in the client.
The client can be a remote webpage control interface, and the system specifically acquires a test task establishment instruction from a first role user in the remote webpage control interface. In the process, multiple user roles can be provided for the client, the first role user is specifically a test task manager role and has more operation permissions, and the second role user can be a common tester user, specifically a designer user of a test case and has relatively fewer permissions. The setting of the different roles can be realized by leading in the users with different roles in batches through a system administrator, adding, deleting, modifying and checking user information, and setting the role authority.
After logging in a remote webpage interface, a test task manager carries out new test tasks, the system acquires a test task establishment instruction of the first role user, establishes the test tasks, and distributes the test tasks to designer users of test cases after successful establishment, so that the related users can complete the establishment of the test cases in time when checking the tasks.
As a preferred embodiment, the step of establishing the test task according to the test task establishment instruction includes:
establishing an instruction according to the test task to obtain a test type and test time; determining target test equipment according to the test type, the test time and the current running state of the test equipment; and establishing a test task comprising the test type, the test time and the target test equipment.
When a test task establishment instruction is obtained, the requirement information of the task required to be established in the task establishment instruction is obtained according to the instruction, the requirement information comprises the test type and the test time of the test task, and the system can select proper idle test equipment to execute the test task according to the test type, the test time and the running state of the test equipment. The operation state of the test equipment comprises an enabling state, an off-line state, an idle state, a fault state, an operation state and the like of the test equipment.
Specifically, the role user with authority, for example, the first role user in the client, that is, the role of the test task manager, or the system administrator, may set the operation state of the device, may set information such as the type of the controller mounted on the test device, the load configuration condition, and the like, and may also automatically count the utilization rate of the device and the test frequency of the project, so as to perform daily data statistics on test jobs of different projects.
As a specific implementation manner, the step of establishing a test task according to the test task establishment instruction further includes: pushing the obtained display information to the client to display the information at the client; the display information includes: the test type, the test time, the current running state of the test equipment and the determined target test equipment.
The client corresponds to a front-end webpage interface in the system, is responsible for providing a concise and large-size interface, visually displays test data, user information and the like, responds to user operation, sends a request to the server, and returns a result to be displayed to a user after the request is processed by the server.
As a specific implementation manner, when the test task is assigned to the second role user in the client, the test method further includes: and sending a notification message to the second role user through an instant communication channel.
The instant communication channel includes but is not limited to: WeChat, mail and the like. Different role users provided by the system can bind own instant messaging account number with the system account number, set the preferred mode of receiving the notification information, and set whether the user needs mail or WeChat reminding in the system setting. When the reminding is set to be required, the system informs the user of the necessary message in the form of the mail or the WeChat according to the running condition of the system. And the notification message is sent to the second role user through an instant communication channel, so that related personnel can timely acquire the message and timely arrange and process related tasks even if the second role user is not in a laboratory or in front of a computer.
Specifically, in the process, after logging in a remote web interface, a first role user in a client performs a new test task, and a specific test task establishment operation may be to select a test type and test time to be tested, click to select usable test equipment determined according to the conditions, click to issue a task, send a test task establishment instruction, distribute the test task to a test case designer user side by a system after the click to issue the task, and notify the role user in a WeChat or email mode.
Step 102: and acquiring a test case creating operation from a second role user in the client, and creating the test case in the test task according to the test case creating operation.
The execution process of the test case creating operation can be to receive the uploading operation of the second role user, acquire the test case uploaded to the test system, establish a corresponding file and complete the test case creating process.
Step 103: and controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client.
When a user uploads a test case and completes the creation of the test case, the test equipment can be controlled to perform static analysis on the test case according to a preset algorithm, or coverage analysis is performed by providing three inputs of hard line configuration, a preset database file and the test case, and a test result is given.
The test output matter is specifically a test report, and after the test is finished, the test result can be automatically uploaded to the server, and the test report can be automatically generated. One device can correspond to a plurality of test tasks, but one test task can correspond to only one test device. Specifically, the control of the test equipment is that the server side transmits a control instruction to a controller of the test equipment, namely, an upper computer, so that the test equipment executes a test task, the upper computer is responsible for communicating with the server side, receives task scheduling from the server side, drives the test equipment to perform automatic test work, and returns a processed test result to the server side after the test is completed, so that the server feeds the result back to the client side for a user to process.
In order to record the document of the test process, the system provides a test log, a test plan and a filling interface of system requirements according to requirements. During the test process, the system provides a series of data statistics and analysis modules for the reference of test related personnel.
As a specific implementation manner, the step of controlling the testing device to execute the testing task according to the test case includes: acquiring the priority of the test task; and controlling the test equipment to execute the test task according to the test case and the priority of the test task.
The first role user in the client can set the priority of the test task aiming at a certain device, when the system control task is executed, the test device is controlled to test according to the priority of the test task, the insertion of the emergency task can be supported by setting the priority of the test task, when the emergency task is met, the emergency task is set to be the highest priority, when the system audit is passed, the current test task of a certain test device is temporarily or delayed, and the task needing to be emergently operated is inserted.
As a specific implementation manner, when the test result is fed back to the client, the test method further includes: and feeding back the question item in the test result to the first role user in the client through an instant communication channel.
The test report comprises a True item and a false item, wherein the false item can be notified to a test responsible person through a WeChat mail, namely, a first role user, the test responsible person can confirm the received information and timely arrange, process and correct, so that interaction processing among role personnel is more convenient, the processing flow of the test is accelerated, and the test efficiency is improved.
Specifically, the feedback reminding process may be that the feedback can remind the person in charge of the message to be signed of the false item, the sign is recorded for reminding, and the person affected is reminded when the task changes. The responsible person can actively initiate operations through the WeChat end, such as: inquiring the running condition of the test equipment; and carrying out signing on the task to be signed.
As a specific implementation manner, before the step of obtaining a test task establishment instruction from a first persona user in a client, and establishing a test task according to the test task establishment instruction, the test method further includes: acquiring a test task application request from a third role user in a client; and sending a notification message of the test task application to the first role user in the client according to the test task application request.
The third role user in the client can be a developer user of the automobile controller in the system and becomes a test task applicant, and before a new task is built, the test applicant can apply for a test task. (including test type setting, filling in project name and controller name, uploading function definition, controller local area network bus CAN protocol, database dbc file and hard line interface file). The client can be a webpage client, and supports the reservation of the test resources through the webpage, so that the first role user can conveniently establish the test task at a proper moment according to the reservation. Specifically, the system can display the type, the running state and the reservation state of the test equipment at the client, and after a user clicks a certain test equipment, the test execution current situation and the running state of the equipment are displayed.
As a specific implementation manner, after the step of feeding back the question item in the test result to the first persona user in the client through an instant communication channel, the test method further includes:
acquiring a question item distribution instruction of the first role user from a client; and distributing the question item to the third triangular color user in the client according to the question item distribution instruction.
After the foregoing false items are notified to the test responsible person through a WeChat or email for confirmation, the test responsible person issues a problem item allocation instruction, all the false items are allocated to the test task applicant, and the test task applicant is responsible for solving the false items, and can monitor the life cycle of the problem items, and can switch between the following states: new, allocated, repaired, confirmed, closed, and rejected. And a problem item query function can be set, searching and matching are carried out according to various types of keyword information, and the searched result is exported in an Excel form to form a report. The system realizes the problem tracking function and the problem solving function, a series of processes such as reservation and establishment of a test task, establishment of a test case, execution of the test task, feedback of a test result, solving of a test problem item and the like are realized on line, the task is pushed and distributed among users with different roles, and in the implementation process of the test task of the automobile controller, operators do not need to be limited in a laboratory, the test process is completed through remote control, so that the test process is more convenient.
According to the testing method of the automobile controller, the testing task is established according to the obtained testing task establishing instruction from the first role user in the client, and the testing task is distributed to the second role user in the client; acquiring a test case creating operation from a second role user in a client, and creating a test case in the test task; controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client; can realize long-range automatic HIL test to automobile controller, realize remote automatic test, carry out propelling movement and distribution of task between different role users, through the operation of the different users of customer end, make automobile controller's test task's implementation process, operating personnel need not confine to the laboratory, can make HIL test work more high-efficient, the tester time is more free, the testing device utilization ratio is higher, the convenience in the automobile test work has been improved, for tester test work raises the efficiency.
Second embodiment
The embodiment discloses a testing system of an automobile controller, which is shown in fig. 2 and includes: a test task establishing and distributing module 201, a test case creating module 202 and a test executing and feedback module 203.
The test task establishing and distributing module 201 is configured to obtain a test task establishing instruction from a first role user in a client, establish a test task according to the test task establishing instruction, and distribute the test task to a second role user in the client.
The test case creating module 202 is configured to obtain a test case creating operation from a second role user in the client, and create a test case in the test task according to the test case creating operation.
And the test execution and feedback module 203 is configured to control the test equipment to execute the test task according to the test case, obtain a test result, and feed the test result back to the client.
The test task creating and distributing module 201 includes:
and the obtaining submodule is used for establishing an instruction according to the test task to obtain the test type and the test time.
And the determining submodule is used for determining the target test equipment according to the test type, the test time and the current running state of the test equipment.
And the establishing submodule is used for establishing a test task containing the test type, the test time and the target test equipment.
The test task creating and distributing module 201 further includes:
and the pushing submodule is used for pushing the obtained display information to the client so as to display the information at the client.
The display information includes: the test type, the test time, the current running state of the test equipment and the determined target test equipment.
Wherein, when the test task is assigned to a second role user in the client, the test system further comprises:
and the first sending module is used for sending a notification message to the second role user through an instant communication channel.
The test execution and feedback module 203 comprises:
and the obtaining submodule is used for obtaining the priority of the test task.
And the execution submodule is used for controlling the test equipment to execute the test task according to the test case and the priority of the test task.
Wherein, when the test result is fed back to the client, the test system further comprises:
and the feedback module is used for feeding back the question items in the test results to the first role user in the client through an instant communication channel.
Wherein the test system further comprises:
the first acquisition module is used for acquiring a test task application request from a third role user in the client;
and the second sending module is used for sending a notification message of the test task application to the first role user in the client according to the test task application request.
Wherein the test system further comprises:
and the second acquisition module is used for acquiring a question item distribution instruction of the first role user from the client.
And the distribution module is used for distributing the question item to the third triangle users in the client according to the question item distribution instruction.
According to the test system of the automobile controller, the test task is established according to the obtained test task establishment instruction from the first role user in the client, and the test task is distributed to the second role user in the client; acquiring a test case creating operation from a second role user in a client, and creating a test case in the test task; controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client; can realize long-range automatic HIL test to automobile controller, realize remote automatic test, carry out propelling movement and distribution of task between different role users, through the operation of the different users of customer end, make automobile controller's test task's implementation process, operating personnel need not confine to the laboratory, can make HIL test work more high-efficient, the tester time is more free, the testing device utilization ratio is higher, the convenience in the automobile test work has been improved, for tester test work raises the efficiency.
It is clear to those skilled in the art that, for convenience and brevity of description, the specific working processes of the above-described systems, apparatuses and units may refer to the corresponding processes in the foregoing method embodiments, and are not described herein again.
In addition, functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The functions, if implemented in the form of software functional units and sold or used as a stand-alone product, may be stored in a computer readable storage medium.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention, and all the changes or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
The embodiments in the present specification are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
While the preferred embodiments of the present invention have been described, it will be understood by those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention as defined in the following claims.

Claims (12)

1. A test method of an automobile controller is characterized by comprising the following steps:
acquiring a test task establishing instruction from a first role user in a client, establishing a test task according to the test task establishing instruction, and distributing the test task to a second role user in the client;
acquiring a test case creating operation from a second role user in a client, and creating a test case in the test task according to the test case creating operation;
controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client;
the step of controlling the test equipment to execute the test task according to the test case comprises the following steps:
acquiring the priority of the test task;
controlling the test equipment to execute the test task according to the test case and the priority of the test task;
before the step of obtaining a test task establishment instruction from a first role user in a client and establishing a test task according to the test task establishment instruction, the test method further comprises the following steps:
acquiring a test task application request from a third role user in a client;
and sending a notification message of the test task application to the first role user in the client according to the test task application request.
2. The method according to claim 1, wherein the step of creating a test task according to the test task creation instruction includes:
according to the test task establishing instruction, obtaining a test type and test time;
determining target test equipment according to the test type, the test time and the current running state of the test equipment;
and establishing a test task comprising the test type, the test time and the target test equipment.
3. The method according to claim 2, wherein the step of creating a test task according to the test task creation instruction further comprises:
pushing the obtained display information to the client to display the information at the client;
the display information includes: the test type, the test time, the current running state of the test equipment and the determined target test equipment.
4. The testing method of claim 1, wherein when assigning the testing task to a second role user in the client, the testing method further comprises:
and sending a notification message to the second role user through an instant communication channel.
5. The testing method according to claim 1, wherein when the testing result is fed back to the client, the testing method further comprises:
and feeding back the question item in the test result to the first role user in the client through an instant communication channel.
6. The testing method of claim 5, wherein after the step of feeding back the question item in the test result to the first persona user in the client via an instant messaging channel, the testing method further comprises:
acquiring a question item distribution instruction of the first role user from a client;
and distributing the question item to the third triangular color user in the client according to the question item distribution instruction.
7. A test system of an automobile controller is characterized by comprising:
the system comprises a test task establishing and distributing module, a test task establishing and distributing module and a test task distributing module, wherein the test task establishing and distributing module is used for acquiring a test task establishing instruction from a first role user in a client, establishing a test task according to the test task establishing instruction and distributing the test task to a second role user in the client;
the test case creating module is used for acquiring a test case creating operation from a second role user in the client, and creating a test case in the test task according to the test case creating operation;
the test execution and feedback module is used for controlling the test equipment to execute the test task according to the test case to obtain a test result and feeding the test result back to the client;
wherein, the test execution and feedback module comprises:
the obtaining submodule is used for obtaining the priority of the test task;
an execution submodule for controlling the test equipment to execute the test task according to the test case and the priority of the test task
The system further comprises:
the first acquisition module is used for acquiring a test task application request from a third role user in the client;
and the second sending module is used for sending a notification message of the test task application to the first role user in the client according to the test task application request.
8. The test system of claim 7, wherein the test task creation and distribution module comprises:
the obtaining submodule is used for establishing an instruction according to the test task and obtaining a test type and test time;
the determining submodule is used for determining target test equipment according to the test type, the test time and the current running state of the test equipment;
and the establishing submodule is used for establishing a test task containing the test type, the test time and the target test equipment.
9. The test system of claim 8, wherein the test task creation and distribution module further comprises:
the pushing submodule is used for pushing the obtained display information to the client so as to display the information at the client;
the display information includes: the test type, the test time, the current running state of the test equipment and the determined target test equipment.
10. The testing system of claim 7, wherein when assigning the testing task to a second role user in the client, the testing system further comprises:
and the first sending module is used for sending a notification message to the second role user through an instant communication channel.
11. The testing system of claim 7, wherein when feeding back the test results to the client, the testing system further comprises:
and the feedback module is used for feeding back the question items in the test results to the first role user in the client through an instant communication channel.
12. The test system of claim 11, further comprising:
the second acquisition module is used for acquiring a question item distribution instruction of the first role user from the client;
and the distribution module is used for distributing the question item to the third triangle users in the client according to the question item distribution instruction.
CN201610929458.4A 2016-10-31 2016-10-31 Test method and system of automobile controller Active CN106502235B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610929458.4A CN106502235B (en) 2016-10-31 2016-10-31 Test method and system of automobile controller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610929458.4A CN106502235B (en) 2016-10-31 2016-10-31 Test method and system of automobile controller

Publications (2)

Publication Number Publication Date
CN106502235A CN106502235A (en) 2017-03-15
CN106502235B true CN106502235B (en) 2020-08-28

Family

ID=58318738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610929458.4A Active CN106502235B (en) 2016-10-31 2016-10-31 Test method and system of automobile controller

Country Status (1)

Country Link
CN (1) CN106502235B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108255707B (en) * 2017-11-30 2020-09-25 平安科技(深圳)有限公司 Development role creating method, device, equipment and storage medium of test case
CN109150653B (en) * 2018-07-24 2020-11-24 北京新能源汽车股份有限公司 Remote hardware-in-loop HIL (hardware in loop) automatic testing method and system
CN108829090A (en) * 2018-08-20 2018-11-16 四川野马汽车股份有限公司 A kind of vehicle control unit of electric vehicle off-line detection system and detection method
CN109062190B (en) * 2018-09-04 2020-11-10 北京汽车研究总院有限公司 Real vehicle testing system of hybrid vehicle controller and application method thereof
CN110687888B (en) * 2019-09-26 2021-09-24 上海赫千电子科技有限公司 Automatic upgrading test device and system applied to locomotive
CN110703726B (en) * 2019-09-26 2021-07-30 上海赫千电子科技有限公司 Automatic upgrading test method applied to locomotive
CN111061556A (en) * 2019-12-26 2020-04-24 深圳前海环融联易信息科技服务有限公司 Optimization method and device for executing priority task, computer equipment and medium
CN111858118B (en) * 2020-07-01 2022-03-29 东风汽车集团有限公司 Hardware platform modular circuit testing method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102520711A (en) * 2011-11-28 2012-06-27 联合汽车电子有限公司 Hardware-in-the-loop simulation system of automatic mechanical transmission (AMT) controller and automatic test method thereof
CN103298016A (en) * 2012-02-27 2013-09-11 展讯通信(上海)有限公司 Test system for mobile terminals

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7672798B2 (en) * 2002-06-27 2010-03-02 Spx Corporation Apparatus and method for determining the temperature of a charging power source
CN101471819A (en) * 2007-12-29 2009-07-01 中国移动通信集团公司 Test system, test method, management domain and operation domain
CN103780455B (en) * 2013-12-11 2017-05-03 国家无线电监测中心检测中心 TETRA digit cluster protocol test method and system based on TTCN-3
DE102014217561B4 (en) * 2014-09-03 2018-02-08 Preh Car Connect Gmbh Method and arrangement for testing a multimedia device
CN104834595B (en) * 2015-02-15 2017-09-12 网易(杭州)网络有限公司 A kind of Visual Automatic Test method and system
CN105786667A (en) * 2016-02-29 2016-07-20 惠州Tcl移动通信有限公司 Distributed automated testing method and system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102520711A (en) * 2011-11-28 2012-06-27 联合汽车电子有限公司 Hardware-in-the-loop simulation system of automatic mechanical transmission (AMT) controller and automatic test method thereof
CN103298016A (en) * 2012-02-27 2013-09-11 展讯通信(上海)有限公司 Test system for mobile terminals

Also Published As

Publication number Publication date
CN106502235A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN106502235B (en) Test method and system of automobile controller
CN106844198B (en) Distributed dispatching automation test platform and method
CN109408337B (en) Interface operation and maintenance method and device
WO2017071425A1 (en) Method and device for updating version
CN105447681B (en) Physical and chemical detection control and information management system
CN103678093B (en) A kind of automated test frame and method of testing
US20060178921A1 (en) Project management system and method therefor
CN102566443A (en) Simulation verification system and method for integrated avionics system model based on artifact design description language (ADDL)
CN109150653B (en) Remote hardware-in-loop HIL (hardware in loop) automatic testing method and system
CN104536965A (en) System and method for data query and presentation under big data condition
CN111651471A (en) Target data query method and device, electronic equipment and storage medium
Lewis et al. Maintenance of mobile mine equipment in the information age
CN109709918A (en) A kind of satellite intelligence production visualization managing and control system
CN111932129A (en) Equipment digital maintenance management and control system
CN103605610A (en) System and method for software testing based on Hadoop
CN104683473A (en) Service quality monitoring method, server side, client and system
CN106357466B (en) A kind of internet product monitoring method and monitoring system
WO2013135016A1 (en) Version construction system and method
CN111667250A (en) Cloud-based management method and system for automatic test execution machine
CN112633850A (en) Method for realizing service flow automation by managing, calling and monitoring RPA robot
CN111555894B (en) Data processing method, device, equipment and storage medium
US11727078B2 (en) Management of client devices for maintenance of a structural product
CN211234994U (en) Test system of electronic lock
CN112348701A (en) Method, device and system for processing power supply station line-to-user data and electronic equipment
CN113723900A (en) Product life cycle management platform, and system and method for executing and managing changed data

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant