CN106501761B - Three-phase intelligent ammeter simulation detection system - Google Patents

Three-phase intelligent ammeter simulation detection system Download PDF

Info

Publication number
CN106501761B
CN106501761B CN201611216293.2A CN201611216293A CN106501761B CN 106501761 B CN106501761 B CN 106501761B CN 201611216293 A CN201611216293 A CN 201611216293A CN 106501761 B CN106501761 B CN 106501761B
Authority
CN
China
Prior art keywords
concentrator
current
power source
electric energy
energy meter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611216293.2A
Other languages
Chinese (zh)
Other versions
CN106501761A (en
Inventor
韩冬军
张加海
孙国栋
王贵现
慕健
孙华玺
王辉昱
宿林昊
刘良涛
李鹏
张金刚
单瞾国
叶剑波
刘春�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yantai Dongfang Wisdom Electric Co Ltd
Original Assignee
Yantai Dongfang Wisdom Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yantai Dongfang Wisdom Electric Co Ltd filed Critical Yantai Dongfang Wisdom Electric Co Ltd
Priority to CN201611216293.2A priority Critical patent/CN106501761B/en
Publication of CN106501761A publication Critical patent/CN106501761A/en
Application granted granted Critical
Publication of CN106501761B publication Critical patent/CN106501761B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a three-phase intelligent ammeter simulation detection system, which comprises a power source, an ammeter and a concentrator connected with the ammeter, wherein the power source is a power source; the power source supplies power to the concentrator and the electric energy meter in a current mode through the switching unit, a current transformer and a change-over switch used for switching the switching unit between a direct power supply mode and an indirect power supply mode are arranged in the switching unit, the direct power supply mode refers to that current output by the power source is directly supplied to the concentrator, and the indirect mode refers to that current output by the power source is supplied to the concentrator after being converted through the current transformer. The invention uses a set of power source to supply power for the concentrator and the electric energy meter in a unified way, and meets the use requirements of the electric energy meters with different current specifications.

Description

Three-phase intelligent ammeter simulation detection system
Technical Field
The invention relates to an electric energy meter simulation detection system.
Background
The intelligent electric energy meter is an important metering device for electric energy trade settlement between a power generation company and a power supply company as well as between the power supply company and a power consumer. In order to verify error verification and reading data of the three-phase intelligent electric energy meter, an analog detection system is required to be built, and the three-phase intelligent electric energy meter is read through a concentrator to complete relevant performance detection.
In the simulation detection system of the three-phase intelligent electric energy meter in the prior art, because the current required by the working of the concentrator and the electric energy meter is different, two sets of power sources are required to be used for supplying power to the concentrator and the electric energy meter respectively, the wiring relationship is complex, and the cost is high. On the other hand, the current specification of the electric energy meter to be detected is different, and the concentrator and the electric energy meter are difficult to be simultaneously powered by the same power source.
Disclosure of Invention
The invention provides a three-phase intelligent ammeter simulation detection system, which aims to solve the problems that: (1) A set of power source is used for supplying power for the concentrator and the electric energy meter together; (2) The operation requirements of the electric energy meter with different power supply current specifications are met.
The technical scheme of the invention is as follows:
the three-phase intelligent ammeter simulation detection system comprises a power source, an ammeter and a concentrator connected with the ammeter;
the power source supplies power to the concentrator and the electric energy meter in a current mode through the switching unit, a current transformer and a change-over switch used for switching the switching unit between a direct power supply mode and an indirect power supply mode are arranged in the switching unit, the direct power supply mode refers to that current output by the power source is directly supplied to the concentrator, and the indirect mode refers to that current output by the power source is supplied to the concentrator after being converted through the current transformer.
As a further improvement of the invention: the switching unit is provided with a current inlet end and a current outlet end which are used for being connected with a power source, and also comprises a first output end and a second output end which are used for supplying power to the electric energy meter, and a third output end and a fourth output end which are used for supplying power to the concentrator;
the primary side of the current transformer is provided with a first wiring terminal and a second wiring terminal, and the secondary side of the current transformer is provided with a third wiring terminal and a fourth wiring terminal;
the switch comprises a first switch and a second switch, wherein the public end of the first switch is connected with the current outlet end, the normally closed end is connected with the first wiring end, the normally open end is connected with the third wiring end, the public end of the second switch is connected with the third output end, the normally closed end is connected with the fourth wiring end, and the normally open end is connected with the second wiring end;
the third wiring terminal is connected with the fourth output end, the current inlet end is connected with the first output end, and the second wiring terminal is connected with the second output end.
As a further improvement of the invention: the control device is connected with the first change-over switch and the second change-over switch respectively to control the first change-over switch and the second change-over switch to synchronously act.
As a further improvement of the invention: the concentrator is connected with the control device.
As a further improvement of the invention: the power source is connected with the control device.
As a further improvement of the invention: the concentrator is connected with the electric energy meter through the collector.
Compared with the prior art, the invention has the following positive effects: the invention converts the current provided by the power source through the switching unit, and provides two direct and indirect power supply modes: in a direct power supply mode, the power source directly supplies small current for the concentrator and the electric energy meter under the control of the control device; in the indirect power supply mode, the power source directly supplies large current to the electric energy meter, and meanwhile, the current is converted into small current through the current transformer to supply power to the concentrator, so that the normal power supply when the concentrator needs the small current and the electric energy meter needs the large current is ensured. The invention can use a set of power source to supply power for the electric energy meter and the concentrator together, and meets the use requirements of the electric energy meter with different current specifications.
Drawings
Fig. 1 is a schematic diagram of a switching unit.
Detailed Description
The technical scheme of the invention is described in detail below with reference to the accompanying drawings:
the three-phase intelligent ammeter simulation detection system comprises a power source, a control device, an ammeter and a concentrator connected with the ammeter. The concentrator is connected with the electric energy meter through the collector, the concentrator is connected with the collector in a carrier mode in a communication mode, the collector is connected with the electric energy meter in an RS485 mode in a communication mode, and the electric energy meter is a three-phase intelligent electric energy meter.
The concentrator and the power source are also respectively connected with a control device, and the control device comprises an industrial personal computer and an upper computer.
The power source supplies power to the concentrator and the electric energy meter in a current mode through the switching unit, a current transformer and a change-over switch used for switching the switching unit between a direct power supply mode and an indirect power supply mode are arranged in the switching unit, the direct power supply mode refers to that current output by the power source is directly supplied to the concentrator, and the indirect mode refers to that current output by the power source is supplied to the concentrator after being converted through the current transformer.
Further: as in fig. 1, the switching unit has a current inlet terminal 1 and a current outlet terminal 2 for interfacing with a power source, and further comprises a first output terminal 5 and a second output terminal 8 for powering an electric energy meter, and a third output terminal 9 and a fourth output terminal 10 for powering a concentrator;
the primary side of the current transformer is provided with a first terminal 3 and a second terminal 4, and the secondary side is provided with a third terminal 6 and a fourth terminal 7;
the diverter switch comprises a first diverter switch 12 and a second diverter switch 11, wherein the public end of the first diverter switch 12 is connected with the current outlet end 2, the normally-closed end is connected with the first wiring end 3, the normally-open end is connected with the third wiring end 6, the public end of the second diverter switch 11 is connected with the third output end 9, the normally-closed end is connected with the fourth wiring end 7, and the normally-open end is connected with the second wiring end 4;
the third terminal 6 is connected to a fourth output 10, the current inlet terminal 1 is connected to the first output 5, and the second terminal 4 is connected to the second output 8.
The control device is connected to the first switch 12 and the second switch 11 respectively to control the first switch 12 and the second switch 11 to operate synchronously.
The first 12 and second 11 switches may be implemented by relays.
The power source can output three-phase currents to supply power for the concentrator and the electric energy meter, and each phase of current is respectively connected with the concentrator and a phase of current input terminal on the electric energy meter through a switching unit.
The working flow of the detection system is as follows:
after wiring is completed, a detector first determines the working current specification of the concentrator and the electric energy meter to be detected. If the concentrator needs to use a small current and the energy meter needs a large current, then the indirect power mode is used with the default setting maintained: the current output by the power source sequentially passes through the current inlet end 1, the first output end 5, a plurality of serially connected electric energy meters, the primary side of the current transformer and the current outlet end 2 to form a loop for supplying large current to the electric energy meters, and meanwhile, the small current converted by the current transformer is output on the secondary side and is supplied to the concentrator through the fourth wiring end 7, the third output end 9, a plurality of serially connected concentrators, the fourth output end 10 and the third wiring end 6. If the current specifications required by the concentrator and the electric energy meter are the same, the control device controls the first switch 12 and the second switch 11 to synchronously act and switch to a direct power supply mode, and at the moment, the current output by the power source sequentially passes through the current inlet end 1, the first output end 5, a plurality of electric energy meters connected in series, the second output end 8, the third output end 9, a plurality of concentrators connected in series, the fourth output end 10, the third wiring end 6 and the electric outlet end 2 to form a total loop, and the electric energy meter is connected in series with the concentrator to supply the same current.

Claims (5)

1. Three-phase intelligent ammeter analog detection system, its characterized in that: the power source comprises a power source, an electric energy meter and a concentrator connected with the electric energy meter;
the power source supplies power to the concentrator and the electric energy meter in a current mode through a switching unit, a current transformer and a change-over switch for switching the switching unit between a direct power supply mode and an indirect power supply mode are arranged in the switching unit, the direct power supply mode refers to that current output by the power source is directly supplied to the concentrator, and the indirect power supply mode refers to that current output by the power source is supplied to the concentrator after being converted through the current transformer;
the switching unit has a current inlet end (1) and a current outlet end (2) for connection to a power source, and further comprises a first output end (5) and a second output end (8) for supplying power to the electric energy meter, and a third output end (9) and a fourth output end (10) for supplying power to the concentrator;
the primary side of the current transformer is provided with a first wiring terminal (3) and a second wiring terminal (4), and the secondary side of the current transformer is provided with a third wiring terminal (6) and a fourth wiring terminal (7);
the diverter switch comprises a first diverter switch (12) and a second diverter switch (11), wherein the public end of the first diverter switch (12) is connected with a current outlet end (2), the normally closed end is connected with a first wiring end (3), the normally open end is connected with a third wiring end (6), the public end of the second diverter switch (11) is connected with a third output end (9), the normally closed end is connected with a fourth wiring end (7), and the normally open end is connected with a second wiring end (4);
the third wiring terminal (6) is connected with the fourth output end (10), the current inlet end (1) is connected with the first output end (5), and the second wiring terminal (4) is connected with the second output end (8).
2. The three-phase intelligent ammeter simulation test system according to claim 1, wherein: the control device is connected with the first change-over switch (12) and the second change-over switch (11) respectively to control the first change-over switch (12) to synchronously act with the second change-over switch (11).
3. The three-phase intelligent ammeter simulation test system according to claim 1, wherein: the concentrator is connected with the control device.
4. The three-phase intelligent ammeter simulation test system according to claim 1, wherein: the power source is connected with the control device.
5. The three-phase intelligent ammeter simulation test system according to any one of claims 1 to 4, wherein: the concentrator is connected with the electric energy meter through the collector.
CN201611216293.2A 2016-12-26 2016-12-26 Three-phase intelligent ammeter simulation detection system Active CN106501761B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611216293.2A CN106501761B (en) 2016-12-26 2016-12-26 Three-phase intelligent ammeter simulation detection system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611216293.2A CN106501761B (en) 2016-12-26 2016-12-26 Three-phase intelligent ammeter simulation detection system

Publications (2)

Publication Number Publication Date
CN106501761A CN106501761A (en) 2017-03-15
CN106501761B true CN106501761B (en) 2023-07-21

Family

ID=58333958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611216293.2A Active CN106501761B (en) 2016-12-26 2016-12-26 Three-phase intelligent ammeter simulation detection system

Country Status (1)

Country Link
CN (1) CN106501761B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0267968A (en) * 1988-09-02 1990-03-07 Omron Tateisi Electron Co Watthour meter
EP1626490A1 (en) * 2004-08-11 2006-02-15 SMK Corporation A synchronous rectifying switching power source circuit
CN101281693A (en) * 2007-12-29 2008-10-08 重庆电力高级技工学校 Device for simulating false wiring of electric energy metering equipment
CN201689169U (en) * 2010-04-28 2010-12-29 保定市博达同创电力科技有限公司 Detector for low-voltage electric energy metering device
CN102110518A (en) * 2009-12-29 2011-06-29 西安华伟光电技术有限公司 Automatic measurement range switching device of electronic current transformer
CN102435869A (en) * 2011-08-26 2012-05-02 东北大学 Experimental device for automatic regulation and compensation of three-phase unbalanced load and control method thereof
CN103021157A (en) * 2012-11-26 2013-04-03 山东电力集团公司电力科学研究院 Device and method for completely simulating site to detect electricity consumption information acquisition terminal
CN203261121U (en) * 2013-05-29 2013-10-30 北京荣华恒信开关技术有限公司 Rapid switching control power supply of solenoid valve
CN103456199A (en) * 2013-09-13 2013-12-18 郑州万特电气股份有限公司 Power utilization information collection simulation system
WO2014083073A1 (en) * 2012-11-27 2014-06-05 Eaton Electrical Ip Gmbh & Co. Kg Switching device having a measuring apparatus
CN104064081A (en) * 2014-05-30 2014-09-24 国家电网公司 Fault simulating training device of current transformer
CN105845007A (en) * 2016-06-13 2016-08-10 国网辽宁省电力有限公司朝阳供电公司 Intelligent electric energy meter simulation application test stand and use method thereof
CN106249019A (en) * 2016-08-12 2016-12-21 山东亿玛信诺电气有限公司 Unified no-load voltage ratio molded breadth width metering current mulual inductor

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2300110Y (en) * 1997-04-14 1998-12-09 北京无线电技术研究所 AC power electric energy meter
CN201638439U (en) * 2010-04-15 2010-11-17 秦皇岛开发区海纳电测仪器有限责任公司 Full-metering simulation device
CN202631626U (en) * 2012-06-19 2012-12-26 上海贝电实业(集团)股份有限公司 Multi-path collection system of intelligent electric meter
CN203324466U (en) * 2013-05-08 2013-12-04 广东电网公司电力科学研究院 Verification system capable of verifying multiple electric-energy meters with different current specifications at the same time
CN104730334A (en) * 2013-12-18 2015-06-24 上海宝钢工业技术服务有限公司 Electric energy metering method based on dynamic switching input signal
CN203981735U (en) * 2014-06-04 2014-12-03 国家电网公司 Variable specific current transformer self-checking device
CN204314448U (en) * 2014-08-01 2015-05-06 云南电力试验研究院(集团)有限公司电力研究院 Single three-phase electric energy meter electrical voltage system tripping device
CN105301551A (en) * 2015-10-29 2016-02-03 国网上海市电力公司 Watt-hour meter calibration device and method outputting current under 1mA
CN205157764U (en) * 2015-12-01 2016-04-13 国家电网公司 Multipurpose is single, three -phase electric energy meter verifying attachment
CN105487044A (en) * 2016-01-29 2016-04-13 国家电网公司 Current switching apparatus for electric energy meter remote calibration apparatus and switching method
CN206258571U (en) * 2016-12-26 2017-06-16 烟台东方威思顿电气有限公司 Three-phase intelligent electric-energy meter simulation detection system

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0267968A (en) * 1988-09-02 1990-03-07 Omron Tateisi Electron Co Watthour meter
EP1626490A1 (en) * 2004-08-11 2006-02-15 SMK Corporation A synchronous rectifying switching power source circuit
CN101281693A (en) * 2007-12-29 2008-10-08 重庆电力高级技工学校 Device for simulating false wiring of electric energy metering equipment
CN102110518A (en) * 2009-12-29 2011-06-29 西安华伟光电技术有限公司 Automatic measurement range switching device of electronic current transformer
CN201689169U (en) * 2010-04-28 2010-12-29 保定市博达同创电力科技有限公司 Detector for low-voltage electric energy metering device
CN102435869A (en) * 2011-08-26 2012-05-02 东北大学 Experimental device for automatic regulation and compensation of three-phase unbalanced load and control method thereof
CN103021157A (en) * 2012-11-26 2013-04-03 山东电力集团公司电力科学研究院 Device and method for completely simulating site to detect electricity consumption information acquisition terminal
WO2014083073A1 (en) * 2012-11-27 2014-06-05 Eaton Electrical Ip Gmbh & Co. Kg Switching device having a measuring apparatus
CN203261121U (en) * 2013-05-29 2013-10-30 北京荣华恒信开关技术有限公司 Rapid switching control power supply of solenoid valve
CN103456199A (en) * 2013-09-13 2013-12-18 郑州万特电气股份有限公司 Power utilization information collection simulation system
CN104064081A (en) * 2014-05-30 2014-09-24 国家电网公司 Fault simulating training device of current transformer
CN105845007A (en) * 2016-06-13 2016-08-10 国网辽宁省电力有限公司朝阳供电公司 Intelligent electric energy meter simulation application test stand and use method thereof
CN106249019A (en) * 2016-08-12 2016-12-21 山东亿玛信诺电气有限公司 Unified no-load voltage ratio molded breadth width metering current mulual inductor

Also Published As

Publication number Publication date
CN106501761A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN105634025A (en) Grid-connected inversion device in direct current microgrid
CN103645363A (en) Two-way metering three-phase intelligent electric energy meter
CN201935973U (en) Integrative test device of electric test of transformer
CN201707433U (en) Intelligent controller characteristic test instrument
CN102565562A (en) Comprehensive testing device for electrical test of transformer
CN204374950U (en) A kind of hybrid simulation test interface of energy-storage units PCS control panel
CN207232252U (en) A kind of dual power supply electric quantity collector
CN203658571U (en) Switching wiring circuit for double-loop ammeter detection instrument
CN206208991U (en) A kind of direct-current resistance tester for transformer
CN106501761B (en) Three-phase intelligent ammeter simulation detection system
CN202093088U (en) Electrical parameter measuring device
CN204681157U (en) A kind of intelligent double-power control system
CN104142414A (en) Detachable combined electricity meter
CN207424664U (en) A kind of testboard automatic checkout system based on LABVIEW
CN101207303A (en) 35KV transformer substation remote monitoring system
CN106655732A (en) Programmable controller-controlled test object control power supply
CN206258571U (en) Three-phase intelligent electric-energy meter simulation detection system
CN206531951U (en) Single-phase electric energy meter with fault simulating function
CN206389304U (en) Motor electromagnetic start system
CN202854250U (en) Power supply control system for load test of electrically operated mechanism for isolating switch
CN107132439A (en) Electric power data simulative display circuit
CN203950029U (en) The integrated calibration equipment of a kind of novel single three-phase electric energy meter
CN209432996U (en) Single-phase meter on-site calibration device
CN202330649U (en) Device of detecting magnetic holding relays in batches
CN203825114U (en) Universal electrical experiment device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 264003 Laishan City, Yantai province Venture Center, Shandong

Applicant after: YANTAI DONGFANG WISDOM ELECTRIC Co.,Ltd.

Address before: 264003 Laishan City, Yantai province Venture Center, Shandong

Applicant before: YANTAI DONGFANG WISDOM ELECTRIC CO.,LTD.

GR01 Patent grant