CN106498969B - 空间框架式钢沉箱支挡结构的施工方法 - Google Patents
空间框架式钢沉箱支挡结构的施工方法 Download PDFInfo
- Publication number
- CN106498969B CN106498969B CN201610912987.3A CN201610912987A CN106498969B CN 106498969 B CN106498969 B CN 106498969B CN 201610912987 A CN201610912987 A CN 201610912987A CN 106498969 B CN106498969 B CN 106498969B
- Authority
- CN
- China
- Prior art keywords
- caisson
- column
- sinking
- steel
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Abstract
空间框架式钢沉箱支挡结构的施工方法,其步骤为:(1)平整场地,对沉箱位置进行夯实处理;(2)在混凝土垫层上根据沉箱尺寸画出刃脚下放准确位置;(3)按照立柱(1)、横梁(2)、斜支撑(3)、水平支撑(4)、板(5)的顺序进行安装;(4)对沉箱拼装焊接进行检验,检验合格后用风镐分组、对称、同步地凿除刃脚下方混凝土;沉箱开始切土下沉;正常下沉时,应自中间向刃脚处均匀对称除土。下沉时应随时注意正位,保持竖直下沉,至少每下沉1米检查一次;(5)对沉箱底标高经量测满足设计及施工要求后,即可进行清理基底工作,保证基底平整;(6)沉箱采用干封底,待沉箱下沉到设计标高后及时浇筑混凝土垫层。
Description
技术领域
本发明涉及空间框架式钢沉箱支挡结构的施工技术。
背景技术
随着深水基础施工技术和机械的发展,围堰结构在深水基础施工中的应用日益广泛。这对沉箱基础施工技术的要求也逐渐提高,而在淤泥沉积多且清理困难、周围水体被严重破坏、环境污染严重的背景之下,越来越多的土围堰(拦河)的桥梁施工技术开始利用钢结构加钢沉箱进行改进,以提供简便且绿色环保的施工平台。然而,在改进过程中,也存在着以下几方面问题:
1、现有的钢结构加钢沉箱一般是采用现场焊接拼装,钢沉箱的形式也势必受地理位置和工程实际情况限制,这势必会影响设计者对其整体安全性的判断,由于设计不当,易导致钢沉箱失稳破坏。若处理不当,还将出现危及施工现场人员生命安全等问题,严重影响钢沉箱的使用。
2、钢沉箱现场焊接拼装施工过程中会产生浪费材料的现象,增大施工成本,甚至会延长施工工期。
发明内容
本发明的目的是提供一种空间框架式钢沉箱支挡结构的施工方法。
本发明是空间框架式钢沉箱支挡结构的施工方法,其步骤为:
(1)平整场地,对沉箱位置进行夯实处理,加铺一层砂层,并在其上浇筑混凝土垫层;
(2)在混凝土垫层上根据沉箱尺寸画出刃脚下放准确位置;
(3)钢沉箱配件采用工厂制作,现场焊接拼装的方式;按照立柱1、横梁2、斜支撑3、水平支撑4、板5的顺序进行安装;内侧采用斜支撑3和水平支撑4支挡;外侧采用缆风绳斜拉,待成为整体后撤除缆风绳;保证沉箱刃脚的垂直度,并进行复测保证其在同一水平面;
(4)对沉箱拼装焊接进行检验,检验合格后用风镐分组、对称、同步地凿除刃脚下方混凝土;沉箱开始切土下沉;正常下沉时,应自中间向刃脚处均匀对称除土。下沉时应随时注意正位,保持竖直下沉,至少每下沉1米检查一次;
(5)对沉箱底标高经量测满足设计及施工要求后,即可进行清理基底工作,保证基底平整;
(6)沉箱采用干封底,待沉箱下沉到设计标高后及时浇筑混凝土垫层。
本发明的有益效果是:所述的一种新型空间框架式钢沉箱支挡结构的施工方法,通过独特的梁、柱和支撑的布置与理论计算,即利用柱、梁和板的节点构造的整体性来保证钢沉箱的稳定与安全,解决了传统土(砂)围堰(或拦河)中桥梁施工技术的一些弊端,同时其施工过程简单易操作,而且能做到节约费用、缩短施工工期。
附图说明
图1为平面图简图,图2为板的计算简图,图3为横梁的计算简图,图4为立柱的计算简图。
具体实现方式
如图1~图4所示,本发明是空间框架式钢沉箱支挡结构的施工方法,其步骤为:
(1)平整场地,使用蛙式打夯机对沉箱位置进行夯实处理,加铺一层30cm厚的砂层,并在其上浇筑15cm厚C25素混凝土垫层;
(2)在混凝土垫层上根据沉箱尺寸画出刃脚下放准确位置;
(3)钢沉箱配件采用工厂制作,现场焊接拼装的方式。按照立柱1、横梁2、斜支撑3、水平支撑4、板5的顺序进行安装。内侧采用斜支撑3和水平支撑4支挡;外侧采用缆风绳斜拉,待成为整体后撤除缆风绳;保证沉箱刃脚的垂直度,并进行复测保证其在同一水平面;
(4)对沉箱拼装焊接进行检验,检验合格后用风镐分组、对称、同步地凿除刃脚下方混凝土。沉箱开始切土下沉。正常下沉时,应自中间向刃脚处均匀对称除土。下沉时应随时注意正位,保持竖直下沉,至少每下沉1米检查一次;
(5)对沉箱底标高经量测满足设计及施工要求后,即可进行清理基底工作,保证基底平整;
(6)沉箱采用干封底,待沉箱下沉到设计标高后及时浇筑10cm厚C15素混凝土垫层。
其中,根据荷载传递路径、受力分析以及工程实际情况,可依次确定板的厚度→横梁数量→立柱的数量→斜支撑数量→水平支撑数量。下面为空间框架式钢沉箱支挡结构强度的计算。
(1)板的强度验算,以图1为例,板的计算简图如图2所示。
钢沉箱板强度的计算需满足下式:
q=γh
γ—土的天然重度,kN/m3;
h—沉箱的深度;
q—从沉箱底算起的第二根横梁从属面积上的均布荷载;
l1—横梁竖向间距;
—板承受的最大弯矩;
—板承受的最大剪力;
—板承受的最大应力;
—板承受的最大剪应力;
γx—截面的塑性发展系数;
Wnx—对x轴的净截面模量;
—计算剪应力处以上毛截面对中和轴的面积矩;
—板的毛截面惯性矩;
b—板的厚度;
f—钢材的抗拉强度设计值;
fv—钢材的抗剪强度设计值;
(2)钢沉箱横梁或立柱强度验算,计算简图如图3、图4所示。
钢沉箱横梁或立柱强度的计算需满足下式:
—梁或柱承受的最大弯矩;
—梁或柱整个横截面对中性轴的惯性矩;
yb、yc—梁或柱上某点到中性轴的最远距离;
—梁或立柱承受的最大剪力;
d—工字钢厚度;
—梁或柱横截面上距中性轴为y以上部分的面积对中性轴的面积矩;—梁或柱承受的最大应力;
—梁或柱承受的最大剪应力;
(3)钢沉箱撑杆稳定性验算,如下所示。
钢沉箱撑杆稳定性的计算需满足下式:
λ—压杆的长细比或柔度;
μ—长度因数;
l2—杆的计算长度;
i—压杆横截面对中性轴的惯性半径,
F—压杆承受的轴向压力;
—压杆的稳定因数,可查表按照差值法计算;
A—压杆横截面面积。
Claims (4)
1.空间框架式钢沉箱支挡结构的施工方法,其步骤为:
(1)平整场地,对沉箱位置进行夯实处理,加铺一层砂层,并在其上浇筑混凝土垫层;
(2)在混凝土垫层上根据沉箱尺寸画出刃脚下放准确位置;
(3)钢沉箱配件采用工厂制作,现场焊接拼装的方式;按照立柱(1)、横梁(2)、斜支撑(3)、水平支撑(4)、板(5)的顺序进行安装;内侧采用斜支撑(3)和水平支撑(4)支挡;外侧采用缆风绳斜拉,待成为整体后撤除缆风绳;保证沉箱刃脚的垂直度,并进行复测保证其在同一水平面;
(4)对沉箱拼装焊接进行检验,检验合格后用风镐分组、对称、同步地凿除刃脚下方混凝土;沉箱开始切土下沉;正常下沉时,应自中间向刃脚处均匀对称除土;下沉时应随时注意正位,保持竖直下沉,至少每下沉1米检查一次;
(5)对沉箱底标高经量测满足设计及施工要求后,即可进行清理基底工作,保证基底平整;
(6)沉箱采用干封底,待沉箱下沉到设计标高后及时浇筑混凝土垫层。
2.根据权利要求1所述的空间框架式钢沉箱支挡结构的施工方法,其特征在于使用蛙式打夯机对沉箱位置进行夯实处理,加铺一层30cm厚的砂土,并在其上浇筑15cm厚C25素混凝土垫层。
3.根据权利要求1所述的空间框架式钢沉箱支挡结构的施工方法,其特征在于待沉箱下沉到设计标高后及时浇筑10cm厚C15素混凝土垫层。
4.根据权利要求1所述的空间框架式钢沉箱支挡结构的施工方法,其特征在于根据荷载传递路径、受力分析以及工程实际情况,依次确定板的厚度、横梁数量、立柱的数量、斜支撑数量、水平支撑数量;下面为空间框架式钢沉箱支挡结构强度的计算:
(1)板的强度验算:钢沉箱板强度的计算需满足下式:
q=γh
γ—土的天然重度,kN/m3;
h—沉箱的深度;
q—从沉箱底算起的第二根横梁从属面积上的均布荷载;
l1—横梁竖向间距;
—板承受的最大弯矩;
—板承受的最大剪力;
—板承受的最大应力;
—板承受的最大剪应力;
γx—截面的塑性发展系数;
Wnx—对x轴的净截面模量;
—计算剪应力处以上毛截面对中和轴的面积矩;
—板的毛截面惯性矩;
b—板的厚度;
f—钢材的抗拉强度设计值;
fv—钢材的抗剪强度设计值;
(2)钢沉箱横梁或立柱强度验算:钢沉箱横梁或立柱强度的计算需满足下式:
—梁或柱承受的最大弯矩;
—梁或柱整个横截面对中性轴的惯性矩;
yb、yc—梁或柱上某点到中性轴的最远距离;
—梁或立柱承受的最大剪力;
d—工字钢厚度;
—梁或柱横截面上距中性轴为y以上部分的面积对中性轴的面积矩;
—梁或柱承受的最大应力;
—梁或柱承受的最大剪应力;
(3)钢沉箱撑杆稳定性验算:钢沉箱撑杆稳定性的计算需满足下式:
λ—压杆的长细比或柔度;
μ—长度因数;
l2—杆的计算长度;
i—压杆横截面对中性轴的惯性半径,
F—压杆承受的轴向压力;
—压杆的稳定因数,可查表按照差值法计算;
A—压杆横截面面积。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610912987.3A CN106498969B (zh) | 2016-10-20 | 2016-10-20 | 空间框架式钢沉箱支挡结构的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610912987.3A CN106498969B (zh) | 2016-10-20 | 2016-10-20 | 空间框架式钢沉箱支挡结构的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106498969A CN106498969A (zh) | 2017-03-15 |
CN106498969B true CN106498969B (zh) | 2018-10-16 |
Family
ID=58317971
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610912987.3A Expired - Fee Related CN106498969B (zh) | 2016-10-20 | 2016-10-20 | 空间框架式钢沉箱支挡结构的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106498969B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577356A (zh) * | 2018-12-28 | 2019-04-05 | 中国十九冶集团有限公司 | 地下管廊箱体及其沉箱方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08319621A (ja) * | 1995-05-24 | 1996-12-03 | Kajima Corp | ケーソンセントル型枠の構築工法及びその撤去工法 |
CN101158162A (zh) * | 2007-11-02 | 2008-04-09 | 上海市基础工程公司 | 无人化气压沉箱施工方法 |
CN101736749A (zh) * | 2008-11-06 | 2010-06-16 | 上海市城市建设设计研究院 | 软土基连续沉箱施工方法 |
CN202144598U (zh) * | 2011-06-21 | 2012-02-15 | 邹宗煊 | 一种下沉式地下构筑物 |
-
2016
- 2016-10-20 CN CN201610912987.3A patent/CN106498969B/zh not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08319621A (ja) * | 1995-05-24 | 1996-12-03 | Kajima Corp | ケーソンセントル型枠の構築工法及びその撤去工法 |
CN101158162A (zh) * | 2007-11-02 | 2008-04-09 | 上海市基础工程公司 | 无人化气压沉箱施工方法 |
CN101736749A (zh) * | 2008-11-06 | 2010-06-16 | 上海市城市建设设计研究院 | 软土基连续沉箱施工方法 |
CN202144598U (zh) * | 2011-06-21 | 2012-02-15 | 邹宗煊 | 一种下沉式地下构筑物 |
Also Published As
Publication number | Publication date |
---|---|
CN106498969A (zh) | 2017-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104866659B (zh) | 基于bim的钢结构整体吊装方法 | |
Zheng et al. | Characteristics and prediction methods for tunnel deformations induced by excavations | |
CN106381866A (zh) | 一种富水软土地区超深地下连续墙施工方法 | |
CN106703437B (zh) | 隔震托换结构及其施工方法 | |
CN107119584A (zh) | 一种混凝土刚架拱桥的拆除方法 | |
CN108193642B (zh) | 一种驳岸加固设施及其施工方法 | |
CN106436788A (zh) | 一种高层建筑摩擦桩基础加固纠倾方法 | |
CN107503344A (zh) | 周转式分节钢护筒护壁人工挖孔灌注桩的施工方法 | |
CN109706952A (zh) | 大型沉井施工方法 | |
CN106498969B (zh) | 空间框架式钢沉箱支挡结构的施工方法 | |
Sereshkeh et al. | Induced settlement reduction of adjacent masonry building in residential constructions | |
CN112456353A (zh) | 动臂塔吊固定式基础施工方法及动臂式塔吊结构 | |
Zucca et al. | Seismic vulnerability assessment of an Italian historical masonry dry dock | |
Gandhi | Observations on pile design and construction practices in India | |
Chen | On the influence of pile foundation settlement of existing high-rise buildings on the surrounding buildings | |
CN108221954B (zh) | 一种易拆卸的预制地下连续墙、吊具以及施工方法 | |
CN202131602U (zh) | 钢板桩围堰结构 | |
CN110485413B (zh) | 一种临近地铁高架桥桩基复合式防护快速成孔方法 | |
CN210031875U (zh) | 顶推用沉井装置 | |
Fantaziu et al. | Study Achievement of Deep Excavations from the Point of View of Their Effects on Surrounding Existing Buildings | |
CN1580411A (zh) | 墩墙式桥墩基础构建方法 | |
CN204571354U (zh) | 一种建筑施工应用的格构柱 | |
Jia | Research on the application of deviation correction technology in building reinforcement | |
CN218757490U (zh) | 胶凝砂砾石坝的灌浆平台结构 | |
Truong et al. | Design and Construction Solution of Foundation for Landmark 81—The Tallest Tower in Vietnam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181016 Termination date: 20191020 |
|
CF01 | Termination of patent right due to non-payment of annual fee |