CN106498938B - A kind of application method of cast-in-place concrete pile head shaping equipment - Google Patents

A kind of application method of cast-in-place concrete pile head shaping equipment Download PDF

Info

Publication number
CN106498938B
CN106498938B CN201610948821.7A CN201610948821A CN106498938B CN 106498938 B CN106498938 B CN 106498938B CN 201610948821 A CN201610948821 A CN 201610948821A CN 106498938 B CN106498938 B CN 106498938B
Authority
CN
China
Prior art keywords
former
bearing plate
concrete
stake
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610948821.7A
Other languages
Chinese (zh)
Other versions
CN106498938A (en
Inventor
刘汉龙
郑长杰
冉进瑜
周航
丁选明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Siwei Architectural Design Institute Co ltd
Original Assignee
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University filed Critical Chongqing University
Priority to CN201610948821.7A priority Critical patent/CN106498938B/en
Publication of CN106498938A publication Critical patent/CN106498938A/en
Application granted granted Critical
Publication of CN106498938B publication Critical patent/CN106498938B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention discloses a kind of application method of cast-in-place concrete pile head shaping equipment, a kind of cast-in-place concrete pile head shaping equipment, which is characterized in that is suitable for soft clay area, including former and bearing plate.The former is the open hollow cylinder of upper and lower side.The former side is equipped with bearing plate, and the bearing plate includes bearing plate I and bearing plate II.The bearing plate I and bearing plate II are symmetrical about the center line of former.The bearing plate I is equipped with lifting lug I far from one end of former, and the bearing plate II is equipped with lifting lug II far from one end of former.The equipment that the lifting lug I and lifting lug II are used to connect lifting former.Former can be effectively prevented concrete and squeeze out to surrounding soil, be conducive to the normal molding of pile body.It is also believed that adjusting the height of pile body and the tip end mass of rest and reorganization pile body in former.So that work progress becomes convenient and easy, the efficiency of construction and the quality of pile body are improved.

Description

A kind of application method of cast-in-place concrete pile head shaping equipment
Technical field
The present invention relates to the realm of building construction, and in particular to a kind of cast-in-place concrete pile head shaping equipment and its user Method.
Background technique
Coastal soft clay area engineering construction is fast-developing, and as the common base form of building, pile foundation is adopted extensively With.Pile foundation is divided into prefabricated pile and bored concrete pile according to construction method.Prefabricated pile needs prefabrication, and transport is inconvenient.Bored concrete pile uses The mode of poured in place concrete, cast-in-situ concrete poured pile constructing process is simple, strong operability, and convenient for detection, single pile is held It is high to carry power, diameter can be very big, therefore, obtains in the ground foundation engineerings such as architectural engineering, traffic engineering and municipal works It is widely applied.
However, being got over when construction bored concrete pile since surface soil layer is softer, and closer to earth's surface soil pressure in soft soil foundation It is small, thus concrete poured in stake holes after soil lateral pressure effect of contraction it is inadequate so that pile concrete to surrounding soil squeeze Out, the size and shape of design are not achieved.
In the filling process of in situ concrete pile, it can usually be extracted in situ concrete pile mold process after perfusion The deformed problem of stake top occurs, it is costly so as to cause the post-processing of pile crown, cause unnecessary waste, and casting Environment can also be impacted with the processing mode of row's concrete.It strikes the mode of chisel when selection to handle pile crown, and can shadow Ring the quality for arriving entire in situ concrete pile pile foundation.
Summary of the invention
The object of the present invention is to provide one kind to use in soft clay area, allows stake under the premise of not influencing pile quality The device of concrete formation is built in top casting, keeps work progress convenient and easy.
To realize the present invention purpose and the technical solution adopted is that such, a kind of cast-in-place concrete pile head sizing dress It sets, which is characterized in that be suitable for soft clay area, including former and bearing plate.
The former is the open hollow cylinder of upper and lower side, and the hollow space of the former is semi-surrounding space, The semi-surrounding space is type chamber.The former be to opening structure, the former include die body I, die body II, articulated section and Fixed mechanism.The hollow cylinder is splitted along axial direction and just obtains shapes and sizes die body I and die body II all the same.The mould Body I and die body II can piece together a complete former.There are two split positions for the die body I and the tool of die body II, wherein One position be it is hinged, have articulated section, another position is equipped with fixed mechanism.The die body I and die body II can be around hinges Socket part is split, and the fixed mechanism is the die body I of closure to be fixedly connected with die body II.
The former side is equipped with bearing plate, and the bearing plate includes bearing plate I and bearing plate II, the bearing plate Plate face normal direction it is consistent with the length direction of former.It is long that the bearing plate I and bearing plate II are respectively arranged in former The two sides in direction are spent, one end of I length direction of bearing plate is fixedly connected with former outer surface, and the other end is hanging.It is described One end of II length direction of bearing plate is fixedly connected with former outer surface, and the other end is hanging.The bearing plate I and bearing plate II Center line about former is symmetrical.
The bearing plate I is equipped with lifting lug I far from one end of former, and the bearing plate II is pacified far from one end of former Equipped with lifting lug II.The equipment that the lifting lug I and lifting lug II are used to connect lifting former.
A kind of cast-in-place concrete pile head shaping equipment, which is characterized in that be suitable for soft clay area, including former and hold Pressing plate.
The former is the open hollow cylinder of upper and lower side, and the hollow space of the former is semi-surrounding space, The semi-surrounding space is type chamber.The former is integrally formed.
The former side is equipped with bearing plate, and the bearing plate includes bearing plate I and bearing plate II, the bearing plate Plate face normal direction it is consistent with the length direction of former.It is long that the bearing plate I and bearing plate II are respectively arranged in former The two sides in direction are spent, one end of I length direction of bearing plate is fixedly connected with former outer surface, and the other end is hanging.It is described One end of II length direction of bearing plate is fixedly connected with former outer surface, and the other end is hanging.The bearing plate I and bearing plate II Center line about former is symmetrical.
The bearing plate I is equipped with lifting lug I far from one end of former, and the bearing plate II is pacified far from one end of former Equipped with lifting lug II.The equipment that the lifting lug I and lifting lug II are used to connect lifting former.
A kind of application method based on a kind of cast-in-place concrete pile head shaping equipment, which is characterized in that including following step It is rapid:
1) stake position setting-out determines the position of pile foundation construction central point, the molding that split is got well and utilizes fixed mechanism fixed Device is placed in stake position, and former is located in bearing plate partial insertion ground below.
2) stake machine is in place, and the mould point of a mould is made to be directed at the center of former.
3) it is pushed down above bearing plate with weight, or is directly connected to a machine, push down bearing plate by the self weight of stake machine.
4) stake mould slowly sinks, and mould point is made slowly to be insert molded device, and then stake mould passes through former and slowly sinks in ground, Reach projected depth.
5) start concrete perfusion, start upper pile pulling mould after being injected more than the concrete of 1/3 height of a mould, draw out benefit on side Fill concrete.Former is pushed down by weight or the self weight of stake machine, remains motionless.
6) after stake mould is extracted completely, a machine is removed, the weight on bearing plate is removed, adjusts concrete later.According to stake top Designed elevation adjusts former inner concrete amount.If top of concrete height exceeds designed elevation, part concrete is dug out. If top of concrete height is lower than designed elevation, continue to add a certain amount of concrete into pile crown former.Finally make coagulation Native top surface absolute altitude reaches designed elevation.
7) after the initial set of pile crown former inner concrete, pile crown former is extracted by ground by lifting lug I and lifting lug II, is opened It is after fixed mechanism that die body I and die body II is split around articulated section, it finally takes former away, achievees the purpose that pile crown is formed.
A kind of application method based on a kind of cast-in-place concrete pile head shaping equipment, which is characterized in that including following step It is rapid:
1) stake position setting-out determines the position of pile foundation construction central point, former is placed in stake position, and former is located at In bearing plate partial insertion ground below.
2) stake machine is in place, and the mould point of a mould is made to be directed at the center of former.
3) it is pushed down above bearing plate with weight, or is directly connected to a machine, push down bearing plate by the self weight of stake machine.
4) stake mould slowly sinks, and mould point is made slowly to be insert molded device, and then stake mould passes through former and slowly sinks in ground, Reach projected depth.
5) start concrete perfusion, start upper pile pulling mould after injecting a certain amount of concrete, draw out supplement concrete on side. Former is pushed down by weight or the self weight of stake machine, remains motionless.
6) after stake mould is extracted completely, a machine is removed, the weight on bearing plate is removed, adjusts concrete later.According to stake top Designed elevation adjusts former inner concrete amount.If top of concrete height exceeds designed elevation, part concrete is dug out. If top of concrete height is lower than designed elevation, continue to add a certain amount of concrete into pile crown former.Finally make coagulation Native top surface absolute altitude reaches designed elevation.
7) after the initial set of pile crown former inner concrete, pile crown former is extracted by ground by lifting lug I and lifting lug II, then It takes former away from pile body, achievees the purpose that pile crown is formed.
The cross sectional shape of the former is determined according to pile body section to be poured, the cross sectional shape of former with to The pile body cross sectional shape poured is consistent.The cross sectional shape of the former can be circle, rectangle, X-shaped or Y shape.
The former, which sinks to ground, can place weight pushing realization in bearing plate I and bearing plate II, can also be direct Stake machine is installed on, the strength of pushing is provided on bearing plate.
The type chamber sectional dimension of the former is greater than pile body sectional dimension to be poured.
The solution have the advantages that unquestionable, former can be effectively prevented concrete and squeeze out to surrounding soil, Be conducive to the normal molding of pile body.It is also believed that adjusting the height of pile body and the top matter of rest and reorganization pile body in former Amount.So that work progress becomes convenient and easy, the efficiency of construction and the quality of pile body are improved.
Detailed description of the invention
Fig. 1 is top view of the invention;
Fig. 2 is the cross-sectional view of Fig. 1;
Fig. 3 is operation schematic diagram of the invention.
In figure: former (1), die body I (101), die body II (102), articulated section (103), fixed mechanism (104), type chamber (105), bearing plate I (2), lifting lug I (201), bearing plate II (3), lifting lug II (301), weight (4), stake mould (5), mould body (501), mould is sharp (502).
Specific embodiment
Below with reference to embodiment, the invention will be further described, but should not be construed the above-mentioned subject area of the present invention only It is limited to following embodiments.Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and used With means, various replacements and change are made, should all include within the scope of the present invention.
Embodiment 1:
A kind of cast-in-place concrete pile head shaping equipment, which is characterized in that be suitable for soft clay area, including 1 He of former Bearing plate.
The former 1 is the open hollow cylinder of upper and lower side, and the hollow space of the former 1 is that semi-surrounding is empty Between, the semi-surrounding space is type chamber 105.The former 1 is to opening structure, and the former 1 includes die body I 101, die body II 102, articulated section 103 and fixed mechanism 104.The hollow cylinder splitted along axial direction to just to obtain shapes and sizes all the same Die body I 101 and die body II 102.The die body I 101 and die body II 102 can piece together a complete former 1.The mould Body I 101 and the tool of die body II 102 there are two split position, one of position be it is hinged, with articulated section 103, another position Fixed mechanism 104 is installed.The die body I 101 and die body II 102 can be split around articulated section 103, the fixed mechanism 104 The die body I 101 of closure to be fixedly connected with die body II 102.
1 side of former is equipped with bearing plate, and the bearing plate includes bearing plate I 2 and bearing plate II 3, described to hold The plate face normal direction of pressing plate is consistent with the length direction of former 1.The bearing plate I 2 and bearing plate II 3 are respectively arranged in into One end of the two sides of 1 length direction of type device, I 2 length direction of bearing plate is fixedly connected with 1 outer surface of former, the other end Vacantly.One end of II 3 length direction of bearing plate is fixedly connected with 1 outer surface of former, and the other end is hanging.The bearing plate I 2 and bearing plate II 3 it is symmetrical about the center line of former 1.
The bearing plate I 2 is equipped with lifting lug I 201 far from one end of former 1, and the bearing plate II 3 is far from former 1 One end lifting lug II 301 is installed.The equipment that the lifting lug I 201 and lifting lug II 301 are used to connect lifting former 1.
A kind of application method based on a kind of cast-in-place concrete pile head shaping equipment, which is characterized in that including following step It is rapid:
1) stake position setting-out determines the position of pile foundation construction central point, split is got well and utilize fixed mechanism 104 it is fixed at Type device 1 is placed in stake position, and former 1 is located in bearing plate partial insertion ground below.
2) stake machine is in place, and the mould point 502 of a mould 5 is made to be directed at the center of former 1.
3) it is pushed down above bearing plate with weight, or is directly connected to a machine, push down bearing plate by the self weight of stake machine.
4) stake mould 5 slowly sinks, and so that mould point 502 is slowly insert molded device 1, then stake mould 5 passes through former 1 and slowly sinks to In ground, reach projected depth.
5) start concrete perfusion, start upper pile pulling mould 5 after being injected more than the concrete of 1/3 height of a mould, drawn out on side Supplement concrete.Former 1 is pushed down by weight or the self weight of stake machine, remains motionless.
6) after stake mould 5 is extracted completely, a machine is removed, the weight on bearing plate is removed, adjusts concrete later.According to stake top Designed elevation adjusts 1 inner concrete amount of former.If top of concrete height exceeds designed elevation, part concrete is dug out. If top of concrete height is lower than designed elevation, continue to add a certain amount of concrete into pile crown former 1.Finally make coagulation Native top surface absolute altitude reaches designed elevation.
7) after the initial set of 1 inner concrete of pile crown former, pile crown former 1 is extracted by lifting lug I 201 and lifting lug II 301 Ground, open fixed mechanism 104 after die body I 101 and die body II 102 is split around articulated section 103, finally take former 1 away, reach The purpose being formed to pile crown.
The cross sectional shape of the former 1 is determined according to pile body section to be poured, the cross sectional shape of former 1 with Pile body cross sectional shape to be poured is consistent.The cross sectional shape of the former 1 can be circle, rectangle, X-shaped or Y shape.
The former 1, which sinks to ground, can place weight pushing realization in bearing plate I 2 and bearing plate II 3, can also be straight It connects for stake machine to be installed on and the strength of pushing is provided on bearing plate.
105 sectional dimension of type chamber of the former 1 is greater than pile body sectional dimension to be poured.
Embodiment 2:
A kind of cast-in-place concrete pile head shaping equipment, which is characterized in that be suitable for soft clay area, including 1 He of former Bearing plate.
The former 1 is the open hollow cylinder of upper and lower side, and the hollow space of the former 1 is that semi-surrounding is empty Between, the semi-surrounding space is type chamber 105.The former 1 is integrally formed.
1 side of former is equipped with bearing plate, and the bearing plate includes bearing plate I 2 and bearing plate II 3, described to hold The plate face normal direction of pressing plate is consistent with the length direction of former 1.The bearing plate I 2 and bearing plate II 3 are respectively arranged in into One end of the two sides of 1 length direction of type device, I 2 length direction of bearing plate is fixedly connected with 1 outer surface of former, the other end Vacantly.One end of II 3 length direction of bearing plate is fixedly connected with 1 outer surface of former, and the other end is hanging.The bearing plate I 2 and bearing plate II 3 it is symmetrical about the center line of former 1.
The bearing plate I 2 is equipped with lifting lug I 201 far from one end of former 1, and the bearing plate II 3 is far from former 1 One end lifting lug II 301 is installed.The equipment that the lifting lug I 201 and lifting lug II 301 are used to connect lifting former 1.
A kind of application method based on a kind of cast-in-place concrete pile head shaping equipment, which is characterized in that including following step It is rapid:
1) stake position setting-out determines the position of pile foundation construction central point, split is got well and utilize fixed mechanism 104 it is fixed at Type device 1 is placed in stake position, and former 1 is located in bearing plate partial insertion ground below.
2) stake machine is in place, and the mould point 502 of a mould 5 is made to be directed at the center of former 1.
3) it is pushed down above bearing plate with weight, or is directly connected to a machine, push down bearing plate by the self weight of stake machine.
4) stake mould 5 slowly sinks, and so that mould point 502 is slowly insert molded device 1, then stake mould 5 passes through former 1 and slowly sinks to In ground, reach projected depth.
5) start concrete perfusion, start upper pile pulling mould 5 after being injected more than the concrete of 1/3 height of a mould, drawn out on side Supplement concrete.Former 1 is pushed down by weight or the self weight of stake machine, remains motionless.
6) after stake mould 5 is extracted completely, a machine is removed, the weight on bearing plate is removed, adjusts concrete later.According to stake top Designed elevation adjusts 1 inner concrete amount of former.If top of concrete height exceeds designed elevation, part concrete is dug out. If top of concrete height is lower than designed elevation, continue to add a certain amount of concrete into pile crown former 1.Finally make coagulation Native top surface absolute altitude reaches designed elevation.
7) after the initial set of 1 inner concrete of pile crown former, pile crown former 1 is extracted by lifting lug I 201 and lifting lug II 301 Ground, open fixed mechanism 104 after die body I 101 and die body II 102 is split around articulated section 103, finally take former 1 away, reach The purpose being formed to pile crown.
The cross sectional shape of the former 1 is determined according to pile body section to be poured, the cross sectional shape of former 1 with Pile body cross sectional shape to be poured is consistent.The cross sectional shape of the former 1 can be circle, rectangle, X-shaped or Y shape.
The former 1, which sinks to ground, can place weight pushing realization in bearing plate I 2 and bearing plate II 3, can also be straight It connects for stake machine to be installed on and the strength of pushing is provided on bearing plate.
105 sectional dimension of type chamber of the former 1 is greater than pile body sectional dimension to be poured.

Claims (5)

1. a kind of application method of cast-in-place concrete pile head shaping equipment, it is characterised in that:
Cast-in-place concrete pile head shaping equipment is suitable for soft clay area, including former (1) and bearing plate;
The former (1) is the open hollow cylinder of upper and lower side, and the hollow space of the former (1) is that semi-surrounding is empty Between, the semi-surrounding space is type chamber (105);The former (1) is to opening structure, and the former (1) includes die body I (101), die body II (102), articulated section (103) and fixed mechanism (104);The hollow cylinder is splitted along axial direction and just obtains shape Shape and size die body I (101) and die body II (102) all the same;The die body I (101) and die body II (102) can piece together One complete former (1);There are two split position, one of positions for the die body I (101) and die body II (102) tool Be it is hinged, have articulated section (103), another position is equipped with fixed mechanism (104);The die body I (101) and die body II (102) can be split around articulated section (103), the fixed mechanism (104) is to the die body I (101) and die body II that will be closed (102) it is fixedly connected;
Former (1) side is equipped with bearing plate, and the bearing plate includes bearing plate I (2) and bearing plate II (3), described The plate face normal direction of bearing plate is consistent with the length direction of former (1);The bearing plate I (2) and bearing plate II (3) are respectively The two sides of former (1) length direction are installed on, one end and former (1) outer surface of bearing plate I (2) length direction are solid Fixed connection, the other end are hanging;One end of bearing plate II (3) length direction is fixedly connected with former (1) outer surface, another End is hanging;The bearing plate I (2) and bearing plate II (3) are symmetrical about the center line of former (1);
The bearing plate I (2) is equipped with lifting lug I (201) far from the one end of former (1), and the bearing plate II (3) is far from molding One end of device (1) is equipped with lifting lug II (301);The lifting lug I (201) and lifting lug II (301) are for connecting lifting former (1) Equipment;
Application method the following steps are included:
1) stake position setting-out determines the position of pile foundation construction central point, the molding that split is got well and utilizes fixed mechanism (104) fixed Device (1) is placed in stake position, and former (1) is located in bearing plate partial insertion ground below;
2) stake machine is in place, makes the center of mould sharp (502) alignment former (1) of a mould (5);
3) it is pushed down above bearing plate with weight, or is directly connected to a machine, push down bearing plate by the self weight of stake machine;
4) stake mould (5) slowly sinks, and so that mould sharp (502) is slowly insert molded device (1), then stake mould (5) is slow across former (1) It is slow falling enter ground in, reach projected depth;
5) start concrete perfusion, start upper pile pulling mould (5) after being injected more than the concrete of 1/3 height of a mould, draw out benefit on side Fill concrete;Former (1) is pushed down by weight or the self weight of stake machine, remains motionless;
6) after stake mould (5) is extracted completely, a machine is removed, the weight on bearing plate is removed, adjusts concrete later;It is set according to stake top Absolute altitude is counted, former (1) inner concrete amount is adjusted;If top of concrete height exceeds designed elevation, part concrete is dug out; If top of concrete height is lower than designed elevation, continue to add a certain amount of concrete into pile crown former (1);Finally make to mix Solidifying soil top surface absolute altitude reaches designed elevation;
7) after the initial set of pile crown former (1) inner concrete, by lifting lug I (201) and lifting lug II (301) by pile crown former (1) Extract ground, open fixed mechanism (104) after die body I (101) and die body II (102) is split around articulated section (103), finally take Former (1) is walked, achievees the purpose that pile crown is formed.
2. a kind of application method of cast-in-place concrete pile head shaping equipment, it is characterised in that:
Cast-in-place concrete pile head shaping equipment is suitable for soft clay area, including former (1) and bearing plate;
The former (1) is the open hollow cylinder of upper and lower side, and the hollow space of the former (1) is that semi-surrounding is empty Between, the semi-surrounding space is type chamber (105);The former (1) is integrally formed;
Former (1) side is equipped with bearing plate, and the bearing plate includes bearing plate I (2) and bearing plate II (3), described The plate face normal direction of bearing plate is consistent with the length direction of former (1);The bearing plate I (2) and bearing plate II (3) are respectively The two sides of former (1) length direction are installed on, one end and former (1) outer surface of bearing plate I (2) length direction are solid Fixed connection, the other end are hanging;One end of bearing plate II (3) length direction is fixedly connected with former (1) outer surface, another End is hanging;The bearing plate I (2) and bearing plate II (3) are symmetrical about the center line of former (1);
The bearing plate I (2) is equipped with lifting lug I (201) far from the one end of former (1), and the bearing plate II (3) is far from molding One end of device (1) is equipped with lifting lug II (301);The lifting lug I (201) and lifting lug II (301) are for connecting lifting former (1) Equipment;
Application method the following steps are included:
1) stake position setting-out determines the position of pile foundation construction central point, and former (1) is placed in stake position, and by former (1) position In bearing plate partial insertion ground below;
2) stake machine is in place, makes the center of mould sharp (502) alignment former (1) of a mould (5);
3) it is pushed down above bearing plate with weight, or is directly connected to a machine, push down bearing plate by the self weight of stake machine;
4) stake mould (5) slowly sinks, and so that mould sharp (502) is slowly insert molded device (1), then stake mould (5) is slow across former (1) It is slow falling enter ground in, reach projected depth;
5) start concrete perfusion, start upper pile pulling mould (5) after being injected more than the concrete of 1/3 height of a mould, draw out benefit on side Fill concrete;Former (1) is pushed down by weight or the self weight of stake machine, remains motionless;
6) after stake mould (5) is extracted completely, a machine is removed, the weight on bearing plate is removed, adjusts concrete later;It is set according to stake top Absolute altitude is counted, former (1) inner concrete amount is adjusted;If top of concrete height exceeds designed elevation, part concrete is dug out; If top of concrete height is lower than designed elevation, continue to add a certain amount of concrete into pile crown former (1);Finally make to mix Solidifying soil top surface absolute altitude reaches designed elevation;
7) after the initial set of pile crown former (1) inner concrete, by lifting lug I (201) and lifting lug II (301) by pile crown former (1) Ground is extracted, then takes former (1) away from pile body, achievees the purpose that pile crown is formed.
3. a kind of application method of cast-in-place concrete pile head shaping equipment according to claim 1 or claim 2, which is characterized in that The cross sectional shape of the former (1) is determined according to pile body section to be poured, the cross sectional shape of former (1) with it is to be poured The pile body cross sectional shape built is consistent;The cross sectional shape of the former (1) can be circle, rectangle, X-shaped or Y shape.
4. a kind of application method of cast-in-place concrete pile head shaping equipment according to claim 1 or claim 2, which is characterized in that The former (1), which sinks to ground, can place weight pushing realization in bearing plate I (2) and bearing plate II (3), can also be direct Stake machine is installed on, the strength of pushing is provided on bearing plate.
5. a kind of application method of cast-in-place concrete pile head shaping equipment according to claim 1 or claim 2, which is characterized in that Type chamber (105) sectional dimension of the former (1) is greater than pile body sectional dimension to be poured.
CN201610948821.7A 2016-10-26 2016-10-26 A kind of application method of cast-in-place concrete pile head shaping equipment Active CN106498938B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610948821.7A CN106498938B (en) 2016-10-26 2016-10-26 A kind of application method of cast-in-place concrete pile head shaping equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610948821.7A CN106498938B (en) 2016-10-26 2016-10-26 A kind of application method of cast-in-place concrete pile head shaping equipment

Publications (2)

Publication Number Publication Date
CN106498938A CN106498938A (en) 2017-03-15
CN106498938B true CN106498938B (en) 2019-05-21

Family

ID=58323025

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610948821.7A Active CN106498938B (en) 2016-10-26 2016-10-26 A kind of application method of cast-in-place concrete pile head shaping equipment

Country Status (1)

Country Link
CN (1) CN106498938B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395314A (en) * 2020-03-27 2020-07-10 宣城市政建设集团有限公司 CFG pile composite foundation construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN202787244U (en) * 2012-07-29 2013-03-13 山西四建集团有限公司 One-step molded test pile head for cast-in-place pile
CN103276729A (en) * 2013-06-03 2013-09-04 浙江金筑交通建设有限公司 Moving steel casing and cast-in-place pile construction method using same
CN203684211U (en) * 2014-01-07 2014-07-02 江苏中瑞路桥建设有限公司 Pile head processing device of bored pile
CN104314072A (en) * 2014-10-28 2015-01-28 中国化学工程第一岩土工程有限公司 Construction method of special-shaped cast-in-situ concrete pile
CN105297714A (en) * 2015-11-18 2016-02-03 中国核工业华兴建设有限公司 Integrative construction device and method for pile cap and pile body of pouring pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN202787244U (en) * 2012-07-29 2013-03-13 山西四建集团有限公司 One-step molded test pile head for cast-in-place pile
CN103276729A (en) * 2013-06-03 2013-09-04 浙江金筑交通建设有限公司 Moving steel casing and cast-in-place pile construction method using same
CN203684211U (en) * 2014-01-07 2014-07-02 江苏中瑞路桥建设有限公司 Pile head processing device of bored pile
CN104314072A (en) * 2014-10-28 2015-01-28 中国化学工程第一岩土工程有限公司 Construction method of special-shaped cast-in-situ concrete pile
CN105297714A (en) * 2015-11-18 2016-02-03 中国核工业华兴建设有限公司 Integrative construction device and method for pile cap and pile body of pouring pile

Also Published As

Publication number Publication date
CN106498938A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN102733376B (en) Composite pile and its construction method
CN101768970B (en) Construction method of concrete pile
CN110682415A (en) Porous ecological slope protection building block prefabricating mold
CN111364464A (en) Construction equipment for pouring concrete into karst cave and construction method thereof
CN106498938B (en) A kind of application method of cast-in-place concrete pile head shaping equipment
CN207878446U (en) A kind of telescopic deep-hole replacement rammer for column base
CN201172820Y (en) Tied joggle pile mould tube with lubricating valve pile toe
CN102828507B (en) The construction treating methods of major diameter cast-in-situ concrete composite pile
CN109024562A (en) A kind of long prefabricated tubular pile of major diameter and its construction method of classification propulsion
CN217810964U (en) Self-stabilizing hollow pile for deep expansive soil area
CN114703854B (en) Construction method of dam in water conservancy and hydropower engineering
CN104831726A (en) Barb grouting type anchor rod and construction method thereof
CN207058842U (en) A kind of assembly concrete prefabricated post slip casting groove and its making mould
CN109853534A (en) A kind of strength core pedestal pile constructing process
CN205329682U (en) What blade was expanded in area expands bottom tube stake
CN106592586B (en) Additional cuff back-up sand building stones prefabricated pile and its construction method
CN208472710U (en) A kind of press repeatedly mentions bottom-enlarging filling pile pile-forming apparatus
CN211646378U (en) Sleeve for immersed tube construction precast pile
CN211143053U (en) Pretensioned prestressed concrete pipe pile
CN102587564B (en) Manufacturing method for anti-separation wall body material
CN212477731U (en) Construction equipment for pouring concrete into karst cave
CN206655223U (en) A kind of prefabricated workpiece
CN214832611U (en) Building combined foundation pile
CN206599784U (en) Filling type stake hollow drill
CN206319314U (en) A kind of additional cuff back-up sand building stones prefabricated pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220530

Address after: 9-1, No. 20-1, Xuelin Yayuan, Shapingba District, Chongqing 400030

Patentee after: Ding Xuanming

Address before: 400044 No. 174, shazheng street, Shapingba District, Chongqing

Patentee before: Chongqing University

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221129

Address after: 213300 Room 406-2, No. 21, Chuangzhi Road, Kunlun Street, Liyang City, Changzhou City, Jiangsu Province

Patentee after: Jiangsu Swell Engineering Technology Co.,Ltd.

Address before: 9-1, No. 20-1, Xuelin Yayuan, Shapingba District, Chongqing 400030

Patentee before: Ding Xuanming

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240430

Address after: Room 524, No. 81 Shangshang Road, Kunlun Street, Liyang City, Changzhou City, Jiangsu Province, 213300

Patentee after: Jiangsu Siwei Architectural Design Institute Co.,Ltd.

Country or region after: China

Address before: 213300 Room 406-2, No. 21, Chuangzhi Road, Kunlun Street, Liyang City, Changzhou City, Jiangsu Province

Patentee before: Jiangsu Swell Engineering Technology Co.,Ltd.