CN106492367A - A kind of steel tower climbs security protection hanging piece - Google Patents
A kind of steel tower climbs security protection hanging piece Download PDFInfo
- Publication number
- CN106492367A CN106492367A CN201611181440.7A CN201611181440A CN106492367A CN 106492367 A CN106492367 A CN 106492367A CN 201611181440 A CN201611181440 A CN 201611181440A CN 106492367 A CN106492367 A CN 106492367A
- Authority
- CN
- China
- Prior art keywords
- connection board
- plate
- locating piece
- right connection
- outside
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- A—HUMAN NECESSITIES
- A62—LIFE-SAVING; FIRE-FIGHTING
- A62B—DEVICES, APPARATUS OR METHODS FOR LIFE-SAVING
- A62B35/00—Safety belts or body harnesses; Similar equipment for limiting displacement of the human body, especially in case of sudden changes of motion
Landscapes
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Business, Economics & Management (AREA)
- Emergency Management (AREA)
- Emergency Lowering Means (AREA)
Abstract
The invention discloses a kind of steel tower climbs security protection hanging piece, it is characterized in that being respectively equipped with relative rectangular shaped slot in two projections, locating piece is respectively equipped with two slotted eyes, locating piece upper end is hinged in slotted eye, locating piece lower end outside is provided with the shell fragment for pushing up which to offside slotted eye direction, two locating piece upper ends are connected with the basculating arm for each extending over out left connection board and right connection board, basculating arm is provided with bar hole, the plate for being leaned against in left connection board and right connection board respectively is interspersed with two bar holes, plate hypomere is provided with an inclined-plane contacted with inner edge on the outside of bar hole, two plate epimeres are provided with and are set in its outside guide hole being connected with left connection board and right connection board respectively, plate upper end connects hanger, hanger is connected with pull rope.Of the invention without taking replacing mounting position, changing gap also has protection, can be reduced and fallen the security incident that will result in real-time guard, and replacing position movement range is little, and the risk that falls is lower.
Description
Technical field
The present invention relates to be the safety protection equipment for climbing staffing during a kind of climbing steel tower, more particularly to a kind of
Steel tower climbs security protection hanging piece.
Background technology
China is vast in territory, and power transmission line and level mobile communications network are intensive, and the high steel tower for towering everywhere may be used
See, in order to ensure that equipment runs well, will climb up steel tower when industrial workers safeguard at ordinary times or rush to repair carries out work high above the ground, in height
Safety rope one end will be hung over a certain bearing on steel tower during idle job, the other end is linked with work high above the ground personnel, to guarantee
Job safety, this security protection that does after simply climbing up steel tower, and during climbing and climbing down, as people is motion
Safety rope can not be fixed on a fixed position, need frequently to take hook replacing mounting position, change gap and do not protect,
There is between two positions before and after when if it happens falling and will result in security incident, and changing the discrepancy in elevation, personnel to move up and down width
Degree is larger to be also susceptible to accident, and in the case that particularly operating personnel bears accessory, action is more clumsy, and risk is higher, before
As steel tower manufacturing enterprise we never have well method go to solve, await further innovating and solve.
Content of the invention
In order to solve the above problems, the invention provides a kind of steel tower climbing security protection hanging piece.
The technical solution used in the present invention is:A kind of steel tower climbs security protection hanging piece, it is characterised in that including left and right
Symmetrical left connection board and right connection board, left connection board with the outside of right connection board by together with end plate connection, left connection
The projection prominent to offside is connected on the inside of plate and right connection board, is respectively equipped with relative rectangular shaped slot in two projections, two
Locating piece is respectively equipped with slotted eye, and locating piece upper end is hinged in slotted eye, and locating piece lower end outside is provided with which to offside slotted eye
The shell fragment on direction top, two locating piece upper ends are connected with the basculating arm for each extending over out left connection board and right connection board, and basculating arm is provided with
Bar hole, is interspersed with the plate for being leaned against in left connection board and right connection board respectively in two bar holes, plate hypomere is provided with one and bar
The inclined-plane of inner edge contact on the outside of shape hole, two plate epimeres are provided with and are set in being connected with left connection board and right connection board respectively for its outside
The guide hole for connecing, plate upper end connect hanger, and hanger is connected with pull rope, is connected with suspension ring on end plate.
Further, safety rope is connected with the suspension ring.
Further, the plate upper end is connected as a single entity by dowel.
Hanging piece is put into when using by the present invention by slide rail upper end or lower end, and shell fragment heads into locating piece lower end inside on slide rail
The through hole of setting, during use, climbing personnel only only need to need to be carried by safety rope hanging on suspension ring, in climbing upwards upwards
Safety rope is drawn, under the effect of through hole upper limb, locating piece lower end overcomes the elastic force retraction slotted eye of shell fragment, reaches upper level through hole
Or personnel now occur fall to make which reach next stage through hole, locating piece lower end all can be again introduced into through hole in shell fragment, and
Make its lower edge withstand on slotted eye bottom, implement positioning and stop dropping, implement protection to climbing personnel, with the rising of climbing height, hanging piece
Also gradually rise, until climbing to the top of a mountain;When climbing downwards, when the personnel of climbing reach hanging piece position, plate is pressed with subordinate, under plate
Inner edge on the outside of section inclined-plane extruding bar hole, makes basculating arm action drives locating piece around its top articulated position rotation, locating piece lower end
Screw out through hole and simultaneously keep back-out state, then make which fall, under fall certain altitude pull rope pulling plate, in shell fragment
The lower locating piece lower end bullet of effect is implemented to slow down to the friction of longitudinal riser, is blocked to pass through aperture again, and personnel can just continue
Descending, reciprocal until landing, without taking replacing mounting position, change gap also has protection to the present invention, can be subtracted with real-time guard
Little fall the security incident that will result in, change that position movement range is little, the risk that falls is lower.
Description of the drawings
Fig. 1 is embodiment of the present invention overall schematic.
Fig. 2 is the embodiment of the present invention and slide rail cooperation schematic diagram.
Fig. 3 is that the embodiment of the present invention coordinates cross-sectional schematic with slide rail.
Reference:1 solebar angle;2 longitudinal risers;3 longitudinal side plates;4 through holes;5 left connection boards;6 right connection boards;7
End plate;8 is raised;9 slotted eyes;10 locating pieces;11 jointed shafts;12 shell fragments;13 basculating arm;14 bar holes;15 plates;16 inclined-planes;17 lead
Hole;18 hangers;19 suspension ring.
Specific embodiment
As shown in Figure 1, 2, 3, the steel tower climbing security protection hanging piece coordinates ferrum as individual components to the embodiment of the present invention
Slide rail on tower is used, and slide rail has a solebar angle 1, and when we are embodied as, solebar angle can be used as the one of steel tower
Column, it is also possible to be connected which with the angle-style column of existing steel tower, connection can adopt welding or bolt connection, solebar angle
The angle on left and right both sides is 90 degree, highly versatile, and solebar angle spine is connected with longitudinal riser 2, longitudinal riser and longitudinal angle
Angle formed by ferrum the right and left is equal, symmetrical, and longitudinal riser is connected with longitudinal direction on the side relative with solebar angle spine
Side plate 3, longitudinal riser constitute symmetrical T font structures with longitudinal side plate, and longitudinal riser is provided with the rectangle being equally spaced up and down
Through hole 4, preferable through 50 centimetres to 200 centimetres of pitch of holes.
Steel tower climbing security protection hanging piece is provided distributed over symmetrical 5 He of left connection board in the longitudinal side plate left and right sides
Linked together by end plate 7 on the outside of right connection board 6, left connection board and right connection board, divided on the inside of left connection board and right connection board
Do not connect the projection 8 towards through hole that oriented offside is projected, in two projections, be respectively equipped with the relative rectangle towards through hole
Slotted eye 9, is respectively equipped with locating piece 10 in two slotted eyes, locating piece upper end is located at outside through hole and is hinged on groove by jointed shaft 11
In hole, locating piece lower end inside probes into through hole, and locating piece lower end outside is provided with and for which to head into through hole to offside slotted eye direction
Shell fragment 12, two locating piece upper ends are connected with the basculating arm 13 for each extending over out left connection board and right connection board, and basculating arm is provided with bar
Shape hole 14, is interspersed with the plate 15 for being leaned against in left connection board and right connection board respectively in two bar holes, plate hypomere be provided with one with
The inclined-plane 16 of inner edge contact on the outside of bar hole, is pushed plate ramp effect inner edge on the outside of the bar hole, can be driven by basculating arm
Locating piece lower end retraction slotted eye, two plate epimeres are provided with and are set in which and outside are connected with left connection board and right connection board respectively
Guide hole 17, carries out spacing, plate upper end connection hanger 18, and hanger is connected with pull rope, makes locating piece lower end for pulling plate
Slotted eye is ejected, and suspension ring 19 is connected with end plate, for attachment security rope.Steel tower of the present invention climbs security protection hanging piece, uses
When just can directly with being set on slide rail, it is also possible to attachment security rope is separately configured and is carried by operating personnel, can be with arbitrary ferrum
Slide rail on tower is used cooperatively.
Locating piece upper end of the present invention is located at outside through hole, and locating piece lower end inside is headed into through hole by shell fragment, during use
Climbing personnel only only need to need to lift safety rope, on through hole by safety rope hanging on suspension ring, in climbing upwards upwards
Under edge effect, locating piece lower end overcomes the elastic force retraction slotted eye of shell fragment, reaches upper level through hole or personnel now occur and fall
Which is made to reach next stage through hole, locating piece lower end all can be again introduced into through hole in shell fragment, and its lower edge is withstood under slotted eye
Portion, implements positioning and stops dropping, and implements protection to climbing personnel, and with the rising of climbing height, hanging piece also gradually rises, until stepping on
Top;When climbing downwards, when the personnel of climbing reach hanging piece position, with subordinate pressure plate, plate hypomere inclined-plane extrudes bar hole
Outside inner edge, makes basculating arm action drives locating piece around its top articulated position rotation, and locating piece lower end screws out through hole and keeps
Back-out state, then make its fall, under fall certain altitude pull rope pull plate, shell fragment act under locating piece lower end
Bullet is implemented to slow down to the friction of longitudinal riser, is blocked to pass through aperture again, and personnel can just continue traveling downwardly, reciprocal until falling
Mounting position is changed without taking in ground, the present invention, and changing gap also has protection, can be reduced and fallen and will be made with real-time guard
Into security incident, change position movement range little, the risk that falls is lower.
During enforcement, safety rope can be directly connected on suspension ring, during use, safety rope is directly linked with operating personnel;
Also which can be made in plate upper end to be connected as a single entity by dowel, synchronization action.
It is only present pre-ferred embodiments in sum, all equivalent modifications that is done according to the application and prior art are added
It is considered as the technology of the present invention category.
Claims (3)
1. a kind of steel tower climbs security protection hanging piece, it is characterised in that the left connection board and right connection including symmetrical distribution
Plate, left connection board are connected on the inside of left connection board and right connection board together with end plate connection is passed through on the outside of right connection board
The projection prominent to offside, is respectively equipped with relative rectangular shaped slot, is respectively equipped with locating piece, locating piece in two slotted eyes in two projections
Upper end is hinged in slotted eye, and locating piece lower end outside is provided with the shell fragment for pushing up which to offside slotted eye direction, and two locating piece upper ends connect
The basculating arm for each extending over out left connection board and right connection board is connected to, basculating arm is provided with bar hole, in two bar holes, is interspersed with difference
The plate in left connection board and right connection board is leaned against, plate hypomere is provided with an inclined-plane contacted with inner edge on the outside of bar hole, and two insert
Plate epimere is provided with and is set in its outside guide hole being connected with left connection board and right connection board respectively, and plate upper end connects hanger,
Hanger is connected with pull rope, is connected with suspension ring on end plate.
2. a kind of steel tower climbs security protection hanging piece according to claim 1, it is characterised in that be connected with the suspension ring
Safety rope.
3. a kind of steel tower climbs security protection hanging piece according to claim 1, it is characterised in that the plate upper end passes through
Dowel is connected as a single entity.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611181440.7A CN106492367A (en) | 2016-12-20 | 2016-12-20 | A kind of steel tower climbs security protection hanging piece |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611181440.7A CN106492367A (en) | 2016-12-20 | 2016-12-20 | A kind of steel tower climbs security protection hanging piece |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106492367A true CN106492367A (en) | 2017-03-15 |
Family
ID=58335093
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611181440.7A Withdrawn CN106492367A (en) | 2016-12-20 | 2016-12-20 | A kind of steel tower climbs security protection hanging piece |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106492367A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108939346A (en) * | 2018-06-01 | 2018-12-07 | 中国建筑第八工程局有限公司 | Fashioned iron construction fall protection equipment and its application method |
CN112043989A (en) * | 2020-09-09 | 2020-12-08 | 魏孝堂 | Auxiliary maintenance device for overhead cable for electric power maintenance |
CN112610151A (en) * | 2021-01-26 | 2021-04-06 | 北京国富科尚装饰工程有限公司 | Be used for tower crane climbing to use protection device |
-
2016
- 2016-12-20 CN CN201611181440.7A patent/CN106492367A/en not_active Withdrawn
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108939346A (en) * | 2018-06-01 | 2018-12-07 | 中国建筑第八工程局有限公司 | Fashioned iron construction fall protection equipment and its application method |
CN108939346B (en) * | 2018-06-01 | 2020-06-30 | 中国建筑第八工程局有限公司 | Section steel construction anti-falling protection device and use method thereof |
CN112043989A (en) * | 2020-09-09 | 2020-12-08 | 魏孝堂 | Auxiliary maintenance device for overhead cable for electric power maintenance |
CN112610151A (en) * | 2021-01-26 | 2021-04-06 | 北京国富科尚装饰工程有限公司 | Be used for tower crane climbing to use protection device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106492367A (en) | A kind of steel tower climbs security protection hanging piece | |
GB2493283A9 (en) | Overhead access platform | |
CN206273290U (en) | A kind of steel tower climbs security protection hanging piece | |
CN206290926U (en) | A kind of monitoring camera hoistable platform | |
CN206273291U (en) | A kind of steel tower climbs safety device | |
CN206267613U (en) | A kind of steel tower with security protection rail | |
CN106512256A (en) | Safety protection device for climbing steel-structure tower | |
CN106522637A (en) | Steel structure tower with safety protection rail | |
CN207323988U (en) | Climber | |
CN106581884A (en) | Safety protection assembly for iron tower climbing | |
CN109854063A (en) | A kind of communication steel tower | |
CN203915953U (en) | Telescopic anti-skidding climber for climbing | |
CN207537892U (en) | Bridge construction fall arrest device | |
CN210317135U (en) | Jar body overhauls device | |
CN106499251B (en) | A kind of spring-piece type steel tower climbing safety extension rail | |
EP2299028A3 (en) | Side guard rail for a scaffold | |
CN211500513U (en) | Telescopic staircase | |
CN205743676U (en) | Electric power network repairing hanging ladder | |
DE102011076088B4 (en) | Compensation device for a climbing protection device of a vertical ladder | |
CN206295518U (en) | A kind of steel tower climbs safety protection component | |
CN211370272U (en) | Safe cat ladder | |
EP2072730A3 (en) | Fitting device for lifting/sliding elements and lifting/sliding element | |
CN220487477U (en) | Photovoltaic power generation project climbing ladder | |
CN206261963U (en) | A kind of electric power tower climbs safety device | |
CN211874364U (en) | Climbing operation ladder stand protected by safety belt |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20170315 |