High-speed railway accurate adjustment double track operational method simultaneously
Technical field
The present invention relates to railway accurate adjustment technical field, be specifically related to high-speed railway accurate adjustment double track operational method simultaneously.
Background technology:
The traditional tune rail method in various countries is first to adjust benchmark rail, adjusts auxiliary rail further according to benchmark rail track forces, track gauge adjuster, should
Method of adjustment can meet technology and require, but efficiency of construction is very low, it is impossible to meet that present skylight point is short, task reappears real bar
Part.
Content of the invention
For the problems referred to above, the technical problem to be solved in the present invention is to provide that a kind of technological design is reasonable, easy to operate, executes
Work efficiency rate is high and stay-in-grade high-speed railway accurate adjustment double track operational method simultaneously.
The high-speed railway accurate adjustment double track of present invention operational method simultaneously, it comprises the steps of:
1st, reach the standard grade and before Window time, the upper road junction set specified must be reached half an hour before operation, and all work machines
Tool, material are put at correct position and are neatly easy to the protected personnel of equipment control unit and check and take pictures.All personnel must wear
Protective garment, all work facility must paste reflecting sign in notable position.Entrance operation orderly after skylight point is given an written reply
Section;
What the 2nd, work facility, material must be in good order piles up on flat bogie, prevents from dropping, it is simple to provide.
3rd, 0 grade of rail inspection instrument is used to detect circuit before operation;
4th, after advancing to operation mileage, scheme mark personnel are labeled in circuit agreement adjustment amount in advance accurately
Position;
5th, providing personnel's conscientious accurately granting following closely of material, inspection personnel verifies at once;
6th, provide packing ring and reclaim the position that old material personnel are placed on new packing ring agreement in turn;
7th, after while above personnel's operation, operating personnel is doing operating reserves.As provided instrument, electric wrench electricity
Source line pulls and puts in place;
8th, about about 20 meters are had to unscrew fastening bolt with regard to engine-generator electric wrench at once above issuance of materials;
9th, looser a bolt and change fastener personnel after 20 at once and take out screw rod, butterfly button, with rail jack jack-up rail at once.
Personnel's all replacings quick, correct by the material provided in place put in place;
10th, in the case of confirming safe, put down rail after having changed material, change new packing ring and so put butterfly button well
And screw rod, the so very clear inspection personnel being easy to below confirms to change performance;
11st, the old material changing all is placed in the middle of circuit, forbids to lose the region beyond circuit, in case the personnel of recovery
Omit.Fastener after inspection personnel exchanges part in time checks, have or not miss change, drain, backing plate dislocation, block is closely connected etc. asks
Topic simultaneously corrects at once.The personnel that simultaneously reclaim are receiving old material;
12nd, pre-loading screw after oiling personnel's oiling after inspection personnel confirms, fastening bolt personnel use internal combustion wrench make-up
Part fastens;
13rd, operation forward impelling more than 50 meters, labeled data personnel just can return to check by track forces after completing work
Gauge, level, be found to have value bigger than normal and make a record, and uses artificial torque spanner to eliminate big value.
14th, detecting track with 0 grade of rail inspection instrument after completing set workload, if any transfiniting, section can at once
The horse back that can affect driving eliminates.After elimination, track is carried out detecting and preserves data by second hand rail inspection instrument;
15th, reach orderly being withdrawn into outside circuit behind lower road junction, at correct position, all work facility, material etc. are put whole
Being easy to together check take pictures, and filling in registration form, protection personnel disappears a little.
When the present invention operates, high-speed railway accurate adjustment double track simultaneously working system can few in the activity duration (restrictions of skylight point), times
Business is more much higher than traditional single track working system work efficiency under conditions of heavy.
Beneficial effects of the present invention:Technological design is reasonable, and operational stability is high, and flexibility is good, and efficiency is high.
Brief description
For ease of explanation, the present invention is embodied as and accompanying drawing is described in detail by following.
Fig. 1 is the structural representation of the present invention;
Fig. 2 is second time accurate adjustment schematic diagram;
Detailed description of the invention
As shown in Figure 1 to Figure 2, this detailed description of the invention is by the following technical solutions:It comprises the steps of:
1st, reach the standard grade and before Window time, the upper road junction set specified must be reached half an hour before operation, and all work machines
Tool, material are put at correct position and are neatly easy to the protected personnel of equipment control unit and check and take pictures.All personnel must wear
Protective garment, all work facility must paste reflecting sign in notable position.Entrance operation orderly after skylight point is given an written reply
Section;
What the 2nd, work facility, material must be in good order piles up on flat bogie, prevents from dropping, it is simple to provide.
3rd, 0 grade of rail inspection instrument is used to detect circuit before operation;
4th, after advancing to operation mileage, scheme mark personnel are labeled in circuit agreement adjustment amount in advance accurately
Position;
5th, providing personnel's conscientious accurately granting following closely of material, inspection personnel verifies at once;
6th, provide packing ring and reclaim the position that old material personnel are placed on new packing ring agreement in turn;
7th, after while above personnel's operation, operating personnel is doing operating reserves.As provided instrument, electric wrench electricity
Source line pulls and puts in place;
8th, about about 20 meters are had to unscrew fastening bolt with regard to engine-generator electric wrench at once above issuance of materials;
9th, looser a bolt and change fastener personnel after 20 at once and take out screw rod, butterfly button, with rail jack jack-up rail at once.
Personnel's all replacings quick, correct by the material provided in place put in place;
10th, in the case of confirming safe, put down rail after having changed material, change new packing ring and so put butterfly button well
And screw rod, the so very clear inspection personnel being easy to below confirms to change performance;
11st, the old material changing all is placed in the middle of circuit, forbids to lose the region beyond circuit, in case the personnel of recovery
Omit.Fastener after inspection personnel exchanges part in time checks, have or not miss change, drain, backing plate dislocation, block is closely connected etc. asks
Topic simultaneously corrects at once.The personnel that simultaneously reclaim are receiving old material;
12nd, pre-loading screw after oiling personnel's oiling after inspection personnel confirms, fastening bolt personnel use internal combustion wrench make-up
Part fastens;
13rd, operation forward impelling more than 50 meters, labeled data personnel just can return to check by track forces after completing work
Gauge, level, be found to have value bigger than normal and make a record, and uses artificial torque spanner to eliminate big value.
14th, detecting track with 0 grade of rail inspection instrument after completing set workload, if any transfiniting, section can at once
The horse back that can affect driving eliminates.After elimination, track is carried out detecting and preserves data by second hand rail inspection instrument;
15th, reach orderly being withdrawn into outside circuit behind lower road junction, at correct position, all work facility, material etc. are put whole
Being easy to together check take pictures, and filling in registration form, protection personnel disappears a little.
When the present invention operates, high-speed railway accurate adjustment double track simultaneously working system can few in the activity duration (restrictions of skylight point), times
Business is more much higher than traditional single track working system work efficiency under conditions of heavy.
Beneficial effects of the present invention:Technological design is reasonable, and operational stability is high, and flexibility is good, and efficiency is high.
The general principle of the present invention and principal character and advantages of the present invention have more than been shown and described.The skill of the industry
The simply explanation it should be appreciated that the present invention is not restricted to the described embodiments, described in above-described embodiment and specification for the art personnel
The principle of the present invention, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, these
Changes and improvements both fall within scope of the claimed invention.Claimed scope by appending claims and
Its equivalent defines.