CN106401148A - Indoor water pipe construction method - Google Patents

Indoor water pipe construction method Download PDF

Info

Publication number
CN106401148A
CN106401148A CN201610794704.XA CN201610794704A CN106401148A CN 106401148 A CN106401148 A CN 106401148A CN 201610794704 A CN201610794704 A CN 201610794704A CN 106401148 A CN106401148 A CN 106401148A
Authority
CN
China
Prior art keywords
water pipe
line
water
construction
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610794704.XA
Other languages
Chinese (zh)
Inventor
颜传赞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Goujia Network Technology Co Ltd
Original Assignee
Hangzhou Goujia Network Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Goujia Network Technology Co Ltd filed Critical Hangzhou Goujia Network Technology Co Ltd
Priority to CN201610794704.XA priority Critical patent/CN106401148A/en
Publication of CN106401148A publication Critical patent/CN106401148A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings

Abstract

The invention discloses an indoor water pipe construction method. The construction method comprises the following steps of (a) construction preparation, (b) water pipe arrangement, (c) positioning and setting-out of a water pipe position, (d) drilling and slotting of a water pipe arrangement position, (e) water pipe pre-arrangement, (f) water pipe installation and (g) water pressure testing. According to the indoor water pipe construction method, a PPR coil pipe serves as a water pipe, drilling and slotting are conducted according to a line drawn between two points during construction, the drawn line is used for primary positioning reference, the water pipe is integrally lifted by a certain distance through square clamping blocks and wooden cushion blocks according to a line drawn between two points, the drawn line is used for secondary positioning reference, the water pipe does not make contact with the ground integrally, and thus a protection effect on the water pipe is achieved; meanwhile, the water pipe can be arranged to be smooth, and water supply is more smooth; and after the water pipe is integrally installed, water pressure testing is conducted, and the construction quality is improved. In this way, the PPR coil pipe is higher in flexibility, the number of fused splices is decreased to a great extent, the water leakage probability is decreased, construction is accelerated, and the construction quality is improved.

Description

A kind of indoor water pipe construction method
Technical field
The present invention relates to interior decoration technical field is and in particular to a kind of indoor water pipe construction method.
Background technology
PPR pipe cry not only three type PA tubes and but also be polypropylene random copolymer pipe or PPR pipe, have energy-saving material-saving, environmental protection, High-strength light, corrosion-resistant, inner wall smooth non-scaling, construction and maintenance is easy, long service life the advantages of, be widely used in building The building industry such as plumbing, town and country plumbing, gas, electric power and cable jacket, industrial fluids conveying, agricultural irrigation, municipal administration, Industry and agriculture field.PPR pipe becomes tubing using atactic copolymerized polypropene is extruded, and injection becomes pipe fitting.
The water pipe of indoor employing is PPR pipe at present, and it has, and lightweight, health is nontoxic, heat-resist, corrosion-resistant, guarantor The advantages of warm nature can be good, in work progress, typically adopts hard PPR pipe, first carries out surveying setting-out, then carries out punching fluting, Then carry out water pipe connection and installation, pipeline is straight, many places branch or corner need to be set, a usual appropriate department need to be equipped with many Place's joint, easily directly disengages at hot melting connector, infiltration phenomenon often, is so accomplished by water piping again, increases into This, reduce efficiency of construction, and hot water pipe arrangement is intricate.
Content of the invention
The present invention is directed in prior art has the easily disengagement of infiltration, joint, provides a kind of indoor water pipe Construction method, using PPR coil pipe as water pipe, in work progress, is punched according to the line of 2 points of pull-outs and is slotted, pull-out Line be used for positioning for the first time reference, the lines further according to 2 points of pull-outs adopt square fixture block and wooden cushion block by water pipe integral raising Certain distance, the line of pull-out is used for the reference of second positioning, rather than by punching and slotting position, water pipe is positioned, and carries The accuracy of high water pipe integral position distribution, and before water pipe is installed, water pipe is not integrally contacted with ground, anti-antipriming pipe table Surface wear, carries out protective effect to water pipe, also water pipe can be arranged smooth-going, water flowing is more smooth simultaneously, after water pipe integral installation, Carry out hydraulic pressure test, improve construction quality, such PPR coil pipe has greater flexibility, largely reduce fusion splice Quantity, reduces leak probability, accelerates construction precision, improves construction quality.
In order to solve above-mentioned technical problem, the present invention is addressed by following technical proposals.
A kind of indoor water pipe construction method, comprises the steps:
(a) preparation of construction;
B () water pipe is arranged:According to construction drawing, the region of water pipe arrangement is drawn on construction drawing, every section of region is not with It is labeled with color, and mark the reserved mouth of pipe set by every section of water pipe layout area, be in charge of position and valve location;
(c) water pipe position construction layout:Water pipe set location is determined according to construction drawing water pipe bit map/bitmap size marking, Ground is arranged and is positioned using 2 points of span wire systems at the position of water pipe, and 2 points of span wire systems adopt and pull out between two nails Line, segmentation carries out bracing wire, then is pushed down the line of pull-out with fragment of brick, and the length of the line of 2 points of pull-outs controls within 2m, completes water After the construction layout of pipe position, the engineering completing is checked with construction drawing one by one it is ensured that water pipe position is correct;
The punching of (d) water pipe set location, fluting:First the line of ink marker, then the line by pull-out are ejected at fluting according to the line of pull-out Remove from nail, then according to the line of ink marker position ejected, carry out punching, slot, then the groove and through hole of setting is carried out Trimming, the actual size of groove and through hole is more than the further groove of design drawing and standard size 5-20mm of through hole, then recessed Carry out cleaning work in groove and through hole, then the stone cleaning out put in snakeskin bag, and be placed into unified place being collected Middle process;
E () water pipe is preset:Select PPR coil pipe as water pipe, first the line of pull-out is connected on nail again, further according to water pipe The position of construction layout, first constructs to the region of the water pipe arrangement being in centre, then the region of the water pipe arrangement to outside Constructed, first lay water main, the position of the line according to pull-out, water pipe is placed on ground, the centre position pressure of water pipe On line, overlook on the basis of water pipe do not expose line by workmen, more square fixture block is set on the ground, and water pipe is arranged on In square fixture block, then wooden cushion block is set between square fixture block, and water pipe is placed on wooden cushion block, then constructor Water pipe is arranged smooth-going by member, the line segmentation being arranged on below water pipe is being cut off, is fastening nail again, and will follow closely at remaining the end of a thread Son setting on the ground, then lays distributive pipe, and the paving mode of distributive pipe is identical with the paving mode of water main, then adopts Water main is connected by elbow with distributive pipe, after overall default water pipe, technical staff checked one by one according to construction drawing it is ensured that Water pipe position is correct, then carries out safeguard measure to water pipe;
F () water pipe is installed:First the line of pull-out is all removed, the set location further according to square fixture block opens up on the ground Draw-in groove, water pipe is arranged in groove and through hole by then segmentation, first removes wooden cushion block, and to wooden cushion block centralized recovery, Again water pipe is arranged in groove and through hole, square fixture block is embedded in draw-in groove simultaneously, then insert groove with cement mortar In through hole, and cement mortar is flattened;
(g) hydraulic pressure test.
Preferably, in step (a) preparation of construction, technical staff audits the reasonability of water pipe arrangement, and to job site Investigated, arrange workmen that product water tube is protected simultaneously.
Preferably, in step (e), be first arranged on water pipe in the housing lower half of square fixture block, then in housing lower half On end face, elastomeric pad is set with glue, then water pipe is arranged on housing lower half, then upper half-shell glue is fixed In elastomeric pad, then with fixing bolt, upper half-shell and housing lower half are fixed, realize water pipe and be arranged in square fixture block.
Preferably, in step (g) hydraulic pressure test, pressure gauge, pressurized equipment are connected with water pipe, and prepare one barrel totally Running water, then running water is pressed into toward in water pipe using pressurized equipment, after waiting mouth of pipe outflow water, and inner air tube is all discharged Afterwards, then with plug blocked, the delivery port of distalmost end selects last closure, starts pressure testing, set using pressurization after the completion of closure Standby when being forced into 0.6MPa, voltage stabilizing 20min, overpressure declines and is not more than 0.05MPa, then water pipe and water pipe junction is entered Row checks.
The present invention, due to employing above technical scheme, has significant technique effect:
1st, the present invention adopts PPR coil pipe as water pipe, and in work progress, 2 points of span wire systems mainly adopt two nails Between pull out line, segmentation carry out bracing wire so that pull-out line be in horizontality, great reference value.Workmen is according to two The line of point pull-out is punched and is slotted, and the line of pull-out is used for positioning for the first time reference;Further according to the line of 2 points of pull-outs, using side , by water pipe integral raising certain distance, square fixture block is embedded in groove together with water pipe, square card for shape fixture block and wooden cushion block Block can be to water pipe position-limiting action, and wooden cushion block energy recycle and reuse, reduces construction cost, and so line of pull-out is for second Secondary positioning reference, rather than by punching and slotting position water pipe is positioned, it is to avoid punching or slotting position not to and make The position obtaining water pipe setting is also inaccurate, improves the accuracy of water pipe integral position distribution, and before water pipe is installed, water pipe Entirety is not contacted with ground, prevents water tube surfaces from wearing and tearing, carries out protective effect to water pipe, also water pipe can be arranged smooth-going simultaneously, Water flowing is more smooth, after water pipe integral installation, carries out hydraulic pressure test, improves construction quality, such PPR coil pipe has bigger spirit Activity, largely reduces the quantity of fusion splice, reduces leak probability, accelerates construction precision, improves construction quality.
2nd, the square fixture block in the present invention is fixed water pipe using upper half-shell and housing lower half two-part structure, convenient Dismounting, can adjust square fixture block and be in position at water pipe, and setting elastomeric pad between upper half-shell and housing lower half, Elastomeric pad has elastic buffer effect, the clamping dynamics of upper half-shell and housing lower half can be adjusted so that upper half-shell and under Produce suitable active force between half shell to act on water pipe, prevent water tube surfaces damaged.
3rd, the present invention is blocked using plug, and the delivery port of distalmost end selects last closure, starts to try after the completion of closure Pressure, when being forced into 0.6MPa using pressurized equipment, voltage stabilizing 20min, overpressure declines no more than 0.05MPa, then to water pipe And water pipe junction is checked, improve construction quality.
Brief description
Fig. 1 is a kind of construction block diagram of present invention indoor water pipe construction method.
Specific embodiment
With embodiment, the present invention is described in further detail below in conjunction with the accompanying drawings.
As shown in figure 1, be a kind of present invention indoor water pipe construction method, the invention mainly relates to instrument include:
1st, electric hammer, it can be used for beating expansion bolt hole when facilities and equipment is fixing.2nd, 5m steel tape, it is used for measuring, again Core sized data.3rd, saw blade, it is used for cutting large pipe and metal material.4th, hammer and chisel, it is used for nailing and digs Hole.5th, pastel, it is used for drawing the region of water pipe arrangement.6th, cutting machine, it is mainly used in the line on wall cutting and ground Groove.7th, nail and rope, it is used for 2 points of bracing wires;8th, PPR Special scissorses, for the cutting of water pipe.9th, fusion splicer, it is used for water Pipe welding.10th, ink fountain, for playing the line of ink marker.Also include some other aids.
The present invention comprises the steps:
(a) preparation of construction:Technical staff audits the reasonability of water pipe arrangement, and job site is investigated, and pacifies simultaneously Row workmen protects to product water tube.Water pipe carrying when must not throw out without care, huddle, firmly conference lead to the mouth of pipe ftracture, Tubing should unify to be placed on specified location, no acidic at stacking, alkaline, oily material, to pollute, when stacking tubing, May be implemented on ground laying thin film, anti-antipriming pipe and the direct directly contact in ground and surface abrasion.
B () water pipe is arranged:According to construction drawing, the region of water pipe arrangement is drawn on construction drawing, every section of region is not with It is labeled with color, and mark the reserved mouth of pipe set by every section of water pipe layout area, be in charge of position and valve location.
(c) water pipe position construction layout:Water pipe set location is determined according to construction drawing water pipe bit map/bitmap size marking, Ground is arranged and is positioned using 2 points of span wire systems at the position of water pipe, and 2 points of span wire systems adopt and pull out between two nails Line, segmentation carries out bracing wire, then is pushed down the line of pull-out with fragment of brick.The length of the line of 2 points of pull-outs controls within 2m, completes water After the construction layout of pipe position, the engineering completing is checked with construction drawing one by one it is ensured that water pipe position is correct.
The punching of (d) water pipe set location, fluting:First the line of ink marker, then the line by pull-out are ejected at fluting according to the line of pull-out Remove from nail, then according to the line of ink marker position ejected, carry out punching, slot, then the groove and through hole of setting is carried out Trimming, the actual size of groove and through hole is more than the further groove of design drawing and standard size 5-20mm of through hole.Then recessed Carry out cleaning work in groove and through hole, then the stone cleaning out put in snakeskin bag, and be placed into unified place being collected Middle process.
E () water pipe is preset:Select PPR coil pipe as water pipe, first the line of pull-out is connected on nail again, further according to water pipe The position of construction layout, first constructs to the region of the water pipe arrangement being in centre, then the region of the water pipe arrangement to outside Constructed.First lay water main, the position of the line according to pull-out, water pipe is placed on ground, the centre position pressure of water pipe On line, overlook on the basis of water pipe do not expose line by workmen.Square fixture block is set on the ground again, and water pipe is arranged on In square fixture block, first water pipe is arranged in the housing lower half of square fixture block, then is arranged with glue on the end face of housing lower half Elastomeric pad, then water pipe is arranged on housing lower half, then upper half-shell glue is fixed on elastomeric pad, Ran Houyong Upper half-shell and housing lower half are fixed by fixing bolt, realize water pipe and are arranged in square fixture block.Then between square fixture block Wooden cushion block is set, and water pipe is placed on wooden cushion block, then water pipe is arranged smooth-going by workmen, will be arranged on water Line segmentation below pipe is cut off, and fastens nail again at remaining the end of a thread, and nail is arranged on the ground, then laying point water Pipe, the paving mode of distributive pipe is identical with the paving mode of water main.
Using elbow, water main is connected with distributive pipe, is mainly fixed using heat melting device, heat melting device adopts when using The dragging line plate of line with ground.Indicator lamp on heat melting device shows to arrive fusion temp when becoming green light, generally 250 DEG C.Water pipe Hot molten time and hot melt depth be considered as the caliber of water pipe and set, weld time is too short can lead to pipe fitting fusion less than Position, overlong time can lead to the mouth of pipe heated soft, concrete setting situation such as table 1:
Table 1
After overall default water pipe, technical staff is checked one by one according to construction drawing it is ensured that water pipe position is correct, then Safeguard measure is carried out to water pipe.
F () water pipe is installed:First the line of pull-out is all removed, the set location further according to square fixture block opens up on the ground Draw-in groove, water pipe is arranged in groove and through hole by then segmentation, first removes wooden cushion block, and to wooden cushion block centralized recovery, Again water pipe is arranged in groove and through hole, square fixture block is embedded in draw-in groove simultaneously, then insert groove with cement mortar In through hole, and cement mortar is flattened.
(g) hydraulic pressure test:Pressure gauge, pressurized equipment are connected with water pipe, and prepare one barrel of clean running water, then adopt Pressurized equipment is pressed into running water toward in water pipe, after waiting mouth of pipe outflow water, and after the whole discharge of inner air tube, then is sealed with plug Stifled, the delivery port of distalmost end selects last closure, starts pressure testing after the completion of closure, when being forced into 0.6MPa using pressurized equipment, Voltage stabilizing 20min, overpressure declines no more than 0.05MPa, then water pipe and water pipe junction is checked, improves construction matter Amount.
The present invention adopts PPR coil pipe as water pipe, in work progress, 2 points of span wire systems mainly adopt two nails it Between pull out line, segmentation carry out bracing wire so that pull-out line be in horizontality, great reference value.Workmen is according to 2 points The line of pull-out is punched and is slotted, and the line of pull-out is used for positioning for the first time reference;Further according to the line of 2 points of pull-outs, using square , by water pipe integral raising certain distance, square fixture block is embedded in groove together with water pipe, square fixture block for fixture block and wooden cushion block Can be to water pipe position-limiting action, and wooden cushion block energy recycle and reuse, reduces construction cost, so line of pull-out is used for for the second time Positioning reference, rather than by punching and slotting position water pipe is positioned, it is to avoid punch or slotting position not to and make The position that water pipe sets is also inaccurate, improves the accuracy of water pipe integral position distribution, and before water pipe is installed, water pipe is whole Body is not contacted with ground, prevents water tube surfaces from wearing and tearing, carries out protective effect to water pipe, also water pipe can be arranged smooth-going simultaneously, lead to Water is more smooth, after water pipe integral installation, carries out hydraulic pressure test, improves construction quality, and such PPR coil pipe has bigger flexible Property, largely reduce the quantity of fusion splice, reduce leak probability, accelerate construction precision, improve construction quality.
Square fixture block in the present invention is fixed water pipe using upper half-shell and housing lower half two-part structure, conveniently tears open Dress, can adjust square fixture block and be in position at water pipe, and setting elastomeric pad, bullet between upper half-shell and housing lower half Property pad there is elastic buffer effect, the clamping dynamics of upper half-shell and housing lower half can be adjusted so that upper half-shell and lower half Produce suitable active force between housing to act on water pipe, prevent water tube surfaces damaged.
In a word, the foregoing is only presently preferred embodiments of the present invention, all equalizations made according to scope of the present invention patent Change and modification, all should belong to the covering scope of patent of the present invention.

Claims (4)

1. a kind of indoor water pipe construction method is it is characterised in that comprise the steps:
(a) preparation of construction;
B () water pipe is arranged:According to construction drawing, the region of water pipe arrangement is drawn on construction drawing, every section of region is with without face Color is labeled, and marks the reserved mouth of pipe set by every section of water pipe layout area, is in charge of position and valve location;
(c) water pipe position construction layout:Water pipe set location is determined according to construction drawing water pipe bit map/bitmap size marking, on ground Positioned using 2 points of span wire systems at the position of setting water pipe, 2 points of span wire systems adopt and pull out line between two nails, Segmentation carries out bracing wire, then is pushed down the line of pull-out with fragment of brick, and the length of the line of 2 points of pull-outs controls within 2m, completes water pipe position After putting construction layout, the engineering completing is checked with construction drawing one by one it is ensured that water pipe position is correct;
The punching of (d) water pipe set location, fluting:First the line of ink marker is ejected at fluting according to the line of pull-out, then by the line of pull-out from nail Remove on son, then according to the line of ink marker position ejected, carry out punching, slot, then the groove and through hole of setting is rebuild, The actual size of groove and through hole is more than the further groove of design drawing and standard size 5-20mm of through hole, then in groove and logical Carry out cleaning work in hole, then the stone cleaning out put in snakeskin bag, and be placed into unified place being focused on;
E () water pipe is preset:Select PPR coil pipe as water pipe, first the line of pull-out is connected on nail again, further according to water pipe positioning The position of setting-out, first constructs to the region of the water pipe arrangement being in centre, then the region of the water pipe arrangement in outside is carried out Construction, first lays water main, the position of the line according to pull-out, water pipe is placed on ground, the centre position of water pipe is pressed in line On, overlook on the basis of water pipe do not expose line by workmen, more square fixture block is set on the ground, and water pipe is arranged on square In fixture block, then wooden cushion block is set between square fixture block, and water pipe is placed on wooden cushion block, then workmen will Water pipe arranges smooth-going, the line segmentation being arranged on below water pipe is being cut off, is fastening nail again, and nail is set at remaining the end of a thread Put on the ground, then lay distributive pipe, the paving mode of distributive pipe is identical with the paving mode of water main, then adopt elbow Water main is connected with distributive pipe, after overall default water pipe, technical staff is checked one by one according to construction drawing it is ensured that water pipe Position is correct, then carries out safeguard measure to water pipe;
F () water pipe is installed:First the line of pull-out is all removed, the set location further according to square fixture block opens up card on the ground Groove, water pipe is arranged in groove and through hole by then segmentation, first removes wooden cushion block, and to wooden cushion block centralized recovery, then Water pipe is arranged in groove and through hole, square fixture block is embedded in draw-in groove simultaneously, then with cement mortar insert groove and In through hole, and cement mortar is flattened;
(g) hydraulic pressure test.
2. a kind of indoor water pipe construction method according to claim 1 it is characterised in that:In step (a) preparation of construction, skill Art personnel audit the reasonability of water pipe arrangement, and job site is investigated, and arrange workmen that product water tube is entered simultaneously Row protection.
3. a kind of indoor water pipe construction method according to claim 1 it is characterised in that:In step (e), first water pipe is set Put in the housing lower half of square fixture block, then on the end face of housing lower half, elastomeric pad is set with glue, then water pipe is set Put on housing lower half, then upper half-shell glue be fixed on elastomeric pad, then with fixing bolt by upper half-shell and Housing lower half is fixed, and realizes water pipe and is arranged in square fixture block.
4. a kind of indoor water pipe construction method according to claim 1 it is characterised in that:In step (g) hydraulic pressure test, will Pressure gauge, pressurized equipment are connected with water pipe, and prepare one barrel of clean running water, then are pressed into toward in water pipe certainly using pressurized equipment Water, after waiting mouth of pipe outflow water, and after the whole discharge of inner air tube, then is blocked with plug, the delivery port of distalmost end selects Finally block, after the completion of closure, start pressure testing, when being forced into 0.6MPa using pressurized equipment, voltage stabilizing 20min, overpressure declines It is not more than 0.05MPa, then water pipe and water pipe junction are checked.
CN201610794704.XA 2016-08-31 2016-08-31 Indoor water pipe construction method Pending CN106401148A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610794704.XA CN106401148A (en) 2016-08-31 2016-08-31 Indoor water pipe construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610794704.XA CN106401148A (en) 2016-08-31 2016-08-31 Indoor water pipe construction method

Publications (1)

Publication Number Publication Date
CN106401148A true CN106401148A (en) 2017-02-15

Family

ID=58001789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610794704.XA Pending CN106401148A (en) 2016-08-31 2016-08-31 Indoor water pipe construction method

Country Status (1)

Country Link
CN (1) CN106401148A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108361476A (en) * 2018-02-12 2018-08-03 上海聚通装饰集团有限公司 A kind of heat preservation color separation identification upper hose and upper hose keep the temperature color separation identification technique
CN108481569A (en) * 2018-05-04 2018-09-04 广西家之宝网络科技有限公司 A kind of method of fluting
CN110566719A (en) * 2019-08-29 2019-12-13 中建二局第一建筑工程有限公司 Construction method for embedding wall pipeline
CN110645409A (en) * 2019-08-26 2020-01-03 广东博意建筑设计院有限公司 Pipeline routing method for floating platform with hidden pipeline structure
CN110685324A (en) * 2019-09-25 2020-01-14 天津建国电气设备销售有限公司 Method for installing PPR water pipe

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103672181A (en) * 2014-01-03 2014-03-26 永升建设集团有限公司 Water supply and drainage pipeline sleeve pre-embedding construction method
CN105178403A (en) * 2015-06-17 2015-12-23 青岛海川建设集团有限公司 Indoor water supply and drainage system concealed layout construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103672181A (en) * 2014-01-03 2014-03-26 永升建设集团有限公司 Water supply and drainage pipeline sleeve pre-embedding construction method
CN105178403A (en) * 2015-06-17 2015-12-23 青岛海川建设集团有限公司 Indoor water supply and drainage system concealed layout construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宜居网: "室内装修给水管道安装施工流程", 《HTTP://WWW.360DOC.COM/CONTENT/13/1020/08/256395_322718426.SHTML》 *
郑丹: "PPR水管施工方案", 《黑龙江科技信息》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108361476A (en) * 2018-02-12 2018-08-03 上海聚通装饰集团有限公司 A kind of heat preservation color separation identification upper hose and upper hose keep the temperature color separation identification technique
CN108481569A (en) * 2018-05-04 2018-09-04 广西家之宝网络科技有限公司 A kind of method of fluting
CN110645409A (en) * 2019-08-26 2020-01-03 广东博意建筑设计院有限公司 Pipeline routing method for floating platform with hidden pipeline structure
CN110566719A (en) * 2019-08-29 2019-12-13 中建二局第一建筑工程有限公司 Construction method for embedding wall pipeline
CN110566719B (en) * 2019-08-29 2022-03-22 中建二局第一建筑工程有限公司 Construction method for embedding wall pipeline
CN110685324A (en) * 2019-09-25 2020-01-14 天津建国电气设备销售有限公司 Method for installing PPR water pipe

Similar Documents

Publication Publication Date Title
CN106401148A (en) Indoor water pipe construction method
CN111456196B (en) Grouting structure for repairing sewage pipeline and pipeline grouting repairing method
CN103672181A (en) Water supply and drainage pipeline sleeve pre-embedding construction method
CN101338847A (en) HDPE tube welding-free interpenetration inner liner pipe-repairing method
CN105570534B (en) Shallow overburden push pipe controls the equipment and construction method of ground structure deformation
CN103883797A (en) Construction method of steel wire mesh framework plastic composite pipe
CN106733278A (en) A kind of ice fog flusher with antifreeze function
CN109610824A (en) A kind of localization method of fixed pre-buried steel casing
CN108661233A (en) A kind of steam-pressing aero-concrete matches hollow pipe gusset
CN110173121A (en) A kind of steel sleeve method for rapidly mounting
CN200940255Y (en) Protecting sleeve for steel cable
CN207308898U (en) A kind of coated sand core shooting machine adds sand system
CN207145867U (en) The commissure external anti-corrosion layer protection structure of long range horizontal directional drilling water supply line
CN206337814U (en) A kind of plumbing hole to be provided sleeve pipe
CN212430058U (en) Ring pressure type connecting thin-wall stainless steel pipe and stainless steel pipe combination
CN103883810B (en) A kind of steel wire mesh frame plastic composite tube and construction method
CN110345314A (en) PVC-C pipeline automatic sprinkler system construction method
CN107270028A (en) A kind of automatically walk pipeline rehabilitation device and pipe repairing method
CN202834386U (en) Three-dimensional hyperbolic steel pipe jacking axis formed transitional device
CN207178964U (en) A kind of connecting pipe double containment attachment structure
CN208874239U (en) Power cable steel spigot-and-socket Prefabricated concrete multi-holes cable fitting
CN207988544U (en) A kind of concrete structure depth filling crack with glue bar
CN204818565U (en) Pressure steel pipe stiffening ring installation tension sleeve device
CN204592557U (en) The hinged pipe joint open control gear of curve steel pipe jacking
CN106565021B (en) Pipeline construction method for ecological wetland

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215