CN106400822A - 深基坑降水井封井施工方法 - Google Patents
深基坑降水井封井施工方法 Download PDFInfo
- Publication number
- CN106400822A CN106400822A CN201610843911.XA CN201610843911A CN106400822A CN 106400822 A CN106400822 A CN 106400822A CN 201610843911 A CN201610843911 A CN 201610843911A CN 106400822 A CN106400822 A CN 106400822A
- Authority
- CN
- China
- Prior art keywords
- well
- precipitation
- water
- concrete
- shut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/20—Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
Abstract
本发明主要应用于建筑施工技术领域,特别涉及一种深基坑降水井封井施工方法,采取以下步骤:1)机械开挖基坑至原状地基土;2)夯打埋入混凝土滤水管;3)安装降水封井主管;4)放入潜水泵;5)在降水封井主管顶部安装盖板套件;6)在降水井密封圈上部将盖板套件与降水封井主管固定;7)将排水管结合器连接至排水管连接法兰盘上;8)启动潜水泵;9)修整边坡;10)浇筑筏板混凝土;11)保持降水;12)移除潜水泵;13)安装降水井密封圈,同步安装封井盖板;14)浇筑降水井封闭混凝土。本发明适合高水位地区和涌水量大的区域,并且可以取出潜水泵,施工步骤简单,降低劳动强度,且容易实现,可以提高工作效率及施工质量。
Description
技术领域
本发明涉及一种深基坑降水井封井施工方法,主要应用于建筑施工技术领域。
背景技术
传统深基坑降水工程,在其封井时,一般采用两种施工方案。一是,取出排水用潜水泵后,浇灌大量混凝土,利用足够量的混凝土配合大量水泥干粉的重力作用封井,利用水泥干粉吸水,使之干硬。但此种方法不适合高水位地区和涌水量大的区域,在取出潜水泵后,混凝土凝固时间不足,混凝土被冲掉,影响防水效果,造成基础的底板渗漏。二是,不取出潜水泵,在抽水状态下,直接浇灌混凝土。待混凝土凝固后,二次封堵管道并断电剪掉电缆。此种方法在浇筑过程中,水泵极易发生堵塞而漏电,触发安全隐患,并且此种方法将潜水泵埋入混凝土中,无法取出,造成经济损失和浪费。
发明内容
本发明要解决的技术问题是:提供一种适用于高水位地区和涌水量大的区域封井,且可将潜水泵取出的深基坑降水井封井施工方法。
本发明所述的深基坑降水井封井施工方法,其特征在于采取以下步骤:
1)机械开挖基坑至原状地基土,达到集水井底标高位置;
2)夯打埋入混凝土滤水管;
3)安装降水封井主管,将圆环形钢板底座,安放于混凝土滤水管上部并对正,并预先穿入降水井密封圈并对正;
4)依次穿过降水封井主管、混凝土滤水管,放入潜水泵附带潜水泵电缆及抽水胶皮管;
5)在降水封井主管顶部安装盖板套件,盖板套件包括抽水盖板、主抽水管及潜水泵电缆进线管,主抽水管和潜水泵电缆进线管均贯穿抽水盖板,将抽水胶皮管上部与主抽水管相连接,并用固定铜丝绑扎牢靠,潜水泵电缆穿出潜水泵电缆进线管;
6)在降水井密封圈上部将盖板套件与降水封井主管用主法兰紧固螺栓固定;
7)主抽水管顶部设有排水管连接法兰盘,在排水管连接法兰盘上放置排水管密封圈,将排水管结合器通过排水管紧固螺栓连接至排水管连接法兰盘上,并拧紧;
8)启动潜水泵,进行降水作业,并将地下水降至工作面以下至少500mm;
9)待边坡土质晾干后,修整边坡;
10)绑扎筏板钢筋,安装混凝土止水钢板,浇筑筏板混凝土;
11)保持降水直至筏板基础全部施工完成,达到停止降水条件;
12)拆除主法兰紧固螺栓,并同步移除潜水泵、抽水胶皮管附带固定铜丝、潜水泵电缆;
13)安装降水井密封圈,同步安装封井盖板,并紧固;
14)浇筑降水井封闭混凝土。
所述的降水封井主管上设置主管止水板,主管止水板设置为两个,轴向分布在降水封井主管上。
本发明的有益效果是:
适合高水位地区和涌水量大的区域,并且可以取出潜水泵,施工步骤简单,降低劳动强度,且容易实现,可以提高工作效率及施工质量。
附图说明
图1是本发明施工过程中的结构示意图。
图2是图1中封井后的结构示意图。
图3是降水封井主管的结构示意图。
图4是封井盖板的结构示意图。
图5是盖板套件的结构示意图。
图6是图5的俯视结构示意图。
图中:1、筏板混凝土;2、混凝土止水钢板;3、固定铜丝;4、降水井密封圈;5、混凝土滤水管;6、潜水泵电缆;7、潜水泵;8、抽水胶皮管;9、集水井底标高;10、降水井封闭混凝土;11、封井盖板;12、主法兰紧固螺栓;13、主管止水板;14、钢板底座;15、排水管结合器;16、排水管密封圈;17、排水管连接法兰盘;18、主抽水管;19、抽水盖板;20、潜水泵电缆进线管。
具体实施方式
下面结合附图对本发明做进一步描述:
如图1~图6所示,本发明所述的深基坑降水井封井施工方法,采取以下步骤:
1)机械开挖基坑至原状地基土,达到集水井底标高9位置;
2)夯打埋入混凝土滤水管5;
3)安装降水封井主管,将圆环形钢板底座14安放于混凝土滤水管5上部并对正,并预先穿入降水井密封圈4并对正;
4)依次穿过降水封井主管、混凝土滤水管5,放入潜水泵7附带潜水泵电缆6及抽水胶皮管8;
5)在降水封井主管顶部安装盖板套件,盖板套件包括抽水盖板19、主抽水管18及潜水泵电缆进线管20,主抽水管18和潜水泵电缆进线管20均贯穿抽水盖板19,将抽水胶皮管8上部与主抽水管18相连接,并用固定铜丝3绑扎牢靠,潜水泵电缆6穿出潜水泵电缆进线管20;
6)在降水井密封圈4上部将盖板套件与降水封井主管用主法兰紧固螺栓12固定;
7)主抽水管18顶部设有排水管连接法兰盘17,在排水管连接法兰盘17上放置排水管密封圈16,将排水管结合器15通过排水管紧固螺栓连接至排水管连接法兰盘17上,并拧紧;
8)启动潜水泵7,进行降水作业,并将地下水降至工作面(即指集水井底标高9)以下至少500mm;
9)待边坡土质晾干后,修整边坡;
10)绑扎筏板钢筋,安装混凝土止水钢板2,浇筑筏板混凝土1;
11)保持降水直至筏板基础全部施工完成,达到停止降水条件;
12)拆除主法兰紧固螺栓12,并同步移除潜水泵7、抽水胶皮管8附带固定铜丝3、潜水泵电缆6;
13)安装降水井密封圈4,同步安装封井盖板11,并紧固;
14)浇筑降水井封闭混凝土10。
降水封井主管上设置主管止水板13,主管止水板13设置为两个,轴向分布在降水封井主管上。
Claims (2)
1.一种深基坑降水井封井施工方法,其特征在于采取以下步骤:
1)机械开挖基坑至原状地基土,达到集水井底标高(9)位置;
2)夯打埋入混凝土滤水管(5);
3)安装降水封井主管,将圆环形钢板底座(14)安放于混凝土滤水管(5)上部并对正,并预先穿入降水井密封圈(4)并对正;
4)依次穿过降水封井主管、混凝土滤水管(5),放入潜水泵(7)附带潜水泵电缆(6)及抽水胶皮管(8);
5)在降水封井主管顶部安装盖板套件,盖板套件包括抽水盖板(19)、主抽水管(18)及潜水泵电缆进线管(20),主抽水管(18)和潜水泵电缆进线管(20)均贯穿抽水盖板(19),将抽水胶皮管(8)上部与主抽水管(18)相连接,并用固定铜丝(3)绑扎牢靠,潜水泵电缆(6)穿出潜水泵电缆进线管(20);
6)在降水井密封圈(4)上部将盖板套件与降水封井主管用主法兰紧固螺栓(12)固定;
7)主抽水管(18)顶部设有排水管连接法兰盘(17),在排水管连接法兰盘(17)上放置排水管密封圈(16),将排水管结合器(15)通过排水管紧固螺栓连接至排水管连接法兰盘(17)上,并拧紧;
8)启动潜水泵(7),进行降水作业,并将地下水降至工作面以下至少500mm;
9)待边坡土质晾干后,修整边坡;
10)绑扎筏板钢筋,安装混凝土止水钢板(2),浇筑筏板混凝土(1);
11)保持降水直至筏板基础全部施工完成,达到停止降水条件;
12)拆除主法兰紧固螺栓(12),并同步移除潜水泵(7)、抽水胶皮管(8)附带固定铜丝(3)、潜水泵电缆(6);
13)安装降水井密封圈(4),同步安装封井盖板(11),并紧固;
14)浇筑降水井封闭混凝土(10)。
2.根据权利要求1所述的深基坑降水井封井施工方法,其特征在于:降水封井主管上设置主管止水板(13),主管止水板(13)设置为两个,轴向分布在降水封井主管上。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610843911.XA CN106400822B (zh) | 2016-09-23 | 2016-09-23 | 深基坑降水井封井施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610843911.XA CN106400822B (zh) | 2016-09-23 | 2016-09-23 | 深基坑降水井封井施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106400822A true CN106400822A (zh) | 2017-02-15 |
CN106400822B CN106400822B (zh) | 2018-06-26 |
Family
ID=57997827
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610843911.XA Expired - Fee Related CN106400822B (zh) | 2016-09-23 | 2016-09-23 | 深基坑降水井封井施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106400822B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110144919A (zh) * | 2019-05-30 | 2019-08-20 | 中冶建工集团有限公司 | 埋置式降水节点施工方法 |
CN110258603A (zh) * | 2019-06-18 | 2019-09-20 | 李贺清 | 深基坑内局部超深基坑的隐形降水工法 |
CN110331732A (zh) * | 2019-07-30 | 2019-10-15 | 杭州江润科技有限公司 | 基坑减压降水体系及施工方法 |
CN113605431A (zh) * | 2021-09-17 | 2021-11-05 | 中建八局天津建设工程有限公司 | 用于集水坑的封堵结构及其施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09158196A (ja) * | 1995-12-05 | 1997-06-17 | Kajima Corp | ニューマチックケーソン工法における排水排土方法 |
CN202124865U (zh) * | 2011-06-22 | 2012-01-25 | 南通海洲建设集团有限公司 | 无砂水泥管深井降水井口快速封堵装置 |
CN103526766A (zh) * | 2013-10-12 | 2014-01-22 | 中建八局第三建设有限公司 | 一种深基坑减压井封堵方法 |
CN103556644A (zh) * | 2013-10-23 | 2014-02-05 | 中天建设集团有限公司 | 地下室底板降水井井口封堵套管及施工方法 |
CN204491645U (zh) * | 2015-03-24 | 2015-07-22 | 平煤神马建工集团有限公司土建处 | 一种深基坑降水封井装置 |
CN104929143A (zh) * | 2015-04-27 | 2015-09-23 | 华东交通大学 | 一种基坑底部降水井封井方法 |
CN105780791A (zh) * | 2014-08-28 | 2016-07-20 | 郭伟新 | 地下车库基坑内深井降水井口封井施工方法 |
-
2016
- 2016-09-23 CN CN201610843911.XA patent/CN106400822B/zh not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09158196A (ja) * | 1995-12-05 | 1997-06-17 | Kajima Corp | ニューマチックケーソン工法における排水排土方法 |
CN202124865U (zh) * | 2011-06-22 | 2012-01-25 | 南通海洲建设集团有限公司 | 无砂水泥管深井降水井口快速封堵装置 |
CN103526766A (zh) * | 2013-10-12 | 2014-01-22 | 中建八局第三建设有限公司 | 一种深基坑减压井封堵方法 |
CN103556644A (zh) * | 2013-10-23 | 2014-02-05 | 中天建设集团有限公司 | 地下室底板降水井井口封堵套管及施工方法 |
CN105780791A (zh) * | 2014-08-28 | 2016-07-20 | 郭伟新 | 地下车库基坑内深井降水井口封井施工方法 |
CN204491645U (zh) * | 2015-03-24 | 2015-07-22 | 平煤神马建工集团有限公司土建处 | 一种深基坑降水封井装置 |
CN104929143A (zh) * | 2015-04-27 | 2015-09-23 | 华东交通大学 | 一种基坑底部降水井封井方法 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110144919A (zh) * | 2019-05-30 | 2019-08-20 | 中冶建工集团有限公司 | 埋置式降水节点施工方法 |
CN110258603A (zh) * | 2019-06-18 | 2019-09-20 | 李贺清 | 深基坑内局部超深基坑的隐形降水工法 |
CN110331732A (zh) * | 2019-07-30 | 2019-10-15 | 杭州江润科技有限公司 | 基坑减压降水体系及施工方法 |
CN113605431A (zh) * | 2021-09-17 | 2021-11-05 | 中建八局天津建设工程有限公司 | 用于集水坑的封堵结构及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106400822B (zh) | 2018-06-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106400822B (zh) | 深基坑降水井封井施工方法 | |
CN102797266B (zh) | 一种降水井封井防水施工方法 | |
CN109736340B (zh) | 一种基础底板预留降水井保证垫层完整性的降水装置与方法 | |
CN204370458U (zh) | 一种明挖基坑排水装置 | |
CN103498486A (zh) | 一种采用套管对后浇带降水管井实施封堵的方法 | |
CN109025899B (zh) | 一种封井装置 | |
CN204080839U (zh) | 一种降排水装置 | |
CN103967015A (zh) | 一种深基坑止水开挖方法及其结构 | |
CN203768925U (zh) | 一种基坑内降水井的封堵装置 | |
CN201679008U (zh) | 基坑刚性排水装置 | |
CN205530388U (zh) | 一种地下工程用压力感应水压控制系统 | |
CN105201009B (zh) | 一种用于河道的杆塔基础负压施工法 | |
CN209040133U (zh) | 适用于地下水丰富区域的降水井封井装置 | |
CN103174154A (zh) | 一种固封地下建筑底板涌水井坑的方法及辅助降水装置 | |
CN203514332U (zh) | 一种对后浇带降水管井实施封堵的套管 | |
CN206070548U (zh) | 深基坑降水井盖板套件 | |
CN203022015U (zh) | 基础筏板底局部深基坑降水装置 | |
CN212715041U (zh) | 一种建筑工程底板后浇带超高压水体泄压装置 | |
CN207452927U (zh) | 一种超大基坑内沉箱排水装置 | |
KR101245334B1 (ko) | 온도유지 해수피막을 이용한 케이슨 기초 콘크리트 양생공법 | |
CN213805525U (zh) | 一种地下连续墙断墙处理装置 | |
CN206070549U (zh) | 深基坑降水井封井连接器 | |
CN217204294U (zh) | 一种地下室底板后浇带冒水节点的封堵结构 | |
CN103590379A (zh) | 电厂循环水系统的易装拆式隧洞口挡水装置及其施工方法 | |
KR20050017815A (ko) | 투 아치 터널의 굴착공법과 구조 및 설계 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Ma Chong Inventor after: Yuan Fengtao Inventor after: Si Jiwei Inventor after: Gao Haiyan Inventor before: Ma Chong Inventor before: Yuan Fengtao Inventor before: Si Jiwei |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180626 Termination date: 20190923 |