CN106384162A - Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification - Google Patents
Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification Download PDFInfo
- Publication number
- CN106384162A CN106384162A CN201610805004.6A CN201610805004A CN106384162A CN 106384162 A CN106384162 A CN 106384162A CN 201610805004 A CN201610805004 A CN 201610805004A CN 106384162 A CN106384162 A CN 106384162A
- Authority
- CN
- China
- Prior art keywords
- standby
- verification
- reserve
- generating set
- electric energy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000012795 verification Methods 0.000 title claims abstract description 54
- 238000000034 method Methods 0.000 title claims abstract description 28
- 238000005457 optimization Methods 0.000 title claims abstract description 23
- 238000005192 partition Methods 0.000 title abstract description 8
- 230000005540 biological transmission Effects 0.000 claims abstract description 42
- 238000009987 spinning Methods 0.000 claims description 33
- 230000009194 climbing Effects 0.000 claims description 15
- 238000009826 distribution Methods 0.000 claims description 9
- 238000012546 transfer Methods 0.000 claims description 9
- 239000011159 matrix material Substances 0.000 claims description 7
- 238000005562 fading Methods 0.000 claims description 6
- 238000005516 engineering process Methods 0.000 claims description 3
- 230000004044 response Effects 0.000 claims description 3
- 238000004088 simulation Methods 0.000 claims description 2
- 238000004804 winding Methods 0.000 claims 1
- OVBPIULPVIDEAO-LBPRGKRZSA-N folic acid Chemical compound C=1N=C2NC(N)=NC(=O)C2=NC=1CNC1=CC=C(C(=O)N[C@@H](CCC(O)=O)C(O)=O)C=C1 OVBPIULPVIDEAO-LBPRGKRZSA-N 0.000 abstract 1
- 230000005611 electricity Effects 0.000 description 13
- 238000012360 testing method Methods 0.000 description 8
- 230000033228 biological regulation Effects 0.000 description 3
- CGFFKDRVHZIQHL-UHFFFAOYSA-N 1-but-3-en-2-yl-3-(methylcarbamothioylamino)thiourea Chemical compound CNC(=S)NNC(=S)NC(C)C=C CGFFKDRVHZIQHL-UHFFFAOYSA-N 0.000 description 1
- 241000196324 Embryophyta Species 0.000 description 1
- 240000002853 Nelumbo nucifera Species 0.000 description 1
- 235000006508 Nelumbo nucifera Nutrition 0.000 description 1
- 235000006510 Nelumbo pentapetala Nutrition 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005283 ground state Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000001629 suppression Effects 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Public Health (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The present invention discloses an electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification. Therefore, a combined optimization model having maximum electric energy and standby cost and considering the partition standby is established. An initial preconceive accident N-1 safety constraint is added into the optimization model, an initial scheduling scheme is obtained through solution, the transmission lines in each partition is subjected to N-1 verification, if the verification passes, the scheme is the optimization scheduling scheme of the next time, if the verification does not pass, the corresponding N-1 verification format is added into the optimization scheduling model to solve and obtain a new scheduling scheme, and the verification mentioned above is repeatedly performed until all the transmission lines pass the N-1 verification so as to obtain the final optimization scheduling scheme. The electric power system electric energy-standby optimization scheduling method considering the partition standby and the N-1 verification is helpful for ensuring the safety of the electric power and the validity of the standby so as to realize the resource optimization configuration.
Description
Technical field
The present invention relates to a kind of power system optimal dispatch method under electricity market, more particularly to examine under electricity market
Consider zonal reserve and the power system electric energy-standby joint optimal operation method of N-1 verification.
Background technology
Generation schedule refers to according to load prediction, on the premise of meeting power-balance, in conjunction with each unit output bound,
The constraintss such as each unit maximum climbing power are it is considered to the actual conditions such as the start and stop of each unit and minimum downtime, and carry
The generated output of each unit of front layout, formulates the important process that generation schedule is electric power system dispatching department.Generate electricity formulating
While plan, need to arrange certain spare capacity to tackle various uncertain factors, such as load fluctuation, generating set
Forced outage and electric network fault etc., thus safeguard the safe and stable operation of electrical network, it is to avoid cutting load causes to damage to power consumer
Lose.In country variant and area, the standby classification of electrical network is different, but according to standby purposes, can be generally divided into tune
Save standby and spinning reserve two big class, wherein, adjust the standby load fluctuation being mainly used in Fast-Balance electrical network, and spinning reserve
After the main generation in power grid accident, for making up the active vacancy that accident causes.Generally, the spare capacity that electrical network is bought
More, the power supply reliability of system is higher;But if the spare capacity bought is excessive, generation assets can be caused to waste, impact
The economy of electrical network.In March, 2015, the Central Committee of the Communist Party of China, State Council issue《With regard to deepening some of power system reform further
Suggestion》(i.e. " No. 9 literary compositions ") opens the gate that new round electricity changes, and it is issued means that China Power system occurs key changing
Become.The final purpose of power system reform is to realize the high-efficient disposition of resource, safe and clean, reliably meet whole society's electricity consumption
Demand.Therefore, while ensureing electric network security and economy, how reasonably to arrange generation schedule and configure standby appearance
Amount, becomes the key issue of electric power system dispatching department urgent need to resolve.
In view of electric energy and standby between there is coupled relation, in recent years, Foreign Electricity Markets in operative practice gradually
Trend towards a few days ago, in Real-time markets using the method for electric energy-standby combined dispatching, the optimization that resource can be better achieved is joined
Put.In conventional electric energy-standby combined scheduling method, typically with economy optimum as object function it is considered to power-balance, send out
The restriction of motor climbing rate, the constraints such as line transmission capacity limit, spare capacity minimum essential requirement, to electric energy and standby
Close and optimize, to obtain the scheduling scheme of network minimal.Due to standby, the security and power supply reliability of safeguarding electrical network are played
Vital effect, therefore Chinese scholars are studied to standby Optimal Configuration Method from different perspectives, mainly examine
Consider the difference factor such as mains frequency recovery, reliability assessment, interconnected network characteristic, forecast accident.
In existing electric energy-standby combined scheduling method, standby generally only need to meet the standby minimum essential requirement amount of the whole network be
Can.But, in actual electric network, due to generation assets maldistribution, cost of electricity-generating gap larger it is possible to can lead to standby
Capacity concentrates in a certain region.In view of line transmission capacity limitation and network congestion, it is possible that standby after accident occurs
The phenomenon that can not called with capacity, has a strong impact on the safety and reliability of operation of power networks.Therefore, in order to standby after guarantee accident
The validity of capacity, it is considered to zonal reserve minimum essential requirement amount is very important in electric energy-standby combined scheduling method.With
This seldom carries out N-1 verification to circuit and transformer in current electric energy-standby combined scheduling method simultaneously, but in reality
In electrical network, the N-1 into row line, transformer and generator is needed to verify thus meeting Network Security Constraints.Therefore, it is necessary to
Consider zonal reserve and N-1 verification, propose a kind of new power system electric energy-standby joint optimal operation method, for electricity
The work of net actual schedule provides reference.
Content of the invention
It is an object of the invention to provide a kind of power system electric energy-standby joint considering zonal reserve and N-1 verification
Optimization Scheduling, the method, with economy optimum as target, considers zonal reserve constraint and the constraint of N-1 fault, to electricity simultaneously
Combined optimization can be carried out with standby, thus obtaining rational scheduling scheme.
For achieving the above object, present invention employs technical scheme below:
Step 1:Determine system reserve minimum essential requirement amount and the zonal reserve minimum essential requirement of next scheduling slot regional power grid
Amount;
Step 2:The electric energy bought with regional power grid and the minimum object function of standby total cost, are set up and consider zonal reserve
The electric energy of demand-standby combined optimization model;
Step 3:The setting initial contingency set of N-1, exerts oneself in a upper scheduling slot including subregion interconnection and each subregion
The N-1 fault of maximum generation machine, and the N-1 security constraint of initial forecast accident is added to above-mentioned steps 2 as constraints
In gained Optimized model, the power system electric energy-standby joint optimal operation model of formation consideration zonal reserve and N-1 constraint is simultaneously
Solution obtains initial schedule scheme;
Step 4:N-1 verification is carried out one by one to the transmission line within each subregion according to scheduling scheme
If the verification of certain transmission lines is passed through, continue to verify next transmission lines, if verification is not passed through, should
The N-1 check formula of transmission line is added in step 3 gained Optimal Operation Model as constraints, obtains new Optimized Operation
Model, obtains new scheduling scheme by solving this Optimal Operation Model, continues next biography of verification according to new scheduling scheme
Defeated line;Repeat above-mentioned N-1 verification, until the N-1 verification of all transmission lines completes, then the scheduling scheme finally giving is next
The Optimized Operation scheme of scheduling slot.
In described step 1, standby can be divided into the standby and spinning reserve of regulation, wherein adjust standby for quick suppression system
The load fluctuation of system, is undertaken by AGC (Automatic Generation Control) units all in regional power grid, therefore only considers that system fading margin is standby
Little demand, usesRepresent;Spinning reserve is mainly used in making up the active vacancy after accident occurs, by all in regional power grid
Schedulable unit undertakes, and in order to ensure the security of standby deliverability and electrical network, needs to consider system spinning reserve simultaneously
Minimum essential requirement amount and subregion spinning reserve minimum essential requirement amount, are expressed asWith Be taken as the whole network (refer to regional power grid, under
The a% of total load together);Determined by the b% of the whole network total load and the minimum of a value of the whole network maximum generation unit installed capacity;It is taken as the c% of each partition load;Coefficient a, b, c can select according to electrical network actual conditions.In addition system reserve and point
The standby minimum essential requirement amount in area needs to obtain by off-line simulation.
In described step 2, the target of this Optimization Scheduling is that economy is optimum, and that is, the whole network is bought in scheduling slot
Electric energy and standby total cost reach minimum, specific object function can be expressed as:
Wherein, PiPlan for i-th generating set is exerted oneself,It is adjusted up the purchase of spare capacity for i-th AGC unit
The amount of buying,Adjust downwards the purchase volume of spare capacity, R for i-th AGC unitiFor i-th generating set spinning reserve capacity
Purchase volume, αi,βi,γiRepresent i-th generating set electric energy respectively, adjust standby and spinning reserve quotation, unit is Yuan/
MW, NgFor the sum of the whole network schedulable unit, NaSum for the whole network AGC unit.
Consider that the electric energy-standby combined optimization model of zonal reserve demand includes power balance equation, generator output work
Rate constraint, the constraint of generator climbing rate, the constraint of standby climbing rate, the constraint of system reserve minimum essential requirement amount, zonal reserve minimum need
The amount of asking constraint and line transmission capacity-constrained, embody as follows:
1) power balance equation
Wherein, DiRepresent the load of i-th node, NdNodes for the whole network.
2) generated output power constraint
For all AGC units (A represents regional power grid AGC unit set):
AndMeanwhile,And
Wherein, PimaxFor i-th generating set maximum active exert oneself, PiminMinimum technology for i-th generating set goes out
Power, AimaxAGC for i-th generating set adjusts the upper limit, AiminAGC for i-th generating set adjusts lower limit.
For all schedulable non-AGC units (B represents the schedulable non-AGC unit collection of regional power grid
Close):
Pi+Ri≤Pimax(4)
3) generator climbing rate constraint
Wherein, P0iFor the previous scheduling slot of i-th generating set of regional power grid active go out force value, can be from power grid energy
Obtain in management system (EMS).
4) standby climbing rate constraint
And
Wherein,For the ratio of slope of climbing of i-th generating set of regional power grid,For i-th generating set of regional power grid
Downward climbing rate, t1For adjusting standby response time, t2Response time for spinning reserve.
5) system reserve minimum essential requirement amount constraint
And
Constraints above condition shows the standby total amount of regulation that the whole network provides and spinning reserve total amount, and should to meet system fading margin standby
With the minimum essential requirement amount with spinning reserve.
6) zonal reserve minimum essential requirement amount constraint
For each subregion z, have:
Wherein,Represent the number of units of schedulable unit in subregion z, this constraint shows, generating set institute in each subregion
The spinning reserve providing should meet subregion spinning reserve minimum essential requirement amount.
7) line transmission capacity-constrained
For circuits all in electrical network:
Under ground state trend, in regional power grid, all line powers should meet the restriction of transmission capacity.Wherein,For kth
Active power on bar circuit,For the maximum transfer capacity of kth bar circuit, HkiShift distribution factor matrix H for power
Row k i-th column element, represents the impact to kth bar circuit active power for the injecting power of i-th node.
N-1 accident set can be divided into two classes:One is system generator fault set, and another kind of is system communications line and transformation
Device fault set.The fault set of this two class needs to consider different modeling pattern in Optimized model:After generator N-1 fault, system
Power-balance be destroyed, need system reserve to recall and dispatched again, it is considered to generator is former therefore when Optimized model model
After barrier, setting new variables is it is ensured that the feasibility of model;After circuit or transformer N-1 fault, the power-balance of system will not be broken
Bad, therefore do not need system reserve to recall and dispatched again, it is considered to circuit or transformer fault therefore when Optimized model models
Do not need afterwards to arrange new variables, Optimized Operation result can meet normal and failure condition constraints simultaneously.
After determining N-1 contingency set, the N-1 principle of circuit, transformer and generator is added to as constraints
In Optimized model described in step 2, form the power system electric energy-standby considering zonal reserve and N-1 constraint under electricity market
Joint optimal operation model.
However, this is a ultra-large optimization problem, actual motion is difficult to solve.Therefore can adopt and dynamically actively collect
Method be iterated solve.The primary fault collection of setting iteration, wherein initial plant N-1 refers to that an important interconnection occurs
Broken string, such as the interconnection between each subregion of electrical network;Initial generator N-1 refers to that the important generating set of each subregion breaks down
Stop transport.Specifically, the constraints of circuit N-1 and generator N-1 is as follows:
1) circuit N-1 constraint
Article one, after anticipation circuit disconnects, the need for electricity in order to meet user ensures the security of electrical network simultaneously, at each
Generating set exert oneself constant on the premise of, all circuits of the whole network still need to meet line transmission capacity-constrained.Assume m-th anticipation line
Road N-1 fault occurs, then the topological structure of electrical network changes, and therefore power transfer distribution factor changes, and is calculated
New power transfer distribution factor matrix Hm.Thus circuit N-1 constraint representation is as follows:
After m-th anticipation circuit N-1 fault occurs, for remaining circuit in regional power grid, have:
Wherein,For m-th anticipation circuit N-1 fault occur rear region electrical network kth bar circuit on active power,
Shift distribution factor matrix H for new powermRow k i-th column element.
Because transformer can be expressed as the form of circuit in a model, therefore no longer individually list the N-1 of transformer about
Bundle.
2) generator N-1 constraint
After n-th anticipation generator N-1 fault occurs, this generator failure is stopped transport it is impossible to continue to provide electric energy, tune
It is active caused by generator N-1 to make up that the standby and spinning reserve of section, therefore remaining generating set of the whole network recall spinning reserve
Vacancy.At this time, it may be necessary to ensure that all circuits of the whole network still need to meet line transmission capacity-constrained thus ensureing the peace of electrical network after fault
Quan Xing.Embodying of generator N-1 constraint is as described below:
After n-th anticipation generator N-1 fault occurs:
Now, system fading margin standby minimum essential requirement amount and spinning reserve minimum essential requirement amount must meet, that is,:
And
Meanwhile, the spinning reserve total amount that remaining generating set of the whole network recalls should meet active power shortage:
Wherein,Represent that n-th anticipation generator N-1 fault occurs the rotation that rear i-th generating set should recall standby
With its value is limited by this i-th generating set spinning reserve purchase volume, that is,:
Meanwhile, after spinning reserve recalls, the whole network circuit remains a need for meeting line transmission capacity-constrained:
Wherein,There is the active power on rear region electrical network kth bar circuit for n-th anticipation generator N-1 fault.
Afterwards, excellent according to the power system electric energy-standby joint of zonal reserve under above-mentioned consideration electricity market and N-1 constraint
Change scheduling model, try to achieve the initial schedule scheme of next scheduling slot.
In described step 4, in order to ensure the security of operation of power networks, each point is carried out to step 3 gained initial schedule scheme
The N-1 verification of area's internal transmission line.Assume that the u article subregion internal transmission line occurs N-1 fault, then power transfer distribution factor square
Battle array is changed into Hu, on the basis of current scheduling scheme, in verification electrical network, whether remaining circuit meets line transmission appearance according to the following formula
Amount constraint (meets then verification to pass through, be unsatisfactory for, verify and do not pass through):
Wherein,There is the wattful power on N-1 fault rear region electrical network kth article circuit for the u article subregion internal transmission line
Rate,Shift distribution factor matrix H for new poweruRow k i-th column element.
N-1 verification is carried out one by one to the transmission line within each subregion, if the verification of certain transmission line is passed through, continues verification
Next transmission lines;If verification is not passed through, using the N-1 check formula (referring to formula 15) of this transmission line as constraints
It is added in step 3 gained Optimal Operation Model, obtains new Optimal Operation Model, obtained by solving this Optimal Operation Model
New scheduling scheme;Repeat above-mentioned N-1 verification, until the N-1 verification of all transmission lines is passed through, then obtain final Optimized Operation
Scheme, returns EMS, and the dispatching of power netwoks for subsequent time provides reference.
Beneficial effects of the present invention are embodied in:
The present invention under conditions of considering zonal reserve minimum essential requirement amount and circuit, transformer and generator N-1 constraint,
With the electricity bought and standby network minimal as target, combined optimization is carried out to electricity-standby, thus obtaining rational dispatching party
So that electrical network overall economy quality more preferably, realizes distributing rationally of resource, N-1 verification simultaneously further ensures system operation to case
Reliability, and provide certain reference to the traffic control of power system.
Brief description
Fig. 1 is the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification of the present invention
Method flow chart;
Fig. 2 is the test sub-area division schematic diagram in the embodiment of the present invention;Heavy line between each subregion of in figure is subregion
Interconnection, numeral 1~118 expression node serial number, G is generating set.
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, below in conjunction with drawings and Examples, right
The present invention is described in further detail.It should be appreciated that embodiment described herein, only in order to explain the present invention, is not used to limit
Determine the present invention.
Below, the present invention is specifically introduced taking the joint optimal operation of certain test electrical network electric energy-standby as a example, but should
It should be appreciated that invention is not limited thereto, it is applied equally to other electrical networks or power operation business are carried out electric energy and standby
Joint optimal operation.
As shown in figure 1, the present invention provide electricity market under consider zonal reserve and N-1 verification power system electric energy-
Standby joint optimal operation method, comprises the following steps:
The first step:Initial data needed for EMS obtains power system optimal dispatch, the main topology knot including electrical network
Structure, partition information, the method for operation, alternator data, the scheduling scheme of a upper period and load prediction, for forming subsequent period
Optimized Operation scheme prepare.In the present embodiment, using IEEE118 node system as test electrical network, 118 sections are comprised altogether
Point, 186 circuits, and it is divided into 3 subregions, the network topology of test electrical network and subregion are as shown in Figure 2.
Second step:According to the scheduling scheme of load prediction, generating machine information, partition information and a upper period, determined and survey
The examination system of electrical network and the minimum essential requirement amount of zonal reserve.Standby be divided into regulation standby and spinning reserve, in the present embodiment, be
The minimum essential requirement amount of system and zonal reserve is all taken as a certain fixed percentage of load.Wherein, adjust standby and consider system
Little demandIt is taken as the 2% of the whole network total load;Spinning reserve is divided into system minimum essential requirement amountWith subregion minimum essential requirement amountTake the 8% of the whole network total load and the minimum of a value of the whole network maximum generation unit installed capacity;It is taken as each subregion to bear
The 8% of lotus.The standby minimum essential requirement of the predicted load, maximum generation unit installed capacity and system and subregion of test electrical network
Amount, as shown in table 1.
Table 1. 118 node test network system, zonal reserve minimum essential requirement amount
3rd step:With the electric energy bought and the minimum object function of standby total cost (referring to formula 1), set up and consider point
The standby electric energy in area-standby combined optimization model, including power balance equation (referring to formula 2), generated output power constraint
(referring to formula 3~4), generator climbing rate constraint (referring to formula 5), standby climbing rate constraint (referring to formula 6), system reserve
Minimum essential requirement amount constraint (referring to formula 7), zonal reserve minimum essential requirement amount constraint (referring to formula 8) and line transmission capacity-constrained
(referring to formula 9).In the present embodiment, total generating set 54, wherein 9 is AGC unit, specifies each AGC unit simultaneously
AGC adjust the upper limit be installed capacity 95%, AGC adjust lower limit be installed capacity 5%, i.e. Aimax=0.95Pimax,Aimin
=0.05Pimax;Scheduling slot length T is set to 15 minutes, adjusts standby response time t1It is set to 5 minutes, spinning reserve rings
T between seasonable2It is set to 10 minutes;Each generating set climbing rate up and down is equal, that is,
4th step:Setting N-1 contingency set, mainly includes the interconnection of each by stages and each subregion in the present embodiment
There is N-1 fault in interior important generating set.In test electrical network, the interconnection of each by stages totally 12;Weight in each subregion
Generating set is wanted to refer to that a upper scheduling slot in this subregion is exerted oneself the generating set of maximum, understands on each subregion according to EMS data
One scheduling slot exert oneself maximum generating set.After determining N-1 contingency set, by the N-1 constraints of forecast accident (referring to
Formula 10~14) add in above-mentioned Optimized model, form the power system electric energy-standby considering zonal reserve and N-1 constraint
Joint optimal operation model.
5th step:Solve above-mentioned Optimal Operation Model using Matlab and Cplex, be met the initial schedule side of constraint
Case, that is, obtain Pi、And RiInitial optimal value.
6th step:Initial schedule scheme is carried out with the N-1 verification of each subregion internal transmission line.In test electrical network, each point
Area's internal transmission line totally 174 (wherein comprises to be expressed as the transformer of circuit).Transmission line within each subregion is carried out one by one
N-1 verifies, if certain transmission lines meets N-1 verification, continues to verify next transmission lines;If be unsatisfactory for, this is passed
The N-1 check formula (referring to formula 15) of defeated line is added in Optimal Operation Model as constraints, obtains new optimization and adjusts
Degree model simultaneously solves and obtains new scheduling scheme, new scheduling scheme is repeated with above-mentioned checking procedure (by will be not validated
The corresponding check formula of transmission line add up in step 4 gained Optimal Operation Model so that under new scheduling scheme
The transmission line of verification all only can need under new scheduling scheme to continue verification to the transmission line not verified by verification, therefore), directly
N-1 verification to all transmission lines is passed through, the Optimized Operation scheme of scheduling scheme as subsequent time now.
Eventually through Matlab and Cplex software, solve the Optimized Operation side being met zonal reserve and N-1 verification
Case, and the electric energy bought and minimum 897814.84 yuan of standby expense, specifically, buy electric energy, adjust standby and rotation
Standby expense is as shown in table 2.
Every buying expenses of table 2. final optimization pass scheduling scheme
According to optimum results, electric energy that each subregion should be bought, to adjust standby and spinning reserve capacity as shown in table 3.
The final optimum results of each subregion of table 3
Table 3 and table 1 are contrasted and understands, the Optimized Operation scheme finally giving can meet workload demand, meet complete simultaneously
Net and the standby minimum essential requirement amount of each subregion.Therefore, this Optimized Operation scheme is meeting zonal reserve requirement, N-1 verification
It is achieved that economy is optimum, be conducive to distributing rationally of resource Deng on the basis of security constraint.
7th step:The Optimized Operation finally giving scheme is returned EMS, the dispatching of power netwoks for subsequent period provides reference.
Claims (8)
1. consider zonal reserve and N-1 verification power system electric energy-standby joint optimal operation method it is characterised in that:Bag
Include following steps:
Step 1:Determine system reserve minimum essential requirement amount and each subregion in this regional power grid of next scheduling slot regional power grid
Zonal reserve minimum essential requirement amount;
Step 2:The electric energy bought with regional power grid and the minimum object function of standby total cost, are set up and consider zonal reserve demand
Electric energy-standby combined optimization model;
Step 3:The setting initial contingency set of N-1, and the N-1 security constraint of initial forecast accident is added as constraints
To in step 2 gained Optimized model, formed and consider that the power system electric energy-standby combined optimization of zonal reserve and N-1 constraint is adjusted
Degree model, obtains initial schedule scheme by solving this Optimal Operation Model;The initial contingency set of described N-1 includes subregion connection
Winding thread N-1 fault and each subregion are exerted oneself in a upper scheduling slot N-1 fault of maximum generation unit;
Step 4:N-1 verification is carried out one by one to the transmission line within each subregion according to scheduling scheme
If the verification of certain transmission lines is passed through, continue to verify next transmission lines, if verification is not passed through, this is transmitted
The N-1 check formula of line is added in step 3 gained Optimal Operation Model as constraints, obtains new Optimized Operation mould
Type, obtains new scheduling scheme by solving this Optimal Operation Model, continues next transmission of verification according to new scheduling scheme
Line;Repeat above-mentioned N-1 verification, until the N-1 verification of all transmission lines completes, then the scheduling scheme finally giving is next tune
Spend the Optimized Operation scheme of period.
2. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 1
Method it is characterised in that:Described system reserve minimum essential requirement amount includes system fading margin standby minimum essential requirement amountAnd system rotation
Standby minimum essential requirement amountZonal reserve minimum essential requirement amount includes subregion spinning reserve minimum essential requirement amount It is taken as region
The a% of electrical network total load;It is taken as the b% of regional power grid total load and regional power grid maximum generation unit installed capacity
Smaller value;It is taken as the c% of corresponding subregion z load.
3. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 2
Method it is characterised in that:The span of described a, b, c is respectively a=2~5, b=8~10, c=8~10.
4. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 1
Method it is characterised in that:The minimum essential requirement amount of described system reserve and zonal reserve is obtained by off-line simulation.
5. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 1
Method it is characterised in that:Described object function is expressed as:
Wherein, PiPlan for i-th generating set is exerted oneself,It is adjusted up the purchase volume of spare capacity for i-th AGC unit,Adjust downwards the purchase volume of spare capacity, R for i-th AGC unitiPurchase for i-th generating set spinning reserve capacity
Amount, αi、βiAnd γiRepresent i-th generating set electric energy respectively, adjust standby and spinning reserve quotation, NgCan for regional power grid
The sum of scheduling generating set, NaSum for regional power grid AGC unit.
6. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 1
Method it is characterised in that:Described electric energy-standby combined optimization the model considering zonal reserve demand includes following constraints:
1) power balance equation
Wherein, PiPlan for i-th generating set is exerted oneself, DiRepresent the load of i-th node, NgFor regional power grid schedulable
The sum of generating set, NdNodes for regional power grid;
2) generated output power constraint
For all AGC units:
AndMeanwhile,And
Wherein,It is adjusted up the purchase volume of spare capacity for i-th AGC unit,Adjust downwards standby for i-th AGC unit
With the purchase volume of capacity, RiFor the purchase volume of i-th generating set spinning reserve capacity, PimaxMaximum for i-th generating set
Active exert oneself, PiminMinimum technology for i-th generating set is exerted oneself, AimaxAGC for i-th generating set adjusts the upper limit,
AiminAGC for i-th generating set adjusts lower limit;
For all schedulable non-AGC units:
Pi+Ri≤Pimax
3) generator climbing rate constraint
Wherein, P0iFor on i-th generating set of regional power grid a scheduling slot active go out force value, ri +For regional power grid i-th
The ratio of slope of climbing of generating set, ri -For the downward climbing rate of i-th generating set of regional power grid, T is scheduling slot length;
4) standby climbing rate constraint
And
Wherein, t1For adjusting standby response time, t2Response time for spinning reserve;
5) system reserve minimum essential requirement amount constraint
And
Wherein,For system fading margin standby minimum essential requirement amount,For system spinning reserve minimum essential requirement amount, NaFor regional power grid
The sum of AGC unit;
6) zonal reserve minimum essential requirement amount constraint
For each subregion z, have:
Wherein,Represent the number of units of schedulable generating set in subregion z,For subregion spinning reserve minimum essential requirement amount;
7) line transmission capacity-constrained
For circuits all in regional power grid:
Wherein,For the active power on kth bar circuit,For the maximum transfer capacity of kth bar circuit, HkiFor power transfer
Row k i-th column element of distribution factor matrix H.
7. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 1
Method it is characterised in that:Constraints in described step 3 includes:
1) circuit N-1 security constraint
Wherein,Active power on kth bar circuit after occurring for m-th anticipation circuit N-1 fault,For kth bar circuit
Maximum transfer capacity,It is calculated power transfer distribution under conditions of m-th anticipation circuit N-1 fault occurs
Factor matrix HmRow k i-th column element, PiPlan for i-th generating set is exerted oneself, DiRepresent the load of i-th node, Nd
For the nodes of regional power grid, NgSum for regional power grid schedulable unit;
2) generator N-1 security constraint
And
Wherein, RiFor the purchase volume of i-th generating set spinning reserve capacity,It is adjusted up standby appearance for i-th AGC unit
The purchase volume of amount,Adjust downwards the purchase volume of spare capacity for i-th AGC unit,For the standby minimum essential requirement of system fading margin
Amount,For subregion spinning reserve minimum essential requirement amount, NaSum for regional power grid AGC unit;
Meet simultaneously:
And
Wherein,Represent n-th and envision the spinning reserve that generator N-1 fault occurs rear i-th generating set should recall, Pn
Represent the active power shortage that n-th anticipation generator N-1 fault causes after occurring;
Also meet simultaneously:
Wherein,Active power on kth bar circuit after occurring for n-th anticipation generator N-1 fault.
8. the power system electric energy-standby joint optimal operation side considering zonal reserve and N-1 verification as claimed in claim 1
Method it is characterised in that:Described N-1 check formula is:
Wherein,There is the active power on kth article circuit after N-1 fault for the u article subregion internal transmission line,For kth
The maximum transfer capacity of bar circuit,It is calculated under conditions of the u article subregion internal transmission line N-1 fault occurs
Power shifts distribution factor matrix HuRow k i-th column element, PiPlan for i-th generating set is exerted oneself, DiRepresent i-th section
The load of point, NdFor the nodes of regional power grid, NgSum for regional power grid schedulable unit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610805004.6A CN106384162B (en) | 2016-09-06 | 2016-09-06 | Consider electric system electric energy-spare joint optimal operation method of zonal reserve and N-1 verification |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610805004.6A CN106384162B (en) | 2016-09-06 | 2016-09-06 | Consider electric system electric energy-spare joint optimal operation method of zonal reserve and N-1 verification |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106384162A true CN106384162A (en) | 2017-02-08 |
CN106384162B CN106384162B (en) | 2019-08-23 |
Family
ID=57939585
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610805004.6A Active CN106384162B (en) | 2016-09-06 | 2016-09-06 | Consider electric system electric energy-spare joint optimal operation method of zonal reserve and N-1 verification |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106384162B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107834548A (en) * | 2017-11-15 | 2018-03-23 | 南方电网科学研究院有限责任公司 | A kind of N 1 methods of calibration of power network containing new energy |
CN108808741A (en) * | 2018-07-03 | 2018-11-13 | 广东电网有限责任公司 | A kind of security constraint economic dispatch method, system, device and readable storage medium storing program for executing |
CN108879795A (en) * | 2018-07-18 | 2018-11-23 | 广西电网有限责任公司电力科学研究院 | The spinning reserve and electric energy combined optimization for considering power system security constraints go out clearing method |
CN109784605A (en) * | 2018-11-20 | 2019-05-21 | 国网浙江省电力有限公司 | Electric system spare capacity joint optimal operation method based on Transient Stability Constraints |
CN110197321A (en) * | 2019-04-17 | 2019-09-03 | 无锡利信能源科技有限公司 | A method of based on the collaboration heat supply safety economy scheduling of multicomputer heating unit |
CN110994594A (en) * | 2019-11-20 | 2020-04-10 | 国电南瑞科技股份有限公司 | Cross-zone standby configuration method and device of power system |
CN112507601A (en) * | 2020-10-12 | 2021-03-16 | 国网浙江省电力有限公司杭州供电公司 | Power system partition standby configuration method based on spectral clustering |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104156887A (en) * | 2014-08-14 | 2014-11-19 | 国家电网公司 | Area new energy development scale and layout analysis method based on power grid constraint |
CN104362617A (en) * | 2014-10-20 | 2015-02-18 | 华东电网有限公司 | Distribution method for reserve capacity of regional power grid control zones |
CN105720575A (en) * | 2016-03-07 | 2016-06-29 | 广东电网有限责任公司电力调度控制中心 | Partition optimization method for power system operation reserves of considering interval support and section constraints |
-
2016
- 2016-09-06 CN CN201610805004.6A patent/CN106384162B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104156887A (en) * | 2014-08-14 | 2014-11-19 | 国家电网公司 | Area new energy development scale and layout analysis method based on power grid constraint |
CN104362617A (en) * | 2014-10-20 | 2015-02-18 | 华东电网有限公司 | Distribution method for reserve capacity of regional power grid control zones |
CN105720575A (en) * | 2016-03-07 | 2016-06-29 | 广东电网有限责任公司电力调度控制中心 | Partition optimization method for power system operation reserves of considering interval support and section constraints |
Non-Patent Citations (1)
Title |
---|
黄庶: "考虑 N-1 安全和抽水蓄能机组运行约束的多目标有功优化调度研究", 《中国优秀硕士学位论文全文数据库工程科技II辑》 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107834548A (en) * | 2017-11-15 | 2018-03-23 | 南方电网科学研究院有限责任公司 | A kind of N 1 methods of calibration of power network containing new energy |
CN107834548B (en) * | 2017-11-15 | 2019-11-01 | 南方电网科学研究院有限责任公司 | A kind of N-1 method of calibration of the power grid containing new energy |
CN108808741A (en) * | 2018-07-03 | 2018-11-13 | 广东电网有限责任公司 | A kind of security constraint economic dispatch method, system, device and readable storage medium storing program for executing |
CN108808741B (en) * | 2018-07-03 | 2021-06-08 | 广东电网有限责任公司 | Safety constraint economic dispatching method, system, device and readable storage medium |
CN108879795A (en) * | 2018-07-18 | 2018-11-23 | 广西电网有限责任公司电力科学研究院 | The spinning reserve and electric energy combined optimization for considering power system security constraints go out clearing method |
CN109784605A (en) * | 2018-11-20 | 2019-05-21 | 国网浙江省电力有限公司 | Electric system spare capacity joint optimal operation method based on Transient Stability Constraints |
CN110197321A (en) * | 2019-04-17 | 2019-09-03 | 无锡利信能源科技有限公司 | A method of based on the collaboration heat supply safety economy scheduling of multicomputer heating unit |
CN110994594A (en) * | 2019-11-20 | 2020-04-10 | 国电南瑞科技股份有限公司 | Cross-zone standby configuration method and device of power system |
CN110994594B (en) * | 2019-11-20 | 2021-04-02 | 国电南瑞科技股份有限公司 | Cross-zone standby configuration method and device of power system |
CN112507601A (en) * | 2020-10-12 | 2021-03-16 | 国网浙江省电力有限公司杭州供电公司 | Power system partition standby configuration method based on spectral clustering |
CN112507601B (en) * | 2020-10-12 | 2023-10-24 | 国网浙江省电力有限公司杭州供电公司 | Power system partition standby configuration method based on spectral clustering |
Also Published As
Publication number | Publication date |
---|---|
CN106384162B (en) | 2019-08-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106384162A (en) | Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification | |
CN102593829B (en) | Method and device for determining transmission section in consideration of key branch circuit | |
CN108122068A (en) | A kind of power distribution network risk-averse retailer method and system | |
CN108418204B (en) | State evaluation method of microgrid based on situation awareness | |
CN106451556A (en) | Method and apparatus for determining capability of receiving distributed power supply by distributed network feeder line | |
CN104701890B (en) | Consider the spinning reserve optimization method of power system containing wind power plant that wind power overflows | |
EP2883196B1 (en) | Method and apparatus for spatiotemporal control of the electric power draw of a telecommunication network on the basis of states of the power supply system | |
CN105720575B (en) | Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section | |
CN106549420A (en) | Consider the electric power system operation standby optimization method of risk and wind-power electricity generation | |
CN103824230B (en) | A kind of systematic failures spare capacity coordinated allocation method based on risk quantification | |
CN108493998B (en) | Robust power transmission network planning method considering demand response and N-1 expected faults | |
CN106096751A (en) | Consider that new forms of energy access and participate in Short Term Generation Schedules arrangement and standby Optimal Configuration Method with Demand Side Response | |
CN113644670B (en) | Method and system for optimally configuring energy storage capacity | |
CN106875287A (en) | A kind of power system switched-mode power supply capacity judging method | |
Avritzer et al. | Survivability models for the assessment of smart grid distribution automation network designs | |
CN107622360A (en) | A kind of critical circuits recognition methods for considering subjective and objective factor | |
CN107181253A (en) | A kind of Electric power network planning method based on power network dynamic reliability probability level | |
Capitanescu | AC OPF-based methodology for exploiting flexibility provision at TSO/DSO interface via OLTC-controlled demand reduction | |
CN106779444A (en) | Based on the active plan load flow rectification method and apparatus that electric network model is extended out | |
CN106684889A (en) | Random reactive optimization method of active distribution network based on scenario method | |
CN107181321A (en) | It is a kind of that the quick method for drawing lotus is realized based on topological structure of electric | |
CN111917139A (en) | Method and system for determining blackable window period of main equipment of power grid | |
CN107069720A (en) | A kind of main distribution integration power supply system | |
CN116131318A (en) | Two-stage robust optimization control method and device for toughness-oriented lifting active power distribution network | |
Gupta et al. | Examining impact of distribution system characteristics on transmission security assessment of future power systems |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |