CN106372857A - Method and system for automatically establishing project - Google Patents
Method and system for automatically establishing project Download PDFInfo
- Publication number
- CN106372857A CN106372857A CN201610793858.7A CN201610793858A CN106372857A CN 106372857 A CN106372857 A CN 106372857A CN 201610793858 A CN201610793858 A CN 201610793858A CN 106372857 A CN106372857 A CN 106372857A
- Authority
- CN
- China
- Prior art keywords
- project
- new projects
- code
- information
- passing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/22—Indexing; Data structures therefor; Storage structures
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Physics & Mathematics (AREA)
- Data Mining & Analysis (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Software Systems (AREA)
- Databases & Information Systems (AREA)
- General Engineering & Computer Science (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a method and a system for automatically establishing a project. The method comprises steps that the historical project information is taken as content to establish a database, a new project is established in the database, and code establishment for the new project is automatically accomplished. Through the method and the system, receiving an instruction emitted by an SPM is only required in the whole project establishment process, one-person individual operation accomplishment can be realized, and manpower saving is realized; project establishment can be accomplished through simply inputting the project information through the SPM, the process is simple and convenient, and efficiency is high; project codes are selected from existing projects in the database, the SPM is not required to deeply know about the codes, and code error risk is reduced.
Description
Technical field
The present invention relates to computer realm, particularly to a kind of method and system automatically creating project.
Background technology
Odm (original designed manufacture), refers to provide from research and development of products to production for client
A complete set of service.Client only need to propose the function of product, performance even only need to provide the design of correlation, odm manufacturer by product from
Imagination comes true.
Have the key link that research and development of products ability is odm enterprise's survival and development.Domestic odm enterprise is to manufacture mostly
Build up, have in terms of tissue large-scale production and compare rich experience.On the contrary, the experience of its research and development management is not very sufficient.
During odm Project-developing, establishment of item management is usually to be safeguarded by spm (software project manager), but
Software project manager is typically ignorant of code, but this very important work also cannot be completed by general code development personnel.Mesh
Front most of company, in project management process, is submitted to after project information by spm, assists in scm (software configuration management) personnel
Under carry out creating with script on code library, submit to, flow process is cumbersome.
As shown in Figure 1, operation of the prior art is usually: step s101 is first carried out, spm creates on the server
Project typing project information;Then carry out step s102, judge whether project creates successfully, such as unsuccessful, then return to step
Rapid s101 re-creates project, and such as creating successfully then spm is sent to scm by project task, carries out step s103, and scm receives spm
Sending of task;Then carry out step s104, scm replicates script according to the project information project implementation in task;Step s105,
Judge that project replicates whether script runs succeeded, such as unsuccessful, then return to step s104 and re-execute project duplication script, such as hold
Go successfully, then enter step s106, code is submitted to git server using git order by scm;Then carry out step s107, sentence
Whether division of history into periods code is submitted to successfully, and if do not become, return to step s106 resubmits, and such as success then enters step s108, treats that scm is true
Recognize after success submitted to by code and notify spm;Then carry out step s109, spm receives all exploit persons of mail notification after the notice of scm
Member's project is set up and is completed;Finally carry out step s110, developer is developed, so far on the fresh code of this project further
Establishment of item completes.
In the process, spm and scm needs repeatedly to participate in establishment of item process, and needs guaranteeing errorless situation
Lower just can be correctly completed automatically creating of item code.But the content or the code development personnel that are related to code are more familiar,
Make non-developer higher to complete these project tasks, error rate.
Content of the invention
In order to solve problem of the prior art, embodiments provide and a kind of automatically create the method for project and be
System.Described technical scheme is as follows:
On the one hand, there is provided a kind of method automatically creating project, comprise the following steps:
Data base is set up for content with passing project information;
Set up new projects and be automatically performed the establishment to new projects' code in data base.
Further, the step of data base is set up particularly as follows: receiving passing project information for content with passing project information,
Set up data base.
Further, set up new projects in data base and be automatically performed concrete to the step of the establishment of new projects' code
For:
Set up new projects in data base, and receive new projects' information;
Contrast passing project information and new projects' information, the item code of passing project is copied to the project generation of new projects
In code, complete new projects and create.
Further, receive passing project information, set up the step of data base particularly as follows:
Receive passing project information and set up tables of data as record, in tables of data, at least include project name and item code
Two fields;
Data base is set up according to tables of data.
Further, data base sets up new projects, and receive new projects' information step particularly as follows:
New projects are set up in data base;
Receive remaining field contents in addition to item code field under new projects.
Further, contrast passing project information and new projects' information, the item code of passing project is copied to new item
In purpose item code, complete new projects establishment concretely comprise the following steps:
Judge new projects the need of automatically creating item code;
If being judged as YES, choose from data base and the same or analogous passing project of field contents under new projects;Will
Content under the item code field of passing project chosen copies under the item code field of new projects;Preserve new projects extremely
Data base, new projects create and complete;
If being judged as NO, directly preserve new projects to data base, new projects create and complete.
Optionally, the field in tables of data also includes code library name, branch title, compiling entry name in the code library of place
Claim, replicate project name, submit node i d and baseline project name to.
Optionally, described item code includes herein below: pre-loading information, kernel information, this device, storehouse, application message
And multimedia messages.
Optionally, described device comprises linux process.
Optionally, after the completion of methods described also includes grassroot project establishment, judge whether to need to send mail notification exploitation
Personnel;
If being judged as YES, send mail notification developer;
If being judged as NO, terminate establishment process.
On the other hand, there is provided a kind of system automatically creating project, comprising:
Project memory module, for storing passing project information and item code;
Establishment of item module, is connected with project memory module, for creating new projects.
Further, in the described system automatically creating project:
Establishment of item module includes:
Project information input module, is connected with project memory module, for inputting the project information of new projects;
Project information contrast module, is connected respectively with project memory module and project information input module, for by new item
Purpose project information and the contrast of passing project information;
Item code replication module, is connected respectively with project memory module and project information input module, for will be passing
Item code copies under new projects' code.
Optionally, automatically create in the system of project, establishment of item module also includes judge module, with project information input
Module, project information contrast module and project memory module connect respectively, are used for judging whether to need passing item code is multiple
Make under new projects' code.
Optionally, automatically create in the system of project, also include mail notification module, be connected with project memory module, use
In judging whether to need to send mail notification developer.
Technical scheme provided in an embodiment of the present invention has the benefit that
The method automatically creating project of the present invention, whole establishment of item process only need to receive the instruction that spm sends, and realizes
One people's handled by itself completes, and saves artificial.Spm only need the contents such as simple cuit information can finished item establishment, mistake
Journey is simple and convenient, efficiency high.Item code is selected from existing project in data base, is not required to spm and code is understood in depth, reduce
The risk of code error.
Brief description
For the technical scheme being illustrated more clearly that in the embodiment of the present invention, will make to required in embodiment description below
Accompanying drawing be briefly described it should be apparent that, drawings in the following description are only some embodiments of the present invention, for
For those of ordinary skill in the art, on the premise of not paying creative work, other can also be obtained according to these accompanying drawings
Accompanying drawing.
Fig. 1 is the method flow diagram of conventional establishment project in prior art of the present invention;
Fig. 2 is the method flow diagram automatically creating project that the embodiment of the present invention one provides;
Fig. 3 is the method flow diagram automatically creating project that the embodiment of the present invention one provides;
Fig. 4 is the method flow diagram automatically creating project that the embodiment of the present invention one provides;
Fig. 5 is the system construction drawing automatically creating project that the embodiment of the present invention two provides;
Fig. 6 is the system construction drawing automatically creating project that the embodiment of the present invention two provides;
Fig. 7 is the system construction drawing automatically creating project that the embodiment of the present invention two provides;
Fig. 8 is the system construction drawing automatically creating project that the embodiment of the present invention two provides.
Specific embodiment
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with accompanying drawing to embodiment party of the present invention
Formula is described in further detail.
Embodiment one
The present invention provides a kind of method automatically creating project as shown in Figure 2.Carry out step s201 first, with passing project
Information sets up data base for content;When needing to create new projects, the instruction that reception spm sends, with execution step s202, is counting
According to setting up new projects in storehouse and be automatically performed the establishment to new projects' code.
Specifically, as shown in figure 3, carrying out step s301 first, receiving passing project information, setting up data base;Then when
When needing to create new projects, the instruction that reception spm sends, with execution step s302, is set up new projects in data base, and is received
New projects' information;Then carry out step s303, contrast passing project information and new projects' information, by the item code of passing project
Copy in the item code of new projects, complete new projects and create.
Specific again, as shown in figure 4, carrying out step s401 first, receiving passing project and setting up tables of data as record, number
According at least including project name and two fields of item code in table, code library name can also be included, in the code library of place point
The fields such as branch title, compiling project name, duplication project name, submission node i d (commit id) and baseline project name;So
After carry out step s402, data base is set up according to tables of data.
When spm needs to start a newly-built project, carry out step s403, receive the instruction here number that spm sends
Set up new projects according in storehouse;Then carry out step s404, according to the field name in tables of data under data base, receive under new projects
Remaining field contents in addition to item code;Then carry out step s405, receive the instruction that spm sends right to judge whether to need
New projects automatically create item code.Item code includes: pre-loading information (preloader), kernel information (kernel), comprises
This device of linux process, storehouse (lib), application message (app) and multimedia messages (media) etc..
If being judged as YES, carrying out step s406, choosing same or similar with field contents under new projects from data base
Passing project;Step s407, the content under the item code field of the described passing project chosen is copied to new projects
Under item code field;Step s408, preserves new projects to data base, new projects create and complete.
If wanting, temporarily ceasing item code creates, and is judged as NO, directly carries out step s408, preserves new projects to data
Storehouse, new projects create and complete.
After the completion of new projects create, the instruction that spm sends can also be received and carry out step s409, judge whether to need to send out
Send mail notification developer.
If being judged as YES, carrying out step s410, sending mail notification developer.
If do not needed to send mail, then it is judged as NO, establishment process terminates.
The method automatically creating project of the present invention, whole establishment of item process only need to receive the instruction that spm sends, and realizes
One people's handled by itself completes, and saves artificial.Spm only need the contents such as simple cuit information can finished item establishment, mistake
Journey is simple and convenient, efficiency high.Item code is selected from existing project in data base, is not required to spm and code is understood in depth, reduce
The risk of code error.
Embodiment two
The present invention also provides a kind of system automatically creating project as shown in figure 5, including project memory module 100 and project
Creation module 200.Project memory module 100, for storing passing project information and item code.Establishment of item module 200, with
Project memory module 100 connects, for creating new projects.
Specifically, as shown in fig. 6, project memory module 100 can be data base, the invention is not limited in this regard.
Establishment of item module 200 includes:
Project information input module 201, is connected with project memory module 100, for inputting the project information of new projects.
Project information contrast module 202, is connected respectively with project memory module 100 and project information input module 201, uses
In by the project information of new projects and passing project information contrast.
Item code replication module 203, is connected respectively with project memory module 100 and project information input module 201, uses
In passing item code is copied under new projects' code.
As shown in fig. 7, optional, establishment of item module 200 also includes judge module 204, with project information input module
201st, project information contrast module 202 and project memory module 100 connect respectively, are used for judging whether to need by passing project generation
Code copies under new projects' code.
As shown in figure 8, optional, in the described system automatically creating project, also include mail notification module 300, with project
Memory module 100 connects, and is used for judging whether to need to send mail notification developer.
The embodiments of the present invention are for illustration only, do not represent the quality of embodiment.
Device embodiment described above is only that schematically the wherein said unit illustrating as separating component can
To be or to may not be physically separate, as the part that unit shows can be or may not be physics list
Unit, you can with positioned at a place, or can also be distributed on multiple NEs.Can be selected it according to the actual needs
In the purpose to realize this embodiment scheme for some or all of module.Those of ordinary skill in the art are not paying creativeness
Work in the case of, you can to understand and to implement.
Through the above description of the embodiments, those skilled in the art can be understood that each embodiment can
Mode by software plus necessary general hardware platform to be realized naturally it is also possible to pass through hardware.Based on such understanding, on
That states that technical scheme substantially contributes to prior art in other words partly can be embodied in the form of software product, should
Computer software product can store in a computer-readable storage medium, such as rom/ram, magnetic disc, CD etc., including some fingers
Order is with so that a computer equipment (can be personal computer, server, or network equipment etc.) executes each enforcement
Example or some partly described methods of embodiment.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all spirit in the present invention and
Within principle, any modification, equivalent substitution and improvement made etc., should be included within the scope of the present invention.
Claims (10)
1. a kind of method automatically creating project is it is characterised in that comprise the following steps:
Data base is set up for content with passing project information;
Set up new projects in the database and be automatically performed the establishment to described new projects code.
2. automatically create the method for project as claimed in claim 1 it is characterised in that
Described with passing project information for content set up data base step particularly as follows:
Receive passing project information, set up data base;
Described set up in the database new projects and be automatically performed the establishment to described new projects code step particularly as follows:
Set up new projects in the database, and receive described new projects information;
Contrast described passing project information and new projects' information, the excessively described item code toward project is copied to the item of new projects
In mesh code, complete new projects and create.
3. automatically create the method for project as claimed in claim 2 it is characterised in that
Described reception passing project information, set up the step of data base particularly as follows:
Receive passing project information and set up tables of data as record, in described tables of data, at least include project name and item code
Two fields;
Data base is set up according to described tables of data;
Described set up new projects in data base, and receive new projects' information step particularly as follows:
Set up new projects in the database;
Receive remaining field contents in addition to item code field under described new projects;
The passing project information of described contrast and new projects' information, the item code of passing project are copied to the project generation of new projects
Code in, complete new projects establishment concretely comprise the following steps:
Judge described new projects the need of automatically creating item code;
If being judged as YES, choose from described data base and the same or analogous passing project of field contents under new projects;Will
Content under the item code field of described passing project chosen copies under the item code field of new projects;Preserve described
New projects create and complete to data base, new projects;
If being judged as NO, directly preserve described new projects to data base, new projects create and complete.
4. automatically create the method for project as claimed in claim 3 it is characterised in that methods described also includes grassroot project wound
After the completion of building, judge whether to need to send mail notification developer;
If being judged as YES, send mail notification developer;
If being judged as NO, terminate establishment process.
5. automatically create the method for project as claimed in claim 4 it is characterised in that the field in described tables of data also includes
Branch title, compiling project name, duplication project name, submission node i d and baseline item in code library name, place code library
Mesh title.
6. automatically create the method for project as claimed in claim 5 it is characterised in that described item code include following interior
Hold: pre-loading information, kernel information, this device, storehouse, application message and multimedia messages.
7. a kind of system automatically creating project is it is characterised in that include:
Project memory module, for storing passing project information and item code;
Establishment of item module, is connected with described project memory module, for creating new projects.
8. automatically create the system of project as claimed in claim 7 it is characterised in that described establishment of item module includes:
Project information input module, is connected with described project memory module, for inputting the project information of new projects;
Project information contrast module, is connected respectively with described project memory module and described project information input module, for inciting somebody to action
The project information of described new projects and the contrast of passing project information;
Item code replication module, is connected respectively with described project memory module and described project information input module, for inciting somebody to action
Passing item code copies under new projects' code.
9. automatically create the system of project as claimed in claim 8 it is characterised in that described establishment of item module also includes sentencing
Disconnected module, is connected with described project information input module, project information contrast module and project memory module, respectively for judging
Copy under new projects' code the need of by passing item code.
10. automatically create the system of project as claimed in claim 9 it is characterised in that the described system automatically creating project
In also include mail notification module, be connected with described project memory module, be used for judging whether needing to send mail notification exploitation
Personnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610793858.7A CN106372857A (en) | 2016-08-31 | 2016-08-31 | Method and system for automatically establishing project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610793858.7A CN106372857A (en) | 2016-08-31 | 2016-08-31 | Method and system for automatically establishing project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106372857A true CN106372857A (en) | 2017-02-01 |
Family
ID=57900337
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610793858.7A Pending CN106372857A (en) | 2016-08-31 | 2016-08-31 | Method and system for automatically establishing project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106372857A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107563789A (en) * | 2017-07-31 | 2018-01-09 | 石河子大学 | Data processing method, system, terminal and computer-readable recording medium |
CN107992995A (en) * | 2017-11-20 | 2018-05-04 | 上海华力微电子有限公司 | A kind of method and system for creating technological process title |
CN113627128A (en) * | 2020-05-07 | 2021-11-09 | 上海同是科技股份有限公司 | Hidden danger troubleshooting check item coding method and system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102065413A (en) * | 2010-11-17 | 2011-05-18 | 北京北方烽火科技有限公司 | Database updating method and system, and base station self-starting method and system |
CN102520959A (en) * | 2011-12-16 | 2012-06-27 | 西安邮电学院 | Reused code matching inquiry method based on meaning |
CN102760058A (en) * | 2012-04-05 | 2012-10-31 | 中国人民解放军国防科学技术大学 | Massive software project sharing method oriented to large-scale collaborative development |
CN104281704A (en) * | 2014-10-22 | 2015-01-14 | 新华瑞德(北京)网络科技有限公司 | Database data copying method and device |
CN105224377A (en) * | 2015-10-08 | 2016-01-06 | 广州华旻信息科技有限公司 | A kind of method by metadata automatic generating software project code file and device |
CN105354037A (en) * | 2015-11-30 | 2016-02-24 | 用友优普信息技术有限公司 | Modularized software developing method and software developing device |
-
2016
- 2016-08-31 CN CN201610793858.7A patent/CN106372857A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102065413A (en) * | 2010-11-17 | 2011-05-18 | 北京北方烽火科技有限公司 | Database updating method and system, and base station self-starting method and system |
CN102520959A (en) * | 2011-12-16 | 2012-06-27 | 西安邮电学院 | Reused code matching inquiry method based on meaning |
CN102760058A (en) * | 2012-04-05 | 2012-10-31 | 中国人民解放军国防科学技术大学 | Massive software project sharing method oriented to large-scale collaborative development |
CN104281704A (en) * | 2014-10-22 | 2015-01-14 | 新华瑞德(北京)网络科技有限公司 | Database data copying method and device |
CN105224377A (en) * | 2015-10-08 | 2016-01-06 | 广州华旻信息科技有限公司 | A kind of method by metadata automatic generating software project code file and device |
CN105354037A (en) * | 2015-11-30 | 2016-02-24 | 用友优普信息技术有限公司 | Modularized software developing method and software developing device |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107563789A (en) * | 2017-07-31 | 2018-01-09 | 石河子大学 | Data processing method, system, terminal and computer-readable recording medium |
CN107992995A (en) * | 2017-11-20 | 2018-05-04 | 上海华力微电子有限公司 | A kind of method and system for creating technological process title |
CN113627128A (en) * | 2020-05-07 | 2021-11-09 | 上海同是科技股份有限公司 | Hidden danger troubleshooting check item coding method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3435235B1 (en) | Method and device for executing data recovery operation | |
US11620277B2 (en) | Transaction processing at non-relational databases | |
CN109828903A (en) | Automated testing method, device, computer installation and storage medium | |
CN101542445A (en) | Apparatus and methods of a zero single point of failure load balancer | |
CN102572896A (en) | Upgrading method and upgrading device for wireless communication system | |
CN106372857A (en) | Method and system for automatically establishing project | |
CN111240812A (en) | Task execution method and device | |
CN109325016A (en) | Data migration method, device, medium and electronic equipment | |
CN109829679A (en) | Project management method, device, computer installation and storage medium | |
CN111382985A (en) | To-do message integrated pushing system and working method | |
CN113706022A (en) | Business process execution method and device, storage medium and electronic equipment | |
CN104301428A (en) | Data synchronization method and server | |
CN106446300A (en) | Transaction processing method and system based on shared storage pool | |
CN110650164A (en) | File uploading method and device, terminal and computer storage medium | |
CN102902574B (en) | Cooperative processing method and device of multiple information flow nodes | |
CN109189431A (en) | A kind of client side upgrading method, device, equipment and readable storage medium storing program for executing | |
CN103856349A (en) | Version upgrading method for multi-core router and multi-core router | |
CN115629746A (en) | Method and system for multi-person collaborative development of low-code platform | |
CN103701653A (en) | Processing method for interface hot plugging and unplugging configuration data and network configuration server | |
CN103516880A (en) | Method and device for sending short messages | |
CN107529180B (en) | Base station cloud test environment construction device and method | |
CN101551758A (en) | System and method for implementing paralleling work of device management and tasks | |
CN104753659B (en) | A kind of method, apparatus and system of more network element data synchronization loads | |
CN113934711B (en) | Method for automatically deploying gbase8s cluster | |
CN103488773A (en) | Website data acquiring method and device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170201 |