CN106367550A - Structure and repair method for eliminating leak coal gas of blast furnace bottom - Google Patents

Structure and repair method for eliminating leak coal gas of blast furnace bottom Download PDF

Info

Publication number
CN106367550A
CN106367550A CN201610900204.XA CN201610900204A CN106367550A CN 106367550 A CN106367550 A CN 106367550A CN 201610900204 A CN201610900204 A CN 201610900204A CN 106367550 A CN106367550 A CN 106367550A
Authority
CN
China
Prior art keywords
blast furnace
closing
furnace bottom
coal gas
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610900204.XA
Other languages
Chinese (zh)
Other versions
CN106367550B (en
Inventor
刘根胜
司翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING UNITED RONGDA ENGINEERING MATERIAL Co Ltd
Original Assignee
NANJING UNITED RONGDA ENGINEERING MATERIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING UNITED RONGDA ENGINEERING MATERIAL Co Ltd filed Critical NANJING UNITED RONGDA ENGINEERING MATERIAL Co Ltd
Priority to CN201610900204.XA priority Critical patent/CN106367550B/en
Publication of CN106367550A publication Critical patent/CN106367550A/en
Application granted granted Critical
Publication of CN106367550B publication Critical patent/CN106367550B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/04Blast furnaces with special refractories

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention belongs to the technical field of blast furnace gas, and relates to a structure and repair method for eliminating leak coal gas of a blast furnace bottom. By means of the steps of sealed groove forming, steel plate implantation, steel plate welding, sealing material filling, sealing and grouting, the whole blast furnace bottom is wrapped in a sealed space on a furnace bottom base, and the coal gas cannot leak to the outside of the sealed space even though a channel can be formed between poured concrete and a furnace body interface or between the concrete and the base through the coal gas. The structure and repair method have the beneficial effects that the problem of the leak coal gas of the blast furnace bottom can be effectively solved, and the defects that the blast furnace bottom is poorly sealed, or space sealing cannot be carried out at the furnace bottom can be overcome; and the overall structure and materials of an original blast furnace cannot be damaged, after construction is finished, the blast furnace can be directly put into use without baking, and production is fast resumed.

Description

A kind of structure solving Blast Furnace Bottom leakage coal gas and method for repairing and mending
Technical field
The present invention relates to a kind of solve structure and the method for repairing and mending that Blast Furnace Bottom leaks coal gas, belong to blast furnace gas technology neck Domain.
Background technology
The main thoroughfare of Blast Furnace Bottom gas leak is to flow to furnace foundation cooling tube along the gap between furnace shell and cooling wall Top, then by the void layer (i.e. charcoal element packing layer) between furnace shell and furnace foundation heat resisting foundation pier, flow at furnace foundation bearing soleplate to stove External leakage spreads.
General method for repairing and mending is directly to take mud jacking to repair in furnace bottom, and this method not can solve Lou coal gas and asks Topic, in use for some time, coal gas also can be from original passage toward blast furnace external leakage.
Content of the invention
In order to overcome the deficiencies in the prior art, the present invention provides a kind of structure solving Blast Furnace Bottom leakage coal gas and repairing side Method.
A kind of method for repairing and mending solving Blast Furnace Bottom leakage coal gas, as follows containing step;By break a seal locked groove, implant plate, Whole Blast Furnace Bottom is wrapped in one on furnace bottom pedestal and more closes by welding steel, filling sealed material, sealing, mud jacking step Space in, even if coal gas cast concrete and body of heater interface or concrete and pedestal between can form passage, coal gas Also the external world of closing space will not be leaked into.
A kind of solve Blast Furnace Bottom leak coal gas structure, on Blast Furnace Bottom concrete foundation connect hard plastic screed, Heat-resisting brick setting, carbon packing layer and last furnace shell, the inner chamber of last furnace shell connects carbon packing layer, the inner chamber of carbon packing layer Connect heat-resisting brick setting, the inner chamber of heat-resisting brick setting connects blast furnace heat resisting foundation pier and hard plastic screed, Blast Furnace Bottom coagulation The opposite side of soil base has the first enclosed slot, and the first enclosed slot is trapezoidal, fills microdilatancy plasticity clay in the first enclosed slot, micro- Expand plastic hinge mud drum and wrap up in closing angle steel and closing steel plate, closing angle steel is l type, closing steel plate is connected to closing and uses The side composition section of angle steel l type is the rectangle of opening, and the height of closing steel plate is more than the height of closing angle steel, in closing The area filling microdilatancy grouting material being surrounded with steel plate and last furnace shell, the surface junction steel plate closing of microdilatancy grouting material.
The size of the first enclosed slot is upper bottom 200mm, go to the bottom 220mm and high 150mm.
A kind of solve Blast Furnace Bottom leak coal gas structure, on Blast Furnace Bottom concrete foundation connect hard plastic screed, Heat-resisting brick setting, carbon packing layer and last furnace shell, the inner chamber of last furnace shell connects carbon packing layer, the inner chamber of carbon packing layer Connect heat-resisting brick setting, the inner chamber of heat-resisting brick setting connects blast furnace heat resisting foundation pier and hard plastic screed, Blast Furnace Bottom coagulation The opposite side of soil base has the second enclosed slot, and the second enclosed slot is rectangle, fills microdilatancy plasticity clay in the second enclosed slot, micro- Expand plastic hinge mud drum and wrap up in closing steel plate, the area filling microdilatancy grouting material surrounding in closing steel plate and last furnace shell, The surface junction steel plate closing of microdilatancy grouting material.
The size of the second enclosed slot is width 30mm and height 200mm.
It is an advantage of the invention that the problem that Blast Furnace Bottom leaks coal gas can be efficiently solved, overcome Blast Furnace Bottom closing bad Or the defects such as confined space cannot be carried out in furnace bottom.Overall structure and the material of original blast furnace will not be destroyed, after construction terminates, Need not toast, use can be direct plungeed into, quickly resume production.
Brief description
When considered in conjunction with the accompanying drawings, by referring to detailed description below, can more completely more fully understand the present invention with And easily learn the adjoint advantage of many of which, but accompanying drawing described herein is used for providing a further understanding of the present invention, Constitute the part of the present invention, the schematic description and description of the present invention is used for explaining the present invention, does not constitute to this Bright improper restriction, such as schemes wherein:
Fig. 1 builds schematic diagram by laying bricks or stones for Blast Furnace Bottom;
Fig. 2-1 is one of furnace bottom ground fluting signal figure;
Fig. 2-2 is two figures of furnace bottom ground fluting signal;
Fig. 3 is pre-buried closing steel construction schematic diagram;
Fig. 4-1 is one of enclosed slot closing signal figure;
Fig. 4-2 closes two figures of signal for enclosed slot;
Fig. 5-1 is one of partial cross section's signal figure after completion;
Fig. 5-2 is two figures of partial cross section's signal after completion;
In figure: 1 Blast Furnace Bottom concrete foundation;2 blast furnace heat resisting foundation piers;3 heat-resisting brick settings;4 carbon packing layers;5 blast furnaces Furnace shell;6 hard plastic screeds;7 enclosed slots;8 closing angle steel;9 closing steel plates;10 microdilatancy plasticity clay;11 is micro- swollen Swollen grouting material.
The present invention is further described with reference to the accompanying drawings and examples.
Specific embodiment
Obviously, those skilled in the art belong to the guarantor of the present invention based on the many modifications and variations that spirit of the invention is done Shield scope.
Those skilled in the art of the present technique are appreciated that unless expressly stated, singulative " " used herein, " Individual ", " described " and " being somebody's turn to do " may also comprise plural form.It is to be further understood that wording " bag used in this specification Include " refer to there is described feature, integer, step, operation, element and/or assembly, but it is not excluded that exist or add one or Other features multiple, integer, step, operation, element, assembly and/or their group.It should be understood that when title element, assembly quilt When ' attach ' to another element, assembly, it can be directly connected to other elements or assembly, or can also there is cental element Part or assembly.Wording "and/or" used herein includes one or more associated any cell of item and complete listed Portion combines.
Those skilled in the art of the present technique are appreciated that unless otherwise defined, and all terms used herein (include technology art Language and scientific terminology) there is general understanding identical meaning with the those of ordinary skill in art of the present invention.
For ease of the understanding to the embodiment of the present invention, explanation will be further explained below, and each embodiment will be not Constitute the restriction to the embodiment of the present invention.
Embodiment 1: a kind of method for repairing and mending solving Blast Furnace Bottom leakage coal gas, by the locked groove that breaks a seal, implant plate, welding steel Plate, fill sealed material, sealing, mud jacking step, whole Blast Furnace Bottom is wrapped on furnace bottom pedestal by the space of a more closing Interior, even if coal gas can form passage between the concrete and body of heater interface or concrete and pedestal of cast, also will not leak To the external world of closing space, the problem that Blast Furnace Bottom leaks coal gas thus can be efficiently solved.
Also contain following steps;
Step 1, first, drives the first enclosed slot 7 for one week along blast furnace on concrete foundation 1 surface, and groove width 200mm is deep 150mm, trench bottom is suitable for reading more bigger than groove, as Suo Shi Fig. 2-1 in order to after preventing cast the long-time stress of matrix after with Original place base departs from.
Step 2, it is implanted into closing steel construction in the first above-mentioned enclosed slot 7 using anchoring piece within one week along blast furnace, such as scheme Shown in 4-1.It is embedded in the closing steel construction part in the first enclosed slot 7, as shown in figure 3, being the angle steel with 63 × 63 × 8mm 8 steel plates 9 thick with 10mm are welded, and both contact surfaces should beat groove full weld it is ensured that the tensile strength of binding site.
Step 3, with microdilatancy plasticity clay 10, the steel construction piece being welded first is embedded in the first enclosed slot 7 of ground 1 In, as shown in Fig. 4-1.The effect of this clay is: prevents from gap between the later steel construction of time length and material and is formed Gas passage.The probability of gas leak can be substantially reduced after being used herein as microdilatancy plasticity clay 10, and wettability good with The contact in steel plate section is tightr.In addition, surface is more smooth after closing, more conducively descend the Engineering Quality Control of surface construction.
Step 4, finally pour in the space of closing using microdilatancy grouting material 11, in closing space, fill microdilatancy grouting Material 11 after closed using steel plate, due to there may be gap, reuse grouting material press-in fill up, after the completion of schematic diagram such as Fig. 5-1.
Embodiment 2: a kind of method for repairing and mending solving Blast Furnace Bottom leakage coal gas, containing following steps;
Step 1, first, drives the second enclosed slot 12 for one week along blast furnace on concrete foundation 1 surface, and groove width 30mm is deep 200mm, as shown in Fig. 2-2.
Step 2, in the second above-mentioned enclosed slot 12 along blast furnace one week implantation closing steel construction piece 9, as Fig. 4-2 institute Show.
Step 3, with microdilatancy plasticity clay 10, the steel construction piece being welded 9 is first embedded in the second enclosed slot of ground 1 In 12, as shown in the Fig. 4-2.The effect of this clay is: prevents gap between the later steel construction of time length and material and shape Become gas passage.The probability of gas leak can be substantially reduced after being used herein as microdilatancy plasticity clay 10, and wettability is good Tightr with the contact in steel plate section.In addition, surface is more smooth after closing, more conducively descend the construction quality control of surface construction System.
Step 4, finally pour in the space of closing using microdilatancy grouting material 11, in closing space, fill microdilatancy grouting Material 11 after closed using steel plate, due to there may be gap, reuse grouting material press-in fill up, after the completion of schematic diagram such as Fig. 5-2.
Embodiment 3: a kind of method for repairing and mending solving Blast Furnace Bottom leakage coal gas, including Kaifeng locked groove, implant plate, welding steel The steps such as plate, filling sealed material, sealing, mud jacking.A kind of method for repairing and mending solving Blast Furnace Bottom leakage coal gas, is behaviour outside blast furnace Make, construct, overall structure and the material of original blast furnace will not be destroyed.After construction terminates, need not toast, use can be direct plungeed into, Quickly resume production, efficiently solve the problem of Blast Furnace Bottom gas leak.
A kind of method for repairing and mending solving Blast Furnace Bottom leakage coal gas, solves Blast Furnace Bottom leakage coal gas;First in Blast Furnace Bottom ground Upper Kaifeng locked groove;It is implanted into steel plate in enclosed slot;The steel plate that enclosed slot is implanted into is u shape;Pour into a mould a kind of heat-resisting in enclosed slot Material;Heat proof material has the characteristics such as microdilatancy, plastically deformable;After integrally hardening Deng material, mud jacking operation is taken to fill up empty Gap.
Embodiment 3: as shown in Figure of description, a kind of structure solving Blast Furnace Bottom leakage coal gas, Blast Furnace Bottom concrete Hard plastic screed 6, heat-resisting brick setting 3, carbon packing layer 4 and last furnace shell 5, the inner chamber of last furnace shell 5 are connected on ground 1 Connect carbon packing layer 4, the inner chamber of carbon packing layer 4 connects heat-resisting brick setting 3, and the inner chamber connection blast furnace of heat-resisting brick setting 3 is resistance to Hot radical pier 2 and hard plastic screed 6, the opposite side of Blast Furnace Bottom concrete foundation 1 has the first enclosed slot 7, the first enclosed slot 7 For trapezoidal, filling microdilatancy plasticity clay 10 in the first enclosed slot 7, microdilatancy plasticity clay 10 parcel closing angle steel 8 and envelope Close with steel plate 9, closing angle steel 8 is l type, the side composition section that closing steel plate 9 is connected to closing angle steel 8l type is to open The rectangle of mouth, closing is more than the height of closing angle steel 8 with the height of steel plate 9, surrounds with last furnace shell 5 in closing steel plate 9 Area filling microdilatancy grouting material 11, the surface junction steel plate closing of microdilatancy grouting material 11.
The size of the first enclosed slot 7 is upper bottom 200mm, go to the bottom 220mm and high 150mm.First enclosed slot 7 is around State of Blast Furnace Shell 5.
Embodiment 4: as shown in Figure of description, a kind of structure solving Blast Furnace Bottom leakage coal gas, Blast Furnace Bottom concrete Hard plastic screed 6, heat-resisting brick setting 3, carbon packing layer 4 and last furnace shell 5, the inner chamber of last furnace shell 5 are connected on ground 1 Connect carbon packing layer 4, the inner chamber of carbon packing layer 4 connects heat-resisting brick setting 3, and the inner chamber connection blast furnace of heat-resisting brick setting 3 is resistance to Hot radical pier 2 and hard plastic screed 6, the opposite side of Blast Furnace Bottom concrete foundation 1 has the second enclosed slot 12, the second enclosed slot 12 is rectangle, fills microdilatancy plasticity clay 10 in the second enclosed slot 12, and microdilatancy plasticity clay 10 wraps up closing steel plate 9, The area filling microdilatancy grouting material 11 surrounding with last furnace shell 5 in closing steel plate 9, the surface of microdilatancy grouting material 11 connects Steel plate is closed.
The size of the second enclosed slot 12 is width 30mm and height 200mm.Second enclosed slot 12 is around last furnace shell 5.
As described above, being explained to embodiments of the invention, but as long as essentially without depart from this Bright inventive point and effect can have a lot of deformation, and this will be readily apparent to persons skilled in the art.Therefore, this The variation of sample is also integrally incorporated within protection scope of the present invention.

Claims (7)

1. a kind of solve Blast Furnace Bottom leak coal gas method for repairing and mending it is characterised in that containing step as follows;By locked groove, the plant of breaking a seal Enter steel plate, welding steel, fill sealed material, sealing, mud jacking step, whole Blast Furnace Bottom is wrapped in one relatively by furnace bottom pedestal In space for closing, even if coal gas can be formed between the concrete and body of heater interface or concrete and pedestal of cast leading to Road, coal gas also will not leak into the external world of closing space.
2. a kind of Blast Furnace Bottom that solves according to claim 1 leaks the method for repairing and mending of coal gas it is characterised in that also containing step Suddenly as follows;
Step 1, broke a seal on concrete ground primary surface locked groove along blast furnace one week, groove width 200mm, deep 150mm, and trench bottom is than on groove Mouth is bigger;
Step 2, it is implanted into closing steel construction in above-mentioned enclosed slot using anchoring piece within one week along blast furnace, be embedded in enclosed slot Closing steel construction part, be welded with the thick steel plate of the angle steel of 63 × 63 × 8mm and 10mm, both contact surfaces should beat slope Mouthful full weld is it is ensured that the tensile strength of binding site;
Step 3, with microdilatancy plasticity clay, the steel construction piece being welded first is embedded in the enclosed slot of ground;
Step 4, finally pour in the space of closing using microdilatancy grouting material, make after filling microdilatancy grouting material in closing space With steel plate closing, exist gap reuse grouting material press-in fill up.
3. a kind of Blast Furnace Bottom that solves according to claim 1 leaks the method for repairing and mending of coal gas it is characterised in that containing following Step;
Step 1, broke a seal on concrete ground primary surface locked groove along blast furnace one week, groove width 30mm, deep 200mm;
Step 2, in above-mentioned enclosed slot along blast furnace one week implantation closing steel construction piece;
Step 3, with microdilatancy plasticity clay, the steel construction piece being welded first is embedded in the enclosed slot of ground;
Step 4, finally pour in the space of closing using microdilatancy grouting material, make after filling microdilatancy grouting material in closing space With steel plate closing, exist gap reuse grouting material press-in fill up.
4. a kind of Blast Furnace Bottom that solves leaks the structure of coal gas it is characterised in that connecting hard plastic on Blast Furnace Bottom concrete foundation Screed, heat-resisting brick setting, carbon packing layer and last furnace shell, the inner chamber of last furnace shell connects carbon packing layer, carbon packing The inner chamber of layer connects heat-resisting brick setting, and the inner chamber of heat-resisting brick setting connects blast furnace heat resisting foundation pier and hard plastic screed, blast furnace The opposite side of furnace bottom concrete foundation has the first enclosed slot, and the first enclosed slot is trapezoidal, and filling microdilatancy in the first enclosed slot is moulded Property clay, microdilatancy plastic hinge mud drum wraps up in closing angle steel and closing steel plate, and closing angle steel is l type, and closing steel plate is even The side composition section being connected on closing angle steel l type is the rectangle of opening, and the height of closing steel plate is more than closing angle steel Highly, the area filling microdilatancy grouting material surrounding in closing steel plate and last furnace shell, the surface of microdilatancy grouting material connects Steel plate is closed.
5. a kind of structure solving Blast Furnace Bottom leakage coal gas according to claim 4, the size of the first enclosed slot is upper bottom 200mm, go to the bottom 220mm and high 150mm.
6. a kind of Blast Furnace Bottom that solves leaks the structure of coal gas it is characterised in that connecting hard plastic on Blast Furnace Bottom concrete foundation Screed, heat-resisting brick setting, carbon packing layer and last furnace shell, the inner chamber of last furnace shell connects carbon packing layer, carbon packing The inner chamber of layer connects heat-resisting brick setting, and the inner chamber of heat-resisting brick setting connects blast furnace heat resisting foundation pier and hard plastic screed, blast furnace The opposite side of furnace bottom concrete foundation has the second enclosed slot, and the second enclosed slot is rectangle, and filling microdilatancy in the second enclosed slot is moulded Property clay, microdilatancy plastic hinge mud drum wraps up in closing steel plate, and the area filling surrounding in closing steel plate and last furnace shell is micro- swollen Swollen grouting material, the surface junction steel plate closing of microdilatancy grouting material.
7. a kind of structure solving Blast Furnace Bottom leakage coal gas according to claim 6, the size of the second enclosed slot is width 30mm and height 200mm.
CN201610900204.XA 2016-10-14 2016-10-14 A kind of structure and method for repairing and mending solving Blast Furnace Bottom leakage coal gas Active CN106367550B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610900204.XA CN106367550B (en) 2016-10-14 2016-10-14 A kind of structure and method for repairing and mending solving Blast Furnace Bottom leakage coal gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610900204.XA CN106367550B (en) 2016-10-14 2016-10-14 A kind of structure and method for repairing and mending solving Blast Furnace Bottom leakage coal gas

Publications (2)

Publication Number Publication Date
CN106367550A true CN106367550A (en) 2017-02-01
CN106367550B CN106367550B (en) 2018-12-11

Family

ID=57896486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610900204.XA Active CN106367550B (en) 2016-10-14 2016-10-14 A kind of structure and method for repairing and mending solving Blast Furnace Bottom leakage coal gas

Country Status (1)

Country Link
CN (1) CN106367550B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109929956A (en) * 2019-04-16 2019-06-25 北京瑞普同创科技发展有限公司 Smelt iron the online controlling device of hot-blast stove basis blowby compressed gas and installation method
CN110863511A (en) * 2019-12-02 2020-03-06 南京联合荣大工程材料有限责任公司 Method for repairing blast of furnace base of hot blast furnace
CN110953876A (en) * 2019-12-18 2020-04-03 攀钢集团工程技术有限公司 Method for repairing vertical kiln refractory layer
TWI826274B (en) * 2023-02-23 2023-12-11 中國鋼鐵股份有限公司 Method for evaluating slurry of repair material of blast furnace and method for repairing runner of blast furnace

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392086A (en) * 2011-11-21 2012-03-28 安阳钢铁股份有限公司 Large blast furnace body gas leakage prevention method
CN104988260A (en) * 2015-07-13 2015-10-21 山东钢铁股份有限公司 A method for sealing gas leakage of furnace foundation of blast furnace
CN204874570U (en) * 2015-08-28 2015-12-16 江苏沙钢集团有限公司 Well seal structure
CN206143229U (en) * 2016-10-14 2017-05-03 南京联合荣大工程材料有限责任公司 Solve structure of bottom of blast furnace coal leaking gas

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392086A (en) * 2011-11-21 2012-03-28 安阳钢铁股份有限公司 Large blast furnace body gas leakage prevention method
CN104988260A (en) * 2015-07-13 2015-10-21 山东钢铁股份有限公司 A method for sealing gas leakage of furnace foundation of blast furnace
CN204874570U (en) * 2015-08-28 2015-12-16 江苏沙钢集团有限公司 Well seal structure
CN206143229U (en) * 2016-10-14 2017-05-03 南京联合荣大工程材料有限责任公司 Solve structure of bottom of blast furnace coal leaking gas

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
付旭威: "防止高炉炉底煤气泄漏方法", 《冶金建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109929956A (en) * 2019-04-16 2019-06-25 北京瑞普同创科技发展有限公司 Smelt iron the online controlling device of hot-blast stove basis blowby compressed gas and installation method
CN110863511A (en) * 2019-12-02 2020-03-06 南京联合荣大工程材料有限责任公司 Method for repairing blast of furnace base of hot blast furnace
CN110953876A (en) * 2019-12-18 2020-04-03 攀钢集团工程技术有限公司 Method for repairing vertical kiln refractory layer
TWI826274B (en) * 2023-02-23 2023-12-11 中國鋼鐵股份有限公司 Method for evaluating slurry of repair material of blast furnace and method for repairing runner of blast furnace

Also Published As

Publication number Publication date
CN106367550B (en) 2018-12-11

Similar Documents

Publication Publication Date Title
CN106367550A (en) Structure and repair method for eliminating leak coal gas of blast furnace bottom
CN206143229U (en) Solve structure of bottom of blast furnace coal leaking gas
CN110939104A (en) Mixed seepage-proofing dam
CN109944314B (en) Rapid construction method for rainfall-free large-diameter wound pipe composite joint
CN104313217B (en) Blast furnace bottom
CN104482298A (en) HDPE (high-density polyethylene) steel-plastic composite spiral winding drainage pipe installation construction method
CN109914472A (en) A kind of soft clay area assembled pipe gallery and its construction method
CN209011159U (en) Buried pipeline leakage protection structure
CN109235495A (en) The preparation method of buried pipeline leakage protection structure and buried pipeline leakage protection structure
CN107288141B (en) A kind of seamless flexible water construction technology of contrary sequence method
US11598065B2 (en) Method for stabilizing and lifting channel boards by underwater grouting
CN101967447A (en) Marsh gas tank
CN210711606U (en) Blast furnace hot blast stove furnace base leaks out and restores structure
CN212000904U (en) Mixed seepage-proofing dam
CN204237807U (en) Blast furnace bottom
KR101969875B1 (en) Joining method for Sink holes prevention Sewer drainage canal
CN207036738U (en) A kind of tunnel roof fire resistance test device
CN206094896U (en) Leak protection heat preservation smelting furnace
CN220703732U (en) Furnace bottom sealing structure
CN217630121U (en) Connecting joint capable of statically sealing basement outlet joint
CN205398662U (en) Energy -conserving long service life's blast furnace crucibe
CN206800418U (en) A kind of buried canal case and pipe gallery soil arch load-relieving structure of drainning off floodwaters
Webb et al. Field tests of buried pipe installation procedures
CN210117738U (en) Underground waterproof structure
CN211498742U (en) Composite geomembrane seepage-proofing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant