CN106364529A - Timetable management method for metro supervision control system - Google Patents

Timetable management method for metro supervision control system Download PDF

Info

Publication number
CN106364529A
CN106364529A CN201610797576.4A CN201610797576A CN106364529A CN 106364529 A CN106364529 A CN 106364529A CN 201610797576 A CN201610797576 A CN 201610797576A CN 106364529 A CN106364529 A CN 106364529A
Authority
CN
China
Prior art keywords
timetable
time
monitoring system
day
plc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610797576.4A
Other languages
Chinese (zh)
Inventor
张睿
江辉
宋文恒
徐腾云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG SUPCON INFORMATION CO Ltd
Original Assignee
ZHEJIANG SUPCON INFORMATION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG SUPCON INFORMATION CO Ltd filed Critical ZHEJIANG SUPCON INFORMATION CO Ltd
Priority to CN201610797576.4A priority Critical patent/CN106364529A/en
Publication of CN106364529A publication Critical patent/CN106364529A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L27/00Central railway traffic control systems; Trackside control; Communication systems specially adapted therefor
    • B61L27/10Operations, e.g. scheduling or time tables
    • B61L27/12Preparing schedules

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Programmable Controllers (AREA)

Abstract

The invention discloses a timetable management method for a metro supervision control system. The timetable management method comprises a timetable downloading method, a timetable switching method and a single timetable executing method; after an integrated supervision control system completes editing of timetables, the timetables are downloaded in a PLC of an environment and equipment supervision control system through the timetable downloading method, the PLC of the environment and equipment supervision control system is switched to the corresponding timetable through the timetable switching method, and then the timetable is executed through the single timetable executing method to control electromechanical equipment. The scheme is additionally provided with the automatic timetable downloading function on the basis of original manual timetable downloading, automatic downloading can be completed before the timetables take effect, and manual intervention links are reduced; the scheme is further additionally provided with the version management function of the timetables, so that the version of the current timetable and the modified timetable are reasonably tracked. The timetable management method is suitable for all the metro supervision control systems.

Description

A kind of subway monitoring system time table management method
Technical field
The present invention relates to subway monitoring of tools field, especially relate to a kind of subway monitoring system time table management method.
Background technology
In subway comprehensive monitoring system, the control of electromechanical equipment based on a control, by Schema control it is achieved that one The collective control of group electromechanical equipment, in order to preferably improve the Automated condtrol efficiency of electromechanical equipment, timetable controls in mode Based on it is achieved that mode control sequence in units of sky, so, in the case of normal operation, electromechanical equipment can basis Operation demand, according to predefined timetable (i.e. mode sequences), in the different time periods, switch to different operation works Condition.Timetable control mode is the senior control mode that a kind of comprehensively monitoring software is be combined with each other with bas plc software, typically , the editor of timetable, issue and version management, completed by comprehensively monitoring software, specific execution is then completed by plc.
In timetable scheme more universal at present, in plc software, only it is configured with the memory space of a timetable, when When timetable scheme changes because of the change on date, then need manually to be downloaded in advance.For example on weekdays and During day off switching, because the time that the peak of artificial abortion occurs is different, the demand of operation also changes therewith, then need establishment different Timetable, and on weekdays formal with day off run before, the timetable weaving is downloaded in plc.On the one hand, weekly Manual download for several times, runs, to timetable, the link that link increased extra human error, on the other hand, when comprehensively monitoring event When barrier, the timetable that cannot complete second day are downloaded, can affect to run.
Content of the invention
The present invention is mainly and solves that memory space existing for prior art is less, technology that is easily making a fault etc. is asked Topic, provides and a kind of have more memory spaces, can not update the subway monitoring system timetable pipe also not interfering with operation on time Reason method.
The present invention is directed to what above-mentioned technical problem was mainly addressed by following technical proposals: a kind of subway monitoring system System time table management method, executes method including timetable method for down loading, timetable changing method and individual timetable, comprehensive prison After the editor of control system deadline table, timetable is downloaded to by environment and equipment monitoring system by timetable method for down loading In plc, environment switches to corresponding timetable with the plc of equipment monitoring system by timetable changing method, then passes through single Open timetable execution method implementation schedule to control electromechanical equipment.
This programme, on the basis of original artificial download time table, increases the automatic download function of timetable, Neng Gou Before timetable comes into force, complete automatically to download, reduce the link of manual intervention;And this programme also add the version pipe of timetable Reason, rationally follows the tracks of the timetable of current timetable version and modification.
Preferably, the plc of described environment and equipment monitoring system comprise the first memory space, the second memory space, the Three memory spaces and running status depositor, deposit timetable on working day, in the second memory space in described first memory space Deposit day off timetable, in the 3rd memory space, deposit special Time of Day table, in running status depositor storage environment with set The status data of standby monitoring system;First memory space, the second memory space, the 3rd memory space and running status depositor are all Comprehensive monitoring system is connected to by interface.
Individual timetable structure in original plc software is changed to three timetables by this programme, passes through for storage Comprehensively monitoring is downloaded to the timetable of plc, have recorded working day, day off and special holidays timetable respectively, by this kind of Mode, decreases artificial down operation.
Preferably, each memory space includes 107 depositors;Each timetable includes 50 groups of start-up mode, times Table starting time, timetable dwell time, serial number, id and version number;Every group of start-up mode includes a starting time and one Individual mode number, a starting time includes hour and minute, is represented with the high byte in a depositor and low byte respectively, that is, One starting time takies a depositor, and each mode number takies a depositor, and that is, every group of start-up mode takies two and post Storage;Timetable starting time and timetable dwell time take two depositors respectively, and the wherein time takies a depositor, The moon and the high byte and the low byte that take respectively day in a depositor;The serial number of timetable, id and version number take respectively One depositor.
This programme increased the version management of timetable, makes the processing procedure of whole timetable more efficiently, rationally.
Preferably, the work in the plc downloading to environment and equipment monitoring system that is stored with running status depositor Time of Day table version information, day off timetable version information, special Time of Day table version information and current run time table version This information, each version information includes serial number, id and version number.
Preferably, described timetable method for down loading comprises the following steps:
A1, the timetable download tool of comprehensive monitoring system issue timetable to the plc of environment and equipment monitoring system;
After a2, plc receive the timetable of download, the version information of timetable is stored to status register;
A3, comprehensive monitoring system pass through the version information of the timetable in interface retaking of a year or grade status register, if set The version information identical version information of the timetable reading in the time and issuing, then report is downloaded success and is terminated flow process; If failing the version information identical version information of timetable reading and issuing in setting time, report is downloaded and is lost Lose and terminate flow process.
Preferably, described timetable changing method comprises the following steps:
The plc of b1, environment and equipment monitoring system detects current system time;
B2, the timetable starting time detecting special Time of Day table and timetable dwell time, if system time is in spy In the timetable starting time and timetable dwell time of different Time of Day table, then enable special Time of Day table and terminate flow process, no Then enter step b3;
B3, the timetable starting time of detection day off timetable and timetable dwell time, if system time is stopped In the timetable starting time and timetable dwell time of breath Time of Day table, then enable day off timetable and terminate flow process, no Then enter step b4;
B4, enable timetable on working day, terminate flow process.
Preferably, described individual timetable execution method comprises the following steps:
The enabled timetable of c1, scanning;
The starting time of all start-up mode in c2, polling schedule, if starting time is consistent with current time, Enter step c3, otherwise continue executing with poll;
C3, the execution corresponding mode number of starting time, environment passes through the switch corresponding to mode number with equipment monitoring system State is controlling each electromechanical equipment.
The substantial effect that the present invention brings is that the design structure for timetable is optimized, will be soft for original plc Individual timetable structure in part is changed to three timetables, is downloaded to the timetable of plc by comprehensively monitoring for storage, point Not have recorded working day, day off and holiday time table, by this kind of mode, decrease artificial down operation, increase meanwhile Add the version management of timetable, made the processing procedure of whole timetable more efficiently, rationally.
Brief description
Fig. 1 is a kind of comprehensive monitoring system and the bas plc coffret figure of the present invention;
Fig. 2 be the present invention a kind of plc in individual timetable structure chart;
Fig. 3 be the present invention a kind of plc in running status register architecture figure;
Fig. 4 is a kind of download flow chart of comprehensively monitoring timetable of the present invention;
Fig. 5 is a kind of plc timetable switching flow figure of the present invention;
Fig. 6 is a kind of execution flow chart of individual timetable of the present invention.
Specific embodiment
Below by embodiment, and combine accompanying drawing, technical scheme is described in further detail.
Embodiment: as shown in fig. 1, be one of optimization of the present invention, first, by individual timetable memory space original Expand to three timetable storages, and design the interface with comprehensively monitoring.
Time table space after extension, is respectively used to store timetable on working day, day off timetable and special holidays Timetable, and interface is set, it is respectively used to the download of three timetables and the retaking of a year or grade of current operating conditions.
As shown in Figure 2, for the storage organization of individual timetable.
Each of timetable mode number, all corresponds to a starting time, in every timetable, supports maximum 50 groups and opens Dynamic time and mode number;Wherein, the starting time of pattern comprises hour and minute, respectively with the height table of bytes in depositor Show, take a depositor, mode number individually takies a depositor, starting time and totally 50 groups of mode number, takies 100 and posts Storage;Timetable starting time and dwell time take two depositors respectively, and wherein, the time takies a depositor, the moon, day With the high low byte storage of a depositor, totally 4 depositors;In order to follow the tracks of the version of timetable and the type of timetable, when Between table serial number, id and version number take a depositor respectively, 3 depositors altogether.
Serial number work 128, from 0 to 4095, afterwards turns over to 0, recycled the span of id 1 to 10 it Between, the species of express time table;Version number often edits once just Jia 1, is 65535 to the maximum.
As shown in Figure 3, describe the running status depositor in plc, for comprehensively monitoring retaking of a year or grade.
In running status depositor, comprise working day, day off and special holidays the version information of download and work as The version information of front Operational Timelines.The version information of the download of working day, day off and special holidays was used in the time In table handling interface, the timetable that labelling has been downloaded, for operator's reference, and for being read back check after downloading; The version of current run time table is used for showing the current state run in operation interface.
As shown in Figure 4, describe comprehensively monitoring to the flow process of plc download time table.
After the editor of comprehensively monitoring deadline table, click on and download knob, start download time table.Plc receives download Timetable after, the version information of download is transferred to status register, for comprehensively monitoring retaking of a year or grade;Meanwhile, comprehensively monitoring is downloaded Afterwards, continually scan for the version information in status register, after a period of time, if receiving the information consistent with download version, Report and successfully terminate, otherwise, report lost property to the authorities and lose and terminate.
As shown in Figure 5, describe the switching flow of timetable in plc.
The switching of timetable is only carried out when changing on the date.Daily plc updates the primary system time, during more new system Between after, the detection of entry condition is carried out to the timetable of storage in current plc, according to the priority of timetable execution, first detects The starting time of special holidays timetable, when system time is in the range of the start-stop time of timetable, during special holidays Between table come into force;When being unsatisfactory for, then detection day off timetable and timetable on working day successively.
As shown in Figure 6, describe the execution flow process of individual timetable in plc, comprise the following steps:
The enabled timetable of c1, scanning;
The starting time of all start-up mode in c2, polling schedule, if starting time is consistent with current time, Enter step c3, otherwise continue executing with poll;
C3, the execution corresponding mode number of starting time, environment passes through the switch corresponding to mode number with equipment monitoring system State is controlling each electromechanical equipment.
Name Resolution:
Iscs: " comprehensive monitoring system (integrated supervisory control system) ";
Bas: " environment and equipment monitoring system (bas) ";
Plc: " programmable logic controller (PLC) (programmable logic controller) ", is the control core of bas The heart, is issued by the computing of cpu, the data acquisition of io module and instruction, realizes the control to electromechanical equipment;
Electromechanical equipment under control mode: bas management, in normal operation, both can carry out Non-follow control by software, Can also be automatically controlled by predetermined control sequence, two kinds of control mode mutual exclusions;
Mode region: according to the technological requirement of air conditioner, need according to the function of realizing, under a part of bas is managed Electromechanical equipment artificially divide one group into, the region being put under the uniform management;
Pattern (number): for the electromechanical equipment in a mode region, a series of device actions pre-defining instruct, And it is equipped with unique number mark;
Timetable: according in one day, the different operational modes of different periods, editing in advance comprise temporal information and The control sequence table (scheme) of pattern information, by software editing content, and is issued in plc, is executed by plc.Timetable is general It is divided into timetable on working day (Mon-Fri), day off timetable (Saturday, Sunday) and special holidays timetable three species Type.
Specific embodiment described herein is only explanation for example to the invention spirit.The affiliated skill of the present invention The technical staff in art field can make various modifications or supplement or using similar side to described specific embodiment Formula substitutes, but the principle without departing from the present invention or surmount scope defined in appended claims.
Although more employing the terms such as timetable, starting time, memory space herein, it is not precluded from using other The probability of term.It is used for the purpose of more easily describing and explaining the essence of the present invention using these terms;They are explained Any additional restriction is become to be all contrary with the invention spirit.

Claims (7)

1. a kind of subway monitoring system time table management method is it is characterised in that include timetable method for down loading, timetable switching Method and individual timetable execute method, after the editor of comprehensive monitoring system deadline table, will by timetable method for down loading Timetable downloads in environment and the plc of equipment monitoring system, and the plc of environment and equipment monitoring system is by timetable switching side Method switches to corresponding timetable, then executes method implementation schedule by individual timetable and controls electromechanical equipment.
2. a kind of subway monitoring system time table management method according to claim 1 it is characterised in that described environment with The plc of equipment monitoring system comprises the first memory space, the second memory space, the 3rd memory space and running status depositor, Deposit timetable on working day in described first memory space, in the second memory space, deposit day off timetable, the 3rd storage is empty Interior deposit special Time of Day table, the status data of storage environment and equipment monitoring system in running status depositor;First deposits Storage space, the second memory space, the 3rd memory space and running status depositor are all connected to comprehensive monitoring system by interface.
3. a kind of subway monitoring system time table management method according to claim 2 is it is characterised in that each storage is empty Between include 107 depositors;Each timetable includes 50 groups of start-up mode, timetable starting time, timetable dwell time, sequence Row number, id and version number;Every group of start-up mode includes a starting time and a mode number, and a starting time includes hour And minute, represented with the high byte in a depositor and low byte respectively, that is, a starting time takies a depositor, often Individual mode number takies a depositor, and that is, every group of start-up mode takies two depositors;Timetable starting time and timetable stop Only the time takies two depositors respectively, and the wherein time takies a depositor, the moon and taking respectively day in a depositor High byte and low byte;The serial number of timetable, id and version number take a depositor respectively.
4. a kind of subway monitoring system time table management method according to Claims 2 or 3 is it is characterised in that run shape It is stored with state depositor timetable version information on working day in the plc downloading to environment and equipment monitoring system, day off Timetable version information, special Time of Day table version information and current run time table version information, each version information wraps Include serial number, id and version number.
5. a kind of subway monitoring system time table management method according to claim 1 is it is characterised in that described timetable Method for down loading comprises the following steps:
A1, the timetable download tool of comprehensive monitoring system issue timetable to the plc of environment and equipment monitoring system;
After a2, plc receive the timetable of download, the version information of timetable is stored to status register;
A3, comprehensive monitoring system pass through the version information of the timetable in interface retaking of a year or grade status register, if in setting time The version information identical version information of the timetable inside reading and issuing, then report is downloaded success and is terminated flow process;If Fail the version information identical version information of timetable reading and issuing in setting time, then report failed download is simultaneously Terminate flow process.
6. according to claim 1 or 5 a kind of subway monitoring system time table management method it is characterised in that when described Between table changing method comprise the following steps:
The plc of b1, environment and equipment monitoring system detects current system time;
B2, the timetable starting time detecting special Time of Day table and timetable dwell time, if system time is in special day In the timetable starting time and timetable dwell time of timetable, then enable special Time of Day table and terminate flow process, otherwise enter Enter step b3;
B3, the timetable starting time of detection day off timetable and timetable dwell time, if system time is on day off In the timetable starting time and timetable dwell time of timetable, then enable day off timetable and terminate flow process, otherwise enter Enter step b4;
B4, enable timetable on working day, terminate flow process.
7. a kind of subway monitoring system time table management method according to claim 6 it is characterised in that described individual when Between table execution method comprise the following steps:
The enabled timetable of c1, scanning;
The starting time of all start-up mode in c2, polling schedule, if starting time is consistent with current time, enters Step c3, otherwise continues executing with poll;
C3, the execution corresponding mode number of starting time, environment passes through the on off state corresponding to mode number with equipment monitoring system To control each electromechanical equipment.
CN201610797576.4A 2016-08-31 2016-08-31 Timetable management method for metro supervision control system Pending CN106364529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610797576.4A CN106364529A (en) 2016-08-31 2016-08-31 Timetable management method for metro supervision control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610797576.4A CN106364529A (en) 2016-08-31 2016-08-31 Timetable management method for metro supervision control system

Publications (1)

Publication Number Publication Date
CN106364529A true CN106364529A (en) 2017-02-01

Family

ID=57899177

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610797576.4A Pending CN106364529A (en) 2016-08-31 2016-08-31 Timetable management method for metro supervision control system

Country Status (1)

Country Link
CN (1) CN106364529A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111098896A (en) * 2019-12-19 2020-05-05 北京交通大学 Weekend train operation scheme modeling method considering passenger flow fluctuation and scheme connectivity
CN111766821A (en) * 2020-07-22 2020-10-13 中交机电工程局有限公司 Mode control method and system for environment and equipment monitoring system
CN113777959A (en) * 2020-06-10 2021-12-10 南京南瑞继保工程技术有限公司 Mode sequential control method and device based on comprehensive monitoring system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01276288A (en) * 1988-04-28 1989-11-06 Hitachi Ltd In-train ticket checker utilizing portable terminal equipment
JPH1153157A (en) * 1997-08-01 1999-02-26 Ricoh Co Ltd Electronic timetable system
JP2002249049A (en) * 2001-02-26 2002-09-03 Nippon Signal Co Ltd:The Traffic control device
JP2006131123A (en) * 2004-11-08 2006-05-25 Hitachi Ltd Operation schedule display device
JP4627303B2 (en) * 2007-01-19 2011-02-09 三菱電機株式会社 Driving arrangement support system
CN102050139A (en) * 2010-11-24 2011-05-11 国电南瑞科技股份有限公司 Method for comprehensively monitoring BAS (Building Automation System) schedule functions
JP4785275B2 (en) * 2001-06-04 2011-10-05 東芝プラントシステム株式会社 Train operation timetable management system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01276288A (en) * 1988-04-28 1989-11-06 Hitachi Ltd In-train ticket checker utilizing portable terminal equipment
JPH1153157A (en) * 1997-08-01 1999-02-26 Ricoh Co Ltd Electronic timetable system
JP2002249049A (en) * 2001-02-26 2002-09-03 Nippon Signal Co Ltd:The Traffic control device
JP4785275B2 (en) * 2001-06-04 2011-10-05 東芝プラントシステム株式会社 Train operation timetable management system
JP2006131123A (en) * 2004-11-08 2006-05-25 Hitachi Ltd Operation schedule display device
JP4627303B2 (en) * 2007-01-19 2011-02-09 三菱電機株式会社 Driving arrangement support system
CN102050139A (en) * 2010-11-24 2011-05-11 国电南瑞科技股份有限公司 Method for comprehensively monitoring BAS (Building Automation System) schedule functions

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
李伟章: "《城市轨道交通通信》", 31 May 2013 *
王菁: "地铁环境与设备监控系统的设计与实现", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *
许超: "轨道交通综合监控系统时间表功能及其实现", 《城市轨道交通研究》 *
黄力宁等: "北京地铁14号线环控系统LK系列冗余可编程控制器应用", 《都市快轨交通》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111098896A (en) * 2019-12-19 2020-05-05 北京交通大学 Weekend train operation scheme modeling method considering passenger flow fluctuation and scheme connectivity
CN111098896B (en) * 2019-12-19 2021-04-13 北京交通大学 Weekend train operation scheme modeling method considering passenger flow fluctuation and scheme connectivity
CN113777959A (en) * 2020-06-10 2021-12-10 南京南瑞继保工程技术有限公司 Mode sequential control method and device based on comprehensive monitoring system
CN111766821A (en) * 2020-07-22 2020-10-13 中交机电工程局有限公司 Mode control method and system for environment and equipment monitoring system

Similar Documents

Publication Publication Date Title
CN101398686A (en) Adaptive industrial systems via embedded historian data
CN110489143A (en) FOTA firmware remote update system and its method on new-energy automobile
CN106364529A (en) Timetable management method for metro supervision control system
CN103384858B (en) Process planning apparatus
CN104571041B (en) Based on 1:The method of data synchronization of 1 controller redundancy
CN105260248B (en) A kind of task scheduling system and dispatching method being dynamically adapted
CN102608965A (en) Methods and apparatus to upgrade and provide control redundancy in process plants
CN109582323A (en) Increment updating method, device, terminal and the server of application installation package
US8010960B2 (en) System and method for providing a software installation or removal status display
CN108345265A (en) Programmed method, visual programming platform, memory and the processor of hardware device
CN107566460B (en) Method and system for distributed deployment of planning tasks
CN103577214B (en) Application program update method and apparatus
CN109358887A (en) A kind of the online upgrading method, apparatus and system of SCM program
CN106062648A (en) Controller
CN101106734B (en) Task dispatching system and method for intelligent network system
CN113325810B (en) Automatic data interaction method
CN109358865A (en) A kind of industrial vehicle car networking instrument and upgrade method with remote upgrade function
CN101436065A (en) Substrate production plan generating method
CN103838762B (en) Uninterrupted data processing unit and method based on tables of data rotation
CN101178660A (en) Memory data automatic update method
CN102065411A (en) Method for dynamically updating wireless sensor network
CN111506449A (en) Air conditioner parameter storage method and device and storage medium
JP2020537269A (en) How to implement an ordering plan that guarantees low latency communication between real-time tasks
CN112527324A (en) Automatic control method for program annotation
CN101159605B (en) Flow control method capable of implementing state memory and recovery

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170201