CN106356896A - Method and system for forming offshore wind plant integration scheme - Google Patents

Method and system for forming offshore wind plant integration scheme Download PDF

Info

Publication number
CN106356896A
CN106356896A CN201610951751.0A CN201610951751A CN106356896A CN 106356896 A CN106356896 A CN 106356896A CN 201610951751 A CN201610951751 A CN 201610951751A CN 106356896 A CN106356896 A CN 106356896A
Authority
CN
China
Prior art keywords
electric field
marine wind
wind electric
access scheme
scheme
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610951751.0A
Other languages
Chinese (zh)
Other versions
CN106356896B (en
Inventor
谭茂强
谢开贵
胡博
徐星旻
徐龙博
郑明�
谭任深
杨源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd filed Critical China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN201610951751.0A priority Critical patent/CN106356896B/en
Publication of CN106356896A publication Critical patent/CN106356896A/en
Application granted granted Critical
Publication of CN106356896B publication Critical patent/CN106356896B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J3/386
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects

Abstract

The invention relates to a method and system for forming an offshore wind plant integration scheme. The method comprises the following steps: acquiring target power grid parameters, and generating an offshore wind plant integration scheme according to the target power grid parameters; acquiring a technical index after the offshore wind plant power in each offshore wind plant integration scheme is integrated into a target power grid; designing a topological structure and equipment reliability parameters according to the offshore wind plant integration scheme having the technical index meeting the requirement of a preset technical index, and calculating an economic index corresponding to the offshore wind plant integration scheme according to the topological structure and equipment reliability parameters of an offshore wind plant; comparing corresponding offshore wind plant integration schemes according to the economic index to acquire an optimized offshore wind plant integration scheme, and outputting; evaluating the technical index and economic index of each offshore integration scheme to acquire an optimized offshore wind plant integration scheme. Therefore, the offshore wind plant integration scheme has optimized investment cost, and the integration cost for an offshore wind plant can be reduced.

Description

Marine wind electric field access scheme forming method and system
Technical field
The present invention relates to electric power network technical field, more particularly to a kind of marine wind electric field access scheme forming method and System.
Background technology
Wind-power electricity generation is a kind of generation mode with fastest developing speed in current renewable energy power generation technology.In recent years, the world Investment in terms of wind-power electricity generation equipment manufacturing and power construction for the rapid countries and regions of economically developed or economic development keeps At a relatively high growth rate.
Compared with land wind energy turbine set, it is excellent and do not account for the advantages such as land resource, to China that marine wind electric field has wind-resources For, the construction of offshore wind farm also has another prominent superiority.The load center of China is concentrated mainly on economically developed, consumption The big maritime provinces of electricity, and land wind energy resources is then mainly in the west area away from load center.Land wind-powered electricity generation on a large scale Exploitation face technology and the economic constraints of long distance powedr transmission.And offshore wind farm then can be directly accessed load center on-site elimination, For leading to local power supply load center less and less electrical network because of land used and environmental protection pressure, the addition of offshore wind farm is undoubtedly It is favorably improved the enabling capabilities of its local power supply.
At sea at the beginning of wind field design, need to determine that multiple feasible programs of marine wind electric field can design to marine wind electric field And finally overall efficiency produces impact, so how different marine wind electric field access schemes are formulated evaluating and selection standard, right The cost of access reducing marine wind electric field is significant.
Content of the invention
Based on this it is necessary to be directed to the problems referred to above, provide a kind of sea turn of the cost of access reducing marine wind electric field Electric field access scheme forming method and system.
A kind of marine wind electric field access scheme forming method, comprises the following steps:
Obtain target grid parameter, and multiple marine wind electric field access schemes are generated according to described target grid parameter;
Obtain marine wind electric field power in each described marine wind electric field access scheme and access the technical finger after target grid Mark;
Technical index according to obtaining meets the marine wind electric field access scheme presetting technical index request, design sea The topological structure of upper wind energy turbine set and equipment dependability parameter, and the topological structure according to described marine wind electric field and equipment dependability Parameter is calculated the economic index of corresponding marine wind electric field access scheme;
According to described economic index, corresponding marine wind electric field access scheme is compared, obtains optimum offshore wind farm Field access scheme simultaneously exports.
A kind of marine wind electric field access scheme forms system, comprising:
Access scheme generation module, for obtaining target grid parameter, and generates multiple according to described target grid parameter Marine wind electric field access scheme;
Technical index selection module, connects for obtaining marine wind electric field power in each described marine wind electric field access scheme Enter the technical index after target grid;
Economic index computing module, for meeting, according to the technical index obtaining, the sea presetting technical index request Upper wind energy turbine set access scheme, the topological structure of design marine wind electric field and equipment dependability parameter, and according to described offshore wind farm Topological structure and equipment dependability parameter be calculated the economic index of corresponding marine wind electric field access scheme;
Optimal case output module, for comparing to corresponding marine wind electric field access scheme according to described economic index Relatively, obtain optimum marine wind electric field access scheme and export.
Above-mentioned marine wind electric field access scheme forming method and system, obtain target grid parameter, and according to target grid Parameter generates multiple marine wind electric field access schemes.Obtain marine wind electric field power in each marine wind electric field access scheme and access mesh Technical index after mark electrical network.The marine wind electric field that technical index according to obtaining meets default technical index request connects Enter scheme, the topological structure of design marine wind electric field and equipment dependability parameter, and the topology knot according to described marine wind electric field Structure and equipment dependability parameter are calculated the economic index of corresponding marine wind electric field access scheme.According to economic index pair Corresponding marine wind electric field access scheme is compared, and obtains optimum marine wind electric field access scheme and exports.By to each sea Upper wind energy turbine set access scheme carries out technical index and economical index evaluation, thus obtaining optimum marine wind electric field access side Case, can provide effective instrument for the access network system design in marine wind electric field Design Fundamentals stage, make marine wind electric field Access system investment cost is optimum, reduces the cost of access of marine wind electric field.
Brief description
Fig. 1 is the flow chart of marine wind electric field access scheme forming method in an embodiment;
Fig. 2 is the structure chart that in an embodiment, marine wind electric field access scheme forms system.
Specific embodiment
In one embodiment, a kind of marine wind electric field access scheme forming method, as shown in figure 1, comprising the following steps:
Step s120: obtain target grid parameter, and multiple marine wind electric field access sides are generated according to target grid parameter Case.
The species of target grid parameter is not unique, specifically can be according to the different access transformer station of target grid, access electricity Pressure grade and line attachment return number, arrange multiple feasible marine wind electric field access system plans.In one embodiment, target Electrical network parameter includes the expected load vacancy of target grid, and each transformer station 110kv and 220kv side vacant outgoing line interval number Amount.Step s120 includes step 122 and step 124.
Step 122: obtain the expected load vacancy of target grid, and according to expected load vacancy setting marine wind electric field dress Machine scale.Consider that target grid expects load vacancy, rationally setting marine wind electric field installation scale.
Step 124: obtain target grid each transformer station 110kv and 220kv side vacant outgoing line interval quantity, select different Access transformer station, line attachment returns number and accesses electric pressure, generates multiple marine wind electric field access schemes.Investigate target grid Each transformer station 110kv and 220kv side vacant outgoing line interval quantity, selects different access transformer stations, line attachment to return number and connect Enter electric pressure, generate different access schemes.
Step s140: obtain marine wind electric field power in each marine wind electric field access scheme and access the technology after target grid Property index.
The particular type of technical index is not unique, and in the present embodiment, it is normal that technical index may include target grid Trend distribution under the method for operation, the distribution of n-1 trend, short circuit current and stability under malfunction.Wherein, target grid is normal The method of operation is to refer to target grid not break down.Carry out respectively under target grid normal operating mode after each scheme access Trend distribution, n-1 trend distribution under malfunction, short circuit current and stable calculation, so that it is determined that the corresponding skill of each scheme Art index.
Step s160: the technical index according to obtaining meets the marine wind electric field access side presetting technical index request Case, the topological structure of design marine wind electric field and equipment dependability parameter, and the topological structure according to marine wind electric field and equipment Dependability parameter is calculated the economic index of corresponding marine wind electric field access scheme.
Different according to the particular type of technical index, default technical index request also can correspond to different.Equally May include the trend distribution under target grid normal operating mode with technical index, the distribution of n-1 trend, short circuit under malfunction As a example electric current and stability, in the present embodiment, preset technical index request and include trend under target grid normal operating mode And under malfunction, n-1 trend is out-of-limit, short circuit current is not out-of-limit and malfunction under system not unstability under n-1 state.Can Pre-set the out-of-limit condition of n-1 trend under trend and malfunction under electrical network normal operating mode, and short circuit current more Limit condition, occurs trend out-of-limit out-of-limit with short circuit current with judging whether.
Not out-of-limit with n-1 trend under trend under normal operating mode and malfunction, short circuit current is not out-of-limit, fault n-1 Under state, unstability is not constraints to system, and whether the technical index studying each scheme meets each constraint requirements, if so, then root According to meeting the scheme presetting technical index request, to marine wind electric field, each equipment and topological structure are designed, and arrange each The dependability parameter of element;If it is not, the program or modification then can be excluded.Specifically, in one embodiment, step s160 Including step 162 to step 166.
Step 162: extractive technique index meets the marine wind electric field access scheme presetting technical index request, obtains Initial option access scheme.
Specifically can extract full after technical index is deleted or modified being unsatisfactory for presetting the scheme of technical index request Foot presets the scheme of technical index request, obtains initial option access scheme.
Step 164: the access electric pressure of 110kv or 220kv according to selected in initial option access scheme, design sea Upper wind energy turbine set Main connection form and transmission voltage grade, obtain the topological structure of marine wind electric field and determine that equipment dependability is joined Number.
The access electric pressure of 110kv or 220kv according to selected in each scheme, designs marine wind electric field main electrical scheme shape Formula and transmission voltage grade obtain the topological structure of marine wind electric field, select relevant device simultaneously to determine each equipment dependability parameter.
Step 166: the topological structure according to marine wind electric field and equipment dependability parameter, calculate marine wind electric field reliability Index year lacks generated energy, and scarce for reliability index year generated energy mark conversion is obtained economic index year lacking power generation loss, as Economic index.
After the topological structure determining marine wind electric field and each equipment dependability parameter, can directly determine in corresponding scheme The generated energy of marine wind electric field, can be calculated in conjunction with expected load vacancy and marine wind electric field reliability index year lack generating Amount, as the generating reliability index of corresponding scheme.Lacked generated energy marine wind electric field reliability index year divided by default damage Loss-rate can get generated energy needed for marine wind electric field, calculates generated energy needed for marine wind electric field and marine wind electric field reliability index The difference of year scarce generated energy obtains economic index year lacking power generation loss, as the economic index of corresponding scheme.Wherein, economy Index year lacks the power generation loss that power generation loss refers to lead to due to equipment fault.
Step s180: according to economic index, corresponding marine wind electric field access scheme is compared, obtains optimum sea Upper wind energy turbine set access scheme simultaneously exports.
Econmics comparison can be carried out to each scheme using minimum comparative annual cost approach, increased on the basis of annual fee relative method The power generation loss being led to due to equipment fault.Specifically, step s180 includes step 182 and step 184.
Step 182: econmics comparison is carried out to each initial option access scheme, obtains the capital project annual fee of corresponding scheme With.It is specially
n f = z [ r 0 ( 1 + r 0 ) n ( 1 + r 0 ) n - 1 ] + u + r
Wherein, nf is capital project annual cost, and z is scheme gross investment, and u is scheme annual operating cost, and r0 is power industry Rate of return on investment, n is industrial economy service life, and r lacks power generation loss for economic index year.
Step 184: obtain the minimum scheme of capital project annual cost in each initial option access scheme, as optimum sea Upper wind energy turbine set access scheme output.
According to each scheme technical comparison and econmics comparison result, meeting the premise presetting technical index request Under, select the minimum scheme of annual fee to export for final scheme.The mode of the optimum marine wind electric field access scheme of output is not only One, can be to export to be managed concentratedly or exported to host computer to be stored to memorizer.
Above-mentioned marine wind electric field access scheme forming method, by carrying out technical finger to each marine wind electric field access scheme Mark and economical index evaluation, thus obtaining optimum marine wind electric field access scheme, can be marine wind electric field Design Fundamentals rank The access network system design of section provides effective instrument, makes marine wind electric field access system investment cost optimum, reduces sea The cost of access of upper wind energy turbine set.
In one embodiment, a kind of marine wind electric field access scheme forms system, as shown in Fig. 2 including access scheme Generation module 120, technical index selection module 140, economic index computing module 160 and optimal case output module 180.
Access scheme generation module 120 is used for obtaining target grid parameter, and generates multiple seas according to target grid parameter Upper wind energy turbine set access scheme.
The species of target grid parameter is not unique, specifically can be according to the different access transformer station of target grid, access electricity Pressure grade and line attachment return number, arrange multiple feasible marine wind electric field access system plans.In one embodiment, target Electrical network parameter includes the expected load vacancy of target grid, and each transformer station 110kv and 220kv side vacant outgoing line interval number Amount.Access scheme generation module 120 first access scheme signal generating unit and the second access scheme signal generating unit.
First access scheme signal generating unit is used for obtaining the expected load vacancy of target grid, and according to expected load vacancy Setting marine wind electric field installation scale.Consider that target grid expects load vacancy, rationally setting marine wind electric field installation scale.
Second access scheme signal generating unit is used for obtaining between the vacant outlet of target grid each transformer station 110kv and 220kv side Every quantity, select different access transformer stations, line attachment to return number and access electric pressure, generate multiple marine wind electric fields and access Scheme.Investigation target grid each transformer station 110kv and 220kv side vacant outgoing line interval quantity, the different access transformer stations of selection, Line attachment returns number and accesses electric pressure, generates different access schemes.
Technical index selection module 140 is used for obtaining marine wind electric field power access in each marine wind electric field access scheme Technical index after target grid.
The particular type of technical index is not unique, and in the present embodiment, it is normal that technical index may include target grid Trend distribution under the method for operation, the distribution of n-1 trend, short circuit current and stability under malfunction.Wherein, target grid is normal The method of operation is to refer to target grid not break down.Carry out respectively under target grid normal operating mode after each scheme access Trend distribution, n-1 trend distribution under malfunction, short circuit current and stable calculation, so that it is determined that the corresponding skill of each scheme Art index.
Economic index computing module 160 is used for being met according to the technical index obtaining presets technical index request Marine wind electric field access scheme, the topological structure of design marine wind electric field and equipment dependability parameter, and according to marine wind electric field Topological structure and equipment dependability parameter be calculated the economic index of corresponding marine wind electric field access scheme.
Different according to the particular type of technical index, default technical index request also can correspond to different.Equally May include the trend distribution under target grid normal operating mode with technical index, the distribution of n-1 trend, short circuit under malfunction As a example electric current and stability, in the present embodiment, preset technical index request and include trend under target grid normal operating mode And under malfunction, n-1 trend is out-of-limit, short circuit current is not out-of-limit and malfunction under system not unstability under n-1 state.Can Pre-set the out-of-limit condition of n-1 trend under trend and malfunction under electrical network normal operating mode, and short circuit current more Limit condition, occurs trend out-of-limit out-of-limit with short circuit current with judging whether.
Not out-of-limit with n-1 trend under trend under normal operating mode and malfunction, short circuit current is not out-of-limit, fault n-1 Under state, unstability is not constraints to system, and whether the technical index studying each scheme meets each constraint requirements, if so, then root According to meeting the scheme presetting technical index request, to marine wind electric field, each equipment and topological structure are designed, and arrange each The dependability parameter of element;If it is not, the program or modification then can be excluded.Specifically, in one embodiment, economy refers to Mark computing module 160 first economic index computing unit, the second economic index computing unit and the 3rd economic index meter Calculate unit.
First economic index computing unit is used for extractive technique index and meets the sea presetting technical index request Wind energy turbine set access scheme, obtains initial option access scheme.
Specifically can extract full after technical index is deleted or modified being unsatisfactory for presetting the scheme of technical index request Foot presets the scheme of technical index request, obtains initial option access scheme.
Second economic index computing unit is used for 110kv or 220kv according to selected in initial option access scheme Access electric pressure, design marine wind electric field Main connection form and transmission voltage grade, obtain the topological structure of marine wind electric field And determine equipment dependability parameter.
The access electric pressure of 110kv or 220kv according to selected in each scheme, designs marine wind electric field main electrical scheme shape Formula and transmission voltage grade obtain the topological structure of marine wind electric field, select relevant device simultaneously to determine each equipment dependability parameter.
3rd economic index computing unit is used for the topological structure and equipment dependability parameter according to marine wind electric field, meter Calculate and marine wind electric field reliability index year lack generated energy, and lacked the conversion of generated energy mark reliability index year and obtain economic index Year scarce power generation loss, as economic index.
After the topological structure determining marine wind electric field and each equipment dependability parameter, can directly determine in corresponding scheme The generated energy of marine wind electric field, can be calculated in conjunction with expected load vacancy and marine wind electric field reliability index year lack generating Amount, as the generating reliability index of corresponding scheme.Lacked generated energy marine wind electric field reliability index year divided by default damage Loss-rate can get generated energy needed for marine wind electric field, calculates generated energy needed for marine wind electric field and marine wind electric field reliability index The difference of year scarce generated energy obtains economic index year lacking power generation loss, as the economic index of corresponding scheme.Wherein, economy Index year lacks the power generation loss that power generation loss refers to lead to due to equipment fault.
Optimal case output module 180 is used for according to economic index, corresponding marine wind electric field access scheme being compared Relatively, obtain optimum marine wind electric field access scheme and export.
Econmics comparison can be carried out to each scheme using minimum comparative annual cost approach, increased on the basis of annual fee relative method The power generation loss being led to due to equipment fault.Specifically, optimal case output module 180 includes the first optimal case output list Unit and the second optimal case output unit.
First optimal case output unit is used for carrying out econmics comparison to each initial option access scheme, obtains counterparty The capital project annual cost of case.It is specially
n f = z [ r 0 ( 1 + r 0 ) n ( 1 + r 0 ) n - 1 ] + u + r
Wherein, nf is capital project annual cost, and z is scheme gross investment, and u is scheme annual operating cost, and r0 is power industry Rate of return on investment, n is industrial economy service life, and r lacks power generation loss for economic index year.
Second optimal case output unit is used for obtaining capital project annual cost minimum in each initial option access scheme Scheme, as optimum marine wind electric field access scheme output.
According to each scheme technical comparison and econmics comparison result, meeting the premise presetting technical index request Under, select the minimum scheme of annual fee to export for final scheme.The mode of the optimum marine wind electric field access scheme of output is not only One, can be to export to be managed concentratedly or exported to host computer to be stored to memorizer.
Above-mentioned marine wind electric field access scheme forms system, by carrying out technical finger to each marine wind electric field access scheme Mark and economical index evaluation, thus obtaining optimum marine wind electric field access scheme, can be marine wind electric field Design Fundamentals rank The access network system design of section provides effective instrument, makes marine wind electric field access system investment cost optimum, reduces sea The cost of access of upper wind energy turbine set.
Each technical characteristic of embodiment described above can arbitrarily be combined, for making description succinct, not to above-mentioned reality The all possible combination of each technical characteristic applied in example is all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all it is considered to be the scope of this specification record.
Embodiment described above only have expressed the several embodiments of the present invention, and its description is more concrete and detailed, but simultaneously Can not therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art Say, without departing from the inventive concept of the premise, some deformation can also be made and improve, these broadly fall into the protection of the present invention Scope.Therefore, the protection domain of patent of the present invention should be defined by claims.

Claims (10)

1. a kind of marine wind electric field access scheme forming method is it is characterised in that comprise the following steps:
Obtain target grid parameter, and multiple marine wind electric field access schemes are generated according to described target grid parameter;
Obtain marine wind electric field power in each described marine wind electric field access scheme and access the technical index after target grid;
Technical index according to obtaining meets the marine wind electric field access scheme presetting technical index request, designs sea turn The topological structure of electric field and equipment dependability parameter, and the topological structure according to described marine wind electric field and equipment dependability parameter It is calculated the economic index of corresponding marine wind electric field access scheme;
According to described economic index, corresponding marine wind electric field access scheme is compared, obtains optimum marine wind electric field and connect Enter scheme and export.
2. marine wind electric field access scheme forming method according to claim 1 is it is characterised in that described technical index Including the trend distribution under target grid normal operating mode, the distribution of n-1 trend, short circuit current and stability under malfunction; Described preset technical index request and include n-1 trend under trend and malfunction under target grid normal operating mode do not get over Limit, short circuit current is not out-of-limit and malfunction under system not unstability under n-1 state.
3. marine wind electric field access scheme forming method according to claim 1 is it is characterised in that described target grid is joined Number includes the expected load vacancy of target grid, and each transformer station 110kv and 220kv side vacant outgoing line interval quantity;Described Obtain target grid parameter, and the step that multiple marine wind electric field access schemes are generated according to described target grid parameter, including Following steps:
Obtain the expected load vacancy of target grid, and marine wind electric field installation scale is arranged according to described expected load vacancy;
Acquisition target grid each transformer station 110kv and 220kv side vacant outgoing line interval quantity, the different access transformer stations of selection, Line attachment returns number and accesses electric pressure, generates multiple marine wind electric field access schemes.
4. marine wind electric field access scheme forming method according to claim 3 it is characterised in that described according to obtain Technical index meets the marine wind electric field access scheme presetting technical index request, the topological structure of design marine wind electric field With equipment dependability parameter, and the topological structure according to described marine wind electric field and equipment dependability parameter are calculated corresponding sea The step of the economic index of upper wind energy turbine set access scheme, comprises the following steps:
Extractive technique index meets the marine wind electric field access scheme presetting technical index request, obtains initial option and accesses Scheme;
The access electric pressure of 110kv or 220kv according to selected in initial option access scheme, design marine wind electric field master connects Line form and transmission voltage grade, obtain the topological structure of marine wind electric field and determine equipment dependability parameter;
Topological structure according to described marine wind electric field and equipment dependability parameter, calculate and lack in marine wind electric field reliability index year Generated energy, and scarce for described reliability index year generated energy mark conversion is obtained economic index year lacking power generation loss, as described Economic index.
5. marine wind electric field access scheme forming method according to claim 4 it is characterised in that described according to described warp Ji property index is compared to corresponding marine wind electric field access scheme, obtains optimum marine wind electric field access scheme and exports Step, comprises the following steps:
Econmics comparison is carried out to each initial option access scheme, obtains the capital project annual cost of corresponding scheme, specially
n f = z [ r 0 ( 1 + r 0 ) n ( 1 + r 0 ) n - 1 ] + u + r
Wherein, nf is capital project annual cost, and z is scheme gross investment, and u is scheme annual operating cost, r0Invest back for power industry Yield, n is industrial economy service life, and r lacks power generation loss for economic index year;
Obtain the minimum scheme of capital project annual cost in each initial option access scheme, access as optimum marine wind electric field Scheme exports.
6. a kind of marine wind electric field access scheme forms system it is characterised in that including:
Access scheme generation module, for obtaining target grid parameter, and generates multiple seas according to described target grid parameter Wind energy turbine set access scheme;
Technical index selection module, accesses mesh for obtaining marine wind electric field power in each described marine wind electric field access scheme Technical index after mark electrical network;
Economic index computing module, for meeting, according to the technical index obtaining, the sea turn presetting technical index request Electric field access scheme, the topological structure of design marine wind electric field and equipment dependability parameter, and according to described marine wind electric field Topological structure and equipment dependability parameter are calculated the economic index of corresponding marine wind electric field access scheme;
Optimal case output module, for being compared to corresponding marine wind electric field access scheme according to described economic index, Obtain optimum marine wind electric field access scheme and export.
7. marine wind electric field access scheme according to claim 6 forms system it is characterised in that described technical index Including the trend distribution under target grid normal operating mode, the distribution of n-1 trend, short circuit current and stability under malfunction; Described preset technical index request and include n-1 trend under trend and malfunction under target grid normal operating mode do not get over Limit, short circuit current is not out-of-limit and malfunction under system not unstability under n-1 state.
8. marine wind electric field access scheme according to claim 6 forms system it is characterised in that described access scheme is given birth to Module is become to include:
First access scheme signal generating unit, for obtaining the expected load vacancy of target grid, and lacks according to described expected load Volume setting marine wind electric field installation scale;
Second access scheme signal generating unit, for obtaining target grid each transformer station 110kv and 220kv side vacant outgoing line interval number Amount, selects different access transformer stations, line attachment to return number and access electric pressure, generates multiple marine wind electric field access sides Case.
9. marine wind electric field access scheme according to claim 8 forms system it is characterised in that described economic index Computing module includes:
First economic index computing unit, meets the offshore wind farm presetting technical index request for extractive technique index Field access scheme, obtains initial option access scheme;
Second economic index computing unit, for the access of 110kv or 220kv according to selected in initial option access scheme Electric pressure, design marine wind electric field Main connection form and transmission voltage grade, obtain the topological structure of marine wind electric field simultaneously really Locking equipment dependability parameter;
3rd economic index computing unit, for the topological structure according to described marine wind electric field and equipment dependability parameter, Calculate and marine wind electric field reliability index year lack generated energy, and lacked the conversion of generated energy mark described reliability index year and obtain economy Property index year lack power generation loss, as described economic index.
10. marine wind electric field access scheme according to claim 9 forms system it is characterised in that described optimal case Output module includes:
First optimal case output unit, for carrying out econmics comparison to each initial option access scheme, obtains corresponding scheme Capital project annual cost, specially
n f = z [ r 0 ( 1 + r 0 ) n ( 1 + r 0 ) n - 1 ] + u + r
Wherein, nf is capital project annual cost, and z is scheme gross investment, and u is scheme annual operating cost, r0Invest back for power industry Yield, n is industrial economy service life, and r lacks power generation loss for economic index year;
Second optimal case output unit, for obtaining the minimum side of capital project annual cost in each initial option access scheme Case, as optimum marine wind electric field access scheme output.
CN201610951751.0A 2016-10-25 2016-10-25 Marine wind electric field access scheme forming method and system Active CN106356896B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610951751.0A CN106356896B (en) 2016-10-25 2016-10-25 Marine wind electric field access scheme forming method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610951751.0A CN106356896B (en) 2016-10-25 2016-10-25 Marine wind electric field access scheme forming method and system

Publications (2)

Publication Number Publication Date
CN106356896A true CN106356896A (en) 2017-01-25
CN106356896B CN106356896B (en) 2019-01-22

Family

ID=57863585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610951751.0A Active CN106356896B (en) 2016-10-25 2016-10-25 Marine wind electric field access scheme forming method and system

Country Status (1)

Country Link
CN (1) CN106356896B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109038657A (en) * 2018-07-20 2018-12-18 中国能源建设集团广东省电力设计研究院有限公司 Processing method, device, server and the medium of marine wind electric field primary system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130063272A1 (en) * 2011-09-13 2013-03-14 International Business Machines Corporation System and method for detecting and localizing abnormal conditions and electrical faults in an electrical grid
CN105226651A (en) * 2015-10-22 2016-01-06 上海交通大学 A kind of consider risk containing large-scale wind power Transmission Expansion Planning in Electric system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130063272A1 (en) * 2011-09-13 2013-03-14 International Business Machines Corporation System and method for detecting and localizing abnormal conditions and electrical faults in an electrical grid
CN105226651A (en) * 2015-10-22 2016-01-06 上海交通大学 A kind of consider risk containing large-scale wind power Transmission Expansion Planning in Electric system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109038657A (en) * 2018-07-20 2018-12-18 中国能源建设集团广东省电力设计研究院有限公司 Processing method, device, server and the medium of marine wind electric field primary system
CN109038657B (en) * 2018-07-20 2021-02-09 中国能源建设集团广东省电力设计研究院有限公司 Processing method, device, server and medium for primary system of offshore wind farm

Also Published As

Publication number Publication date
CN106356896B (en) 2019-01-22

Similar Documents

Publication Publication Date Title
CN106874630B (en) Electric quantity consumption-based regional power grid new energy development potential evaluation method
Billinton et al. Adequacy assessment considerations in wind integrated power systems
CN104281737B (en) A kind of wind power collection system of offshore wind power plant topological structure selection method
Vallee et al. System reliability assessment method for wind power integration
Dalabeeh Techno-economic analysis of wind power generation for selected locations in Jordan
CN102934312B (en) Energy production system and control thereof
CN102760195B (en) Topology design method and device of current collecting system of offshore wind farm
CN101425686A (en) Electrical power system on-line safety and stability evaluation forecast failure collection adaptive selection method
CN108599268B (en) Day-ahead optimization scheduling method considering wind power plant space-time association constraint
CN109617065A (en) A kind of electric system power grids circuits planing method considering magnanimity Run-time scenario
CN101567561B (en) Comparing and selecting system of power transmission network planning scheme
CN101814743A (en) Wind power integration on-line safety early warning system based on short-term wind power prediction
CN110119888A (en) A kind of active gridding planing method based on distributed generation resource access
CN102751729A (en) Research method for stably controlling static voltage of electric network comprising wind farm
CN108717608A (en) Million kilowatt beach photovoltaic plant accesses electric network synthetic decision-making technique and system
CN105244890A (en) Reactive power optimization method for new energy grid connection
CN101277014A (en) Method for selecting wind power generation access system plan
CN103617572A (en) Method for evaluating capacity adequacy of power transmission line of power grid
CN111582598A (en) Grid planning scheme automatic generation method based on grid structure and grid index analysis
CN106356896A (en) Method and system for forming offshore wind plant integration scheme
CN111882228A (en) Reliability evaluation method for power distribution network containing distributed power supply
CN115618616A (en) Method for constructing hybrid energy storage reliability evaluation model of source, network and load resources
CN113242018A (en) Photovoltaic equipment fault diagnosis method and application device thereof
CN115358639B (en) Offshore wind power operation risk analysis system based on data analysis
CN115117941A (en) Reliability evaluation method for power distribution network containing distributed power supply

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant