CN106340863A - Protection method for adaptive instantaneous current quick tripping - Google Patents

Protection method for adaptive instantaneous current quick tripping Download PDF

Info

Publication number
CN106340863A
CN106340863A CN201610999955.1A CN201610999955A CN106340863A CN 106340863 A CN106340863 A CN 106340863A CN 201610999955 A CN201610999955 A CN 201610999955A CN 106340863 A CN106340863 A CN 106340863A
Authority
CN
China
Prior art keywords
current
line
value
fault
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610999955.1A
Other languages
Chinese (zh)
Other versions
CN106340863B (en
Inventor
宁景云
郭冰
陈钊
宁宁
宁一
王小朋
张长盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610999955.1A priority Critical patent/CN106340863B/en
Publication of CN106340863A publication Critical patent/CN106340863A/en
Application granted granted Critical
Publication of CN106340863B publication Critical patent/CN106340863B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

The invention provides a protection method for adaptive instantaneous current quick tripping. The method comprises: a current current value of a power supply line is read; a current value, read at last time, of the power supply line is subtracted from the read current current value of the power supply line to obtain a fault current component; according to the fault current component, whether starting of a sudden change of a current occurs is determined; a fault type is determined; whether a practically measured current is larger than a short-current calculation value at the tail end of the line is determined; and a tripping signal is sent and the like. The method has the following effects: although the short-circuit current at the tail end of the line and the short-circuit current at any point of the line change simultaneously with the change of the reactance of the system, the short-circuit current at any point of the line is larger than or equal to the short-circuit current at the tail end of the line all the time. On the basis of the adaptive change, the sensitivity of the protection device is improved; and the complete protection range of the overall line is realized. The protection device can cut off the fault instantaneously. Compared with the traditional instantaneous current quick-tripping way, the provided method enables protection to be improved essentially.

Description

A kind of guard method of self adaptation transient current quick-break
Technical field
The invention belongs to power line protection technical field, more particularly to a kind of protection of self adaptation transient current quick-break Method.
Background technology
In power system, traditional transient current fast tripping protection setting valve will be matched with next stage quick-break electric current, by In it without the time limit, the therefore protection seting value of the current quick-breaking adjacent lines outlet three-phase under maximum operational mode that will stagger is short The electric current of protection device installation place is flow through during road.When in non-maximum operational mode or minimum operational mode, the scope protected To diminish, it could even be possible to the situation that protection domain is zero occurs.The protection domain of transient current quick-break is subject to system operation mode Impact is very big, is a very serious defect.
Fig. 1 is a kind of existing power system electrical primary wiring diagram, now taking system shown in Figure 1 as a example illustrates:
Calculate the short circuit current in b busbar short-circuit for this system:
Three short circuit current under maximum operational mode:
i k 1 ( 3 ) = e s 3 × ( x s 1 max + x 1 a b ) = 37000 3 × ( 5 + 8 ) = 1643 a
Line to line fault electric current:
i k 1 ( 2 ) = 3 2 × i k 1 ( 3 ) = 0.87 × 1643 = 1429 a
Three short circuit current under minimum operational mode:
i k 1 ( 3 ) = e s 3 × ( x s 1 min + x 1 a b ) = 37000 3 × ( 10 + 8 ) = 1187 a
Line to line fault electric current:
i k 1 ( 2 ) = 3 2 × i k 1 ( 3 ) = 0.87 × 1187 = 1033 a
From result of calculation, for the short circuit current staggering under maximum operational mode at b bus, protection seting value needs It is greater than 1643a (three-phase shortcircuit) and 1429a (line to line fault), and the short circuit current at b bus under minimum operational mode is far little In above numerical value, therefore under system minimum operational mode, current fault-clearing protective relays will be difficult to effective action.
Content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of protection side of self adaptation transient current quick-break Method.
In order to achieve the above object, the guard method of the self adaptation transient current quick-break that the present invention provides includes holding in order The following step of row:
Step 1) current sample: described current sample is the circulating sampling of each cycle for supply line's electric current In unitary sampling, using line current transformer read supply line present current value;
Step 2) calculate fault current component: the power supply that the present current value last time of this supply line reading reads Current value=the fault current component of circuit;
Step 3) judge whether that jump-value of current starts according to above-mentioned fault current component: above-mentioned fault current is divided The protection seting value measuring the current supply line short circuit current being calculated in real time with this moment microcomputer is compared, if above-mentioned fault Current component is more than or equal to the protection seting value of current supply line short circuit current, judges that jump-value of current starts, under One step execution step 5), otherwise next step execution step 4);
Step 4) normal operation program: terminate this circular flow, return and wait subsequent cycle to run;
Step 5) determine fault type;Failure classes are carried out according to a, b, c three-phase electricity flow valuve that line current transformer records Type judges, if meeting ia+ic=-ib or ia+ib+ic=0, for three phase short circuit fault, otherwise for two-phase short-circuit fault;
Step 6) judge whether measured current is more than the calculation of short-circuit current value of line end: by above-mentioned steps 1) obtain The present current value of supply line is compared with the calculation of short-circuit current value of line end, if the current flow of supply line Value is more than the calculation of short-circuit current value of line end, next step execution step 7), otherwise next step execution step 4);
Step 7) send trip signal: tripping line switching, disengagement failure line power.
The guard method of the self adaptation transient current quick-break that the present invention provides has the effect that
Although the short circuit current of any point change with system reactance simultaneously on the short circuit current of line end and circuit Change and change, but on circuit, the short circuit current of arbitrfary point is always greater than or is equal to the short circuit current that line end calculates, this Adaptive change, so that the sensitivity of protection device is improved it is achieved that the protection domain of total track length 100%, is protected Protection unit can instantaneously excise fault, and more traditional instantaneous quick-break current protection has the lifting of matter.
Brief description
Fig. 1 is a kind of existing power system electrical primary wiring diagram.
The guard method flow chart of the self adaptation transient current quick-break that Fig. 2 provides for the present invention.
Specific embodiment
The guard method of the self adaptation transient current quick-break with specific embodiment, the present invention being provided below in conjunction with the accompanying drawings is entered Row describes in detail.
As shown in figure 1, in order that protection domain can include a, b supply line total length, using b busbar short-circuit electric current as guarantor Shield setting valve.This protection seting value is to change with the change of the method for operation, also different because of the difference of short-circuit-type, for this Microcomputer Calculation system reactance value xs1 must be utilized in real time, calculate short-circuit current value at b bus further according to system reactance value xs1, This value is the protection seting value of current supply line short circuit current.By the current supply line calculating in real time short circuit current Protection seting value is stored in a certain region of ram random access memory, then measures supply line in real time using line current transformer Present current value, then calculate fault current component, afterwards by the fault current component of synchronization and above-mentioned current confession The protection seting value of electric line short circuit current is compared, if current failure current component is more than or equal to this moment microcomputer meter The protection seting value of the supply line's short circuit current calculating, you can be judged as that this short circuit occurs in ab supply line region, so Determine fault type afterwards, finally according to the supply line measuring in real time present current value whether more than the short circuit of line end Current calculation value is deciding whether to send trip signal.
As shown in Fig. 2 the guard method of the self adaptation transient current quick-break of present invention offer includes executing down in order Row step:
Step 1) current sample: described current sample is the circulating sampling of each cycle for supply line's electric current In unitary sampling, using line current transformer read supply line present current value;
Step 2) calculate fault current component: the power supply that the present current value last time of this supply line reading reads Current value=the fault current component of circuit;
Step 3) judge whether that jump-value of current starts according to above-mentioned fault current component: above-mentioned fault current is divided The protection seting value measuring the current supply line short circuit current being calculated in real time with this moment microcomputer is compared, if above-mentioned fault Current component is more than or equal to the protection seting value of current supply line short circuit current, judges that jump-value of current starts, under One step execution step 5), otherwise next step execution step 4);
Step 4) normal operation program: terminate this circular flow, return and wait subsequent cycle to run;
Step 5) determine fault type;Failure classes are carried out according to a, b, c three-phase electricity flow valuve that line current transformer records Type judges, if meeting ia+ic=-ib or ia+ib+ic=0, for three phase short circuit fault, otherwise for two-phase short-circuit fault;
Step 6) judge whether measured current is more than the calculation of short-circuit current value of line end: by above-mentioned steps 1) obtain The present current value of supply line is compared with the calculation of short-circuit current value of line end, if the current flow of supply line Value is more than the calculation of short-circuit current value of line end, next step execution step 7), otherwise next step execution step 4);
Step 7) send trip signal: tripping line switching, disengagement failure line power.

Claims (1)

1. a kind of guard method of self adaptation transient current quick-break it is characterised in that: described self adaptation transient current quick-break Guard method includes the following step executing in order:
Step 1) current sample: described current sample is in the circulating sampling for each cycle of supply line's electric current Unitary sampling, reads the present current value of supply line using line current transformer;
Step 2) calculate fault current component: the supply line that the present current value last time of this supply line reading reads Current value=fault current component;
Step 3) judge whether to occur jump-value of current according to above-mentioned fault current component and start: by above-mentioned fault current component with The protection seting value of the current supply line short circuit current that this moment microcomputer calculates in real time is compared, if above-mentioned fault current Component is more than or equal to the protection seting value of current supply line short circuit current, judges that jump-value of current starts, next step Execution step 5), otherwise next step execution step 4);
Step 4) normal operation program: terminate this circular flow, return and wait subsequent cycle to run;
Step 5) determine fault type;Carry out fault type according to a, b, c three-phase electricity flow valuve that line current transformer records to sentence Disconnected, if meeting ia+ic=-ib or ia+ib+ic=0, for three phase short circuit fault, otherwise for two-phase short-circuit fault;
Step 6) judge measured current whether more than the calculation of short-circuit current value of line end: by above-mentioned steps 1) power supply that obtains The present current value of circuit is compared with the calculation of short-circuit current value of line end, if the present current value of supply line is big In the calculation of short-circuit current value of line end, next step execution step 7), otherwise next step execution step 4);
Step 7) send trip signal: tripping line switching, disengagement failure line power.
CN201610999955.1A 2016-11-14 2016-11-14 A kind of guard method of adaptive transient current quick-break Active CN106340863B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610999955.1A CN106340863B (en) 2016-11-14 2016-11-14 A kind of guard method of adaptive transient current quick-break

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610999955.1A CN106340863B (en) 2016-11-14 2016-11-14 A kind of guard method of adaptive transient current quick-break

Publications (2)

Publication Number Publication Date
CN106340863A true CN106340863A (en) 2017-01-18
CN106340863B CN106340863B (en) 2018-05-08

Family

ID=57841307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610999955.1A Active CN106340863B (en) 2016-11-14 2016-11-14 A kind of guard method of adaptive transient current quick-break

Country Status (1)

Country Link
CN (1) CN106340863B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108736437A (en) * 2018-05-28 2018-11-02 国网天津市电力公司 A kind of adaptive fast-tripping zero-sequence current protections method
CN109298289A (en) * 2018-11-29 2019-02-01 广东电网有限责任公司 Localization method, system and the electronic equipment of distribution network failure point
CN109360777A (en) * 2018-11-01 2019-02-19 湖南长高思瑞自动化有限公司 A kind of fuse switch on-line monitoring method
CN109462204A (en) * 2017-09-06 2019-03-12 国家电网公司 A kind of method and device improving distribution line current quick sensitivity
CN110416981A (en) * 2019-07-31 2019-11-05 华北电力大学 A kind of access power distribution network zone current guard method of electric car and system
CN110556784A (en) * 2019-10-09 2019-12-10 鞍钢集团工程技术有限公司 relay protection configuration and setting method for high-voltage distribution system of ferroalloy electric furnace

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102508076A (en) * 2011-11-09 2012-06-20 东北大学 Fault diagnosis device and method based on multi-agent system and wavelet analysis
CN103050933A (en) * 2012-12-13 2013-04-17 福建省电力有限公司 Large-scale battery storage power station interface protection method based on single-ended break variable of current
CN103439635A (en) * 2013-09-06 2013-12-11 华北电力大学 Electric power system wave-recoding file based fault detection method and system
CN103490394A (en) * 2013-09-30 2014-01-01 山东大学 Self-synchronizing positive sequence fault component current differential protection method of active power distribution network
CN103730882A (en) * 2013-12-24 2014-04-16 西安交通大学 Current protection system and method for being automatically adapted to distributed power connection
CN205265233U (en) * 2015-12-18 2016-05-25 江苏省电力公司宿迁供电公司 Main step -down backup protection equipment that volume of taking sudden change starts
CN106058830A (en) * 2016-07-26 2016-10-26 华北电力大学 Current protection system with DG power distribution network and protection method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102508076A (en) * 2011-11-09 2012-06-20 东北大学 Fault diagnosis device and method based on multi-agent system and wavelet analysis
CN103050933A (en) * 2012-12-13 2013-04-17 福建省电力有限公司 Large-scale battery storage power station interface protection method based on single-ended break variable of current
CN103439635A (en) * 2013-09-06 2013-12-11 华北电力大学 Electric power system wave-recoding file based fault detection method and system
CN103490394A (en) * 2013-09-30 2014-01-01 山东大学 Self-synchronizing positive sequence fault component current differential protection method of active power distribution network
CN103730882A (en) * 2013-12-24 2014-04-16 西安交通大学 Current protection system and method for being automatically adapted to distributed power connection
CN205265233U (en) * 2015-12-18 2016-05-25 江苏省电力公司宿迁供电公司 Main step -down backup protection equipment that volume of taking sudden change starts
CN106058830A (en) * 2016-07-26 2016-10-26 华北电力大学 Current protection system with DG power distribution network and protection method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
冯巧玲等: "自适应电流速断保护分析", 《郑州轻工业学院学报》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109462204A (en) * 2017-09-06 2019-03-12 国家电网公司 A kind of method and device improving distribution line current quick sensitivity
CN108736437A (en) * 2018-05-28 2018-11-02 国网天津市电力公司 A kind of adaptive fast-tripping zero-sequence current protections method
CN109360777A (en) * 2018-11-01 2019-02-19 湖南长高思瑞自动化有限公司 A kind of fuse switch on-line monitoring method
CN109298289A (en) * 2018-11-29 2019-02-01 广东电网有限责任公司 Localization method, system and the electronic equipment of distribution network failure point
CN110416981A (en) * 2019-07-31 2019-11-05 华北电力大学 A kind of access power distribution network zone current guard method of electric car and system
CN110556784A (en) * 2019-10-09 2019-12-10 鞍钢集团工程技术有限公司 relay protection configuration and setting method for high-voltage distribution system of ferroalloy electric furnace
CN110556784B (en) * 2019-10-09 2022-02-08 鞍钢集团工程技术有限公司 Relay protection configuration and setting method for high-voltage distribution system of ferroalloy electric furnace

Also Published As

Publication number Publication date
CN106340863B (en) 2018-05-08

Similar Documents

Publication Publication Date Title
CN106340863A (en) Protection method for adaptive instantaneous current quick tripping
CN104852354A (en) Adaptive-slope transformer zero-sequence differential protection method and device
CN105140893A (en) Differential protection current transformer (CT) saturation recognition method
Mahapatra et al. Analysis of symmetrical fault in IEEE 14 bus system for enhancing over current protection scheme
CN103823160A (en) Self-adaption ground fault line selection method and device for power distribution network
KR20130003225A (en) Method for determining fault direction, overcurrent protection and displaying fault indication in distribution system with dispersed generation
CN103683228A (en) Control method of breaker failure protection and automatic reclosing device
CN101800414B (en) Method for judging and protecting low voltage in transformer short circuit fault
CN103986133B (en) The time delay over-current guard method started based on reactive power Sudden Changing Rate
JP5312546B2 (en) Circuit breaker contact consumption control system
CN102969695A (en) Grounding forecasting method in neutral-point low-resistance grounding mode
CN112731211A (en) Grounding transformer low-voltage winding turn-to-turn short circuit fault and phase identification method
CN104052033B (en) A kind of guard method based on zero-sequence current correlation coefficient identification fault branch
CN103779847B (en) Based on the guard method of SV network samples common-tower double-circuit lines single-phase earthing voltage ratio phase
CN104332973A (en) Line interphase short circuit fault relay protection method through fault active power
KR101372823B1 (en) Over current relay considering application of superconducting fault current limiter, and method for setting the relay
CN104078951B (en) A kind of based on inter-phase arc voltage characteristic line inter-phase fault two end protection method
Bjerkan Efficient fault management using remote fault indicators
CN101267099A (en) Method for realizing self-adapted over-current protection of power and distribution supply cable
CN104953565B (en) Line interphase fault relay protection method is surveyed based on transition resistance
Devipriya et al. Design of numerical relay for over flux and over current protection in transformers
CN108666985B (en) Accurate diagnosis and protection method for power frequency overvoltage of power transmission line
RU2685746C1 (en) METHOD OF DETERMINING POINT AND DISTANCE TO SINGLE-PHASE GROUND FAULT IN 6-35 kV ELECTRIC NETWORKS WITH ISOLATED OR COMPENSATED NEUTRAL POINT
Sidhu et al. A numerical technique based on symmetrical components for protecting three-winding transformers
CN100416961C (en) Method for prtecting power network

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant