CN106340863A - Protection method for adaptive instantaneous current quick tripping - Google Patents
Protection method for adaptive instantaneous current quick tripping Download PDFInfo
- Publication number
- CN106340863A CN106340863A CN201610999955.1A CN201610999955A CN106340863A CN 106340863 A CN106340863 A CN 106340863A CN 201610999955 A CN201610999955 A CN 201610999955A CN 106340863 A CN106340863 A CN 106340863A
- Authority
- CN
- China
- Prior art keywords
- current
- line
- value
- fault
- short
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/26—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
Landscapes
- Emergency Protection Circuit Devices (AREA)
Abstract
The invention provides a protection method for adaptive instantaneous current quick tripping. The method comprises: a current current value of a power supply line is read; a current value, read at last time, of the power supply line is subtracted from the read current current value of the power supply line to obtain a fault current component; according to the fault current component, whether starting of a sudden change of a current occurs is determined; a fault type is determined; whether a practically measured current is larger than a short-current calculation value at the tail end of the line is determined; and a tripping signal is sent and the like. The method has the following effects: although the short-circuit current at the tail end of the line and the short-circuit current at any point of the line change simultaneously with the change of the reactance of the system, the short-circuit current at any point of the line is larger than or equal to the short-circuit current at the tail end of the line all the time. On the basis of the adaptive change, the sensitivity of the protection device is improved; and the complete protection range of the overall line is realized. The protection device can cut off the fault instantaneously. Compared with the traditional instantaneous current quick-tripping way, the provided method enables protection to be improved essentially.
Description
Technical field
The invention belongs to power line protection technical field, more particularly to a kind of protection of self adaptation transient current quick-break
Method.
Background technology
In power system, traditional transient current fast tripping protection setting valve will be matched with next stage quick-break electric current, by
In it without the time limit, the therefore protection seting value of the current quick-breaking adjacent lines outlet three-phase under maximum operational mode that will stagger is short
The electric current of protection device installation place is flow through during road.When in non-maximum operational mode or minimum operational mode, the scope protected
To diminish, it could even be possible to the situation that protection domain is zero occurs.The protection domain of transient current quick-break is subject to system operation mode
Impact is very big, is a very serious defect.
Fig. 1 is a kind of existing power system electrical primary wiring diagram, now taking system shown in Figure 1 as a example illustrates:
Calculate the short circuit current in b busbar short-circuit for this system:
Three short circuit current under maximum operational mode:
Line to line fault electric current:
Three short circuit current under minimum operational mode:
Line to line fault electric current:
From result of calculation, for the short circuit current staggering under maximum operational mode at b bus, protection seting value needs
It is greater than 1643a (three-phase shortcircuit) and 1429a (line to line fault), and the short circuit current at b bus under minimum operational mode is far little
In above numerical value, therefore under system minimum operational mode, current fault-clearing protective relays will be difficult to effective action.
Content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of protection side of self adaptation transient current quick-break
Method.
In order to achieve the above object, the guard method of the self adaptation transient current quick-break that the present invention provides includes holding in order
The following step of row:
Step 1) current sample: described current sample is the circulating sampling of each cycle for supply line's electric current
In unitary sampling, using line current transformer read supply line present current value;
Step 2) calculate fault current component: the power supply that the present current value last time of this supply line reading reads
Current value=the fault current component of circuit;
Step 3) judge whether that jump-value of current starts according to above-mentioned fault current component: above-mentioned fault current is divided
The protection seting value measuring the current supply line short circuit current being calculated in real time with this moment microcomputer is compared, if above-mentioned fault
Current component is more than or equal to the protection seting value of current supply line short circuit current, judges that jump-value of current starts, under
One step execution step 5), otherwise next step execution step 4);
Step 4) normal operation program: terminate this circular flow, return and wait subsequent cycle to run;
Step 5) determine fault type;Failure classes are carried out according to a, b, c three-phase electricity flow valuve that line current transformer records
Type judges, if meeting ia+ic=-ib or ia+ib+ic=0, for three phase short circuit fault, otherwise for two-phase short-circuit fault;
Step 6) judge whether measured current is more than the calculation of short-circuit current value of line end: by above-mentioned steps 1) obtain
The present current value of supply line is compared with the calculation of short-circuit current value of line end, if the current flow of supply line
Value is more than the calculation of short-circuit current value of line end, next step execution step 7), otherwise next step execution step 4);
Step 7) send trip signal: tripping line switching, disengagement failure line power.
The guard method of the self adaptation transient current quick-break that the present invention provides has the effect that
Although the short circuit current of any point change with system reactance simultaneously on the short circuit current of line end and circuit
Change and change, but on circuit, the short circuit current of arbitrfary point is always greater than or is equal to the short circuit current that line end calculates, this
Adaptive change, so that the sensitivity of protection device is improved it is achieved that the protection domain of total track length 100%, is protected
Protection unit can instantaneously excise fault, and more traditional instantaneous quick-break current protection has the lifting of matter.
Brief description
Fig. 1 is a kind of existing power system electrical primary wiring diagram.
The guard method flow chart of the self adaptation transient current quick-break that Fig. 2 provides for the present invention.
Specific embodiment
The guard method of the self adaptation transient current quick-break with specific embodiment, the present invention being provided below in conjunction with the accompanying drawings is entered
Row describes in detail.
As shown in figure 1, in order that protection domain can include a, b supply line total length, using b busbar short-circuit electric current as guarantor
Shield setting valve.This protection seting value is to change with the change of the method for operation, also different because of the difference of short-circuit-type, for this
Microcomputer Calculation system reactance value xs1 must be utilized in real time, calculate short-circuit current value at b bus further according to system reactance value xs1,
This value is the protection seting value of current supply line short circuit current.By the current supply line calculating in real time short circuit current
Protection seting value is stored in a certain region of ram random access memory, then measures supply line in real time using line current transformer
Present current value, then calculate fault current component, afterwards by the fault current component of synchronization and above-mentioned current confession
The protection seting value of electric line short circuit current is compared, if current failure current component is more than or equal to this moment microcomputer meter
The protection seting value of the supply line's short circuit current calculating, you can be judged as that this short circuit occurs in ab supply line region, so
Determine fault type afterwards, finally according to the supply line measuring in real time present current value whether more than the short circuit of line end
Current calculation value is deciding whether to send trip signal.
As shown in Fig. 2 the guard method of the self adaptation transient current quick-break of present invention offer includes executing down in order
Row step:
Step 1) current sample: described current sample is the circulating sampling of each cycle for supply line's electric current
In unitary sampling, using line current transformer read supply line present current value;
Step 2) calculate fault current component: the power supply that the present current value last time of this supply line reading reads
Current value=the fault current component of circuit;
Step 3) judge whether that jump-value of current starts according to above-mentioned fault current component: above-mentioned fault current is divided
The protection seting value measuring the current supply line short circuit current being calculated in real time with this moment microcomputer is compared, if above-mentioned fault
Current component is more than or equal to the protection seting value of current supply line short circuit current, judges that jump-value of current starts, under
One step execution step 5), otherwise next step execution step 4);
Step 4) normal operation program: terminate this circular flow, return and wait subsequent cycle to run;
Step 5) determine fault type;Failure classes are carried out according to a, b, c three-phase electricity flow valuve that line current transformer records
Type judges, if meeting ia+ic=-ib or ia+ib+ic=0, for three phase short circuit fault, otherwise for two-phase short-circuit fault;
Step 6) judge whether measured current is more than the calculation of short-circuit current value of line end: by above-mentioned steps 1) obtain
The present current value of supply line is compared with the calculation of short-circuit current value of line end, if the current flow of supply line
Value is more than the calculation of short-circuit current value of line end, next step execution step 7), otherwise next step execution step 4);
Step 7) send trip signal: tripping line switching, disengagement failure line power.
Claims (1)
1. a kind of guard method of self adaptation transient current quick-break it is characterised in that: described self adaptation transient current quick-break
Guard method includes the following step executing in order:
Step 1) current sample: described current sample is in the circulating sampling for each cycle of supply line's electric current
Unitary sampling, reads the present current value of supply line using line current transformer;
Step 2) calculate fault current component: the supply line that the present current value last time of this supply line reading reads
Current value=fault current component;
Step 3) judge whether to occur jump-value of current according to above-mentioned fault current component and start: by above-mentioned fault current component with
The protection seting value of the current supply line short circuit current that this moment microcomputer calculates in real time is compared, if above-mentioned fault current
Component is more than or equal to the protection seting value of current supply line short circuit current, judges that jump-value of current starts, next step
Execution step 5), otherwise next step execution step 4);
Step 4) normal operation program: terminate this circular flow, return and wait subsequent cycle to run;
Step 5) determine fault type;Carry out fault type according to a, b, c three-phase electricity flow valuve that line current transformer records to sentence
Disconnected, if meeting ia+ic=-ib or ia+ib+ic=0, for three phase short circuit fault, otherwise for two-phase short-circuit fault;
Step 6) judge measured current whether more than the calculation of short-circuit current value of line end: by above-mentioned steps 1) power supply that obtains
The present current value of circuit is compared with the calculation of short-circuit current value of line end, if the present current value of supply line is big
In the calculation of short-circuit current value of line end, next step execution step 7), otherwise next step execution step 4);
Step 7) send trip signal: tripping line switching, disengagement failure line power.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610999955.1A CN106340863B (en) | 2016-11-14 | 2016-11-14 | A kind of guard method of adaptive transient current quick-break |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610999955.1A CN106340863B (en) | 2016-11-14 | 2016-11-14 | A kind of guard method of adaptive transient current quick-break |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106340863A true CN106340863A (en) | 2017-01-18 |
CN106340863B CN106340863B (en) | 2018-05-08 |
Family
ID=57841307
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610999955.1A Active CN106340863B (en) | 2016-11-14 | 2016-11-14 | A kind of guard method of adaptive transient current quick-break |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106340863B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108736437A (en) * | 2018-05-28 | 2018-11-02 | 国网天津市电力公司 | A kind of adaptive fast-tripping zero-sequence current protections method |
CN109298289A (en) * | 2018-11-29 | 2019-02-01 | 广东电网有限责任公司 | Localization method, system and the electronic equipment of distribution network failure point |
CN109360777A (en) * | 2018-11-01 | 2019-02-19 | 湖南长高思瑞自动化有限公司 | A kind of fuse switch on-line monitoring method |
CN109462204A (en) * | 2017-09-06 | 2019-03-12 | 国家电网公司 | A kind of method and device improving distribution line current quick sensitivity |
CN110416981A (en) * | 2019-07-31 | 2019-11-05 | 华北电力大学 | A kind of access power distribution network zone current guard method of electric car and system |
CN110556784A (en) * | 2019-10-09 | 2019-12-10 | 鞍钢集团工程技术有限公司 | relay protection configuration and setting method for high-voltage distribution system of ferroalloy electric furnace |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102508076A (en) * | 2011-11-09 | 2012-06-20 | 东北大学 | Fault diagnosis device and method based on multi-agent system and wavelet analysis |
CN103050933A (en) * | 2012-12-13 | 2013-04-17 | 福建省电力有限公司 | Large-scale battery storage power station interface protection method based on single-ended break variable of current |
CN103439635A (en) * | 2013-09-06 | 2013-12-11 | 华北电力大学 | Electric power system wave-recoding file based fault detection method and system |
CN103490394A (en) * | 2013-09-30 | 2014-01-01 | 山东大学 | Self-synchronizing positive sequence fault component current differential protection method of active power distribution network |
CN103730882A (en) * | 2013-12-24 | 2014-04-16 | 西安交通大学 | Current protection system and method for being automatically adapted to distributed power connection |
CN205265233U (en) * | 2015-12-18 | 2016-05-25 | 江苏省电力公司宿迁供电公司 | Main step -down backup protection equipment that volume of taking sudden change starts |
CN106058830A (en) * | 2016-07-26 | 2016-10-26 | 华北电力大学 | Current protection system with DG power distribution network and protection method |
-
2016
- 2016-11-14 CN CN201610999955.1A patent/CN106340863B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102508076A (en) * | 2011-11-09 | 2012-06-20 | 东北大学 | Fault diagnosis device and method based on multi-agent system and wavelet analysis |
CN103050933A (en) * | 2012-12-13 | 2013-04-17 | 福建省电力有限公司 | Large-scale battery storage power station interface protection method based on single-ended break variable of current |
CN103439635A (en) * | 2013-09-06 | 2013-12-11 | 华北电力大学 | Electric power system wave-recoding file based fault detection method and system |
CN103490394A (en) * | 2013-09-30 | 2014-01-01 | 山东大学 | Self-synchronizing positive sequence fault component current differential protection method of active power distribution network |
CN103730882A (en) * | 2013-12-24 | 2014-04-16 | 西安交通大学 | Current protection system and method for being automatically adapted to distributed power connection |
CN205265233U (en) * | 2015-12-18 | 2016-05-25 | 江苏省电力公司宿迁供电公司 | Main step -down backup protection equipment that volume of taking sudden change starts |
CN106058830A (en) * | 2016-07-26 | 2016-10-26 | 华北电力大学 | Current protection system with DG power distribution network and protection method |
Non-Patent Citations (1)
Title |
---|
冯巧玲等: "自适应电流速断保护分析", 《郑州轻工业学院学报》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109462204A (en) * | 2017-09-06 | 2019-03-12 | 国家电网公司 | A kind of method and device improving distribution line current quick sensitivity |
CN108736437A (en) * | 2018-05-28 | 2018-11-02 | 国网天津市电力公司 | A kind of adaptive fast-tripping zero-sequence current protections method |
CN109360777A (en) * | 2018-11-01 | 2019-02-19 | 湖南长高思瑞自动化有限公司 | A kind of fuse switch on-line monitoring method |
CN109298289A (en) * | 2018-11-29 | 2019-02-01 | 广东电网有限责任公司 | Localization method, system and the electronic equipment of distribution network failure point |
CN110416981A (en) * | 2019-07-31 | 2019-11-05 | 华北电力大学 | A kind of access power distribution network zone current guard method of electric car and system |
CN110556784A (en) * | 2019-10-09 | 2019-12-10 | 鞍钢集团工程技术有限公司 | relay protection configuration and setting method for high-voltage distribution system of ferroalloy electric furnace |
CN110556784B (en) * | 2019-10-09 | 2022-02-08 | 鞍钢集团工程技术有限公司 | Relay protection configuration and setting method for high-voltage distribution system of ferroalloy electric furnace |
Also Published As
Publication number | Publication date |
---|---|
CN106340863B (en) | 2018-05-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106340863A (en) | Protection method for adaptive instantaneous current quick tripping | |
CN104852354A (en) | Adaptive-slope transformer zero-sequence differential protection method and device | |
CN105140893A (en) | Differential protection current transformer (CT) saturation recognition method | |
Mahapatra et al. | Analysis of symmetrical fault in IEEE 14 bus system for enhancing over current protection scheme | |
CN103823160A (en) | Self-adaption ground fault line selection method and device for power distribution network | |
KR20130003225A (en) | Method for determining fault direction, overcurrent protection and displaying fault indication in distribution system with dispersed generation | |
CN103683228A (en) | Control method of breaker failure protection and automatic reclosing device | |
CN101800414B (en) | Method for judging and protecting low voltage in transformer short circuit fault | |
CN103986133B (en) | The time delay over-current guard method started based on reactive power Sudden Changing Rate | |
JP5312546B2 (en) | Circuit breaker contact consumption control system | |
CN102969695A (en) | Grounding forecasting method in neutral-point low-resistance grounding mode | |
CN112731211A (en) | Grounding transformer low-voltage winding turn-to-turn short circuit fault and phase identification method | |
CN104052033B (en) | A kind of guard method based on zero-sequence current correlation coefficient identification fault branch | |
CN103779847B (en) | Based on the guard method of SV network samples common-tower double-circuit lines single-phase earthing voltage ratio phase | |
CN104332973A (en) | Line interphase short circuit fault relay protection method through fault active power | |
KR101372823B1 (en) | Over current relay considering application of superconducting fault current limiter, and method for setting the relay | |
CN104078951B (en) | A kind of based on inter-phase arc voltage characteristic line inter-phase fault two end protection method | |
Bjerkan | Efficient fault management using remote fault indicators | |
CN101267099A (en) | Method for realizing self-adapted over-current protection of power and distribution supply cable | |
CN104953565B (en) | Line interphase fault relay protection method is surveyed based on transition resistance | |
Devipriya et al. | Design of numerical relay for over flux and over current protection in transformers | |
CN108666985B (en) | Accurate diagnosis and protection method for power frequency overvoltage of power transmission line | |
RU2685746C1 (en) | METHOD OF DETERMINING POINT AND DISTANCE TO SINGLE-PHASE GROUND FAULT IN 6-35 kV ELECTRIC NETWORKS WITH ISOLATED OR COMPENSATED NEUTRAL POINT | |
Sidhu et al. | A numerical technique based on symmetrical components for protecting three-winding transformers | |
CN100416961C (en) | Method for prtecting power network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |