CN106334595A - Mechatronic fast mineral processing equipment - Google Patents

Mechatronic fast mineral processing equipment Download PDF

Info

Publication number
CN106334595A
CN106334595A CN201611068147.XA CN201611068147A CN106334595A CN 106334595 A CN106334595 A CN 106334595A CN 201611068147 A CN201611068147 A CN 201611068147A CN 106334595 A CN106334595 A CN 106334595A
Authority
CN
China
Prior art keywords
welded
plate
cylinder
bracing wire
fixed pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611068147.XA
Other languages
Chinese (zh)
Inventor
王晓军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Polytechnic Normal University
Original Assignee
Guangdong Polytechnic Normal University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Polytechnic Normal University filed Critical Guangdong Polytechnic Normal University
Priority to CN201611068147.XA priority Critical patent/CN106334595A/en
Publication of CN106334595A publication Critical patent/CN106334595A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C1/00Crushing or disintegrating by reciprocating members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C1/00Crushing or disintegrating by reciprocating members
    • B02C1/005Crushing or disintegrating by reciprocating members hydraulically or pneumatically operated

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Food Science & Technology (AREA)
  • Combined Means For Separation Of Solids (AREA)

Abstract

The invention relates to a processing equipment, in particular to a mechatronic fast mineral processing equipment. The invention mainly solves the technical problems of the provision of a mechatronic fast mineral processing equipment with complete processing, consistent processing fineness and convenient operation. In order to solve the problems listed above the invention provides such a mechatronic fast mineral processing equipment which comprises the base plate, left rack, collecting frame, right rack, pressing block, placement plate, processing frame, pushing plate, first cylinder, first sliding rail, first fixing plate and the like; the leftest side of the base plate top is welded with the left rack. The top of right side of the left rack is welded with the second installation plate. Both the left and right sides of the top of the second installation plate are connected with the second spring by hooks. The invention achieves the effects of complete processing, consistent fineness of processing and convenient operation. Plus the equipment also enjoys the advantages of low costs, reasonable structure, simple maintenance, easy usage and low investment of human resources and money.

Description

A kind of quick processing equipment of electromechanical integration Ore
Technical field
The present invention relates to a kind of processing equipment, the quick processing equipment of more particularly, to a kind of electromechanical integration Ore.
Background technology
Japanese enterprises circle proposed " electromechanical integration technology " this concept, i.e. connected applications machinery earliest at 1970 about Technology and electronic technology are in one.Fast development with computer technology and extensive application, before electromechanical integration technology obtains Not some development.Present electromechanical integration technology, become an all round computer and information technology, automatic control technology, The systems technology of the intersections such as sensing detection technology, servo drive technology and mechanical technique, positive light mechanical and electrical integration direction Development, range of application is more and more wide.
Ore refers to mined from ore body, the therefrom ore deposit of extractable useful constituent (element, compound or mineral) Thing aggregation.Ore is to be formed in various geology mineralization, and the Ore that different geology mineralization is formed has difference Feature.Under modern technologies economic condition, can process from mineral on an industrial scale and extract metal or other products.It is originally Refer to solid matter mined from metalliferous deposit, after having expanded formation to, be deposited in sulfur in parent rock, fluorite and weight Spar etc nonmetallic mineral.In Ore, the ratio of useful component (element or mineral) weight and ore weight is referred to as the grade of ore, The precious metal ore g ton such as gold, platinum represents, other Ores are commonly used percent and represented.The conventional grade of ore is weighing Ore Be worth, the composition of Ore and objectionable impurities number also impact Ore be worth.
Typically, when some too small Ores in ore processing, need it is further processed, high-grade ore Stone: granularity is excessive cannot to enter stove;Granularity is not easy to smelting reducing more than 40mm in blast furnace, too small, can reduce blast furnace and breathe freely Property.So too small Ore passes through after can only crushing to a certain extent again selects processing, current processing equipment presence is processed Not exclusively, process fineness differ, the shortcoming of complex operation, therefore need badly research and development a kind of process completely, process that fineness is consistent, operation The convenient quick processing equipment of electromechanical integration Ore.
Content of the invention
(1) technical problem to be solved
In order to overcome current processing equipment, the present invention haves the shortcomings that process is incomplete, process fineness differs, complex operation, originally Invention technical problem to be solved is to provide a kind of electromechanical integration Ore that process is complete, process fineness is consistent, easy to operate Quick processing equipment.
(2) technical scheme
In order to solve above-mentioned technical problem, the invention provides the quick processing equipment of such a electromechanical integration Ore, including Have base plate, left frame, collect frame, right shelf, briquetting, place plate, processing block, push pedal, the first cylinder, the first slide rail, the first slide block, the One fixed plate, the second cylinder, pole, push rod, gear, tooth bar, the first bracing wire, the first fixed pulley, the second fixed pulley, the first installation Plate, the second slide block, the second slide rail, the second bracing wire, the first spring, the 3rd fixed pulley, the second fixed plate, rocking handle, reel, gear Plate, second spring and the second installing plate, the base plate top leftmost side is welded with left frame, and left frame right upper portion is welded with the second installation Plate, the second installing plate top left and right sides is connected with second spring by way of hook connects, and second spring top is passed through to hang The mode of hook connects is connected with baffle plate, has aperture in the middle part of baffle plate, and reel is welded on left frame right upper portion, coiling by support Wheel is located above baffle plate, and reel is rotatable, reel is wound with bracing wire, on front side of reel, center weld has rocking handle, and left frame is right Upper lateral part is welded with the second fixed plate, and the second fixed plate is located above reel, and the second fixed plate bottom right is welded with second Slide rail, on the second slide rail, slidingtype is connected with the second slide block, the second slide rail and the cooperation of the second slide block, is welded with the right side of the second slide block First installing plate, the second fixed plate bottom right is connected with the first spring by way of hook connects, and the first spring bottom end leads to The mode crossing hook connection is connected with the second slider top, and the 3rd fixed pulley is welded on the second fixed plate bottom, right by support Side, the 3rd fixed pulley is located on the right side of the first spring, and the second bracing wire bypasses the 3rd fixed pulley, and the second bracing wire bottom is connected by hook Mode be connected with the first installing plate top, base plate top left side is placed with collection frame, and base plate top right side is welded with right shelf, right Frame left lower is welded with placement plate, and placement top of the plate portion passes on left bolted mode and is connected with processing block, the first installation Plate bottom and processing block left contact, have aperture, the mode that right shelf left side central portion is bolted connects on the right side of processing block There is the first cylinder, the termination of the first cylinder has external screw thread, and push pedal right side central has female thread, the first cylinder passes through aperture left The mode being threaded connection is held to be connected with push pedal, push pedal is located at and processes inframe, and right shelf left upper portion is welded with the first fixed plate, Second fixed pulley is welded on the first fixed plate top left, the side that the first fixed plate top center is bolted by support Formula is connected with the first slide rail, and on the first slide rail, slidingtype is connected with the first slide block, the first slide block and the cooperation of the first slide rail, and first is sliding The mode being bolted on block is connected with tooth bar, and the first fixed pulley is welded on the first fixed plate top left side by support, The mode that right shelf left upper portion is bolted is connected with the second cylinder, and the second cylinder is located above the first fixed plate, and second Cylinder left end is welded with tooth bar right-hand member, and right shelf left upper portion is welded with pole, and pole is located above the second cylinder, pole rotary type Be provided with gear, wheel and rack engages, and is welded with push rod on rear side of gear, first bracing wire one end by way of hook connects with push away Masthead portion connects, and the first bracing wire bypasses the first fixed pulley and the second fixed pulley, and the first bracing wire other end passes through the side that hook connects Formula is connected with briquetting top center, and briquetting is located above processing block.
Preferably, also include handle, collect the right both sides of outer frame wall and be symmetrically welded with handle.
Preferably, also include crushing teeth, briquetting bottom even is welded with crushing teeth.
Preferably, baseboard material is rustless steel.
Preferably, left frame material is q235 steel.
Preferably, bracing wire is steel wire rope.
Operation principle: when needing using processing to Ore, pour Ore into process inframe first, then, control Second cylinder elongation or contraction, the second cylinder band carry-over bar side-to-side movement, and then carry moving gear clockwise or counterclockwise, when When gear turns clockwise, drive push rod to swing to the right to a certain degree, drive briquetting to move upwards by the first bracing wire, work as gear During rotate counterclockwise, push rod is driven to swing to a certain degree to the left, the first bracing wire is released, and briquetting is transported downwards under gravity Dynamic, so repeatedly so that briquetting is quickly processed to Ore, when briquetting is in top, control the second cylinder to stop elongation, Meanwhile, staff shakes rocking handle counterclockwise, and rocking handle drives reel rotate counterclockwise, and the second bracing wire is by around rising, and then drives First installing plate and the second slide block move upwards, and the first spring is compressed, and now, rocking handle is stuck on circular hole staff, enters And driving baffle plate to move downward, the first spring is compressed, and controls the first cylinder elongation or shrink, and then drives fortune about push pedal Dynamic, when push pedal is to left movement, promote the Ore handled well to left movement, now, Ore falls collection inframe, when Ore is whole After falling collection inframe, and when push pedal moves right original position, the first cylinder is controlled to stop shrinking, finally, staff will The rocking handle being stuck on circular hole takes out, and baffle plate moves under the elastic force effect of second spring upwards, so, staff, work people Member shakes clockwise rocking handle, and rocking handle drives reel to turn clockwise, and the second bracing wire is released, the first installing plate and the second slide block It is moved downwardly to initial position under the elastic force effect of the first spring, staff stops shaking clockwise rocking handle.
Because also including handle, collecting the right both sides of outer frame wall and being symmetrically welded with handle.Handle can make staff more square Just frame is collected in carrying.
Because also including crushing teeth, briquetting bottom even is welded with crushing teeth.Crushing teeth can strengthen crushing effect, can break More thoroughly broken.
Because baseboard material is rustless steel, rustless steel corrosion resistance and acid resistance are strong, can extension fixture service life.
Because left frame material is q235 steel it is not easy to deform, make the service life of device longer.
Because bracing wire is steel wire rope, steel wire rope hardness is big and density is little, and tensile strength is big, is difficult to be pulled off, and steel wire rope resists Corrosivity are strong, are difficult to get rusty, it is possible to extending the service life of bracing wire.
(3) beneficial effect
Invention achieves and process effect complete, that process fineness is consistent, easy to operate, and low cost of manufacture, it is rational in infrastructure, Maintenance easy to maintain, easy to use, reduce the input of manpower and materials, improve work efficiency, there is higher promotional value.
Brief description
Fig. 1 is the first main structure diagram of the present invention.
Fig. 2 is the second main structure diagram of the present invention.
Fig. 3 is the third main structure diagram of the present invention.
Being labeled as in accompanying drawing: 1- base plate, the left frame of 2-, 3- collects frame, 4- right shelf, 5- briquetting, and 6- places plate, 7- process Frame, 8- push pedal, 9- first cylinder, 10- aperture, 11- first slide rail, 12- first slide block, 13- first fixed plate, 14- second gas Cylinder, 15- pole, 16- push rod, 17- gear, 18- tooth bar, 19- first bracing wire, 20- first fixed pulley, 21- second fixed pulley, 22- first installing plate, 23- second slide block, 24- second slide rail, 25- second bracing wire, 26- first spring, 27- the 3rd fixed pulley, 28- second fixed plate, 29- rocking handle, 30- reel, 31- baffle plate, 32- second spring, 33- circular hole, 34- second installing plate, 35- Handle, 36- crushing teeth.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
A kind of quick processing equipment of electromechanical integration Ore, as Figure 1-3, includes base plate 1, left frame 2, collects frame 3, right shelf 4th, briquetting 5, place plate 6, processing block 7, push pedal 8, the first cylinder 9, the first slide rail 11, the first slide block 12, the first fixed plate 13, the Two cylinders 14, pole 15, push rod 16, gear 17, tooth bar 18, the first bracing wire 19, the first fixed pulley 20, the second fixed pulley 21, One installing plate 22, the second slide block 23, the second slide rail 24, the second bracing wire 25, the first spring 26, the 3rd fixed pulley 27, second are fixing Plate 28, rocking handle 29, reel 30, baffle plate 31, second spring 32 and the second installing plate 34, the base plate 1 top leftmost side is welded with a left side Frame 2, left frame 2 right upper portion is welded with the second installing plate 34, and the side that hook connects is passed through in the second installing plate 34 top left and right sides Formula is connected with second spring 32, and second spring 32 top is connected with baffle plate 31 by way of hook connects, and opens in the middle part of baffle plate 31 There is aperture 10, reel 30 is welded on left frame 2 right upper portion by support, reel 30 is located above baffle plate 31, reel 30 Rotatably, reel 30 is wound with bracing wire, reel 30 front side center weld has rocking handle 29, left frame 2 right upper portion is welded with the Two fixed plates 28, the second fixed plate 28 is located above reel 30, and the second fixed plate 28 bottom right is welded with the second slide rail 24, On second slide rail 24, slidingtype is connected with the second slide block 23, and the second slide rail 24 is coordinated with the second slide block 23, on the right side of the second slide block 23 It is welded with the first installing plate 22, the second fixed plate 28 bottom right is connected with the first spring 26 by way of hook connects, the One spring 26 bottom is connected with the second slide block 23 top by way of hook connects, and the 3rd fixed pulley 27 is welded on by support Second fixed plate 28 bottom right, the 3rd fixed pulley 27 is located on the right side of the first spring 26, and the second bracing wire 25 bypasses the 3rd fixed pulley 27, the second bracing wire 25 bottom is connected with the first installing plate 22 top by way of hook connects, and base plate 1 top left side is placed with Collect frame 3, base plate 1 top right side is welded with right shelf 4, right shelf 4 left lower is welded with placement plate 6, place plate 6 top left side and lead to Cross bolted mode and be connected with processing block 7, the first installing plate 22 bottom and processing block 7 left contact, processing block 7 right side opening There is aperture 10, the mode that right shelf 4 left side central portion is bolted is connected with the first cylinder 9, the termination of the first cylinder 9 has outward Screw thread, push pedal 8 right side central has female thread, and the mode that the first cylinder 9 is threaded connection through aperture 10 left end is connected with Push pedal 8, push pedal 8 is located in processing block 7, and right shelf 4 left upper portion is welded with the first fixed plate 13, and the second fixed pulley 21 passes through support It is welded on the first fixed plate 13 top left, it is sliding that the mode that the first fixed plate 13 top center is bolted is connected with first Rail 11, on the first slide rail 11, slidingtype is connected with the first slide block 12, and the first slide block 12 is coordinated with the first slide rail 11, the first slide block 12 On the mode that is bolted be connected with tooth bar 18, the first fixed pulley 20 is welded on the first fixed plate 13 top left by support Side, the mode that right shelf 4 left upper portion is bolted is connected with the second cylinder 14, and the second cylinder 14 is located at the first fixed plate 13 Top, the second cylinder 14 left end is welded with tooth bar 18 right-hand member, and right shelf 4 left upper portion is welded with pole 15, and pole 15 is located at second Above cylinder 14, pole 15 rotary type is provided with gear 17, and gear 17 is engaged with tooth bar 18, is welded with push rod 16 on rear side of gear 17, First bracing wire 19 one end is connected with push rod 16 top by way of hook connects, and the first bracing wire 19 bypasses the first fixed pulley 20 He Second fixed pulley 21, the first bracing wire 19 other end is connected with briquetting 5 top center by way of hook connects, and briquetting 5 is located at Above processing block 7.
Also include handle 35, collect the right both sides of frame 3 outer wall and be symmetrically welded with handle 35.
Also include crushing teeth 36, briquetting 5 bottom even is welded with crushing teeth 36.
Base plate 1 material is rustless steel.
Left frame 2 material is q235 steel.
Bracing wire is steel wire rope.
Operation principle: when needing using processing to Ore, first Ore is poured in processing block 7, then, control Second cylinder 14 extends or shrinks, and the second cylinder 14 carries carry-over bar 18 side-to-side movement, and then carries moving gear 17 clockwise or the inverse time Pin rotates, and when gear 17 turns clockwise, drives push rod 16 to swing to the right to a certain degree, drives briquetting by the first bracing wire 19 5 move upwards, when gear 17 rotate counterclockwise, drive push rod 16 to swing to a certain degree to the left, the first bracing wire 19 is released, pressure Block 5 moves downward under gravity, so repeatedly so that briquetting 5 is quickly processed to Ore, when briquetting 5 is in Fang Shi, controls the second cylinder 14 to stop elongation, and meanwhile, staff shakes rocking handle 29 counterclockwise, and rocking handle 29 drives reel 30 Rotate counterclockwise, the second bracing wire 25 is by around rising, and then drives the first installing plate 22 and the second slide block 23 to move upwards, the first spring 26 are compressed, and now, rocking handle 29 is stuck on circular hole 33 staff, and then drive baffle plate 31 to move downward, the first spring 26 Compressed, and control the first cylinder 9 to extend or shrink, and then driven push pedal 8 side-to-side movement, when push pedal 8 is to left movement, promoted The Ore handled well to left movement, now, fall in collection frame 3, after Ore is all fallen in collection frame 3, and pushes away by Ore When plate 8 moves right original position, the first cylinder 9 is controlled to stop shrinking, finally, staff is by the rocking handle 29 being stuck on circular hole 33 Take out, baffle plate 31 moves under the elastic force effect of second spring 32 upwards, so, staff, staff shakes clockwise Rocking handle 29, rocking handle 29 drives reel 30 to turn clockwise, and the second bracing wire 25 is released, the first installing plate 22 and the second slide block 23 It is moved downwardly to initial position under the elastic force effect of the first spring 26, staff stops shaking clockwise rocking handle 29.
Because also including handle 35, collecting the right both sides of frame 3 outer wall and being symmetrically welded with handle 35.Handle 35 can make work people Frame 3 is collected in member's more easily carrying.
Because also including crushing teeth 36, briquetting 5 bottom even is welded with crushing teeth 36.Crushing teeth 36 can strengthen broken effect Really, can crush more thorough.
Because base plate 1 material is rustless steel, rustless steel corrosion resistance and acid resistance are strong, can extension fixture service life.
Because left frame 2 material is q235 steel it is not easy to deform, make the service life of device longer.
Because bracing wire is steel wire rope, steel wire rope hardness is big and density is little, and tensile strength is big, is difficult to be pulled off, and steel wire rope resists Corrosivity are strong, are difficult to get rusty, it is possible to extending the service life of bracing wire.
Embodiment described above only have expressed the preferred embodiment of the present invention, and its description is more concrete and detailed, but simultaneously Therefore the restriction to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for those of ordinary skill in the art For, without departing from the inventive concept of the premise, some deformation, improvement and replacement can also be made, these broadly fall into this Bright protection domain.Therefore, the protection domain of patent of the present invention should be defined by claims.

Claims (6)

1. a kind of quick processing equipment of electromechanical integration Ore is it is characterised in that including base plate (1), left frame (2), collecting frame (3), right shelf (4), briquetting (5), place plate (6), processing block (7), push pedal (8), the first cylinder (9), the first slide rail (11), first Slide block (12), the first fixed plate (13), the second cylinder (14), pole (15), push rod (16), gear (17), tooth bar (18), first Bracing wire (19), the first fixed pulley (20), the second fixed pulley (21), the first installing plate (22), the second slide block (23), the second slide rail (24), the second bracing wire (25), the first spring (26), the 3rd fixed pulley (27), the second fixed plate (28), rocking handle (29), reel (30), baffle plate (31), second spring (32) and the second installing plate (34), base plate (1) the top leftmost side is welded with left frame (2), left Frame (2) right upper portion is welded with the second installing plate (34), and the side that hook connects is passed through in the second installing plate (34) the top left and right sides Formula is connected with second spring (32), and second spring (32) top is connected with baffle plate (31), baffle plate by way of hook connects (31) have aperture (10) in the middle part of, reel (30) is welded on left frame (2) right upper portion by support, reel (30) is located at gear Above plate (31), reel (30) is rotatable, reel (30) is wound with bracing wire, on front side of reel (30), center weld has rocking handle (29), left frame (2) right upper portion is welded with the second fixed plate (28), and the second fixed plate (28) is located above reel (30), the Two fixed plates (28) bottom right is welded with the second slide rail (24), and the upper slidingtype of the second slide rail (24) is connected with the second slide block (23), the second slide rail (24) and the second slide block (23) coordinate, and are welded with the first installing plate (22) on the right side of the second slide block (23), and second Fixed plate (28) bottom right is connected with the first spring (26) by way of hook connects, and the first spring (26) bottom is passed through to hang The mode of hook connects is connected with the second slide block (23) top, and the 3rd fixed pulley (27) is welded on the second fixed plate (28) by support Bottom right, the 3rd fixed pulley (27) is located on the right side of the first spring (26), and the second bracing wire (25) bypasses the 3rd fixed pulley (27), the Two bracing wires (25) bottom is connected with the first installing plate (22) top by way of hook connects, and base plate (1) top left side is placed There is collection frame (3), base plate (1) top right side is welded with right shelf (4), right shelf (4) left lower is welded with placement plate (6), place The mode that plate (6) top left side is bolted is connected with processing block (7), the first installing plate (22) bottom and processing block (7) Left contact, has aperture (10) on the right side of processing block (7), the mode that right shelf (4) left side central portion is bolted is connected with One cylinder (9), the termination of the first cylinder (9) has external screw thread, and push pedal (8) right side central has female thread, and the first cylinder (9) is worn The mode that small holes (10) left end is threaded connection is connected with push pedal (8), and push pedal (8) is located in processing block (7), right shelf (4) Left upper portion is welded with the first fixed plate (13), and the second fixed pulley (21) is welded on the first fixed plate (13) top left by support End, the mode that the first fixed plate (13) top center is bolted is connected with the first slide rail (11), on the first slide rail (11) Slidingtype is connected with the first slide block (12), and the first slide block (12) is coordinated with the first slide rail (11), and the first slide block (12) is upper to pass through spiral shell Tether the mode connecing and be connected with tooth bar (18), the first fixed pulley (20) is welded on the first fixed plate (13) top left by support Side, the mode that right shelf (4) left upper portion is bolted is connected with the second cylinder (14), and it is solid that the second cylinder (14) is located at first Above fixed board (13), the second cylinder (14) left end is welded with tooth bar (18) right-hand member, and right shelf (4) left upper portion is welded with pole (15), pole (15) is located above the second cylinder (14), and pole (15) rotary type is provided with gear (17), gear (17) and tooth bar (18) engage, be welded with push rod (16) on rear side of gear (17), the first bracing wire (19) one end by hook connect by way of and push rod (16) top connects, and the first bracing wire (19) bypasses the first fixed pulley (20) and the second fixed pulley (21), and the first bracing wire (19) is another End is connected with briquetting (5) top center by way of hook connects, and briquetting (5) is located above processing block (7).
2. a kind of quick processing equipment of electromechanical integration Ore according to claim 1 is it is characterised in that also include handle Handss (35), collect the right both sides of frame (3) outer wall and are symmetrically welded with handle (35).
3. a kind of quick processing equipment of electromechanical integration Ore according to claim 1 is it is characterised in that also include brokenly Broken tooth (36), briquetting (5) bottom even is welded with crushing teeth (36).
4. a kind of quick processing equipment of electromechanical integration Ore according to claim 1 is it is characterised in that base plate (1) material Expect for rustless steel.
5. the quick processing equipment of a kind of electromechanical integration Ore according to claim 1 is it is characterised in that left frame (2) material Expect for q235 steel.
6. a kind of quick processing equipment of electromechanical integration Ore according to claim 1 is it is characterised in that bracing wire is steel wire Rope.
CN201611068147.XA 2016-11-29 2016-11-29 Mechatronic fast mineral processing equipment Pending CN106334595A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611068147.XA CN106334595A (en) 2016-11-29 2016-11-29 Mechatronic fast mineral processing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611068147.XA CN106334595A (en) 2016-11-29 2016-11-29 Mechatronic fast mineral processing equipment

Publications (1)

Publication Number Publication Date
CN106334595A true CN106334595A (en) 2017-01-18

Family

ID=57841318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611068147.XA Pending CN106334595A (en) 2016-11-29 2016-11-29 Mechatronic fast mineral processing equipment

Country Status (1)

Country Link
CN (1) CN106334595A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07163897A (en) * 1993-12-10 1995-06-27 Isamu Yoshizawa Crusher
JP2000271504A (en) * 1999-03-26 2000-10-03 Kurimoto Ltd Vertical mill
JP2008188584A (en) * 2007-02-07 2008-08-21 Ramusa Abe:Kk Collecting bag-breaking machine
CN103861709A (en) * 2012-12-10 2014-06-18 盂县社会福利高锰耐磨件厂 Slide rail crusher
CN204656700U (en) * 2015-05-26 2015-09-23 诸馨怡 With the sweet potato vine shredder mechanism of quick feeding assembly
CN205462391U (en) * 2016-02-24 2016-08-17 安远县松远林业化工有限公司 Automatic breaker of rosin

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07163897A (en) * 1993-12-10 1995-06-27 Isamu Yoshizawa Crusher
JP2000271504A (en) * 1999-03-26 2000-10-03 Kurimoto Ltd Vertical mill
JP2008188584A (en) * 2007-02-07 2008-08-21 Ramusa Abe:Kk Collecting bag-breaking machine
CN103861709A (en) * 2012-12-10 2014-06-18 盂县社会福利高锰耐磨件厂 Slide rail crusher
CN204656700U (en) * 2015-05-26 2015-09-23 诸馨怡 With the sweet potato vine shredder mechanism of quick feeding assembly
CN205462391U (en) * 2016-02-24 2016-08-17 安远县松远林业化工有限公司 Automatic breaker of rosin

Similar Documents

Publication Publication Date Title
CN205988805U (en) A kind of fluorite ore multiple stage crushing sorting unit
CN109806930B (en) High-speed rail multi-metal zinc ore smelting furnace
CN205761323U (en) A kind of Copper Ores efficiency crushing device
CN205761337U (en) A kind of intelligent type automatic disintegrating machine
CN205731356U (en) A kind of copper metallurgy Copper Ores quick crashing device
CN107127008A (en) A kind of mining industry ore quick crashing device
CN201644943U (en) Device for removing burr from surface of object
CN205109857U (en) Slag iron autosegregation production line
CN205995497U (en) A kind of useless brick for building quickly crushes device
CN106334595A (en) Mechatronic fast mineral processing equipment
CN109384232A (en) A kind of smelting industrial silicon system
CN117625991A (en) Aluminum ash separation and recovery system
CN105564982B (en) Grabbing device
CN201543499U (en) Combined deslagging screen used for magnetic separator
CN103213825A (en) Novel anti-blockage and early-warning device of funnel
CN206597629U (en) A kind of special tubular type magnetic separator of rice
CN207287541U (en) A kind of use for laboratory ore treatment ore reduction device
CN102179303A (en) Magnetic agglomeration magnetic separation separation frame structure
CN208727741U (en) A kind of iron remover for belt conveyor
CN202343320U (en) Magnetic separation and recovery device for strongly-magnetic fine iron ore materials
CN205462652U (en) Conveying line
CN202591590U (en) Ladle spout slag partition device favorable for slagging-off
CN105149088A (en) Production line for automatically separating slag iron
CN207057016U (en) A kind of iron ore concentration equipment
CN211838124U (en) Mechanism capable of separating and crushing ferro-manganese elements in ferro-manganese ore

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170118