CN106323157A - 一种监测钢桁架桥静荷载变化的简易方法 - Google Patents
一种监测钢桁架桥静荷载变化的简易方法 Download PDFInfo
- Publication number
- CN106323157A CN106323157A CN201610721322.4A CN201610721322A CN106323157A CN 106323157 A CN106323157 A CN 106323157A CN 201610721322 A CN201610721322 A CN 201610721322A CN 106323157 A CN106323157 A CN 106323157A
- Authority
- CN
- China
- Prior art keywords
- monitoring
- strain
- steel girder
- girder bridge
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01B—MEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
- G01B7/00—Measuring arrangements characterised by the use of electric or magnetic techniques
- G01B7/16—Measuring arrangements characterised by the use of electric or magnetic techniques for measuring the deformation in a solid, e.g. by resistance strain gauge
Abstract
本发明涉及一种监测钢桁架桥静荷载变化的简易方法,在钢桁架桥支座顶节点对应的竖杆及斜杆上布设应变传感器,监测其在更换桥面板或桥面铺装前后的应变变化值,计算竖杆及斜杆轴力变化值,以此推断支反力变化量,即钢桁架桥上桥面板或桥面铺装更换前后的重量变化。由于桥梁在维修改造时,须确保更换后的行车道板及桥面铺装等静荷载不大于原荷载,常规的千斤顶称重方法十分繁琐,对实施环境要求较高,且费用昂贵。本发明可从根本上解决了钢桁架桥称重工作繁琐且费用高昂的问题。
Description
技术领域
本发明涉及桥梁施工过程监测控制技术领域,具体涉及一种监测钢桁架桥静荷载变化的简易方法。
背景技术
我国在建国后建造的一批跨江公铁两用桥,如武汉长江大桥、南京长江大桥、九江长江大桥等,其主体结构形式基本类似,目前也大都表现出了共同的特征,即主体结构都被检测评估鉴定为处于安全状态,但类似如公路桥行车道板、桥面铺装、伸缩装置等大都出现严重病,需要及时更换,为了结构承载的要求,必须确保更换后的行车道板及桥面铺装等静荷载不大于原荷载。
常规的测量桥梁自重的方法主要是利用千斤顶称重,这种方法十分繁琐,对实施环境要求较高,且费用昂贵,因此在桥梁维修过程中一般不对桥梁自重变化进行监测,难以判断桥梁在维修改造后的实际承载能力,给使用安全带来隐患。为了获得桥梁在维修改造后的实际自重,需要一种相对简易的测量方法。
发明内容
本发明的目的是提供一种简单易行、降低成本的监测钢桁架桥静荷载变化的方法。
为达到上述目的,本发明提供的技术方案是:
一种监测钢桁架桥静荷载变化的简易方法,在钢桁架桥支座顶节点对应的竖杆及斜杆上布设应变传感器,监测其在更换桥面板或桥面铺装前后的应变变化值,计算竖杆及斜杆轴力变化值,以此推断支反力变化量,即钢桁架桥上桥面板或桥面铺装更换前后的重量变化。
所述的监测钢桁架桥静荷载变化的简易方法,具体包括如下步骤:
(1)查询、搜集钢桁架桥的设计图纸、竣工图纸相关资料,建立计算模型,对钢桁架桥的结构进行理论分析,确定需要监测的竖杆及斜杆;
(2)选取满足标准规定的应变传感器,并进行标定;
(3)安装应变传感器前,在竖杆及斜杆各面的轴线上进行标识,并安装温度补偿片;
(4)对应变传感器监测系统进行调试,确保无误后,在交通封闭状况下,在桥面板或桥面铺装开始拆除前,进行初始值测量;
(5)在桥面板或桥面铺装拆除过程中进行定期监测,在新的桥面板或桥面铺装安装前,确定安装前的应变变化值;
(6)在新的桥面板或桥面铺装安装过程中进行定期监测,在开放交通前,确定最终的应变变化值;
(7)对监测数据进行必要的数据处理,确定实际应变值,换算杆件轴力变化,确定支座反力变化量,推算桥梁自重在维修改造前后的变化。
其中,所述需要监测的竖杆及斜杆,须经过对钢桁架结构进行理论分析来确定。
安装应变传感器前,对杆件表面进行处理,确保平整光洁。
应变传感器的应变片安装位置控制在±0.1mm偏差范围内。
安装应变传感器后,对应变传感器进行防潮处理。
所述应变传感器的初始值的确定须在交通封闭状况下,桥面板或桥面铺装开始拆除前。
在监测过程中,须对应变传感器的整个监测系统采取必要的保护措施,防止测试元件的损坏。
本发明公开了一种监测钢桁架桥静荷载变化的简易方法,通过在支座节点处竖杆及斜杆布设应力传感器,监测其在更换桥面板及桥面铺前后的轴力变化,判断其静荷载变化情况。由于桥梁在维修改造时,须确保更换后的行车道板及桥面铺装等静荷载不大于原荷载,常规的千斤顶称重方法十分繁琐,对实施环境要求较高,且费用昂贵。本发明可从根本上解决了称重工作繁琐且费用高昂的问题。
附图说明
图1:实施例中支座节点处杠杆结构示意图。
图2:图1中杠杆截面应变测点布置示意图。
具体实施方式
下面结合具体实施例对本发明作进一步说明。
本发明为一种监测钢桁架桥静荷载变化的简易方法,具体实施步骤如下:
步骤一:搜集、查询钢桁架桥设计图纸、竣工图纸等相关资料,建立计算模型,对结构进行理论分析,确定需要监测的竖杆及斜杆。
步骤二:选取满足标准GB/T 13992-2010要求的应变传感器,并进行标定。
步骤三:安装应变传感器前,应在竖杆及斜杆各面的轴线上进行标识,并对杆件表面进场处理,确保平整光洁,应变片的安装位置偏差应控制在0.1mm内,安装后对应变传感器进行防潮处理,并安装温度补偿片。
步骤四:对监测系统进行调试,确保无误后,在交通封闭状况下,桥面板及桥面铺装等构件开始拆除前,进行初始值测量。
步骤五:在桥面板及桥面铺装等构件拆除过程中进行定期监测,在新的桥面板及桥面铺装等构件安装前,确定安装前的应变变化值。
步骤六:在新桥面板及桥面铺装等构件安装过程中进行定期监测,在开放交通前,确定最终的应变变化值。
步骤七:对监测数据进行必要的数据处理,确定实际应变值,换算杆件轴力变化,确定支座反力变化量,推算桥梁自重在维修改造前后的变化。
如图1所示,支座节点处连接杆件1、杆件2、杆件3,在每根杆件截面的a、b、c、d位置(如图2,杠杆1的A-A、杠杆2的B-B、杠杆3的C-C杆截面图)安装4个应变传感器,计算公式如下:
杆件1轴力变化值:
杆件2轴力变化值:
杆件3轴力变化值:
支座反力变化值:ΔF=N1cosθ+N2+N3cosθ
式中:εan、εbn、εcn、εdn——指杆件对应截面a、b、c、d位置4个应变传感器实测变化值(n=1、2、3,分别表示杆件1、杆件2、杆件3);
E1、E2、E3——指杆件1、杆件2、杆件3的弹性模量,单位MPa;
A1、A2、A3——指杆件1、杆件2、杆件3的截面面积,单位mm2。
以上所述,仅是本发明的较佳实施例,并非对本发明作任何形式上的限制,任何熟悉本专业的技术人员,在不脱离本发明技术方案范围内,依据本发明的技术实质,对以上实施例所作的任何简单的修改、等同替换与改进等,均仍属于本发明技术方案的保护范围之内。
Claims (8)
1.一种监测钢桁架桥静荷载变化的简易方法,其特征在于:在钢桁架桥支座顶节点对应的竖杆及斜杆上布设应变传感器,监测其在更换桥面板或桥面铺装前后的应变变化值,计算竖杆及斜杆轴力变化值,以此推断支反力变化量,即钢桁架桥上桥面板或桥面铺装更换前后的重量变化。
2.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:包括如下步骤:
(1)查询、搜集钢桁架桥的设计图纸、竣工图纸相关资料,建立计算模型,对钢桁架桥的结构进行理论分析,确定需要监测的竖杆及斜杆;
(2)选取满足标准规定的应变传感器,并进行标定;
(3)安装应变传感器前,在竖杆及斜杆各面的轴线上进行标识,并安装温度补偿片;
(4)对应变传感器监测系统进行调试,确保无误后,在交通封闭状况下,在桥面板或桥面铺装开始拆除前,进行初始值测量;
(5)在桥面板或桥面铺装拆除过程中进行定期监测,在新的桥面板或桥面铺装安装前,确定安装前的应变变化值;
(6)在新的桥面板或桥面铺装安装过程中进行定期监测,在开放交通前,确定最终的应变变化值;
(7)对监测数据进行必要的数据处理,确定实际应变值,换算杆件轴力变化,确定支座反力变化量,推算桥梁自重在维修改造前后的变化。
3.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:所述需要监测的竖杆及斜杆,须经过对钢桁架结构进行理论分析来确定。
4.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:安装应变传感器前,对杆件表面进行处理,确保平整光洁。
5.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:应变传感器的应变片安装位置控制在±0.1mm偏差范围内。
6.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:安装应变传感器后,对应变传感器进行防潮处理。
7.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:所述应变传感器的初始值的确定须在交通封闭状况下,桥面板或桥面铺装开始拆除前。
8.如权利要求1所述的监测钢桁架桥静荷载变化的简易方法,其特征在于:在监测过程中,须对应变传感器的整个监测系统采取必要的保护措施,防止测试元件的损坏。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610721322.4A CN106323157A (zh) | 2016-08-24 | 2016-08-24 | 一种监测钢桁架桥静荷载变化的简易方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610721322.4A CN106323157A (zh) | 2016-08-24 | 2016-08-24 | 一种监测钢桁架桥静荷载变化的简易方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106323157A true CN106323157A (zh) | 2017-01-11 |
Family
ID=57791943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610721322.4A Pending CN106323157A (zh) | 2016-08-24 | 2016-08-24 | 一种监测钢桁架桥静荷载变化的简易方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106323157A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109708565A (zh) * | 2019-02-14 | 2019-05-03 | 北京市劳动保护科学研究所 | 一种桁架结构的监测装置及系统 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101016728A (zh) * | 2007-02-06 | 2007-08-15 | 同济大学 | 中、下承式拱桥吊杆更换过程中的施工监控方法 |
CN101976277A (zh) * | 2010-09-29 | 2011-02-16 | 江苏省交通科学研究院股份有限公司 | 桥梁施工过程中应力监测点优化布置方法 |
CN203982627U (zh) * | 2014-05-22 | 2014-12-03 | 大连理工大学 | 多功能桁架结构实验装置 |
CN104344993A (zh) * | 2013-07-23 | 2015-02-11 | 国家电网公司 | 一种构件承载力和材料性能参数的试验测量方法 |
-
2016
- 2016-08-24 CN CN201610721322.4A patent/CN106323157A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101016728A (zh) * | 2007-02-06 | 2007-08-15 | 同济大学 | 中、下承式拱桥吊杆更换过程中的施工监控方法 |
CN101976277A (zh) * | 2010-09-29 | 2011-02-16 | 江苏省交通科学研究院股份有限公司 | 桥梁施工过程中应力监测点优化布置方法 |
CN104344993A (zh) * | 2013-07-23 | 2015-02-11 | 国家电网公司 | 一种构件承载力和材料性能参数的试验测量方法 |
CN203982627U (zh) * | 2014-05-22 | 2014-12-03 | 大连理工大学 | 多功能桁架结构实验装置 |
Non-Patent Citations (1)
Title |
---|
孙博: "海珠桥大修施工的受力特性仿真分析与监控", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑 (月刊 )》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109708565A (zh) * | 2019-02-14 | 2019-05-03 | 北京市劳动保护科学研究所 | 一种桁架结构的监测装置及系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106092775B (zh) | 水泥混凝土桥面铺装层与桥面板层间抗剪刚度测试方法 | |
CN103470041B (zh) | 采用散砂加载的现浇混凝土梁模板钢管支架预压施工方法 | |
CN110376058A (zh) | 爬升模架设备附着混凝土结构强度实时监测方法 | |
CN104099868A (zh) | 桥梁顶升同步控制整合系统 | |
CN107607412A (zh) | 一种混凝土结构组合式应变监测单元及其状态评估方法 | |
CN106649925B (zh) | 基于细宏观动态复杂应力监测的混凝土疲劳损伤分析方法 | |
CN109723910A (zh) | 支吊架量化安装检测调整工器具及使用其进行支吊架载荷测量的方法 | |
AU2014415547A1 (en) | A system and method of estimating fatigue in a lifting member | |
Powrie et al. | Centrifuge modelling of embedded retaining walls with stabilising bases | |
Xiao-ling et al. | Model test study on horizontal bearing behavior of pile under existing vertical load | |
KR101074569B1 (ko) | 배관 지지대의 하중측정 장치 및 방법 | |
CN106323157A (zh) | 一种监测钢桁架桥静荷载变化的简易方法 | |
CN204112240U (zh) | 挂篮用整体预压装置 | |
CN203938406U (zh) | 一种塔机顶升配平监控系统和监测仪 | |
CN107084812B (zh) | 混凝土箱梁桥腹板竖向预应力筋张拉力的检测系统及方法 | |
CN106403858B (zh) | 一种超高空大悬挑钢平台端部挠度监测方法 | |
CN112095484A (zh) | 全桥单幅顶升监测系统 | |
CN107271648A (zh) | 考虑混凝土徐变影响的收缩应力测量装置 | |
CN204027842U (zh) | 一种识别桥梁结构刚度损伤的系统 | |
Bilodeau et al. | Direct estimation of vertical strain at the top of the subgrade soil from interpretation of falling weight deflectometer deflection basins | |
Yang et al. | Live-load test results of Missouri’s first high-performance concrete superstructure bridge | |
KR101631799B1 (ko) | 교량 거더의 시공중 전도 안정성 유지를 위한 시공 관리기준 설정방법 | |
CN205784976U (zh) | 桥梁位移测量辅助装置 | |
CN105116133A (zh) | 一种用于监测混凝土应力的装置及方法 | |
CN212426785U (zh) | 全桥单幅顶升监测系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination |