CN106320703A - First-three-step construction method for reinforced concrete stairway - Google Patents

First-three-step construction method for reinforced concrete stairway Download PDF

Info

Publication number
CN106320703A
CN106320703A CN201510360112.2A CN201510360112A CN106320703A CN 106320703 A CN106320703 A CN 106320703A CN 201510360112 A CN201510360112 A CN 201510360112A CN 106320703 A CN106320703 A CN 106320703A
Authority
CN
China
Prior art keywords
stair
template
batten
stairway
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510360112.2A
Other languages
Chinese (zh)
Inventor
张树丛
刘家铭
曹光建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201510360112.2A priority Critical patent/CN106320703A/en
Publication of CN106320703A publication Critical patent/CN106320703A/en
Pending legal-status Critical Current

Links

Landscapes

  • Steps, Ramps, And Handrails (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention provides a first-three-step construction method for a reinforced concrete stairway. The first-three-step construction method for the reinforced concrete stairway is characterized by comprising the following steps of (a), manufacturing of a stairway formwork; (b), mounting and reinforcing of a bench bottom formwork of the stairway; (c), mounting of other formworks of the stairway; (d), concrete pouring of the current storey; (e), dismounting of side formworks of the stairway and partition boards (5) of the first three steps after concrete is finally solidified; (f), concrete curing; (g), mounting and reinforcing of side formworks of the stairway and the rest of step partition boards of the current storey; (h), drawing-out of a drawing type movable module; (i), pouring of the rest of steps of the stairway; (j) dismounting of all the formworks; (k) concrete pouring; and (l) repairing of the position of the drawing type movable module connected to a construction joint of the bench of the stairway into a strip shape with mortar with the concentration ratio being 1:2. According to the first-three-step construction method for the reinforced concrete stairway, the movable module structure is ingeniously used, and thus the first-three-step construction method has the advantages that waste, such as dust, concrete residues and cigarette butts, on construction joints of the bench of the stairway can be removed rapidly, the impression of the stairway is improved after the formworks are dismounted, the manual repairing cost in the later stage is reduced, and the engineering cost is reduced.

Description

Three step construction methods on a kind of reinforced concrete stairs
Technical field
The present invention relates to a kind of reinforced concrete stairs construction method, specifically, be three step construction methods on a kind of reinforced concrete stairs.
Background technology
In architectural engineering, the construction joint of stair bench (step plate) every layer should be retained in plate across 1/3 section in, general concrete construction joint is to stay at three steps.But find in practical operation, conventionally construct, the phenomenons such as pitted skin often occur at the construction joint of stair bench, cause surface stone at construction joint to loosen, come off.
On the most known reinforced concrete stairs, three step construction methods also exist above-mentioned all inconvenience and problem.
Summary of the invention
The purpose of the present invention, is to propose a kind of to promote after stair form removal three step construction methods on the reinforced concrete stairs of perception.
It is another object of the present invention to propose three step construction methods on a kind of reinforced concrete stairs reducing later stage manual repair expense.
A further object of the present invention, is to propose at a kind of quick cleaning stair bench construction joint three step construction methods on the reinforced concrete stairs of the rubbish such as dust, concrete slag, cigarette end.
For achieving the above object, the technical solution of the present invention is:
Three step construction methods on a kind of reinforced concrete stairs, it is characterised in that comprise the following steps:
A, stair template make, including template, side template bottom stair bench, dividing plate of marking time, dividing plate at construction joint, and drawable out moving module, described active module includes the 1st batten and the 2nd batten, 1st batten width >=50mm, thickness is with bottom template thickness, and length is with stair bench width;2nd batten width >=25mm, thickness is with bottom template thickness, and length is with stair bench width;Below above at 1st batten and at the 2nd batten, the justified margin on long limit, both sides, overlapping, connect fixing with nail;
The installation of template and reinforcing bottom b, the stair bench that will process according to drawing, including template bottom upper three steps, side template, wherein at construction joint divider upright in bottom template, 2nd batten of active module is embedded in the middle of the template of bottom, make the 2nd batten become a part for bottom template, and make the 1st batten be at construction joint at the intersection point of dividing plate and bottom template;
Other model sheetinstallat of c, stair and reinforcing, including stair step dividing plate;
After all model sheetinstallat of d, stair complete, when pouring This floor concrete, pour three step on stair, note vibrating the most closely knit;
E, dividing plate of stair side template and upper three steps being marked time after concrete final set are removed, but do not remove drawable out moving module;
F, stair side template and upper three steps mark time dividing plate removed after maintenance concrete immediately;
G, when last layer stair template construction, dividing plate of this floor side of the ladder mould and residue being marked time installs and reinforces;
If h stair joint part rubbish is more, drawable out moving module can be extracted out, expose owing to the 2nd batten detaches the refuse sweeping mouth of formation, again drawable out moving module be turned back to after having cleared up rubbish in situ;
I, when last layer concrete placings, stair are remained step and have poured, note vibrating the most closely knit;
J, after concrete final set, template is all removed, be careful not to destroy corner;
K, stair template carry out maintenance to concrete after having torn open immediately;
L, with 1:2 mortar by connect at the construction joint of stair bench stubble drawable out moving module position repair become band, it is ensured that the flatness after repairing.
On the reinforced concrete stairs of the present invention, three step construction methods can also be further achieved by the following technical measures.
Aforesaid method, the material of wherein said 1st batten is identical with bottom template.
Aforesaid method, the material of wherein said 2nd batten is identical with bottom template.
After using technique scheme, on the reinforced concrete stairs of the present invention, three step construction methods have the advantage that
1, drawable out moving modular structure is simple, easy to make, practical;
2, the quick rubbish such as dust, concrete slag, cigarette end at cleaning stair bench construction joint;
3, perception after stair form removal is promoted;
4, reduce later stage manual repair expense, reduce engineering cost.
Accompanying drawing explanation
Fig. 1 is the structural representation of three steps on the stair of the embodiment of the present invention;
Fig. 2 is the P position enlarged drawing in Fig. 1;
Fig. 3 is the stair template floor map of the embodiment of the present invention.
In figure: 1 the 1st batten, template bottom 2 bench, 3 the 2nd battens, dividing plate at 4 construction joints, 5 stair step dividing plates, 6 concrete.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing thereof, the present invention is illustrated further.
Embodiment 1
On the reinforced concrete stairs of the present invention, three step construction methods are for following sequence of construction:
Model sheetinstallat and reinforcing → reinforcing bar binding → side form bottom stair template making → stair bench, mark time dividing plate, at construction joint dividing plate and 50mm batten installation → concreting (being only poured into three steps to put) → stair template remove (50mm batten is not torn open with bed die) → maintenance → makings stair remainder mark time dividing plate and install → 50mm batten extracted out clear up rubbish after be inserted into original position → concreting (pour stair and remain step) → form removable (all dismountings) → maintenance → connect stubble with the repairing of 1:2 mortar and become band.
Three step construction method on the reinforced concrete stairs of the present invention, it is characterised in that comprise the following steps:
A, stair template make, including template 2, side template bottom stair bench, and dividing plate 6 of marking time, dividing plate 4 at construction joint, and drawable out moving module.
Referring now to the structural representation of three steps on the stair that Fig. 1 and Fig. 2, Fig. 1 are the embodiment of the present invention, Fig. 2 is the P position enlarged drawing in Fig. 1.As it can be seen, described active module includes the 1st batten the 1 and the 2nd batten 3, the wide 50mm of the 1st batten 1, thickness is with bottom template 2 thickness, and length is with stair bench width;The wide 25mm of 2nd batten 3, thickness is with bottom template 2 thickness, and length is with stair bench width;Below above at 1st batten 1 and at the 2nd batten 3, the justified margin on long limit, both sides, overlapping, connect fixing with nail;1st batten 1 is all identical with the material of template 2 bottom stair bench with the material of the 2nd batten 3.
The installation of template and reinforcing bottom b, the stair bench that will process according to drawing, including template 2 bottom upper three steps, side template, wherein at construction joint, dividing plate 4 is perpendicular to bottom template 2,2nd batten 3 of active module is embedded in the middle of the template 2 of bottom, make the 2nd batten 3 become a part for bottom template 2, and make the 1st batten 1 be at dividing plate at construction joint 4 and the intersection point of bottom template 2.
Other model sheetinstallat of c, stair and reinforcing, including stair step dividing plate 5.
After all model sheetinstallat of d, stair complete, when pouring This floor concrete, pour three step on stair, note vibrating the most closely knit.
E, dividing plate of stair side template and upper three steps being marked time after concrete final set remove 5, but do not remove drawable out moving module;
F, stair side template and upper three steps mark time dividing plate removed after maintenance concrete immediately.
G, when last layer stair template construction, dividing plate of this floor side of the ladder mould and residue being marked time installs and reinforces.
If h stair joint part rubbish is more, drawable out moving module can be extracted out, expose owing to the 2nd batten 3 detaches the refuse sweeping mouth of formation, again drawable out moving module be turned back to after having cleared up rubbish in situ;Fig. 3 is the stair template floor map of the embodiment of the present invention.
I, when last layer concrete placings, stair are remained step and have poured, note vibrating the most closely knit.
J, after concrete final set, template is all removed, be careful not to destroy corner.
K, stair template carry out maintenance to concrete after having torn open immediately.
L, with 1:2 mortar by connect at the construction joint of stair bench stubble drawable out moving module position repair become band, it is ensured that the flatness after repairing.
The present invention has substantive distinguishing features and significant technological progress, three step construction method on the reinforced concrete stairs of the present invention of the present invention, use active module structure dexterously, beyond thought work efficiency is produced in construction, reach quickly to clear up the rubbish such as dust, concrete slag, cigarette end at stair bench construction joint, promote perception after stair form removal, reduce later stage manual repair expense, reduce engineering cost.
On the reinforced concrete stairs of the present invention, three step construction methods dispose in cellular engineering Bangbu Qin market town peasant and use, and construction method is simple, with low cost, it is easy to operation, and effect is notable, have obtained exploiting entity, supervisor and owner's abundant affirmation.
Above example is used for illustrative purposes only, rather than limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, it is also possible to make various conversion or change.Therefore, the technical scheme of all equivalents also should belong to scope of the invention, should be limited by each claim.

Claims (3)

1. three step construction methods on a reinforced concrete stairs, it is characterised in that comprise the following steps:
A, stair template make, including template (2) bottom stair bench, side template, mark time dividing plate (6), dividing plate (4) at construction joint, and drawable out moving module, described active module includes the 1st batten (1) and the 2nd batten (3), 1st batten (1) width >=50mm, thickness is with bottom template (2) thickness, and length is with stair bench width;2nd batten (3) width >=25mm, thickness is with bottom template (2) thickness, and length is with stair bench width;Below above 1st batten (1) place and the 2nd batten (3) place, the justified margin on long limit, both sides, overlapping, connect fixing with nail;
The installation of template and reinforcing bottom b, the stair bench that will process according to drawing, including template (2) bottom upper three steps, side template, wherein at construction joint, dividing plate (4) is perpendicular to bottom template (2), 2nd batten (3) of active module is embedded in the middle of bottom template (2), make the 2nd batten (3) become a part for bottom template (2), and make the 1st batten (1) be at the intersection point of dividing plate at construction joint (4) and bottom template (2);
Other model sheetinstallat of c, stair and reinforcing, including stair step dividing plate (5);
After all model sheetinstallat of d, stair complete, when pouring This floor concrete, pour three step on stair, note vibrating the most closely knit;
E, dividing plate of stair side template and upper three steps being marked time after concrete final set remove (5), but do not remove drawable out moving module;
F, stair side template and upper three steps mark time dividing plate removed after maintenance concrete immediately;
G, when last layer stair template construction, dividing plate of this floor side of the ladder mould and residue being marked time installs and reinforces;
If h stair joint part rubbish is more, drawable out moving module can be extracted out, expose owing to the 2nd batten (3) detaches the refuse sweeping mouth of formation, again drawable out moving module be turned back to after having cleared up rubbish in situ;
I, when last layer concrete placings, stair are remained step and have poured, note vibrating the most closely knit;
J, after concrete final set, template is all removed, be careful not to destroy corner;
K, stair template carry out maintenance to concrete after having torn open immediately;
L, with 1:2 mortar by connect at the construction joint of stair bench stubble drawable out moving module position repair become band, it is ensured that the flatness after repairing.
2. three step construction methods on reinforced concrete stairs as claimed in claim 1, it is characterised in that the material of described 1st batten (1) is identical with bottom template (2).
3. three step construction methods on reinforced concrete stairs as claimed in claim 1, it is characterised in that the material of described 2nd batten (3) is identical with bottom template (2).
CN201510360112.2A 2015-06-26 2015-06-26 First-three-step construction method for reinforced concrete stairway Pending CN106320703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510360112.2A CN106320703A (en) 2015-06-26 2015-06-26 First-three-step construction method for reinforced concrete stairway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510360112.2A CN106320703A (en) 2015-06-26 2015-06-26 First-three-step construction method for reinforced concrete stairway

Publications (1)

Publication Number Publication Date
CN106320703A true CN106320703A (en) 2017-01-11

Family

ID=57729573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510360112.2A Pending CN106320703A (en) 2015-06-26 2015-06-26 First-three-step construction method for reinforced concrete stairway

Country Status (1)

Country Link
CN (1) CN106320703A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958349A (en) * 2017-05-24 2017-07-18 中国建筑第二工程局有限公司 Upper three step of aluminum alloy template stair matches somebody with somebody die body system and stair
CN106988529A (en) * 2017-05-02 2017-07-28 闫相明 A kind of stair template structure and the stair construction method using the formwork structure
CN110725319A (en) * 2019-09-11 2020-01-24 北京翔鲲水务建设有限公司 Large-angle concrete pouring method
CN112144904A (en) * 2020-09-04 2020-12-29 中建四局第三建设有限公司 Chiseling-free construction method for connecting stubbles of stair step construction joints

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988529A (en) * 2017-05-02 2017-07-28 闫相明 A kind of stair template structure and the stair construction method using the formwork structure
CN106988529B (en) * 2017-05-02 2018-12-25 闫相明 A kind of stair template structure and the stair construction method using the formwork structure
CN106958349A (en) * 2017-05-24 2017-07-18 中国建筑第二工程局有限公司 Upper three step of aluminum alloy template stair matches somebody with somebody die body system and stair
CN106958349B (en) * 2017-05-24 2022-12-27 中国建筑第二工程局有限公司 Last three-step mold matching system of aluminum alloy template stair and stair
CN110725319A (en) * 2019-09-11 2020-01-24 北京翔鲲水务建设有限公司 Large-angle concrete pouring method
CN110725319B (en) * 2019-09-11 2022-01-25 北京清河水利建设集团有限公司 Large-angle concrete pouring method
CN112144904A (en) * 2020-09-04 2020-12-29 中建四局第三建设有限公司 Chiseling-free construction method for connecting stubbles of stair step construction joints

Similar Documents

Publication Publication Date Title
CN103817778B (en) Prefabricated fair-faced concrete component construction method
CN106320703A (en) First-three-step construction method for reinforced concrete stairway
CN101644079B (en) Construction method of reinforced concrete shear wall body
CN108638324A (en) A kind of construction method of prefabricated case beam
CN104264984B (en) Concrete structures formwork for casting and casting construction method
CN208534025U (en) Floor slab back casting band separate support formwork erecting structure
CN109129826A (en) Precast concrete alcove production method as the indoor strong and weak electronic box of house
CN109723140A (en) A kind of construction method between precast stair
CN103321423A (en) Cast-in-place concrete stair construction method
CN102747837A (en) Cleaning method for cast-in-place reinforced concrete stair segment timber template
CN104594654B (en) A kind of concrete structure reinforcement scheme generation method
CN211974342U (en) Floor slab reserved hole device with embedded bar planting holes
CN102733600A (en) Totally-enclosed stair template components
CN105064500A (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
CN109868751B (en) Assembled track beam concrete post-pouring notch, template and construction method
CN209114504U (en) A kind of basement bottom plate rear pouring tape structure
CN201137298Y (en) Post pouring strip, construction joint side steel die
CN203622616U (en) Integral template used for cable trough pouring
CN205857707U (en) Stair step constructing device
CN113700157A (en) Concrete constructional column supporting method for roof post-cast strip
CN205476468U (en) Non - design, can all rotary die plate bodys be prefabricated staircase bench template
CN213330014U (en) Post-pouring strip template supporting system with function of back jacking after disassembly
CN208844772U (en) Plate integrally drops in concrete
CN112443083B (en) Construction method of cast-in-place concrete stair
CN101240569A (en) In-situ integrated placing construction method for aerated concrete wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170111

RJ01 Rejection of invention patent application after publication