CN106320178B - A kind of bridge structure hanging method and bridge hoisting mechanism skid - Google Patents

A kind of bridge structure hanging method and bridge hoisting mechanism skid Download PDF

Info

Publication number
CN106320178B
CN106320178B CN201610714997.6A CN201610714997A CN106320178B CN 106320178 B CN106320178 B CN 106320178B CN 201610714997 A CN201610714997 A CN 201610714997A CN 106320178 B CN106320178 B CN 106320178B
Authority
CN
China
Prior art keywords
bridge
hoisting mechanism
skid
hoisting
longeron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610714997.6A
Other languages
Chinese (zh)
Other versions
CN106320178A (en
Inventor
程小龙
陈世珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd
Original Assignee
WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd filed Critical WUHAN WUCHUAN HEAVY EQUIPMENT ENGINEERING Co Ltd
Priority to CN201610714997.6A priority Critical patent/CN106320178B/en
Publication of CN106320178A publication Critical patent/CN106320178A/en
Application granted granted Critical
Publication of CN106320178B publication Critical patent/CN106320178B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/72Counterweights or supports for balancing lifting couples
    • B66C23/78Supports, e.g. outriggers, for mobile cranes

Abstract

The present invention relates to bridge steel structures to lift field, relates generally to lift steel truss bridge.Disclose a kind of bridge structure hanging method, the bridge hoisting mechanism of the bridge stability longeron along bridge structure lower end is not influenced using weight to travel and lifted, the working depth of hoisting mechanism is reduced, while reducing the vibrations in bridge hoisting stage so that hoisting process is more safe and reliable.Also, the nonstandard revolution loop wheel machine that need not use specific customization, reduces steel truss bridge hoisting cost, shortens total period of bridge manufacture.The present invention also provides a kind of bridge hoisting mechanism skids, and walking of the bridge hoisting mechanism on middle longeron can be made more reliable and more stable.

Description

A kind of bridge structure hanging method and bridge hoisting mechanism skid
Technical field
The present invention relates to bridge steel structures to lift field, relates generally to lift steel truss bridge.
Background technology
Steel structure bridge is seen everywhere.Construction site steel truss structure bridge cantilever hanging method has:The installation of steel girder bridge, It needs using special revolution loop wheel machine at the top of truss, i.e., using the upper end longeron of bridge structure as its running track, to bridge It is lifted.Before lifting, revolution loop wheel machine producer is waited for be carried out for bridge technology parameter, revolution loop wheel machine is designed, is made It makes, in-site installation.Often recover slewing crane cost at least million.
How to reduce the vibrations in bridge hoisting stage, hoisting cost, and manufacture total period is the research of bridge installation method Direction.
Invention content
Technical problem to be solved by the invention is to provide a kind of bridge structure hanging methods, can be suitable for steel girder bridge Beam lifts, and have does not influence the bridge hoisting mechanism of bridge stability using weight, by it along bridge structure lower end longeron Traveling, lifts bridge portion so that hoisting mechanism is on the middle longeron of bridge lower end, reduces hoisting mechanism work Highly, while the vibrations in bridge hoisting stage being reduced so that the more safe and reliable feature of hoisting process.The present invention also provides A kind of bridge hoisting mechanism skid, by the present apparatus can make walking of the bridge hoisting mechanism on middle longeron more steady It is fixed reliable.
In order to solve the above technical problems, the present invention provides a kind of bridge structure hanging method, bridge is not influenced using weight The bridge hoisting mechanism of beam stability longeron traveling along bridge structure lower end is lifted, and is included the following steps:
A. bridge end bay is lifted;
B. the bridge hoisting mechanism is moved in the bridge structure lower end at end bay edge on longeron, is fixed in bridge On;
C. the preceding one third of span is to preceding half internode in being lifted by bridge hoisting mechanism, and uses interim End bay and middle span are rigidly connected by connection, after often having lifted an internode, by bridge hoisting mechanism along bridge structure lower end Longeron moves forward at next internode lifting position, and then bridge hoisting mechanism is fixed on bridge, starts to lift next Internode;
D. bridge hoisting mechanism is moved rearwardly into end bay end, and be fixed on bridge, pass through bridge hoisting machine Structure lifts steel construction button tower and cable;
F. by bridge hoisting mechanism, longeron moves forward along bridge structure lower end, continues to lift by the way of step C Middle span remainder.
It is to further include to the technical solution that the above method is improved:Skid;The weight does not influence bridge stability Property bridge hoisting mechanism by the skid along the bridge structure lower end longeron travel;
In the step B, the bridge hoisting mechanism is moved to by the skid under the bridge structure at end bay edge In end on longeron;
In the step C, by skid, the longeron along bridge structure lower end moves forward to down for bridge hoisting mechanism One internode lifts by crane at position;
In the step D, bridge hoisting mechanism is moved rearwardly into end bay end by skid;
In the step F, by skid, by bridge hoisting mechanism, the longeron along bridge structure lower end moves forward.
Making preferred technical solution to above-mentioned improvement project is, the weight of use does not influence the bridge of bridge stability Beam hoisting mechanism is the pedrail crane for laying down track wheel;Further include step B1 between step A and step B;
The step A is to be lifted to bridge end bay on river bank using pedrail crane;
The step B1 is that the pedrail crane is unloaded the crawler crane that track wheel lays down track wheel as described in The pedrail crane for laying down track wheel is fixed on the skid by vehicle.
The present invention also provides a kind of bridge hoisting mechanism skids, including:Hoisting mechanism bearing seat, driving machine Structure, removable retention mechanism, position-limit mechanism;
Bridge hoisting mechanism is fixed on by the position-limit mechanism on the hoisting mechanism bearing seat, hoisting mechanism bearing seat Connect with the driving mechanism, hoisting mechanism bearing seat by longeron in the removable retention mechanism and bridge structure lower end with Removable mode is fixed.
Carrying out preferred technical solution to above structure is, the position-limit mechanism is multiple, and each position-limit mechanism distinguishes cloth It is placed in the surrounding of the hoisting mechanism bearing seat, wherein the position-limit mechanism at least one direction is with removable or adjustable stroke Mode be set on hoisting mechanism bearing seat.
Further preferred technical solution is, in the position-limit mechanism, is in the limit of hoisting mechanism bearing seat front and rear ends Position mechanism is in the structure mutually chimeric with the bridge hoisting actuator base front and back ends respectively, before hoisting mechanism bearing seat, The position-limit mechanism at both ends afterwards, at least one is set in a manner of removable or adjustable stroke on hoisting mechanism bearing seat.
Technical solution still further preferably is that the removable retention mechanism includes two groups, two groups of removable fastening machines Structure is respectively arranged below the hoisting mechanism bearing seat, is particularly located at corresponding with two middle longerons of bridge structure lower end At position.
Further preferred technical solution is that every group of removable retention mechanism is more sets, often covers removable fastening Mechanism includes:Top board, lower platen, connection bolt;The top board is set on the hoisting mechanism bearing seat, the pushing Plate is in the lower section of longeron in the bridge structure lower end, and lower platen is by connecting bolt and the top board removably company of fastening It connects.
Further improved technical solution is to be provided with servoboard between the hoisting mechanism bearing seat and bridge.
More preferred technical solution is that the driving mechanism is hydraulic drive mechanism.
The beneficial effects of the present invention are:
It is lifted 1. the present invention can be suitable for steel truss bridge, does not influence the bridge hoisting machine of bridge stability using weight Structure, by it, longeron travels along bridge structure lower end, is lifted to bridge portion so that hoisting mechanism is in bridge lower end Middle longeron on, reduce the working depth of hoisting mechanism, while reducing the vibrations in bridge hoisting stage so that hoisting process It is more safe and reliable.
2. the present invention need not use the nonstandard revolution loop wheel machine of specific customization, can directly be hung using ready-made crawler type Vehicle.After pedrail crane completes end bay lifting, the track wheel for laying down pedrail crane mitigates its dead weight, you can as this hair The weight of bright middle use does not influence the bridge hoisting mechanism of bridge stability, to significantly reduce steel truss bridge lifting Cost.Due to being not belonging to nonstandard product, compared with prior art, the present invention can also shorten total period of bridge manufacture.
3. the present invention also provides a kind of bridge hoisting mechanism skids, bridge hoisting machine can be made by the present apparatus Walking of the structure on middle longeron is more stable and reliable.
Bridge structure hanging method provided by the invention, bridge hoisting mechanism longeron in bridge structure lower end travel, drop The low working depth of hoisting mechanism, while reducing the vibrations in bridge hoisting stage so that hoisting process is more safe and reliable. Also, the nonstandard revolution loop wheel machine that need not use specific customization, reduces steel truss bridge hoisting cost, shortens bridge manufacture Total period.The bridge hoisting mechanism skid provided through the invention, can make bridge hoisting mechanism on middle longeron It walks more stable and reliable.
Description of the drawings
Fig. 1 is the structural schematic diagram of the embodiment of the present invention.
Fig. 2 is steel truss bridge bay structural schematic diagram in the embodiment of the present invention.
Fig. 3 is skid structural schematic diagram in the embodiment of the present invention.
Wherein, 1-hoisting mechanism bearing seat, 2-1-lateral Displacement mechanism, 2-2-front limit mechanism, 2-3-are limited afterwards Mechanism, 3-1-top board, 3-2-connection bolt, 3-3-lower platen, 4- driving mechanism interfaces are indulged in 5-bridge structure lower ends Beam, the upper end longeron of 6-bridge structures.
Specific implementation mode
For the present invention is further explained to reach the technological means and effect that predetermined goal of the invention is taken, below in conjunction with attached Figure and preferred embodiment, to the tool of the bridge structure hanging method and bridge hoisting mechanism skid that propose according to the present invention Body embodiment and operation principle are described in detail.
Bridge structure hanging method provided by the present invention, as shown in Figure 1, not influencing the bridge of bridge stability using weight Beam hoisting mechanism traveling of longeron 5 along bridge structure lower end is lifted, and is included the following steps:
A. bridge end bay is lifted;
B. the bridge hoisting mechanism is moved in the bridge structure lower end at end bay edge on longeron, is fixed in bridge On;
C. the preceding one third of span is to preceding half internode in being lifted by bridge hoisting mechanism, and uses interim End bay and middle span are rigidly connected by connection, after often having lifted an internode, by bridge hoisting mechanism along bridge structure lower end Longeron moves forward at next internode lifting position, and then bridge hoisting mechanism is fixed on bridge, starts to lift next Internode;
D. bridge hoisting mechanism is moved rearwardly into end bay end, and be fixed on bridge, pass through bridge hoisting machine Structure lifts steel construction button tower and cable;
F. by bridge hoisting mechanism, longeron moves forward along bridge structure lower end, continues to lift by the way of step C Middle span remainder.
For bridge hoisting mechanism, the present embodiment uses the pedrail crane for laying down track wheel, and passes through skid The pedrail crane for laying down track wheel traveling of longeron 5 along bridge structure lower end is set to be lifted.Specifically lifting step includes:
A. it constructs the incipient stage, bridge end bay is lifted on river bank using pedrail crane;
B1. pedrail crane is unloaded into track wheel as bridge hoisting mechanism, the pedrail crane for laying down track wheel is consolidated It is scheduled on skid;
B. bridge hoisting mechanism is moved to by carriage in the bridge structure lower end at end bay edge on longeron 5, by it It is fixed on bridge;
C. the preceding one third of span is to preceding half internode in being lifted by bridge hoisting mechanism, and uses interim End bay and middle span are rigidly connected by connection:After often having lifted an internode, by bridge hoisting mechanism along bridge structure lower end Longeron moves forward at next internode lifting position, and then bridge hoisting mechanism is fixed on bridge, starts to lift next Internode;
D. bridge hoisting mechanism will be moved rearwardly into end bay end, and be fixed on bridge by carriage, Steel construction button tower and cable are lifted by bridge hoisting mechanism;
F. by carriage, by bridge hoisting mechanism, longeron moves forward along bridge structure lower end, using step C Mode continue lifting in span remainder.
Bridge structure hanging method provided by the present invention is the bridge hoisting machine for not influencing bridge stability using weight Structure is lifted along the traveling of longeron 5 in bridge structure lower end.The special revolution loop wheel machine of use in the prior art is in purlin Top of the trellis will be travelled and be lifted on the upper end longeron 6 of bridge structure.Present invention reduces the work of hoisting mechanism height Degree, while reducing the vibrations in bridge hoisting stage so that hoisting process is more safe and reliable.Common pedrail crane may be used It is slid on longeron 5 in bridge structure lower end by carriage after being laid down track wheel, reaches operating position and hung Dress thus greatly reduces steel truss bridge hoisting cost, shortens total period of bridge manufacture.
The skid used in the present embodiment is as shown in figure 3, include:It is hoisting mechanism bearing seat 1, driving mechanism, removable Formula retention mechanism, position-limit mechanism.Wherein, bridge hoisting mechanism is fixed on by position-limit mechanism on hoisting mechanism bearing seat 1, lifting For mechanism bearing seat 1 by being connect with driving mechanism with driving mechanism interface 4, hoisting mechanism bearing seat 1 passes through removable fastening machine Structure is removably fixed with longeron 5 in bridge structure lower end.
Position-limit mechanism is multiple, and each position-limit mechanism is respectively arranged in the surrounding of hoisting mechanism bearing seat 1, wherein at least There are one the position-limit mechanisms in direction to be set in a manner of removable or adjustable stroke on hoisting mechanism bearing seat 1.So as to bridge Hoisting mechanism is installed.In position-limit mechanism, front limit mechanism 2-2 in 1 front of hoisting mechanism bearing seat, held in hoisting mechanism The rear position-limit mechanism 2-3 at 1 rear portion of seat is carried, is in the structure mutually chimeric with bridge hoisting actuator base front and back ends, the present embodiment respectively In, the position-limit mechanism in 1 front end of hoisting mechanism bearing seat is set to hoisting mechanism bearing seat 1 in a manner of adjustable stroke On.After bridge hoisting mechanism is seated on hoisting mechanism bearing seat 1, lateral Displacement mechanism 2-1 coordinates 1 support of hoisting mechanism bearing seat Firmly bridge hoisting mechanism prevents it from lateral shift occurs;Position-limit mechanism 2-3 blocks the rear end of bridge hoisting actuator base afterwards, prevents Only it is deviated upwards and backwards;Front limit mechanism 2-3 is by adjusting its stroke, before so that it is blocked bridge hoisting actuator base End, prevents it forward and offsets up, bridge hoisting mechanism is made to be fixed with skid.
Removable retention mechanism includes two groups, and two groups of removable retention mechanisms are respectively arranged in hoisting mechanism bearing seat 1 Lower section is particularly located at position corresponding with two middle longerons 5 of bridge structure lower end.Every group of removable retention mechanism is more Set, often covering removable retention mechanism includes:Top board 3-1, lower platen 3-3, connection bolt 3-2.Top board 3-1 is set to lifting On mechanism bearing seat 1, lower platen 3-3 is in the lower section of longeron 5 in bridge structure lower end, and lower platen 3-3 is by connecting bolt 3-2 It is removably fastenedly connected with top board 3-1.Servoboard is set between hoisting mechanism bearing seat and bridge.Driving mechanism is liquid Driving mechanism is pressed, is mainly acted on simultaneously by two oil cylinders, ensures that equipment can be slided along fixed-direction, prevents slipping In shift phenomenon.
The operation principle of skid is:Bridge hoisting mechanism is fixed on hoisting mechanism bearing seat 1 by position-limit mechanism On, so that bridge hoisting mechanism longeron 5 along bridge structure lower end is slid by hoisting mechanism bearing seat 1 by driving mechanism, when After reaching operating position, the spacing of top board 3-1 and lower platen 3-3 are reduced by connecting bolt 3-2, and equipment and bridge are locked Tightly, it is positioned.After having lifted an internode, connection bolt 3-2 is unclamped, but is not moved out, makes in slipping lower platen 3-3 still With connect bolt 3-2 connections, its purpose is that:On the one hand in order to avoid special circumstances occur, prevent skid and crane this Overall offset has occurred in entirety, guarantees safe production;On the other hand, it reduces in hoisting process, the set time of skid.
It should be noted last that the above specific implementation mode is merely illustrative of the technical solution of the present invention and unrestricted, Although being described the invention in detail with reference to example, it will be understood by those of ordinary skill in the art that, it can be to the present invention Technical solution be modified or replaced equivalently, without departing from the spirit of the technical scheme of the invention and range, should all cover In the scope of the claims of the present invention.

Claims (10)

1. a kind of bridge structure hanging method, which is characterized in that do not influence the bridge hoisting mechanism of bridge stability using weight Longeron traveling is lifted along bridge structure lower end, is included the following steps:
A. bridge end bay is lifted;
B. the bridge hoisting mechanism is moved in the bridge structure lower end at end bay edge on longeron, is fixed on bridge;
C. the preceding one third of span is to preceding half internode in being lifted by bridge hoisting mechanism, and uses interim connection End bay and middle span are rigidly connected, after often having lifted an internode, by bridge hoisting mechanism along bridge structure lower end longeron It moves forward at next internode lifting position, then bridge hoisting mechanism is fixed on bridge, starts to lift next internode;
D. bridge hoisting mechanism is moved rearwardly into end bay end, and be fixed on bridge, mechanism is hung by bridge hoisting Steel loading structure button tower and cable;
F. by bridge hoisting mechanism, longeron moves forward along bridge structure lower end, and it is intermediate to continue lifting by the way of step C Across remainder.
2. bridge structure hanging method as described in claim 1, which is characterized in that further include:Skid;The weight is not By the skid, the longeron along the bridge structure lower end travels for the bridge hoisting mechanism of influence bridge stability;
In the step B, the bridge hoisting mechanism is moved to by the skid in the bridge structure lower end at end bay edge On longeron;
In the step C, by skid, the longeron along bridge structure lower end moves forward to next section for bridge hoisting mechanism Between lifting position at;
In the step D, bridge hoisting mechanism is moved rearwardly into end bay end by skid;
In the step F, by skid, by bridge hoisting mechanism, the longeron along bridge structure lower end moves forward.
3. bridge structure hanging method as claimed in claim 2, which is characterized in that it is steady that the weight of use does not influence bridge Qualitative bridge hoisting mechanism is to lay down the pedrail crane of track wheel;Further include step B1 between step A and step B;
The step A is to be lifted to bridge end bay on river bank using pedrail crane;
The step B1 is that the pedrail crane is unloaded the pedrail crane that track wheel lays down track wheel as described in, will The pedrail crane for laying down track wheel is fixed on the skid.
4. a kind of bridge hoisting mechanism skid, which is characterized in that including:It is hoisting mechanism bearing seat, driving mechanism, removable Formula retention mechanism, position-limit mechanism;
Bridge hoisting mechanism is fixed on by the position-limit mechanism on the hoisting mechanism bearing seat, and hoisting mechanism bearing seat passes through Driving mechanism interface is connect with driving mechanism, and hoisting mechanism bearing seat passes through the removable retention mechanism and bridge structure lower end Middle longeron is removably fixed.
5. bridge hoisting mechanism as claimed in claim 4 skid, which is characterized in that the position-limit mechanism be it is multiple, Each position-limit mechanism is respectively arranged in the surrounding of the hoisting mechanism bearing seat, wherein the position-limit mechanism at least one direction It is set in a manner of removable or adjustable stroke on hoisting mechanism bearing seat.
6. bridge hoisting mechanism as claimed in claim 5 skid, which is characterized in that in the position-limit mechanism, be in The position-limit mechanism of hoisting mechanism bearing seat front and rear ends is in mutually chimeric with the bridge hoisting actuator base front and back ends respectively Structure is in the position-limit mechanism of hoisting mechanism bearing seat front and rear ends, at least one is with removable or adjustable stroke side Formula is set on hoisting mechanism bearing seat.
7. the bridge hoisting mechanism skid as described in any one of claim 4 to 6, which is characterized in that it is described can It includes two groups to tear formula retention mechanism open, and two groups of removable retention mechanisms are respectively arranged below the hoisting mechanism bearing seat and bridge At two middle corresponding positions of longeron of girder construction lower end.
8. bridge hoisting mechanism as claimed in claim 7 skid, which is characterized in that every group of removable fastening machine Structure is more sets, and often covering removable retention mechanism includes:Top board, lower platen, connection bolt;The top board is set to described hang On mounting mechanism bearing seat, the lower platen is in the lower section of longeron in the bridge structure lower end, and lower platen is by connecting bolt It is removably fastenedly connected with top board.
9. bridge hoisting mechanism as claimed in claim 8 skid, which is characterized in that the hoisting mechanism bearing seat with Servoboard is provided between bridge.
10. bridge hoisting mechanism as claimed in claim 9 skid, which is characterized in that the driving mechanism is hydraulic pressure Driving mechanism.
CN201610714997.6A 2016-08-24 2016-08-24 A kind of bridge structure hanging method and bridge hoisting mechanism skid Active CN106320178B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610714997.6A CN106320178B (en) 2016-08-24 2016-08-24 A kind of bridge structure hanging method and bridge hoisting mechanism skid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610714997.6A CN106320178B (en) 2016-08-24 2016-08-24 A kind of bridge structure hanging method and bridge hoisting mechanism skid

Publications (2)

Publication Number Publication Date
CN106320178A CN106320178A (en) 2017-01-11
CN106320178B true CN106320178B (en) 2018-07-20

Family

ID=57790220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610714997.6A Active CN106320178B (en) 2016-08-24 2016-08-24 A kind of bridge structure hanging method and bridge hoisting mechanism skid

Country Status (1)

Country Link
CN (1) CN106320178B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503514A (en) * 2017-08-15 2017-12-22 四川路桥华东建设有限责任公司 A kind of large-tonnage steel truss arch section fixed point hoisting method accurately calculated based on CABLEWAY ERECTION SYSTEM
CN107458966B (en) * 2017-09-05 2019-06-25 四川路桥华东建设有限责任公司 A kind of sea large-tonnage opposite sex steel truss frame member cable crane entirety vertical transfer hoisting construction method
CN111005303A (en) * 2019-12-30 2020-04-14 武汉武船重型装备工程有限责任公司 Hidden long-span movable bridging device and bridging method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457513A (en) * 2008-12-30 2009-06-17 中铁大桥局集团第三工程有限公司 Bridge erection method
RU2381326C1 (en) * 2008-11-14 2010-02-10 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for lifting and erecting units of superstructure
CN202626840U (en) * 2012-06-07 2012-12-26 中铁十二局集团第七工程有限公司 Hanging basket device used in construction of slag retaining wall of railway cast-in-situ edge beam
CN103669216A (en) * 2013-11-21 2014-03-26 中建三局建设工程股份有限公司 Steel box girder scattered-splicing sliding device and installation method
CN206052570U (en) * 2016-08-24 2017-03-29 武汉武船重型装备工程有限责任公司 A kind of bridge hoisting mechanism skid

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2381326C1 (en) * 2008-11-14 2010-02-10 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for lifting and erecting units of superstructure
CN101457513A (en) * 2008-12-30 2009-06-17 中铁大桥局集团第三工程有限公司 Bridge erection method
CN202626840U (en) * 2012-06-07 2012-12-26 中铁十二局集团第七工程有限公司 Hanging basket device used in construction of slag retaining wall of railway cast-in-situ edge beam
CN103669216A (en) * 2013-11-21 2014-03-26 中建三局建设工程股份有限公司 Steel box girder scattered-splicing sliding device and installation method
CN206052570U (en) * 2016-08-24 2017-03-29 武汉武船重型装备工程有限责任公司 A kind of bridge hoisting mechanism skid

Also Published As

Publication number Publication date
CN106320178A (en) 2017-01-11

Similar Documents

Publication Publication Date Title
CN106978784B (en) A kind of Long span highway suspension bridge Demolition Construction method
CN106320178B (en) A kind of bridge structure hanging method and bridge hoisting mechanism skid
CN202768021U (en) Waterproof board laying trolley
CN108004929B (en) A kind of hanging method of H-type road-cum-rail bridge floorings hanging apparatus
CN107974944B (en) A kind of hanging method of Y type road-cum-rail bridge floorings hanging apparatus
CN104060844A (en) Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
CN104762882B (en) Bridge subsection hanging apparatus and hanging method
CN104533466A (en) Multifunctional flexible traction type paving rack for waterproof board
CN106522112A (en) Cable-stayed bridge side span beam section erecting system and method thereof
CN106049208A (en) High-speed railway turnout large-size component replacing and laying device and method
CN205876339U (en) Boxing girder half -through is hydraulic pressure invert trestle by oneself
CN206617175U (en) A kind of automatic liquid pressure type inverted arch trestle
CN104533461B (en) A kind of tunnel construction trolley horizontal mobile device
CN102606172A (en) Hydraulic self-propelled large-gradient concrete pouring trolley
JP4559370B2 (en) Girder erection method by erection gutter from the side of bridge
CN201250058Y (en) Improved lifting trolley
CN205874987U (en) Simply put up bridge crane
CN105155427B (en) The construction method that suspension bridge cat road is laid
CN204282843U (en) The sliding hoisted in position device of steel girder erection in a kind of stiffness combination construction
CN203865878U (en) Underground foundation pit deslagging and supporting gantry crane device
CN203007843U (en) Variable amplitude deck derrick crane
CN108217448A (en) A kind of integrated bridge floor device for hoisting for composite beam construction
CN206052570U (en) A kind of bridge hoisting mechanism skid
CN206343805U (en) Positioner for lower frame of excavator
CN205653068U (en) Reinforcement type gantry crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant