A kind of stopping means with energy-absorbing buffering ability
Technical field
The invention belongs to building and science of bridge building Seismic Isolation And Dissipation of Civil Structures technical field, has energy-absorbing buffering more particularly to one kind
The stopping means of ability.
Background technology
It is a kind of technology that can improve structural seismic performance and reduce seismic hazard to subtract seismic isolation technology, now with increasingly
More is applied in all kinds of newly-built, reconstructions and reinforcing engineering, in order that engineering structure resists earthquake and wind load with stronger
Etc. the ability of external applied load, while prevent engineering structure burst from hitting and being destroyed, it will usually to be set up in engineering structure spacing
Device.
For existing stopping means, it does not simultaneously have energy-absorbing buffering ability, and the shock resistance of stopping means
It is poor, engineering structure can not be played a very good protection.
The content of the invention
The problem of existing for prior art, the present invention provide a kind of stopping means with energy-absorbing buffering ability, make limit
Position device possesses stronger shock resistance, and engineering structure can be played a very good protection.
To achieve these goals, the present invention adopts the following technical scheme that:A kind of spacing dress with energy-absorbing buffering ability
Put, including energy-absorbing buffering steel ring, upper steel ring limit base and lower steel ring limit base, the upper steel ring limit base are fixedly mounted on top
On structural member, the lower steel ring limit base is fixedly mounted on lower structural features, upper steel ring limit base and lower steel ring limit base knot
Structure is identical and distribution symmetrical above and below;The upper steel ring limit base includes pedestal, bearing pin with lower steel ring limit base and is oriented to steel wheel,
Bearing pin is arranged on pedestal, is oriented to steel wheel and is sleeved on bearing pin, and be oriented to steel wheel has rotational freedom relative to bearing pin;On described
It is connected between the guiding steel wheel of steel ring limit base and the guiding steel wheel of lower steel ring limit base by energy-absorbing buffering steel ring.
Local strengthening steel plate is provided between the pedestal of steel ring limit base and upper structure part on described, under described
Lower local strengthening steel plate, the upper local strengthening steel plate and top are provided between the pedestal and lower structural features of steel ring limit base
It is fixedly connected between structural member, between lower local strengthening steel plate and lower structural features by strengthening anchor pole.
Between the pedestal and upper local strengthening steel plate of the upper steel ring limit base, the pedestal of lower steel ring limit base and lower part
Strengthen using detachable connection structure between steel plate.
Between the pedestal and upper local strengthening steel plate of the upper steel ring limit base, the pedestal of lower steel ring limit base and lower part
Strengthen being connected by screw bolts between steel plate.
The energy-absorbing buffering steel ring uses waist type structure, and energy-absorbing buffering steel ring both ends are semicircular arc, energy-absorbing buffering steel ring
Middle part is flat segments.
Beneficial effects of the present invention:
The present invention compared with prior art, makes stopping means have energy-absorbing buffering ability, and possess stronger antidetonation energy
Power.The present invention absorbs the energy of earthquake by the tension deformation of energy-absorbing buffering steel ring using energy-absorbing buffering steel ring as dissipative member
Amount, and there is larger impact failure using elastic-plastic deformation caused by energy-absorbing buffering steel ring to limit engineering structure, so as to right
Engineering structure plays a very good protection.
Brief description of the drawings
Fig. 1 is a kind of stopping means (original state) structural representation with energy-absorbing buffering ability of the present invention;
Fig. 2 is A-A sectional views in Fig. 1;
Fig. 3 is a kind of stopping means (free resigning state) structural representation with energy-absorbing buffering ability of the present invention;
Fig. 4 is a kind of stopping means (energy-absorbing buffering state) structural representation with energy-absorbing buffering ability of the present invention;
In figure, 1-energy-absorbing buffering steel ring, 2-upper steel ring limit base, 3-lower steel ring limit base, 4-upper structure part,
5-lower structural features, 6-pedestal, 7-bearing pin, 8-be oriented to steel wheel, 9-upper local strengthening steel plate, 10-lower local strengthening steel
Plate, 11-strengthen anchor pole.
Embodiment
The present invention is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
As shown in figures 1-4, a kind of stopping means with energy-absorbing buffering ability, including energy-absorbing buffering steel ring 1, upper steel ring
Limit base 2 and lower steel ring limit base 3, the upper steel ring limit base 2 are fixedly mounted in upper structure part 4, the lower steel ring limit
Position seat 3 is fixedly mounted on lower structural features 5, identical and symmetrical above and below point of upper steel ring limit base 2 and the structure of lower steel ring limit base 3
Cloth;The upper steel ring limit base 2 includes pedestal 6, bearing pin 7 with lower steel ring limit base 3 and is oriented to steel wheel 8, and the installation of bearing pin 7 is present
On body 6, it is oriented to steel wheel 8 and is sleeved on bearing pin 7, be oriented to steel wheel 8 has rotational freedom relative to bearing pin 7;The upper steel ring limit
It is connected between the guiding steel wheel 8 and the guiding steel wheel 8 of lower steel ring limit base 3 of position seat 2 by energy-absorbing buffering steel ring 1.It is oriented to steel wheel 8
Energy-absorbing buffering steel ring 1 is also prevented to a certain extent stress concentration phenomenon occurs.
Local strengthening steel plate 9 is provided between the pedestal 6 of steel ring limit base 2 and upper structure part 4 on described, in institute
State and lower local strengthening steel plate 10 is provided between the pedestal 6 of lower steel ring limit base 3 and lower structural features 5, the upper local strengthening
Consolidated between steel plate 9 and upper structure part 4, between lower local strengthening steel plate 10 and lower structural features 5 by strengthening the phase of anchor pole 11
Even.
Between the pedestal 6 and upper local strengthening steel plate 9 of the upper steel ring limit base 2, the pedestal 6 of lower steel ring limit base 3 with
Detachable connection structure is used between lower local strengthening steel plate 10.
Between the pedestal 6 and upper local strengthening steel plate 9 of the upper steel ring limit base 2, the pedestal 6 of lower steel ring limit base 3 with
It is connected by screw bolts between lower local strengthening steel plate 10.
The energy-absorbing buffering steel ring 1 uses waist type structure, and the both ends of energy-absorbing buffering steel ring 1 are semicircular arc, energy-absorbing buffering steel
The middle part of circle 1 is flat segments.
, will particularly between upper structure part 4 and lower structural features 5 under ground seismic wave function exemplified by when earthquake occurs
Bear cross shear, cause occur relatively transverse displacement between upper structure part 4 and lower structural features 5, when lateral displacement compared with
Hour, energy-absorbing buffering steel ring 1 can be realized in the case where not deforming upon and freely stepped down, now the energy-absorbing buffering without more renewing
Steel ring 1.When lateral displacement is larger, i.e., the relatively transverse displacement between upper structure part 4 and lower structural features 5 has exceeded
The remained amount of energy-absorbing buffering steel ring 1, energy-absorbing buffering steel ring 1 will be oriented to steel wheels 8 by upper and lower two and pull deformation, in energy-absorbing buffering
In the deformation process of steel ring 1, will constantly it absorb and earthquake energy, and to the relatively horizontal of upper structure part 4 and lower structural features 5
Enter row buffering and limitation to displacement, reduce the earthquake response of upper and lower part structural member, so as to be served very to upper and lower part structural member
Good protection.
After earthquake terminates, upper structure part 4 and lower structural features 5 are saved from damage, but energy-absorbing buffering steel ring 1 is damaged
It is bad, now the bearing pin 7 on upper and lower two pedestals 6 need to only be pulled down, the energy-absorbing buffering steel ring 1 of damage can be pulled down, then change
Upper brand-new energy-absorbing buffering steel ring 1.If upper steel ring limit base 2 and lower steel ring limit base 3 have also damaged, only need to lay down pedestal with
Bolt between local strengthening steel plate, you can by upper and lower two pedestals 6 respectively from upper local strengthening steel plate 9 and lower local strengthening steel
Plate 10 is pulled down, and can replace with brand-new steel ring limit base.Therefore, critical piece of the present invention replacing and installation all very just
Victory, and it is time saving and energy saving.
According to the difference of actual anti-seismic performance, energy-absorbing buffering steel ring 1, pedestal 6, bearing pin 7 and the size for being oriented to steel wheel 8
According to adaptation manufacture is actually needed, to realize the setting to the energy-absorbing buffering ability of stopping means.During specific setting, it is ensured that energy-absorbing
Steel ring 1 is buffered when largest deformation amount occurs, do not reach capacity lateral displacement yet between upper structure part 4 and lower structural features 5
Amount.
Scheme in embodiment and the scope of patent protection for being not used to the limitation present invention, it is all without departing from carried out by the present invention etc.
Effect implements or change, is both contained in the scope of the claims of this case.