CN106300147A - 带有敷设张力监控功能的海缆下水桥 - Google Patents
带有敷设张力监控功能的海缆下水桥 Download PDFInfo
- Publication number
- CN106300147A CN106300147A CN201610726093.5A CN201610726093A CN106300147A CN 106300147 A CN106300147 A CN 106300147A CN 201610726093 A CN201610726093 A CN 201610726093A CN 106300147 A CN106300147 A CN 106300147A
- Authority
- CN
- China
- Prior art keywords
- cable
- bracket
- arc skateboard
- tension force
- control function
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/10—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle in or under water
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
一种带有敷设张力监控功能的海缆下水桥,包括:一托架、安装在托架上的用于海缆下水用的弧形滑板,其中,该弧形滑板的两侧安装有边挡板,弧形滑板的弧度为90度,弧形滑板上设有数个用于确定下水海缆入水角度的刻度;在托架的边上,还安装有一用于实时拍摄记录下水海缆的压线、离线角度摄像头。本发明由于采用上述技术方案,其操作简便,通过置入较详细的基准点,使得观测的角度精度、可靠性大幅提高,不仅解决现行敷缆工艺中,人为目测估计的角度误差较大的问题;而且,还大大降低了生产成本。
Description
技术领域
本发明涉及下水桥,尤其涉及一种带有敷设张力监控功能的海缆下水桥。属于海洋石油工程领域。
背景技术
海缆敷设机具主要包括:海缆容器(Reel/Carousel)、塔架(Gantry/Quadrant/Sheave)、转向弯道(Arch、Diverter)、托辊(Support Roller)、张紧器(Tensioner)、下水桥(Chute)。其中,下水桥的作用如同铺管船上的托管架(Stinger),使海缆的下水绕附设定的弧形轨道平滑地由甲板过渡到水中,防止海缆过度弯曲发生损伤。
海缆敷设工艺与海管敷设工艺大相径庭,安装工程的初期设计阶段,工程师会根据不同海域的工况、工作水深、产品特性、敷缆相关设备的工作性能、能力等,综合考虑各种影响海缆敷设安全的因素,合理的选择作业天气条件,设计出敷设选用的张力(tension)、着床点距离(layback)和入水角度(departure angle),用于作为指导现场施工人员的操作依据。
对于张紧器的操作模式,一般会选用手动恒速式放缆,而非选择敷管恒张力式放缆,其原因是海缆的单位重量比较轻,所需敷设张力较小,铺缆船升降运动产生的加速度力等外力的作用,对小吨位张紧器的恒张力控制功能影响非常大,海缆着床点位置精度没有保障。
对于张紧器的手动恒速放缆模式,其是将张紧器的放缆速度设置为铺缆船的走船速度,此时的敷设张力大小是根据数学悬链线理论、数学方程求解得到的,敷设张力(F)、入水角度(α)、着床点(TDP)三者之间互为对应关系。现场操作中,如果动用水下机器人(ROV)作为水下声学定位系统的载体,对着床点(TDP)进行定位,可以得到海缆的入水角度(α)和入水点的悬挂力(F)数据;同样道理,如果动用角度测量设备测定海缆的入水角度(α),也可以得到着床点(TDP)的位置和入水点的悬挂力(F)数据。
目前,大部分海缆敷设工程是通过控制入水角度这一理论完成的,将海面作为基线参考点,海缆入水角度是海面与海缆的夹角。值班人员依据目测的海缆入水角度,适时调整、增减张紧器的放缆速度。然而,这一比较粗放的测量方法,所得到的入水角度也会因人而异,可靠性较差。
随着海洋工程的发展以及海上结构物安装的标准化、国际规范化,现行的以海面作为参考基线、人为目测、估计入水角度的方法已不能满足国际工程中对敷设张力、入水角度、着床点进行实时监测的“精度”要求。
发明内容
本发明的主要目的在于克服现有技术存在的上述缺点,而提供一种带有敷设张力监控功能的海缆下水桥,其操作简便,通过置入较详细的基准点,使得观测的角度精度、可靠性大幅提高,不仅解决现行敷缆工艺中,人为目测估计的角度误差较大的问题;而且,还大大降低了生产成本。
本发明的目的是由以下技术方案实现的:
一种带有敷设张力监控功能的海缆下水桥,其特征在于:包括:一托架、安装在托架上的用于海缆下水用的弧形滑板,其中,该弧形滑板的两侧安装有边挡板,弧形滑板的弧度为90度,弧形滑板上设有数个用于确定下水海缆入水角度的刻度;在托架的边上,还安装有一用于实时拍摄记录下水海缆的压线、离线角度摄像头。
所述托架的底部安装工字钢架,用于舷边的安装固定。
所述弧形滑板的底部为双层底板,双层底板之间安装有数个加强筋;弧形滑板的加工半径为2.5m米。
所述边挡板的四周边沿、出入口边沿采用焊接方式安装有圆管;边档板的高度为0.4m,上窄口宽为0.5m,下宽口宽为1m。
本发明的有益效果:本发明由于采用上述技术方案,其操作简便,通过置入较详细的基准点,使得观测的角度精度、可靠性大幅提高,不仅解决现行敷缆工艺中,人为目测估计的角度误差较大的问题;而且,还大大降低了生产成本。
附图说明
图1为本发明结构示意图。
图2为本发明结构侧视示意图。
图3为本发明结构主视示意图。
图中主要标号说明:
1.托架,2.边挡板、3.双层底板,4.加强筋;5.圆管,6.弧长、7.入水角度的点位、8.下水海缆、9.入水角度标示线。
具体实施方式
如图1—图3所示,本发明包括:托架1、采用焊接方式安装在托架1上的用于海缆下水用的弧形滑板,其中,弧形滑板的两侧采用焊接方式安装有边挡板2,弧形滑板的弧度为90度,弧形滑板上设有数个设有数个用于确定下水海缆8入水角度刻度;在托架1的边上,还安装有一摄像头,用于实时拍摄记录下水海缆的压线、离线角度。
上述托架1的底部采用焊接方式安装工字钢架,用于舷边的安装固定。
上述弧形滑板的底部为双层底板3,双层底板3之间采用焊接方式安装有数个加强筋4;弧形滑板的加工半径为2.5m米。
如图2,图3所示,弧形滑板的角度线标示方法:把本发明水平放在地面上,将弧形滑板的弧长6平分18等份,每份弧长6约等于0.218m,以上窄口为测量起始点零点位,弧长6的2.18m对应50度、弧长的2.4m对应55度、依次用软尺绕弧测量确定入水角度的点位7,横向画线平行于下水桥的端口面,线的端点直到两边的边挡板2,线的宽度为2cm,并在横线的中间置入水角度标示线9的数字为:50、55、60、65、70、75、80、85、90。
上述边挡板2的四周边沿、出入口边沿采用焊接方式安装有圆管5;边档板2的高度为0.4m,上窄口宽为0.5m,下宽口宽为1m。
在敷缆过程中,张紧器操作员,可根据观测到的入水角度标示线9的数字,适时增减张紧器的放缆速度。
上述托架1,边挡板2、双层底板3,加强筋4;圆管5均为钢材;摄像头为现有技术故不再赘述。
以上所述,仅是本发明的较佳实施例而已,并非对本发明作任何形式上的限制,凡是依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。
Claims (4)
1.一种带有敷设张力监控功能的海缆下水桥,其特征在于:包括:一托架、安装在托架上的用于海缆下水用的弧形滑板,其中,该弧形滑板的两侧安装有边挡板,弧形滑板的弧度为90度,弧形滑板上设有数个用于确定下水海缆入水角度的刻度;在托架的边上,还安装有一用于实时拍摄记录下水海缆的压线、离线角度摄像头。
2.根据权利要求1所述的带有敷设张力监控功能的海缆下水桥,其特征在于:所述托架的底部安装工字钢架,用于舷边的安装固定。
3.根据权利要求1所述的带有敷设张力监控功能的海缆下水桥,其特征在于:所述弧形滑板的底部为双层底板,双层底板之间安装有数个加强筋;弧形滑板的加工半径为2.5m米。
4.根据权利要求1所述的带有敷设张力监控功能的海缆下水桥,其特征在于:所述边挡板的四周边沿、出入口边沿采用焊接方式安装有圆管;边档板的高度为0.4m,上窄口宽为0.5m,下宽口宽为1m。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610726093.5A CN106300147B (zh) | 2016-08-25 | 2016-08-25 | 带有敷设张力监控功能的海缆下水桥 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610726093.5A CN106300147B (zh) | 2016-08-25 | 2016-08-25 | 带有敷设张力监控功能的海缆下水桥 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106300147A true CN106300147A (zh) | 2017-01-04 |
CN106300147B CN106300147B (zh) | 2018-04-20 |
Family
ID=57616372
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610726093.5A Active CN106300147B (zh) | 2016-08-25 | 2016-08-25 | 带有敷设张力监控功能的海缆下水桥 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106300147B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR3079081A1 (fr) * | 2018-03-19 | 2019-09-20 | Naval Energies | Connecteur de raccordement de cables sous-marins et notamment de cables ombilicaux pour des fermes d'energie marine renouvelable |
CN116598959A (zh) * | 2023-07-13 | 2023-08-15 | 中天科技集团海洋工程有限公司 | 一种海缆上缆及铺设系统 |
CN118654797A (zh) * | 2024-08-20 | 2024-09-17 | 上海建工集团股份有限公司 | 一种敷设施工中海缆张力测量方法及装置 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2546491B1 (de) * | 1975-10-17 | 1977-03-03 | Richard Weiss | Verfahren und vorrichtung zum begradigen von nach dem vorpressverfahren hergestellten stollen und kanaelen |
CN202221881U (zh) * | 2011-09-09 | 2012-05-16 | 中国海洋石油总公司 | 油井井口电缆用角度可调电缆导向装置 |
CN103043428A (zh) * | 2012-12-13 | 2013-04-17 | 江西洪都航空工业集团有限责任公司 | 一种自驱动精密导轨式型架精确定位推运装置 |
CN203553802U (zh) * | 2013-11-18 | 2014-04-16 | 广州广船国际股份有限公司 | 一种船用电缆托架 |
CN104981396A (zh) * | 2013-02-13 | 2015-10-14 | 张英柱 | 使用浸没式浮桥的系泊装置 |
-
2016
- 2016-08-25 CN CN201610726093.5A patent/CN106300147B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2546491B1 (de) * | 1975-10-17 | 1977-03-03 | Richard Weiss | Verfahren und vorrichtung zum begradigen von nach dem vorpressverfahren hergestellten stollen und kanaelen |
CN202221881U (zh) * | 2011-09-09 | 2012-05-16 | 中国海洋石油总公司 | 油井井口电缆用角度可调电缆导向装置 |
CN103043428A (zh) * | 2012-12-13 | 2013-04-17 | 江西洪都航空工业集团有限责任公司 | 一种自驱动精密导轨式型架精确定位推运装置 |
CN104981396A (zh) * | 2013-02-13 | 2015-10-14 | 张英柱 | 使用浸没式浮桥的系泊装置 |
CN203553802U (zh) * | 2013-11-18 | 2014-04-16 | 广州广船国际股份有限公司 | 一种船用电缆托架 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR3079081A1 (fr) * | 2018-03-19 | 2019-09-20 | Naval Energies | Connecteur de raccordement de cables sous-marins et notamment de cables ombilicaux pour des fermes d'energie marine renouvelable |
WO2019179986A1 (fr) * | 2018-03-19 | 2019-09-26 | Naval Energies | Connecteur de raccordement de câbles sous-marins et notamment de câbles ombilicaux pour des fermes d'énergie marine renouvelable |
US11677180B2 (en) | 2018-03-19 | 2023-06-13 | Naval Energies | Connector for connecting together underwater cables and in particular umbilical cables for renewable marine energy farms |
CN116598959A (zh) * | 2023-07-13 | 2023-08-15 | 中天科技集团海洋工程有限公司 | 一种海缆上缆及铺设系统 |
CN116598959B (zh) * | 2023-07-13 | 2023-09-15 | 中天科技集团海洋工程有限公司 | 一种海缆上缆及铺设系统 |
CN118654797A (zh) * | 2024-08-20 | 2024-09-17 | 上海建工集团股份有限公司 | 一种敷设施工中海缆张力测量方法及装置 |
Also Published As
Publication number | Publication date |
---|---|
CN106300147B (zh) | 2018-04-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2022519559A (ja) | 杭打ち船、並びにその姿勢調整、測位制御及び杭打ち方法 | |
CN104696588B (zh) | 深水海底管线起始铺设的方法 | |
US20140284296A1 (en) | Vessel and crane with full dynamic compensation for vessel and wave motions and a control method thereof | |
CN106300147A (zh) | 带有敷设张力监控功能的海缆下水桥 | |
CN202928548U (zh) | 护底软体排水下定位检测系统 | |
US10435865B2 (en) | Trenching assembly for laying in a trench a continuous pipeline and trenching method | |
CN103439130B (zh) | 模拟钢悬链线立管与海床动力耦合的装置及方法 | |
BR112013001087B1 (pt) | dispositivo para despejar material em um fundo ou instalação sob a água | |
CN104762973B (zh) | 一种深水抛石高程控制系统 | |
CN104696589B (zh) | 深水海底管线终止铺设的方法 | |
CN212772503U (zh) | 一种沉箱安装双gps测量定位装置 | |
US10378331B2 (en) | Monitoring integrity of a riser pipe network | |
CN105464049A (zh) | 深水抛填船实时测控验收系统及施工方法 | |
CN101588031A (zh) | 一种电缆敷设与打捞整合方法 | |
US11280174B2 (en) | System and method for determining the shape and position of an underwater riser | |
US10941636B2 (en) | Drilling or work-over rig comprising an operational control and/or state unit and a computer-implemented method of providing operational control and/or state | |
CN102953366B (zh) | 浅海区域沉浮式水工建筑物地基监测装置 | |
CN107084784A (zh) | 一种移动式可升降四体船型水下测量平台 | |
CN109398615B (zh) | 一种浮标用沉块的深海布放方法 | |
CN109178203B (zh) | 一种浮托安装实测的船体姿态校准方法 | |
CN116161172A (zh) | 一种组合式混凝土锚碇海上施工方法 | |
KR20100003448A (ko) | 해저 케이블 포설공법 및 이에 사용되는 탐지기 | |
CN203111485U (zh) | 一种用于内河航道整治施工测量的扫床架 | |
KR20230126349A (ko) | 장력제어 및 IoT 데이터 분석 가능한 해저케이블 자동 포설용 케이블 텐셔너 | |
CN117074068B (zh) | 一种海底电缆抢修打捞回放过程试验装置及方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee after: Offshore Oil Engineering Co., Ltd. Patentee after: China Offshore Oil Group Co., Ltd. Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee before: Offshore Oil Engineering Co., Ltd. Patentee before: China National Offshore Oil Corporation |
|