CN106285186A CN201610841790.5A CN201610841790A CN106285186A CN 106285186 A CN106285186 A CN 106285186A CN 201610841790 A CN201610841790 A CN 201610841790A CN 106285186 A CN106285186 A CN 106285186A
Authority
CN
China
Prior art keywords
air
main body
film main
tube wall
air film
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610841790.5A
Other languages
Chinese (zh)
Other versions
CN106285186B (en
Inventor
薛飞龙
张辉
肖龙
王秦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Bodewei Technology Co ltd
Original Assignee
Shenzhen Braodwell Environment Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Braodwell Environment Protection Technology Co Ltd filed Critical Shenzhen Braodwell Environment Protection Technology Co Ltd
Priority to CN201610841790.5A priority Critical patent/CN106285186B/en
Publication of CN106285186A publication Critical patent/CN106285186A/en
Priority to PCT/CN2017/102637 priority patent/WO2018054318A1/en
Application granted granted Critical
Publication of CN106285186B publication Critical patent/CN106285186B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H15/00Tents or canopies, in general
    • E04H15/20Tents or canopies, in general inflatable, e.g. shaped, strengthened or supported by fluid pressure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H15/00Tents or canopies, in general
    • E04H15/20Tents or canopies, in general inflatable, e.g. shaped, strengthened or supported by fluid pressure
    • E04H2015/206Details of inflation devices, e.g. valves, connections to fluid pressure source

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Tents Or Canopies (AREA)
  • Duct Arrangements (AREA)
  • Ventilation (AREA)

Abstract

The present invention relates to a kind of pneumatic membrane building and interior ventilation duct structure thereof, pneumatic membrane building also includes air film main body, air inlet is offered in air film main body, interior ventilation duct structure includes tube wall, tube wall is arranged at ventilation shaft in the inner side of air film main body, tube wall and air film main body are collectively forming, and air film main body offers air inlet, the air that blower fan is sent is entered in interior ventilation shaft by air inlet, and on tube wall, the position away from bottom offers venthole.During blower fan work, the air that blower fan is sent blows in the interior ventilation shaft that air film main body and tube wall are collectively forming by air supply duct structure, on tube wall, the position away from bottom offers venthole, therefore air quantity is filled into air film body interior by venthole, the position height of venthole is higher, therefore can avoid the activity of personnel bottom impact, and venthole is arranged to multiple, multiple ventholes interval is arranged, and therefore can avoid the problem that local velocity is too high.

Description

Pneumatic membrane building and interior ventilation duct structure thereof
Technical field
The present invention relates to pneumatic membrane building technical field, particularly relate to a kind of pneumatic membrane building and interior ventilation duct structure thereof.
Background technology
Pneumatic membrane building is to do shell with special building film material, by blower fan to air film inner inflatable, makes profile in air film Pressure differential is become to maintain stable shape.Pneumatic membrane building with its low cost, quickly, be easy to dismounting, the feature such as light gets more and more Apply to all trades and professions.
Pneumatic membrane building is to air film inner inflatable by separate ventilation pipeline.Traditional pneumatic membrane building, directly fills in air film During gas, easily have influence on the activity of bottom personnel, air velocity near gas outlet can be caused too high, uneven, it is impossible to meet one A little certain applications, the Badminton Stadium such as competed, air velocity is required the highest.
Summary of the invention
Based on this, it is necessary to for above-mentioned technical problem, it is provided that one can avoid personnel activity and avoiding bottom impact Pneumatic membrane building that local velocity is too high and interior ventilation duct structure thereof.
A kind of interior ventilation duct structure of pneumatic membrane building, including:
Tube wall, is arranged at ventilation shaft in the inner side of air film main body, described tube wall and described air film main body are collectively forming, Offering air inlet in described air film main body, the air that blower fan is sent enters in described interior ventilation shaft by described air inlet, On described tube wall, the position away from bottom offers multiple spaced venthole.
Wherein in an embodiment, described tube wall is welded in the inner side of described air film main body.
Wherein in an embodiment, described tube wall sets out pore at bottom 3~4 meters.
Wherein in an embodiment, multiple described ventholes are uniformly distributed on described tube wall.
Wherein in an embodiment, the diameter range of described venthole is 2-5cm.
Wherein in an embodiment, described tube wall being further opened with interface, described interface is used for installing outer air duct.
A kind of pneumatic membrane building, including:
Air film main body, offers air inlet;And
Interior ventilation duct structure as described in any of the above one, described tube wall is arranged at inside described air film main body.
Wherein in an embodiment, also include that air supply duct structure, described air supply duct structure include being flexible coupling, blowing Pipe and support, described in be flexible coupling and be arranged at the outside of described air film main body, described in be flexible coupling by described air inlet and described gas Film body interior is connected, and described ajutage is scalable, one end of described ajutage with described be flexible coupling be connected.
Wherein in an embodiment, also include that blower fan, the other end of described ajutage are connected with blower fan.
Wherein in an embodiment, described in be flexible coupling and be welded in the outside of described air film main body.
Above-mentioned pneumatic membrane building and interior ventilation duct structure thereof at least have the advantage that
During blower fan work, the air that blower fan is sent blows to what air film main body and tube wall were collectively forming by air supply duct structure In interior ventilation shaft, on tube wall, the position away from bottom offers venthole, and therefore air quantity is filled into air film master by venthole Internal portion, the position height of venthole is higher, therefore can avoid the activity of personnel bottom impact, and venthole is arranged to many Individual, multiple ventholes interval is arranged, and therefore can avoid the problem that local velocity is too high.
Accompanying drawing explanation
Fig. 1 is the side sectional view of the pneumatic membrane building in an embodiment;
Fig. 2 is the partial schematic diagram of pneumatic membrane building shown in Fig. 1;
Fig. 3 is the structural representation of telescopic ajutage in Fig. 2;
Fig. 4 is the structural representation at another visual angle of pneumatic membrane building shown in Fig. 2;
Fig. 5 is the structural representation after pneumatic membrane building shown in Fig. 2 arranges external air duct structure;
Fig. 6 is the schematic diagram at another visual angle of local in Fig. 5.
Detailed description of the invention
Understandable, below in conjunction with the accompanying drawings to the present invention for enabling the above-mentioned purpose of the present invention, feature and advantage to become apparent from Detailed description of the invention be described in detail.Elaborate a lot of detail in the following description so that fully understanding this Bright.But the present invention can implement to be much different from alternate manner described here, and those skilled in the art can be not Doing similar improvement in the case of running counter to intension of the present invention, therefore the present invention is not limited by following public being embodied as.
It should be noted that when element is referred to as " being fixed on " another element, and it can be directly on another element Or element placed in the middle can also be there is.When an element is considered as " connection " another element, and it can be to be directly connected to To another element or may be simultaneously present centering elements.Term as used herein " vertical ", " level ", " left ", For illustrative purposes only, being not offered as is unique embodiment for " right " and similar statement.
Unless otherwise defined, all of technology used herein and scientific terminology and the technical field belonging to the present invention The implication that technical staff is generally understood that is identical.The term used the most in the description of the invention is intended merely to describe tool The purpose of the embodiment of body, it is not intended that in limiting the present invention.Each technical characteristic of embodiment described above can be carried out arbitrarily Combination, for making description succinct, all possible combination of each technical characteristic in above-described embodiment is not all described, so And, as long as the combination of these technical characteristics does not exist contradiction, all it is considered to be the scope that this specification is recorded.
See also Fig. 1, Fig. 2, Fig. 4 and Fig. 5, be the pneumatic membrane building 10 in an embodiment.This pneumatic membrane building 10 can For fair, exhibition, it is also possible to as industrial premises, storage workshop, be also used as Badminton Stadium etc..Specifically Ground, this pneumatic membrane building 10 includes blower fan 100, air film main body 200, air supply duct structure 300, interior ventilation duct structure 400 and outer Air duct structure 500.
Blower fan 100 is for inflating in air film main body 200.Certainly, in other embodiments, pneumatic membrane building 10 also may be used Not carry blower fan 100, and by the way of external, now blower fan 100 can not together with pneumatic membrane building 10 complete production or/pin Sell.
Offering air inlet 210 in air film main body 200, the air that blower fan is sent is filled with air film main body by air inlet 210 In 200.Air film main body 200 is prepared from by special building film material, utilizes inner and outer air pressure difference to support whole pneumatic membrane building 10. When needing to strut air film main body 200, constantly it is passed through air by blower fan 100 internal to air film main body 200.Air film main body 200 Inner surface be provided with heat-insulation layer (not shown), heat-insulation layer is made up of insulation material, can improve the heat insulating ability of pneumatic membrane building 10 Energy.
Air supply duct structure 300 includes telescopic ajutage 310, support 320, snap ring (not shown) and is flexible coupling 330. Telescopic ajutage 310 side of resting on the ground, therefore builds underground air passage without passing through to dig on the ground.
Seeing also Fig. 3, the material of ajutage 310 is bubble-tight.One end of ajutage 310 is connected with blower fan 100 Logical.Specific in present embodiment, the air outlet of blower fan 100 is located at by flange sleeve in one end of ajutage 310, by flange pair Connect and be axially fixed ajutage 310.Sealing gasket (not shown) can also be set between ajutage 310 and blower fan 100, and close The joint of vehicle-mounted flange on packing, and compress with pressing plate and realize sealing, close with increase between ajutage 310 and blower fan 100 Sealing property.
Certainly, in other embodiments, one end of ajutage can also be arranged at the air outlet of blower fan by clip, Clip is that to be enclosed within the outside of ajutage radially secure.Being socketed for clip, sealing gasket is at ajutage inwall and in combination Sealing outer wall annular seal ring.
Being provided with heat-insulation layer 311 on ajutage 310, heat-insulation layer 311 is made up of insulation material, can improve ajutage 310 Heat-insulating property, lose too many heat when preventing from being passed through hot blast, or when preventing from being passed through cold wind, absorb too many heat.
Specifically, ajutage 310 is cylindrical shape, and therefore the blast of all directions is uniform, and columnar structured saving material, Comprcssive strength is big.The air-out of blower fan 100 when the length of ajutage 310 is greater than or does not blows afloat slightly larger than air film main body 200 Mouthful to be flexible coupling 330 center between distance.It is in order at pneumatic membrane building 10 by the longer of length setting of ajutage 310 The when of the most not blowing afloat, ajutage 310 length can reach the position of air film main body 200, just compression when of blowing afloat To the normal length used.
Support 320 is used for supporting ajutage 310.Specifically, support 320 can with rustless steel square tube or angle steel make with The structure that ajutage 310 matches.Being provided with arc groove on support 320, the outside of ajutage 310 matches with arc groove Close, form the structure that ajutage 310 matches with support 320.When blower fan 100 works, ajutage 310 compresses, will with support 320 After ajutage 310 supports, telescopic ajutage 310 can be avoided to bend, affect after ajutage 310 bending can be avoided and send Wind.
Specifically, the height of support 320 is gradually increased along the direction near air film main body 200, to coordinate ajutage 310 to exist State during ventilation, prevents ajutage 310 from bending.
When will be in the environment of outdoor application and outdoor wind be relatively big, it is also possible to the outer peripheral edge card at ajutage 310 sets snap ring, Snap ring is fixed on support 320 again.Such as, snap ring is screwed on support 320.The diameter of snap ring is more than ajutage The diameter of 310.
Be flexible coupling 330 one end be arranged in air film main body 200, being flexible coupling 330 internal with air film main body 200 is connected. The other end of ajutage 310 330 is connected with being flexible coupling.Such as, it is flexible coupling and 330 is arranged on air film main body 200 and offers air intake At mouthfuls 210, it is internal that the air quantity come in from ajutage 310 enters air film main body 200 through being flexible coupling after 330 by air inlet 210.
Specifically, be flexible coupling 330 one end be welded in the outside of air film main body 200, be flexible coupling 330 the other end be welded in On ajutage 310.After pneumatic membrane building 10 molding, air film main body 200 possesses certain degree of hardness, in the case of atrocious weather (such as strong wind or heavy snow weather), air film main body 200 can produce swing or deformation.And being flexible coupling 330 is deformable, at air film When main body 200 swings, ajutage 310 and air film master when 330 deformation that are flexible coupling can absorb these displacements thus reduce swing The local stress that body 200 junction produces, protects air film main body 200.Be flexible coupling 330 inner surface be also equipped with heat-insulation layer, protect Temperature layer is made up of insulation material, can increase heat-insulating property.
Above-mentioned air supply duct structure 300 at least has the advantage that
The air that blower fan 100 is sent by telescopic ajutage 310, again through being flexible coupling 330, after air inlet 210 logical Enter air film main body 200 internal, maintain stable shape in air film main body 200 after inflation, owing to ajutage 310 rest on the ground Side, therefore without building underground air passage, also to realize the quick and convenient air film main body 200 that is inflated to internal, advantageously reduces construction difficulty Degree, also reduces construction cost and duration.And by arranging support 320 and snap ring, snap ring is arranged in outside ajutage 310 Periphery, for limiting the radial displacement of ajutage 310, but ajutage 310 can be axially retractable, therefore can be prevented effectively from and send Airduct 310 bends, thus avoids affecting air output and blast.
Interior ventilation duct structure 400 includes that tube wall 410, tube wall 410 are arranged at the inner side of air film main body 200.Tube wall 410 with Air film main body 200 be collectively forming one in ventilating duct 201, at this moment from 330 air quantity entered through air inlet 210 that are flexible coupling interior logical In air channel 201.On tube wall 410, the position away from bottom offers venthole 411, and the air quantity in interior ventilating duct 201 is again through going out It is internal that pore 411 enters air film main body 200.
Specifically, tube wall 410 is arranged at the inner side of air film main body 200 by the way of welding, is therefore possible not only to increase Tube wall 410 and the fastness of air film main body 200, it is also possible to increase the sealing between tube wall 410 and air film main body 200.
Specifically, tube wall 410 starts to set out pore 411 at bottom 3~4 meters, and therefore the position of venthole 411 is offered More much higher than the height of the personnel of air film main body 200 activity, thus without the activity affecting personnel.
The quantity of venthole 411 is multiple, and multiple ventholes 411 are spaced on tube wall 410.Specifically, multiple go out Pore 411 is uniformly distributed on tube wall 410.Therefore, the air quantity entered within air film main body 200 by venthole 411 is also compared Uniformly.The diameter range of venthole is 2~5cm.
Specific in present embodiment, tube wall 410 being further opened with interface 412, interface 412 is used for installing outer air duct.
In above-mentioned gas, ventilation duct structure 400 at least has the advantage that
When blower fan 100 works, the air that blower fan 100 is sent blows to air film main body 200 and pipe by air supply duct structure 300 In interior ventilation duct 310 road that wall 410 is collectively forming, on tube wall 410, the position away from bottom offers venthole 411, therefore wind Measuring and be filled into air film main body 200 inside by venthole 411, the position height of venthole 411 is higher, therefore can avoid impact The activity of bottom personnel.And being arranged to of venthole 411 is multiple, multiple ventholes 411 interval is arranged, and therefore can avoid office The problem that portion's flow velocity is too high.
External air duct structure 500 includes outer air duct 510, joint 520, suspender belt 530 and the gimbal lever 540.Outer air duct 510 One end be connected with the interface 412 on tube wall 410.Specifically, one end of outer air duct 510 is by joint 520 and interface 412 Being connected, joint 520 is arranged on the interface 412 on tube wall 410.Such as, one end of air duct 510 and joint 520 are by weldering The mode connect connects.The periphery of outer air duct 510 offers airduct pore 511.The other end of outer air duct 510 can be out Mouthful, it is also possible to it is to close, or offers multiple airduct pore 511 again on the end closed.
Certainly, in other embodiments, it is also possible to directly draw in an independent wind from the outside of air film main body Pipe, connects on outer air duct in the present embodiment, is filled with air by this outside air duct of independent airduct.
Outer air duct 510 is suspended in air film main body 200.Specifically, suspender belt is set by the periphery of air duct 510 outside 530, suspension centre 220 is set inside air film main body 200, one end of suspender belt 530 is connected with outer air duct 510, the other end of suspender belt 530 Being connected with suspension centre 220, outer air duct 510 is arranged on the suspension centre 220 inside air film main body 200 by suspender belt 530.
The quantity of suspender belt 530 is multiple, and multiple suspender belt 530 parallel interval are arranged on outer air duct 510, each to disperse The weight that suspender belt 530 is born.
Seeing also Fig. 6, specifically, one end of suspender belt 530 is by being connected with the gimbal lever 540, and the gimbal lever 540 is again with outward Air duct 510 is connected.Such as, external air duct structure also includes that slide block 550 and suspension rod 560, the gimbal lever 540 are hollow structure, and The bottom of the gimbal lever 540 offers guide groove 541.Slide block 550 can move along the bottom of the gimbal lever 540, and one end of suspension rod 560 is arranged On slide block 550, the other end of suspension rod 560 is arranged on outer air duct 510.Specifically, slide block can be pulley or roller.
Specifically, external air duct structure 500 also includes suspension ring 570, withholds 580 and connector 590, another of suspension rod 560 End is arranged on suspension ring 570, withholds 580 and is buckled on suspension ring 570, withholds 580 and be arranged on connector 590, and connector 590 is direct It is arranged on outer air duct 510.Therefore, outer air duct 510 can be by withholding 580 Convenient buttons on suspension ring 570.
Above-mentioned outer air duct 510 structure 500 at least has the advantage that
The air that blower fan 100 is sent is after air inlet 210 enters in interior ventilation duct 310 road, and a part is from from tube wall 410 Venthole 411 to enter air film main body 200 internal, a part enters in outer air duct 510 by the interface 412 on tube wall 410, Again by the airduct pore 511 of outer air duct 510 periphery, wind is delivered to other region within air film main body 200, make to be charged into Hot blast or cold wind are evenly distributed to the regional within air film main body 200.
Embodiment described above only have expressed the several embodiments of the present invention, and it describes more concrete and detailed, but also Can not therefore be construed as limiting the scope of the patent.It should be pointed out that, come for those of ordinary skill in the art Saying, without departing from the inventive concept of the premise, it is also possible to make some deformation and improvement, these broadly fall into the protection of the present invention Scope.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (10)

1. the interior ventilation duct structure of a pneumatic membrane building, it is characterised in that including:
Tube wall, is arranged at ventilation shaft in the inner side of air film main body, described tube wall and described air film main body are collectively forming, described Offering air inlet in air film main body, the air that blower fan is sent enters in described interior ventilation shaft by described air inlet, described On tube wall, the position away from bottom offers multiple spaced venthole.
Interior ventilation duct structure the most according to claim 1, it is characterised in that described tube wall is welded in described air film main body Inner side.
Interior ventilation duct structure the most according to claim 1, it is characterised in that described tube wall is offered at bottom 3~4 meters Venthole.
Interior ventilation duct structure the most according to claim 1, it is characterised in that multiple described ventholes are uniformly distributed in institute State on tube wall.
Interior ventilation duct structure the most according to claim 1, it is characterised in that the diameter range of described venthole is 2- 5cm。
Interior ventilation duct structure the most according to claim 1, it is characterised in that be further opened with interface, institute on described tube wall State interface for installing outer air duct.
7. a pneumatic membrane building, it is characterised in that including:
Air film main body, offers air inlet;And
Interior ventilation duct structure as described in any one in claim 1 to 6, described tube wall is arranged in described air film main body Side.
The most according to claim 7, pneumatic membrane building, it is characterised in that also include air supply duct structure, described air supply duct is tied Structure includes being flexible coupling, ajutage and support, described in be flexible coupling and be arranged at the outside of described air film main body, described in be flexible coupling by institute Stating air inlet to be connected with described air film body interior, described ajutage is scalable, one end of described ajutage and described soft company Connect and be connected.
Pneumatic membrane building the most according to claim 8, it is characterised in that also include blower fan, the other end of described ajutage and wind Machine is connected.
Pneumatic membrane building the most according to claim 8, it is characterised in that described in be flexible coupling and be welded in outside described air film main body Side.
CN201610841790.5A 2016-09-22 2016-09-22 Pneumatic membrane building and its interior ventilation duct structure Active CN106285186B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610841790.5A CN106285186B (en) 2016-09-22 2016-09-22 Pneumatic membrane building and its interior ventilation duct structure
PCT/CN2017/102637 WO2018054318A1 (en) 2016-09-22 2017-09-21 Air-supported membrane structure and internal ventilation duct for same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610841790.5A CN106285186B (en) 2016-09-22 2016-09-22 Pneumatic membrane building and its interior ventilation duct structure

Publications (2)

Publication Number Publication Date
CN106285186A true CN106285186A (en) 2017-01-04
CN106285186B CN106285186B (en) 2019-01-22

Family

ID=57712263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610841790.5A Active CN106285186B (en) 2016-09-22 2016-09-22 Pneumatic membrane building and its interior ventilation duct structure

Country Status (2)

Country Link
CN (1) CN106285186B (en)
WO (1) WO2018054318A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190856A (en) * 2017-02-22 2017-09-22 深圳市中德膜结构有限公司 Pneumatic membrane building exhaust apparatus
WO2018054318A1 (en) * 2016-09-22 2018-03-29 深圳市博德维环境技术股份有限公司 Air-supported membrane structure and internal ventilation duct for same
WO2021207995A1 (en) * 2020-04-16 2021-10-21 上海易托邦建筑科技有限公司 Virus detection laboratory with inflatable membrane structure, biosafety laboratory, and virus detection laboratory with earth-sheltered structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2126242B2 (en) * 1971-05-26 1974-05-09 L. Stromeyer & Co Gmbh, 7750 Konstanz
CN202902513U (en) * 2012-10-12 2013-04-24 西安工程大学 Laminar flow ventilation type evaporative cooling air conditioning system
CN103572833A (en) * 2012-07-19 2014-02-12 深圳市博德维建筑技术有限公司 Pressure relief device for air film building
CN105241044A (en) * 2015-11-11 2016-01-13 深圳市博德维环境技术股份有限公司 Combined air flue applied to air membrane building and air membrane building
CN105804249A (en) * 2016-05-13 2016-07-27 华电郑州机械设计研究院有限公司 Solar fabric architecture with auxiliary power system
CN105849343A (en) * 2013-10-24 2016-08-10 霍特波德瑜伽有限公司 Inflatable Exercise Chamber
CN205540161U (en) * 2016-01-27 2016-08-31 郑州市卧龙游乐设备有限公司 Double -deck air film building monitored control system
CN206190001U (en) * 2016-09-22 2017-05-24 深圳市博德维环境技术股份有限公司 Air film building and interior air pipe structure thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1127956A1 (en) * 1983-06-29 1984-12-07 Войсковая Часть 44526 Inflatable structure
JP2012246740A (en) * 2011-05-26 2012-12-13 Toshio Hagiwara Air dome for planetarium
CN205242621U (en) * 2015-11-11 2016-05-18 深圳市博德维环境技术股份有限公司 Air film building and exhaust apparatus
CN205536357U (en) * 2016-01-22 2016-08-31 成都市旭泰仓储设备有限公司 Grain depot ventilation system
CN106285186B (en) * 2016-09-22 2019-01-22 深圳市博德维环境技术股份有限公司 Pneumatic membrane building and its interior ventilation duct structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2126242B2 (en) * 1971-05-26 1974-05-09 L. Stromeyer & Co Gmbh, 7750 Konstanz
CN103572833A (en) * 2012-07-19 2014-02-12 深圳市博德维建筑技术有限公司 Pressure relief device for air film building
CN202902513U (en) * 2012-10-12 2013-04-24 西安工程大学 Laminar flow ventilation type evaporative cooling air conditioning system
CN105849343A (en) * 2013-10-24 2016-08-10 霍特波德瑜伽有限公司 Inflatable Exercise Chamber
CN105241044A (en) * 2015-11-11 2016-01-13 深圳市博德维环境技术股份有限公司 Combined air flue applied to air membrane building and air membrane building
CN205540161U (en) * 2016-01-27 2016-08-31 郑州市卧龙游乐设备有限公司 Double -deck air film building monitored control system
CN105804249A (en) * 2016-05-13 2016-07-27 华电郑州机械设计研究院有限公司 Solar fabric architecture with auxiliary power system
CN206190001U (en) * 2016-09-22 2017-05-24 深圳市博德维环境技术股份有限公司 Air film building and interior air pipe structure thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018054318A1 (en) * 2016-09-22 2018-03-29 深圳市博德维环境技术股份有限公司 Air-supported membrane structure and internal ventilation duct for same
CN107190856A (en) * 2017-02-22 2017-09-22 深圳市中德膜结构有限公司 Pneumatic membrane building exhaust apparatus
CN107190856B (en) * 2017-02-22 2023-06-20 中成空间(深圳)智能技术有限公司 Air film building exhaust device
WO2021207995A1 (en) * 2020-04-16 2021-10-21 上海易托邦建筑科技有限公司 Virus detection laboratory with inflatable membrane structure, biosafety laboratory, and virus detection laboratory with earth-sheltered structure

Also Published As

Publication number Publication date
WO2018054318A1 (en) 2018-03-29
CN106285186B (en) 2019-01-22

Similar Documents

Publication Publication Date Title
CN106284666A (en) Pneumatic membrane building and air supply duct structure thereof
CN106285186A (en) Pneumatic membrane building and interior ventilation duct structure thereof
CN108729949B (en) Rapid sealing device for underground communication roadway and using method thereof
CN106437284A (en) Air film building and externally connected air pipe structure thereof
CN206190000U (en) Air film building and outer air pipe structure thereof
CN202898445U (en) Combined brick structure for inlet and outlet pipe orifice of hot-blast stove
US1884477A (en) Vibration dampener
CN101775957A (en) Sealing device used for access door of air conditioning cabinet and access door of air conditioning cabinet
CN206190001U (en) Air film building and interior air pipe structure thereof
CN206554258U (en) Pneumatic membrane building and its air supply duct structure
CN203785214U (en) IRR (internal retention ring) fabric air duct system
CN202216358U (en) Ventilation structure of air inflation film building
CN206197692U (en) Inflatable packer
CN205444357U (en) Take vapour -pressure type pipeline dredging device of gasbag
CN203977973U (en) The combined type air film structure of inflation film building
CN209354773U (en) Pipeline wears case flexible gland
CN204043148U (en) Adjustable Ball shape nozzle
CN203035220U (en) Plastic-coated cloth thermal-insulation wind cylinder
CN106705333A (en) Air circulation device for air structure
CN201865405U (en) Inflatable framework of tent
CN205618823U (en) Double bracing formula elastic supporting tube card mechanism
CN207298230U (en) A kind of building heating pipeline
CN207145334U (en) A kind of deflector
CN214616623U (en) Mine outburst-prevention air door air duct reverse partition device
CN206203333U (en) For the transmission line of stabilization transmission bottle

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 518000 b1-603, building B, Kexing Science Park, 15 Keyuan Road, Science Park community, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: BROADWELL (SHENZHEN) TECHNOLOGY Co.,Ltd.

Address before: 518000 Guangdong science and Technology Park, Shenzhen, Nanshan District, science and Technology Park, 15 Kexing Science Park, 2 B unit 12, 3

Patentee before: BROADWELL (SHENZHEN) TECHNOLOGY Co.,Ltd.

CP02 Change in the address of a patent holder
CP03 Change of name, title or address

Address after: 518000, 2002, Building B, Smart Plaza, No. 4068 Qiaoxiang Road, Gaofa Community, Shahe Street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: Shenzhen Bodewei Technology Co.,Ltd.

Country or region after: China

Address before: 518000 b1-603, building B, Kexing Science Park, 15 Keyuan Road, Science Park community, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: BROADWELL (SHENZHEN) TECHNOLOGY Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address