CN106285018A - Pressing article, drip installation exercise method - Google Patents
Pressing article, drip installation exercise method Download PDFInfo
- Publication number
- CN106285018A CN106285018A CN201610742372.0A CN201610742372A CN106285018A CN 106285018 A CN106285018 A CN 106285018A CN 201610742372 A CN201610742372 A CN 201610742372A CN 106285018 A CN106285018 A CN 106285018A
- Authority
- CN
- China
- Prior art keywords
- drip
- pressing article
- install
- installation
- pressing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention provides a kind of pressing article, drip installation exercise method, comprise the following steps: operation preparation, setting-out labelling, the installation of wallboard pressing article, the installation of beam slab pressing article, beam, the window template drip that wafts installation, installation quality inspection.Compared with correlation technique, the present invention has the beneficial effects that, by formulating relevant job step, and normative operation standard.Improve pressing article, the precision of drip installation, efficiency, and improve the safety of operation.
Description
[technical field]
The present invention relates to technical field of building construction, particularly relate to a kind of pressing article, drip installation exercise method.
[background technology]
In construction, needing to carry out pressing article, drip installation exercise, in correlation technique, pressing article, drip are pacified
Dress operational method relies on personal liability sense and Personal Skills without specification, installation quality and efficiency.The deficiency of correlation technique is, effect
Rate is low, installation quality cannot ensure, and there is potential safety hazard.
Therefore, it is necessary to provide a kind of new pressing article, drip installation exercise method to overcome above-mentioned technical problem in fact.
[summary of the invention]
The technical issues that need to address of the present invention are to provide a kind of pressing plate that can improve efficiency, quality and security performance
Bar, drip installation exercise method.
One pressing article of the present invention, drip installation exercise method, comprise the following steps:
The first step: operation prepares
1.1 in storehouse to be installed, will install needed for Work tool fluted drill, electric hand drill, charging driver, drum,
Cutting machine, marking pen, hammer, crowbar and material M5 bolt and nut is some is ready to, be placed on the region specified;
1.2 according to material designing BOM table, checks pressing article, drip model and quantity;
Piled up neatly by specification size, model, and carried out labelling with marking pen;
Second step: setting-out labelling
2.1 get pressing article, drip installation drawing, and confide a technological secret with design, and examination & verification examines that drawing is to errorless;
2.2, according to installation drawing, carry out mark in the template that need to install pressing article, drip, according to wall pressing article-beam
Pressing article-beam drip, waft window drip, carries out setting-out labelling;
3rd step: wallboard pressing article is installed
3.1 are found the wallboard needing to install pressing article by drawing and setting-out labelling;
3.2, with hammer, crowbar form removal, are then carried to install pressing article region;
3.3 first, template is kept flat to level ground, and pressing article upward, is placed on specific bit by concrete surface
Putting, both sides are put down anyhow, slam with a foot and stablize motionless, and both hands fix electric hand drill, vertical open pores;
Bolt and nut is fastened by 3.4 by charging driver;
4th step: beam slab pressing article is installed
4.1 are found the beam side plate and beam side C groove needing to install pressing article by drawing and setting-out labelling;
4.2, with hammer, crowbar form removal, are then carried to install pressing article region;
4.3 first, template is kept flat to level ground, and pressing article upward, is placed on specific bit by concrete surface
Putting, both sides are put down anyhow, slam with a foot and stablize motionless, and both hands fix electric hand drill, vertical open pores;
Bolt and nut is fastened by 4.4 by charging driver;
The template of pressing article will be installed, be carried to tram and install;
5th step: beam, the window template drip that wafts are installed
5.1 are found the beam base plate and beam low C groove, Gu Ding needing to install drip by drawing and setting-out labelling;
5.2, with hammer, crowbar form removal, are then carried to install drip region;
5.3 first, template is kept flat to level ground, and drip upward, is placed on specific bit by concrete surface
Put, fix by drip frock;Slamming with a foot and stablize motionless, both hands fix electric hand drill, vertical open pores;
Bolt and nut is fastened by 5.4 by charging driver;
5.5 will install the template of drip, be carried to tram and install;
Complete pressing article, drip installation exercise.
3, pressing article according to claim 1, drip installation exercise method, also includes:
6th step: installation quality inspection
6.1 check whether bolt and nut fastens;
6.2 check that pressing article, drip are with or without faulting of slab ends phenomenon;
6.3 check that pressing article, drip are the most consistent with drawing, have exhaustive.
Preferably, in 1.1 steps in the first step, the specifications and models of fluted drill are staight shank M5*57.
Preferably, in 2.2 steps in second step, according to installation drawing, the template that need to install pressing article, drip is done
Good position and the mark of length.
Preferably, in 5.1 in step 5, Gu Ding comprises standby Gu Ding.
Compared with correlation technique, the present invention has the beneficial effects that, by formulating relevant job step, and normative operation mark
Accurate.Improve pressing article, the precision of drip installation, efficiency, and improve the safety of operation.
[accompanying drawing explanation]
Fig. 1 is pressing article of the present invention, the operation process chart of drip installation exercise method.
In figure: 1 prepares for operation, 2 is setting-out labelling, and 3 install for wallboard pressing article, and 4 install for beam slab pressing article, and 5 are
Beam, the window template drip that wafts are installed, and 6 is installation quality inspection.
[detailed description of the invention]
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
See accompanying drawing 1, one pressing article of the present invention, drip installation exercise method, comprise the following steps: 1 is accurate for operation
Standby, 2 is setting-out labelling, and 3 install for wallboard pressing article, and 4 install for beam slab pressing article, and 5 is beam, the window template drip that wafts installation, 6
For installation quality inspection.
Specifically comprise the following steps that
The first step: operation prepares
1.1 in storehouse to be installed, will install needed for Work tool fluted drill, electric hand drill, charging driver, drum,
Cutting machine, marking pen, hammer, crowbar and material M5 bolt and nut is some is ready to, be placed on the region specified.
1.2 according to material designing BOM table, checks pressing article, drip model and quantity.
Piled up neatly by specification size, model, and carried out labelling with marking pen.
The points for attention of the first step are: before operation, Labor protection clothing, safety helmet are dressed by standard, fasten chin strap, work card
Put into front working clothing pocket.
The operation or work standard of the first step is: aid is equipped with complete.
Second step: setting-out labelling
2.1 get pressing article, drip installation drawing, and confide a technological secret with design, and examination & verification examines that drawing is to errorless.
2.2, according to installation drawing, carry out mark in the template that need to install pressing article, drip, according to wall pressing article-beam
Pressing article-beam drip, waft window drip, carries out setting-out labelling.
The points for attention of second step are:
1, during template setting-out labelling, confirm to have carried out template coding.
2, standby top admittedly setting-out labelling must not be omitted.
The operation or work standard of second step is:
1, pressing article, drip position are consistent with drawing;
2, setting-out labelling is clear, be easily understood;
3rd step: wallboard pressing article is installed
3.1 are found the wallboard needing to install pressing article by drawing and setting-out labelling.
3.2, with hammer, crowbar form removal, are then carried to install pressing article region.
3.3 first, template is kept flat to level ground, and pressing article upward, is placed on specific bit by concrete surface
Putting, both sides are put down anyhow, slam with a foot and stablize motionless, and both hands fix electric hand drill, vertical open pores.
Bolt and nut is fastened by 3.4 by charging driver.
The points for attention of the 3rd step are:
1, during electric hand drill perforate, need to wear protective spectacles, fluted drill is vertically downward.
2, in installation region, on-the-spot 5S is up to standard.
3, after pressing article installs, install in time.
The operation or work standard of the 3rd step is as follows:
1, pressing article is installed correct, without faulting of slab ends.
2, formwork assembling and disassembling position is correct.
3, pressing article bolt and nut fastening non-loosening.
4, position, pressing plate cylindrical void position is as the criterion with design standard.
4th step: beam slab pressing article is installed
4.1 are found the beam side plate and beam side C groove needing to install pressing article by drawing and setting-out labelling.
4.2, with hammer, crowbar form removal, are then carried to install pressing article region.
4.3 first, template is kept flat to level ground, and pressing article upward, is placed on specific bit by concrete surface
Putting, both sides are put down anyhow, slam with a foot and stablize motionless, and both hands fix electric hand drill, vertical open pores.
Bolt and nut is fastened by 4.4 by charging driver.
The template of pressing article will be installed, be carried to tram and install.
The points for attention of the 4th step are:
1, during electric hand drill perforate, need to wear protective spectacles, fluted drill is vertically downward;
2, in installation region, on-the-spot 5S is up to standard;
3, after pressing article installs, install in time.
The operation or work standard of the 4th step is:
1, pressing article is installed correct, without faulting of slab ends;
2, formwork assembling and disassembling position is correct;
3, pressing article bolt and nut fastening non-loosening;
4, position, pressing plate cylindrical void position is as the criterion with design standard;
5, beam side plate and C groove seam gap, beam side are not more than 3mm.
5th step: beam, the window template drip that wafts are installed
5.1 are found the beam base plate and beam low C groove, Gu Ding needing to install drip by drawing and setting-out labelling.
5.2, with hammer, crowbar form removal, are then carried to install drip region.
5.3 first, template is kept flat to level ground, and drip upward, is placed on specific bit by concrete surface
Put, fix by drip frock.Slamming with a foot and stablize motionless, both hands fix electric hand drill, vertical open pores.
Bolt and nut is fastened by 5.4 by charging driver.
5.5 will install the template of drip, be carried to tram and install.
Complete pressing article, drip installation exercise.
The points for attention of the 5th step are:
1, during electric hand drill perforate, need to wear protective spectacles, fluted drill is vertically downward;
2, in installation region, on-the-spot 5S is up to standard;
3, after drip installs, install in time.
The operation or work standard of the 5th step is:
1, drip is installed correct, without faulting of slab ends;
2, formwork assembling and disassembling position is correct;
3, drip bolt and nut fastening non-loosening;
4, position, string holes of dripping position is as the criterion with design standard;
5, C groove at the bottom of beam base plate, beam and admittedly top seam gap be not more than 3mm.
6th step: installation quality inspection
6.1 check whether bolt and nut fastens.
6.2 check that pressing article, drip are with or without faulting of slab ends phenomenon.
6.3 check that pressing article, drip are the most consistent with drawing, have exhaustive.
The operation or work standard of the 6th step is:
1, pressing article, drip installation site are consistent with drawing;
2, seam≤3mm, without faulting of slab ends;
3, formwork assembling and disassembling position consistency.
In 1.1 steps in the first step, the specifications and models of fluted drill are staight shank M5*57.
In 2.2 steps in second step, according to installation drawing, the template that need to install pressing article, drip does good position
Mark with length.
In in step 5 5.1, Gu Ding comprises standby Gu Ding.
Compared with correlation technique, the present invention has the beneficial effects that, by formulating relevant job step, and normative operation mark
Accurate.Improve pressing article, the precision of drip installation, efficiency, and improve the safety of operation.
Above-described is only embodiments of the present invention, it should be noted here that for those of ordinary skill in the art
For, without departing from the concept of the premise of the invention, it is also possible to make improvement, but these belong to the protection model of the present invention
Enclose.
Claims (5)
1. a pressing article, drip installation exercise method, it is characterised in that comprise the following steps:
The first step: operation prepares
1.1 in storehouse to be installed, the Work tool fluted drill needed for installing, electric hand drill, charging driver, drum, cutting
Machine, marking pen, hammer, crowbar and material M5 bolt and nut is some is ready to, be placed on the region specified;
1.2 according to material designing BOM table, checks pressing article, drip model and quantity;
Piled up neatly by specification size, model, and carried out labelling with marking pen;
Second step: setting-out labelling
2.1 get pressing article, drip installation drawing, and confide a technological secret with design, and examination & verification examines that drawing is to errorless;
2.2, according to installation drawing, carry out mark in the template that need to install pressing article, drip, according to wall pressing article-beam pressing plate
Bar-beam drip, waft window drip, carries out setting-out labelling;
3rd step: wallboard pressing article is installed
3.1 are found the wallboard needing to install pressing article by drawing and setting-out labelling;
3.2, with hammer, crowbar form removal, are then carried to install pressing article region;
3.3 first, template is kept flat to level ground, and pressing article upward, is placed on appointment position by concrete surface, horizontal
Perpendicular both sides are put down, and slam with a foot and stablize motionless, and both hands fix electric hand drill, vertical open pores;
Bolt and nut is fastened by 3.4 by charging driver;
4th step: beam slab pressing article is installed
4.1 are found the beam side plate and beam side C groove needing to install pressing article by drawing and setting-out labelling;
4.2, with hammer, crowbar form removal, are then carried to install pressing article region;
4.3 first, template is kept flat to level ground, and pressing article upward, is placed on appointment position by concrete surface, horizontal
Perpendicular both sides are put down, and slam with a foot and stablize motionless, and both hands fix electric hand drill, vertical open pores;
Bolt and nut is fastened by 4.4 by charging driver;
The template of pressing article will be installed, be carried to tram and install;
5th step: beam, the window template drip that wafts are installed
5.1 are found the beam base plate and beam low C groove, Gu Ding needing to install drip by drawing and setting-out labelling;
5.2, with hammer, crowbar form removal, are then carried to install drip region;
5.3 first, template is kept flat to level ground, and drip upward, is placed on appointment position, uses by concrete surface
Drip frock is fixed;Slamming with a foot and stablize motionless, both hands fix electric hand drill, vertical open pores;
Bolt and nut is fastened by 5.4 by charging driver;
5.5 will install the template of drip, be carried to tram and install;
Complete pressing article, drip installation exercise.
Pressing article the most according to claim 1, drip installation exercise method, it is characterised in that also include:
6th step: installation quality inspection
6.1 check whether bolt and nut fastens;
6.2 check that pressing article, drip are with or without faulting of slab ends phenomenon;
6.3 check that pressing article, drip are the most consistent with drawing, have exhaustive.
Pressing article the most according to claim 1 and 2, drip installation exercise method, it is characterised in that in the first step
In 1.1 steps, the specifications and models of fluted drill are staight shank M5*57.
Pressing article the most according to claim 1 and 2, drip installation exercise method, it is characterised in that in second step
In 2.2 steps, according to installation drawing, the template that need to install pressing article, drip is done the mark of good position and length.
Pressing article the most according to claim 1 and 2, drip installation exercise method, it is characterised in that in step 5
In 5.1, Gu Ding comprises standby Gu Ding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610742372.0A CN106285018B (en) | 2016-08-26 | 2016-08-26 | Pressing article, drip installation exercise method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610742372.0A CN106285018B (en) | 2016-08-26 | 2016-08-26 | Pressing article, drip installation exercise method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106285018A true CN106285018A (en) | 2017-01-04 |
CN106285018B CN106285018B (en) | 2018-08-31 |
Family
ID=57677926
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610742372.0A Active CN106285018B (en) | 2016-08-26 | 2016-08-26 | Pressing article, drip installation exercise method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106285018B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109469292A (en) * | 2018-12-24 | 2019-03-15 | 漳州职业技术学院 | A kind of construction method of moulding and double drips |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07292953A (en) * | 1994-04-28 | 1995-11-07 | Ig Tech Res Inc | End construction |
JPH08199764A (en) * | 1995-01-25 | 1996-08-06 | Shinsei Kogyo Kk | Fixing method of external wall material for repair |
CN203613799U (en) * | 2013-12-16 | 2014-05-28 | 广东众科建筑技术发展有限公司 | Building aluminum alloy template profile |
CN204081479U (en) * | 2014-09-28 | 2015-01-07 | 中建四局第三建筑工程有限公司 | A kind of device making drip in aluminum alloy mould plate |
CN204357108U (en) * | 2014-12-18 | 2015-05-27 | 晟通科技集团有限公司 | Aluminum dipping form presser device |
-
2016
- 2016-08-26 CN CN201610742372.0A patent/CN106285018B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07292953A (en) * | 1994-04-28 | 1995-11-07 | Ig Tech Res Inc | End construction |
JPH08199764A (en) * | 1995-01-25 | 1996-08-06 | Shinsei Kogyo Kk | Fixing method of external wall material for repair |
CN203613799U (en) * | 2013-12-16 | 2014-05-28 | 广东众科建筑技术发展有限公司 | Building aluminum alloy template profile |
CN204081479U (en) * | 2014-09-28 | 2015-01-07 | 中建四局第三建筑工程有限公司 | A kind of device making drip in aluminum alloy mould plate |
CN204357108U (en) * | 2014-12-18 | 2015-05-27 | 晟通科技集团有限公司 | Aluminum dipping form presser device |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109469292A (en) * | 2018-12-24 | 2019-03-15 | 漳州职业技术学院 | A kind of construction method of moulding and double drips |
Also Published As
Publication number | Publication date |
---|---|
CN106285018B (en) | 2018-08-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
GB2534734A (en) | Systems and methods for optimizing drilling operations using transient cuttings modeling and real-time data | |
MX2014002902A (en) | Cutting elements for earth-boring tools, earth-boring tools including such cutting elements and related methods. | |
WO2007018860A8 (en) | Well modeling associated with extraction of hydrocarbons from subsurface formations | |
CN205096590U (en) | Simple and easy auxiliary device of ceiling punching operation | |
CN106285018A (en) | Pressing article, drip installation exercise method | |
GB2474955B (en) | Pay zone protection | |
CN102071791B (en) | Quick perforation method and device for suspended ceiling | |
CN107649490A (en) | Intelligent electronic device reclaims detachment device | |
CN204819389U (en) | Portable strike to bind put | |
CN108071203A (en) | The technique quickly constructed in furniture construction of hydropower to plank base | |
CN209007098U (en) | A kind of steel plate drilling aid | |
He et al. | Software system for large deformation mechanical analysis of soft rock engineering at great depth. | |
CN203330451U (en) | Roof drilling device | |
CN202684422U (en) | Frame splicing tool for steel doorframe | |
CN205967519U (en) | Double -station drilling tool | |
CN205599961U (en) | Brill machine of attacking | |
CN109424130A (en) | The technique of plank base construction efficiency is improved in construction | |
CN205237132U (en) | Counter sinking device | |
CN207431324U (en) | A kind of auto-parts die punching device | |
CN203125144U (en) | Button bit hole-drilling base | |
CN206690188U (en) | A kind of architectural decoration perforating device | |
CN108285936A (en) | A kind of belt cutting and boring machine | |
CN202274265U (en) | Quick installation device for oil field measurement and control box | |
CN203361665U (en) | Stair step external corner protector | |
CN209509933U (en) | A kind of build uses aluminum alloy mould plate window frame indent section components |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |