CN106228216A - A kind of asphalt haulage time cycle collecting test method - Google Patents

A kind of asphalt haulage time cycle collecting test method Download PDF

Info

Publication number
CN106228216A
CN106228216A CN201610630549.8A CN201610630549A CN106228216A CN 106228216 A CN106228216 A CN 106228216A CN 201610630549 A CN201610630549 A CN 201610630549A CN 106228216 A CN106228216 A CN 106228216A
Authority
CN
China
Prior art keywords
asphalt
haulage
time
vehicle
transport
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610630549.8A
Other languages
Chinese (zh)
Inventor
唐建亚
徐慧
张志祥
许沛龙
刘宏晋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Sinoroad Information Technology Co Ltd
Original Assignee
Jiangsu Sinoroad Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Sinoroad Information Technology Co Ltd filed Critical Jiangsu Sinoroad Information Technology Co Ltd
Priority to CN201610630549.8A priority Critical patent/CN106228216A/en
Publication of CN106228216A publication Critical patent/CN106228216A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • G06K17/0029Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device the arrangement being specially adapted for wireless interrogation of grouped or bundled articles tagged with wireless record carriers
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/083Shipping
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of asphalt haulage time cycle collecting test method, by using RFID, GNSS two item data acquisition technique and computer network communication technology, propose practicable asphalt haul-cycle time collecting test method.The acquisition technique market maturity used is high, and RFID is mountable on the haulage vehicle of disposable type, low cost, installs simple and flexible, applied widely;The method of testing proposed, can the arbitrary supply centre of online query, the compound haul-cycle time of arbitrary vehicle number, avoid the materials application of haul-cycle time time-out in engineering construction project, management of engineering construction level can be effectively improved, ensure engineering construction quality, there is good popularizing application prospect, there is good economic benefit.

Description

A kind of asphalt haulage time cycle collecting test method
Technical field
The present invention relates to a kind of asphalt haulage time cycle collecting test method, belong to highway engineering road surface matter Amount control field produces technical field.
Background technology
Colophonium is as one typical viscoelastic body material, in engineering construction quality control, the temperature of asphalt It is important link, and the temperature of asphalt is to be produced by mix to be formed and it needs to transport within the time cycle of regulation Transport to job site, to prevent haulage time excessive cycle, cause the decline of mixture temperature, it is impossible to meet site operation and want Ask.
In traditional pavement construction, it is to be controlled by manually filling in list, when i.e. asphalt transport is set out, hands Work fills in a time value at list, transports to manually carrying out during job site and checks haulage time.On the one hand the method expends , on the other hand due to problems such as personnel's responsibility, there is bigger drawback in manpower.During the asphalt pavement construction of present stage controls, right It is substantially at runaway condition in the haul-cycle time of asphalt.
Because the needs of control of Asphalt Pavement for Quality, and the defect of existing control method, the present inventor is based on being engaged in Asphalt Pavement Construction Quality controls practical experience abundant for many years and Professional knowledge, and coupled computer, network technology, actively adds With research and innovation, to proposing a kind of asphalt haulage time cycle collecting test method, and there is significant practicality.
Summary of the invention
The technical problem to be solved is to provide a kind of asphalt haulage time cycle collecting test method, Can the arbitrary supply centre of online query, the compound haul-cycle time of arbitrary vehicle number, it is to avoid the materials application of haul-cycle time time-out in Engineering construction project, can be effectively improved management of engineering construction level, it is ensured that engineering construction quality.
In order to solve above-mentioned technical problem, the technical solution adopted in the present invention is:
A kind of asphalt haulage time cycle collecting test method, comprises the steps: that (1) installs in transport vehicle The electronic tag corresponding with license board information, installs the first card reader at asphalt mixture mixing back court, paves front court in construction The second card reader installed, installs location measurement module on construction paver simultaneously;(2) in the computer server of backstage, will The device id of the electronic tag in engineering project, engineering bid section, haulage vehicle license plate number ID, transport vehicle, is installed on Colophonium mixing Expect the first card reader of mix back court, be installed on the device id information of the second card reader of the front court that paves, beforehand through setting up number Typing is carried out according to structural table;(3) asphalt has been loaded when haulage vehicle, and when leaving asphalt mixture mixing back court, the One card reader reads the electronic tag on vehicle, and license board information ID of record haulage vehicle, transport start place A1, transport start Time T1, and by the first wireless transport module, send information to background server;(4) before haulage vehicle arrives and paves During field, the second card reader reads the electronic tag on vehicle, and license board information ID of record haulage vehicle, transport reach time T2, The same time reads and positions the geographical location information K that measurement module obtains on paver1, by the second wireless transport module, will Information sends to background server;(5) background server is with information of vehicles ID for coupling, gets transport time started T1, fortune Defeated time of advent T2, it is calculated the haul-cycle time T of vehicleS=T2-T1
A kind of aforesaid asphalt haulage time cycle collecting test method, it is characterised in that: described electronic tag For type active RFID electronic label.
A kind of aforesaid asphalt haulage time cycle collecting test method, it is characterised in that: described transport vehicle It is provided with electronic tag on side case and boot.
A kind of aforesaid asphalt haulage time cycle collecting test method, it is characterised in that: described second Card Reader Device is UHF band, and working frequency range is 800-1000MHz, and identification distance is 4-8m.
A kind of aforesaid asphalt haulage time cycle collecting test method, it is characterised in that: described location is measured Module is that GNSS location measures rover station.
The invention has the beneficial effects as follows: the method for testing in the asphalt haulage time cycle of the present invention, bound bitumen The technology requirement that mixture quality controls, by using RFID, GNSS two item data acquisition technique and computer network communication Technology, proposes practicable asphalt haul-cycle time collecting test method.The acquisition technique market maturity used Height, RFID is mountable on the haulage vehicle of disposable type, low cost, installs simple and flexible, applied widely; The method of testing proposed, can the arbitrary supply centre of online query, the compound haul-cycle time of arbitrary vehicle number, it is to avoid the haul-cycle time surpasses Time materials application in engineering construction project, management of engineering construction level can be effectively improved, it is ensured that engineering construction quality, have good Good popularizing application prospect, has good economic benefit.
Accompanying drawing explanation
Fig. 1 is the module connection diagram of the present invention a kind of asphalt haulage time cycle collecting test method.
Detailed description of the invention
Below in conjunction with Figure of description, the present invention is further illustrated.
As it is shown in figure 1, a kind of asphalt haulage time cycle collecting test method, it is characterised in that: include as follows Step:
(1) electronic tag corresponding with license board information is installed in transport vehicle, installs at asphalt mixture mixing back court First card reader, the second card reader of the front court installation that paves in construction, location measurement module is installed on construction paver simultaneously; In the present embodiment, electronic tag uses type active RFID electronic label, the construction environment complicated to tackle highway engineering, it is ensured that gather Rate, and it is mounted on electronic tag on the side case and boot of transport vehicle, it is simple to card reader reads, and the second card reader is hyperfrequency Frequency band, working frequency range is 800-1000MHz, and identification distance is 4-8m, to prevent haulage vehicle information to be paved such as misreading, wherein Location measurement module uses GNSS location to measure rover station;(2) in the computer server of backstage, by engineering project, engineering bid section, The device id of the electronic tag in haulage vehicle license plate number ID, transport vehicle, is installed on the first reading of asphalt mixture mixing back court Card device, it is installed on the device id information of the second card reader of the front court that paves, carries out typing beforehand through setting up data structure table; (3) loaded asphalt when haulage vehicle, and when leaving asphalt mixture mixing back court, the first card reader has read on vehicle Electronic tag, record haulage vehicle license board information ID, transport start place A1, transport time started T1, and by the first nothing Line transport module, sends information to background server;(4) when haulage vehicle arrives and paves front court, the second card reader reads Electronic tag on vehicle, license board information ID of record haulage vehicle, transport reach time T2, on reading of same time paver The geographical location information K that location measurement module obtains1, by the second wireless transport module, send information to background server; (5) background server is with information of vehicles ID for coupling, gets transport time started T1, the transport T time of advent2, it is calculated car Haul-cycle time TS=T2-T1
User can access background server, the arbitrary supply centre of online query, the mixing of arbitrary vehicle number by application program The material haul-cycle time, example as shown in the table.
Table 1 compound haulage time cycle information query example table
During practice of construction, asphalt pavement construction management personnel can consult by logging in client computer server, Understand the travel position of each car, for carrying out the early warning of the form such as wechat, note beyond the haulage vehicle in cycle stipulated time, Prevent the use of defective material, it is ensured that engineering construction quality;Construction manager also can be consulted online and currently transport Vehicle fleet size, to determine rational speed of application, it is to avoid site operation personnel wait the situation of haulage vehicle for a long time, time-consuming Cost.
In sum, a kind of asphalt haulage time cycle collecting test method that the present invention provides, can look into online Ask the compound haul-cycle time of arbitrary supply centre, arbitrary vehicle number, it is to avoid the materials application of haul-cycle time time-out is in engineering construction Project, can be effectively improved management of engineering construction level, it is ensured that engineering construction quality.
The above, be only presently preferred embodiments of the present invention, and the present invention not makees any pro forma restriction, though So the present invention is disclosed above with preferred embodiment, but is not limited to the present invention, any technology people being familiar with this specialty Member, in the range of without departing from technical solution of the present invention, when the technology contents of available the disclosure above makes a little change or modification For the Equivalent embodiments of equivalent variations, as long as being the content without departing from technical solution of the present invention, the technical spirit of the foundation present invention Any simple modification, equivalent variations and the modification being made above example, all still falls within the range of technical solution of the present invention.

Claims (5)

1. an asphalt haulage time cycle collecting test method, it is characterised in that: comprise the steps:
(1) electronic tag corresponding with license board information is installed in transport vehicle, installs first at asphalt mixture mixing back court Card reader, the second card reader of the front court installation that paves in construction, location measurement module is installed on construction paver simultaneously;
(2) in the computer server of backstage, by the electronics in engineering project, engineering bid section, haulage vehicle license plate number ID, transport vehicle The device id of label, is installed on the first card reader of asphalt mixture mixing back court, is installed on the second card reader of the front court that paves Device id information, carry out typing beforehand through setting up data structure table;
(3) loaded asphalt when haulage vehicle, and when leaving asphalt mixture mixing back court, the first card reader has read car Electronic tag on, license board information ID of record haulage vehicle, transport start place A1, transport time started T1, and by the One wireless transport module, sends information to background server;
(4) when haulage vehicle arrives and paves front court, the second card reader reads the electronic tag on vehicle, record haulage vehicle License board information ID, transport reach time T2, reading of same time paver positions the geographical location information that measurement module obtains K1, by the second wireless transport module, send information to background server;
(5) background server is with information of vehicles ID for coupling, gets transport time started T1, the transport T time of advent2, calculate Haul-cycle time T to vehicleS= T2- T1
A kind of asphalt haulage time cycle collecting test method the most according to claim 1, it is characterised in that: institute Stating electronic tag is type active RFID electronic label.
A kind of asphalt haulage time cycle collecting test method the most according to claim 1, it is characterised in that: institute State and be provided with electronic tag on the side case of transport vehicle and boot.
A kind of asphalt haulage time cycle collecting test method the most according to claim 1, it is characterised in that: institute Stating the second card reader is UHF band, and working frequency range is 800-1000MHz, and identification distance is 4-8m.
A kind of asphalt haulage time cycle collecting test method the most according to claim 1, it is characterised in that: institute Stating location measurement module is that GNSS location measures rover station.
CN201610630549.8A 2016-08-03 2016-08-03 A kind of asphalt haulage time cycle collecting test method Pending CN106228216A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610630549.8A CN106228216A (en) 2016-08-03 2016-08-03 A kind of asphalt haulage time cycle collecting test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610630549.8A CN106228216A (en) 2016-08-03 2016-08-03 A kind of asphalt haulage time cycle collecting test method

Publications (1)

Publication Number Publication Date
CN106228216A true CN106228216A (en) 2016-12-14

Family

ID=57546868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610630549.8A Pending CN106228216A (en) 2016-08-03 2016-08-03 A kind of asphalt haulage time cycle collecting test method

Country Status (1)

Country Link
CN (1) CN106228216A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110472855A (en) * 2019-08-07 2019-11-19 江苏中路信息科技有限公司 A kind of device and method calculating pavement construction mixture transportational process with the position that paves
CN110838005A (en) * 2019-11-14 2020-02-25 苏交科集团股份有限公司 Method and device for identifying state of mixture transport vehicle in pavement construction operation
CN111679638A (en) * 2020-05-29 2020-09-18 安徽汉高信息科技有限公司 Asphalt mixing production construction process monitoring system based on Internet of things

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007257187A (en) * 2006-03-22 2007-10-04 Cosmo Oil Co Ltd Asphalt shipping system and asphalt shipping method
CN101866172A (en) * 2010-04-28 2010-10-20 武汉启鑫物联网技术应用有限公司 RFID technology based concrete quality monitoring system and working method thereof
CN103064394A (en) * 2012-12-31 2013-04-24 武汉英思工程科技有限公司 Concrete dam construction quality real-time monitoring method and system
CN103336499A (en) * 2013-06-19 2013-10-02 中山市拓维电子科技有限公司 System and method of dynamic management for construction quality of asphalt concrete pavement
CN104915780A (en) * 2015-06-16 2015-09-16 葛洲坝集团项目管理有限公司 RFID-based concrete transport vehicle automatic statistical system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007257187A (en) * 2006-03-22 2007-10-04 Cosmo Oil Co Ltd Asphalt shipping system and asphalt shipping method
CN101866172A (en) * 2010-04-28 2010-10-20 武汉启鑫物联网技术应用有限公司 RFID technology based concrete quality monitoring system and working method thereof
CN103064394A (en) * 2012-12-31 2013-04-24 武汉英思工程科技有限公司 Concrete dam construction quality real-time monitoring method and system
CN103336499A (en) * 2013-06-19 2013-10-02 中山市拓维电子科技有限公司 System and method of dynamic management for construction quality of asphalt concrete pavement
CN104915780A (en) * 2015-06-16 2015-09-16 葛洲坝集团项目管理有限公司 RFID-based concrete transport vehicle automatic statistical system and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110472855A (en) * 2019-08-07 2019-11-19 江苏中路信息科技有限公司 A kind of device and method calculating pavement construction mixture transportational process with the position that paves
CN110838005A (en) * 2019-11-14 2020-02-25 苏交科集团股份有限公司 Method and device for identifying state of mixture transport vehicle in pavement construction operation
CN111679638A (en) * 2020-05-29 2020-09-18 安徽汉高信息科技有限公司 Asphalt mixing production construction process monitoring system based on Internet of things

Similar Documents

Publication Publication Date Title
Rezaei et al. Experimental-based model for predicting the skid resistance of asphalt pavements
CN106228216A (en) A kind of asphalt haulage time cycle collecting test method
US20130346043A1 (en) Localized mobile decision support method and system for analyzing and performing transportation infrastructure maintenance activities
CN105155599A (en) Remote information monitoring and analyzing device and method for cement soil mixing pile
CN109460947A (en) Highway engineering process based on BIM+GIS technology is applied for checking and examination system
CN207192347U (en) A kind of coal yard intelligence shipping system
KR20090040467A (en) A method of, a system and an apparatus for distributing categorized map correction data
Schneider Radio frequency identification (RFID) technology and its applications in the commercial construction industry
CN111008810B (en) System and method for monitoring paving system components
CN108978420B (en) Highway pavement construction quality remote monitering system
CN107169747A (en) A kind of management system of various engineering of civil construction
Khasawneh et al. Investigation of the factors influencing wavelet-based macrotexture values for HMA pavements
Hinkka et al. Integrated winter road maintenance management—New directions for cold regions research
Patel et al. Evaluating the performance of e-construction tools in highway resurfacing projects
CN202093378U (en) Device for monitoring mixing proportioning real-time data of asphalt mixing stations
CN207998778U (en) System for tracking milling material
CN207895474U (en) System for tracking milling material
Park et al. Primary causes of cracking of asphalt pavement in North Carolina: field study
CN105874127B (en) Antifreezing agent spreads control device, program and method automatically
Rasdorf et al. IT issues for the management of high-quantity, low-cost assets
CN208815382U (en) A kind of highway paves construction quality control system
CN108646641A (en) One kind paves material handling vehicle monitoring system
Hashemi Vaziri Investigation of environmental impacts on piezoelectric weigh-in-motion sensing system
Salem Automated productivity models for earthmoving operations
Wang et al. Investigation of the bond and shear strength between open-graded friction course (OGFC) and dense-graded asphalt concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161214

RJ01 Rejection of invention patent application after publication