CN106208096A CN201610578313.4A CN201610578313A CN106208096A CN 106208096 A CN106208096 A CN 106208096A CN 201610578313 A CN201610578313 A CN 201610578313A CN 106208096 A CN106208096 A CN 106208096A
Authority
CN
China
Prior art keywords
reactive
substation
power
standard
compensation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610578313.4A
Other languages
Chinese (zh)
Other versions
CN106208096B (en
Inventor
邢超
赵军
刘宏亮
韩光
梁博渊
王卓然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hebei Electric Power Co Ltd
Hebei Electric Power Construction Adjustment Test Institute
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hebei Electric Power Co Ltd
Hebei Electric Power Construction Adjustment Test Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hebei Electric Power Co Ltd, Hebei Electric Power Construction Adjustment Test Institute filed Critical State Grid Corp of China SGCC
Priority to CN201610578313.4A priority Critical patent/CN106208096B/en
Publication of CN106208096A publication Critical patent/CN106208096A/en
Application granted granted Critical
Publication of CN106208096B publication Critical patent/CN106208096B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/18Arrangements for adjusting, eliminating or compensating reactive power in networks
    • H02J3/1821Arrangements for adjusting, eliminating or compensating reactive power in networks using shunt compensators
    • H02J3/1871Methods for planning installation of shunt reactive power compensators
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/30Reactive power compensation

Abstract

The present invention relates to a kind of Substation Reactive-power Compensation grading method, its by calculate Substation Reactive-power Compensation than when Bb, substation operation for a long time in transformer efficiency factor Qg and power factor Hg after reactive power compensator all puts into during peak load Substation Reactive-power Compensation degree is carried out classification;Introduce by Substation Reactive-power Compensation degree abundance whether with compensate before and after power factor and design initial stage compensate ratio and be combined, system analyzes Substation Reactive-power Compensation degree comprehensively, solve the not increase-volume substantially of current transformer substation reactive power compensator or device be out of order after just change and a difficult problem for increase-volume;The present invention is applied widely, owing to standard all having strict demand to power factor when different electric pressure Substation Design initial stage reactive compensation capacities, operation, and these parameters are all readily available, therefore the present invention can carry out reactive-load compensation grading to various different electric pressure transformer stations.

Description

A kind of Substation Reactive-power Compensation grading method
Technical field
The present invention relates to substation operation field, be specifically related to a kind of Substation Reactive-power Compensation grading method.
Background technology
Along with gradually forming of national areas Power System Interconnection and supertension backbone's electrical network, power system is to var and electricity Adjusting of pressure is more and more higher with the requirement controlled.When System Reactive Power under-reserve, it is possible to collapse of voltage can be occurred to make electrical network Disintegrate.Additionally in transformer station, transformator and outer load of standing are both needed to consume certain reactive power, and rational reactive-load compensation configures The power factor of transformator can be improved, improve voltage level of power grid, the most just improve the level of Network Voltage Stability simultaneously.
Each department are when configuring reactive power compensator at present, the most do not combine practical situation, directly according under standard-required Limit configuration capacitive reactive power compensation device, make transformer station's capacitive reactive power compensativity too low, idle can not in-situ balancing.Or according to meter Calculation value configures reactive compensation capacity but the later stage still is apparent not enough along with load increases its reactive compensation capacity.Therefore, by calculating Solve whether Substation Reactive-power Compensation degree meets on-the-spot service requirement, be the situation of current run unit urgent need grasp.
Summary of the invention
The technical problem to be solved is to provide a kind of applied widely, Substation Reactive-power Compensation that reliability is high Grading method.
The technical solution adopted in the present invention is: a kind of Substation Reactive-power Compensation grading method, it is become by calculating Power station reactive-load compensation than when Bb, substation operation for a long time in transformer efficiency factor Qg and reactive-load compensation dress during peak load Put power factor Hg after all putting into and Substation Reactive-power Compensation degree carried out classification, method particularly includes:
The first order: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency Factor Qg meets standard-required;
The second level: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformator merit Rate factor Qg meets standard-required;
The third level: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency Factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load meets standard and wants Ask;
The fourth stage: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformator merit Rate factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load meets standard and wants Ask;
Level V: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformator merit Rate factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load is unsatisfactory for standard Requirement;
6th grade: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency Factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load is unsatisfactory for standard and wants Ask.
The positive effect of the present invention is: 1, introduce by Substation Reactive-power Compensation degree abundance whether with compensate before and after power because of Number and design initial stage compensate ratio and are combined, and system analyzes Substation Reactive-power Compensation degree comprehensively, solves current power transformation Stand reactive power compensator not increase-volume substantially or device be out of order after just change and a difficult problem for increase-volume;2, the scope of application of the present invention Extensively, owing to power factor when different electric pressure Substation Design initial stage reactive compensation capacities, operation all being had strictly by standard Requirement, and these parameters are all readily available, and therefore the present invention can carry out reactive-load compensation to various different electric pressure transformer stations Grading;3, reliability of the present invention height, low cost, owing to can calculate in real time by common computer, reduce hardware Input cost, decreases the participation of staff simultaneously, improves the operating error that work efficiency and minimizing personnel participate in bringing, Improve reliability.
Detailed description of the invention
The present invention by calculate Substation Reactive-power Compensation than when Bb, substation operation for a long time in transformer efficiency factor Qg And power factor Hg after reactive power compensator all puts into during peak load carries out classification to Substation Reactive-power Compensation degree, Concrete stage division is:
The first order: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency Factor Qg meets standard-required, shows that reactive compensation capacity of substation is the most sufficient.
The second level: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformator merit Rate factor Qg meets standard-required, shows that reactive compensation capacity of substation is more sufficient.
The third level: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency Factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load meets standard and wants Ask, show that reactive compensation capacity of substation is sufficient.
The fourth stage: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformator merit Rate factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load meets standard and wants Asking, show that reactive compensation capacity of substation is general, running power factor according to current loads will not decline, but answers standby one constant volume The reactive power compensator of amount.
Level V: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformator merit Rate factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load is unsatisfactory for standard Requirement, shows that reactive compensation capacity of substation is short of, and runs power factor according to current loads and can be consistently less than standard-required, should Increase reactive power compensator immediately.
6th grade: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency Factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load is unsatisfactory for standard and wants Asking, now condition is the most severe, shows that power factor reduces and is not due to this grade of substation transformer reactive requirement too much, i.e. Make to be further added by reactive compensation capacity power factor still will not be greatly improved, should investigate whether be because next stage transformer station without Merit demand causes this grade of transformer station's power factor to reduce too much.
Following table is stage division form signal table:
In table, Bb represents Substation Reactive-power Compensation ratio, when Qg represents substation operation for a long time in transformer efficiency because of Number, the power factor after reactive power compensator all puts into when Hg represents peak load.
In this application, Substation Reactive-power Compensation ratio: the transformer station of each electric pressure should require setting according to relevant criterion Meter initial stage configuration reactive compensation capacity, or combines Electric Power Network Planning and power construction, through computational analysis, configuration appropriate scale, The reactive power compensator of type, to meet the reactive-load compensation ratio in standard-required;Run time peak load time power factor: phase For having strict demand without high voltage side of transformer power factor in the transformer station of electric pressure in the standard of pass, this item data can be by Dispatching patcher obtains;Power station reactive power compensator all put into after transformer efficiency factor: this parameter can be by below equation Calculate:
Cos φ is high-pressure side power factor, and P is full station peak value burden with power, and Q is full station peak value load or burden without work, and Qc is complete Stand reactive compensation capacity.

Claims (1)

1. a Substation Reactive-power Compensation grading method, it is characterised in that its by calculate Substation Reactive-power Compensation than Bb, During substation operation for a long time in transformer efficiency factor Qg and the merit after reactive power compensator all puts into during peak load Rate factor Hg carries out classification to Substation Reactive-power Compensation degree, method particularly includes:
The first order: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency factor Qg meets standard-required;
The second level: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformer efficiency because of Number Qg meets standard-required;
The third level: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load meets standard-required;
The fourth stage: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformer efficiency because of Number Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load meets standard-required;
Level V: Substation Reactive-power Compensation is unsatisfactory for standard-required than Bb, during substation operation for a long time in transformer efficiency because of Number Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load is unsatisfactory for standard and wants Ask;
6th grade: Substation Reactive-power Compensation meets standard-required than Bb, during substation operation for a long time in transformer efficiency factor Qg is unsatisfactory for standard-required, and power factor Hg after reactive power compensator all puts into during peak load is unsatisfactory for standard-required.
CN201610578313.4A 2016-07-21 2016-07-21 A kind of Substation Reactive-power Compensation grading method Active CN106208096B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610578313.4A CN106208096B (en) 2016-07-21 2016-07-21 A kind of Substation Reactive-power Compensation grading method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610578313.4A CN106208096B (en) 2016-07-21 2016-07-21 A kind of Substation Reactive-power Compensation grading method

Publications (2)

Publication Number Publication Date
CN106208096A true CN106208096A (en) 2016-12-07
CN106208096B CN106208096B (en) 2018-09-21

Family

ID=57492076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610578313.4A Active CN106208096B (en) 2016-07-21 2016-07-21 A kind of Substation Reactive-power Compensation grading method

Country Status (1)

Country Link
CN (1) CN106208096B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111009906A (en) * 2019-12-04 2020-04-14 国网河北省电力有限公司雄安新区供电公司 Reactive compensation balance method of full cable net rack

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1143849A (en) * 1995-08-18 1997-02-26 郭宝库 High-low voltage capacitor complete compensator
CN101286641A (en) * 2007-12-19 2008-10-15 福建省电力试验研究院 Reactive and grouped compensation device for capacitor
CN102904287A (en) * 2012-09-27 2013-01-30 中国电力科学研究院 Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1143849A (en) * 1995-08-18 1997-02-26 郭宝库 High-low voltage capacitor complete compensator
CN101286641A (en) * 2007-12-19 2008-10-15 福建省电力试验研究院 Reactive and grouped compensation device for capacitor
CN102904287A (en) * 2012-09-27 2013-01-30 中国电力科学研究院 Coordination control method for flexible alternate current transmission system (FACTS) devices of new energy delivery system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
俞诗思: "论区域电压无功控制方案在地区电网中的作用", 《广东科技》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111009906A (en) * 2019-12-04 2020-04-14 国网河北省电力有限公司雄安新区供电公司 Reactive compensation balance method of full cable net rack
CN111009906B (en) * 2019-12-04 2023-12-19 国网河北省电力有限公司雄安新区供电公司 Reactive compensation balancing method for full cable net rack

Also Published As

Publication number Publication date
CN106208096B (en) 2018-09-21

Similar Documents

Publication Publication Date Title
CN103094905B (en) Selection method of dynamic reactive power compensation configuration point
KR101132107B1 (en) System for controlling voltage and reactive power in electric power system connected with distributed generation and method for the same
Su et al. PSO and improved BSFS based sequential comprehensive placement and real-time multi-objective control of delta-connected switched capacitors in unbalanced radial MV distribution networks
CN102368619B (en) Method for evaluating access requirement of direct-current solitary island power transmission system
CN108520362A (en) A kind of integrated evaluating method of rural area intelligent grid level
CN106451446B (en) The constant volume method of urban distribution network subregion interconnect device based on flexible direct current technology
CN106816883A (en) Three-phase imbalance regulating system parallel connection input coefficient, control method and device
CN103427427B (en) Power grid source steady state voltage regulating optimization method for improving transient voltage support capability of power grid
CN110365019B (en) Multi-terminal direct-current power distribution network converter capacity configuration method and system
CN106058934B (en) Micro-grid system and its control method
Sivaraman et al. Enhancing the voltage profile in distribution system with 40 GW of solar PV rooftop in Indian grid by 2022: a review
CN108964076A (en) Regional power grid is idle program evaluation method and system, computer equipment, medium
CN106208096A (en) A kind of Substation Reactive-power Compensation grading method
CN107276103B (en) A kind of series-parallel inverter coordination control strategy of UPFC improving ac bus voltage support intensity
CN105427182A (en) Transformer area low-voltage cause analysis method and transformer area low-voltage cause analysis device
Rahimi et al. Application of Distributed Series Reactors in relieving congestion costs
CN203135457U (en) Three-phase load equalization adjusting apparatus for low-voltage distribution box
CN102646983A (en) Long-term reactive voltage analyzing and optimizing method in power system
da Silva et al. Line losses and power capacity in low voltage AC and DC distribution systems: A numerical comparative study
CN203135456U (en) Three-phase load equalization adjusting apparatus for low-voltage distribution box
CN203732593U (en) Device for monitoring real demand for reactive compensation of distribution transformer
CN104037812A (en) Node voltage deviation change based new energy planning installed capacity distribution method
Nguyen Power system voltage stability and agent based distribution automation in smart grid
CN204118753U (en) A kind of distribution transforming detects compensation control system
ETTA et al. Improved Performance of Elelenwo 11kv Electric Power Distribution Network Using Newton Raphson Load Flow

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant