CN106202507A - Electric power first-aid rehearsal analogue system and method - Google Patents
Electric power first-aid rehearsal analogue system and method Download PDFInfo
- Publication number
- CN106202507A CN106202507A CN201610575919.2A CN201610575919A CN106202507A CN 106202507 A CN106202507 A CN 106202507A CN 201610575919 A CN201610575919 A CN 201610575919A CN 106202507 A CN106202507 A CN 106202507A
- Authority
- CN
- China
- Prior art keywords
- rehearsal
- case
- information
- data
- module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/24—Querying
- G06F16/245—Query processing
- G06F16/2455—Query execution
- G06F16/24553—Query execution of query operations
- G06F16/24554—Unary operations; Data partitioning operations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/24—Querying
- G06F16/245—Query processing
- G06F16/2455—Query execution
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/24—Querying
- G06F16/245—Query processing
- G06F16/2458—Special types of queries, e.g. statistical queries, fuzzy queries or distributed queries
- G06F16/2462—Approximate or statistical queries
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/24—Querying
- G06F16/248—Presentation of query results
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/90—Details of database functions independent of the retrieved data types
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Abstract
The present invention relates to a kind of electric power first-aid rehearsal analogue system and method, receive current power repairing event arranges data, it is analyzed screening obtains keyword message according to arranging data, and from data memory module, obtain the case information matched according to keyword message.Carry out the case information obtained processing generation drill plan according to arranging data, according to arranging parameter, rehearsal prediction scheme is disassembled and combined, obtain drill plan and show.The data retrieval that arranges according to receiving finds similar cases to generate rehearsal prediction scheme, and carry out effective reasoning by cases show that drill plan shows according to arranging parameter, the unit that is supplied to take part in a performance is taken part in a performance, solve the Intelligent generation of simulated scenario and the problem of dynamic evolution, and it is actual to make simulated maneuver sight more suit accident scene, improves simulation accuracy.
Description
Technical field
The present invention relates to urban electric power repairing management technical field, particularly relate to a kind of electric power first-aid rehearsal analogue system
And method.
Background technology
All the time, power system has been made in terms of the traditional stability analysis to put prevention first and technical cue in a large number
Research.But, under the situation that various natural disasters take place frequently, power system is suffered to destroy (such as typhoon, floods etc. certainly because of external force
So disaster) or the artificial premeditated electrical network dismemberent situation caused the most of common occurrence.The various catastrophe that the whole world recurs in recent years
The power system accident caused shows, conventional System Safety Analysis means only rest on the technological layer that puts prevention first be
Inadequate, need security of system is simulated rehearsal, predict electric power accident in advance.
Traditional electric power first-aid simulated maneuver mode is the countermeasure and examination machine arranged for particular event scene
System, arranging of simulated maneuver sight can take a substantial amount of time and energy, and the result of Situated design is with actual burst event sometimes
Disconnection, traditional electric power first-aid simulated maneuver mode is had to there is the shortcoming that simulation accuracy is low.
Summary of the invention
Based on this, it is necessary to for the problems referred to above, it is provided that a kind of electric power first-aid rehearsal emulation improving simulation accuracy
System and method.
A kind of electric power first-aid rehearsal analogue system, including:
Data memory module, for the case information of storage organization;
Parameter setting module, for receive current power repairing event data are set;
Reasoning by cases module, for being analyzed screening obtain keyword message, according to described according to the described data that arrange
Keyword message obtains the case information matched from described data memory module, and according to the described data that arrange to acquisition
Case information carries out processing generating drills prediction scheme;
Rehearsal planning module, for described rehearsal prediction scheme being disassembled and combined according to the described parameter that arranges, is drilled
Practice scheme and show.
A kind of electric power first-aid rehearsal emulation mode, comprises the following steps:
Receive current power repairing event arranges data;
It is analyzed screening obtains keyword message according to the described data that arrange, and obtain phase according to described keyword message
The case information of coupling;
Carry out the case information obtained processing generation rehearsal prediction scheme according to the described data that arrange;
According to the described parameter that arranges, described rehearsal prediction scheme is disassembled and combined, obtain drill plan and show.
Above-mentioned electric power first-aid rehearsal analogue system and method, receive current power repairing event arranges data, according to setting
Put data to be analyzed screening and obtain keyword message, and obtain from data memory module according to keyword message and match
Case information.Carry out the case information obtained processing generation drill plan, according to arranging parameter to rehearsal according to arranging data
Prediction scheme is disassembled and is combined, and obtains drill plan and shows.The data retrieval that arranges according to receiving finds similar cases to generate
Rehearsal prediction scheme, and carry out effective reasoning by cases show that drill plan shows according to arranging parameter, it is provided that give unit of taking part in a performance
Take part in a performance, solve the Intelligent generation of simulated scenario and the problem of dynamic evolution, and simulated maneuver sight is more suited
Accident scene is actual, improves simulation accuracy.
Accompanying drawing explanation
Fig. 1 is the structure chart of electric power first-aid rehearsal analogue system in an embodiment;
Fig. 2 is the structure chart of electric power first-aid rehearsal analogue system in another embodiment;
Fig. 3 is the flow chart of electric power first-aid rehearsal emulation mode in an embodiment;
Fig. 4 is the flow chart of electric power first-aid rehearsal emulation mode in another embodiment.
Detailed description of the invention
In one embodiment, a kind of electric power first-aid rehearsal analogue system, as it is shown in figure 1, include data memory module
110, parameter setting module 120, reasoning by cases module 130 and rehearsal planning module 140.Data memory module 110 is used for storing
Structurized case information.
Structurized case information specifically can include in history case and the rehearsal of conventional analog simulation through assessment and correction
After rehearsal sight case.Specifically, data memory module 110 can include job network library module, case library module, knowledge base
Module, document library module and event information library module.
Job network library module is for storing electric power mechanism, the address list of electrical management personnel and contact method;Case library
Module is for the case information of storage configuration;Base module be used for storing emergency first-aid repair relating basic concepts, theoretical knowledge,
Factual data, and rule, common-sense understanding, heuristic rule and the experience and lessons information obtained;Document library module is used for
Storage plain text, common document, XML (Extensible Markup Language, extensible markup language) file, image and
Voice data;Event information library module is used for storing sudden incidents report data.Event information library module is to join with business
System one of data base the most closely, its Data Source, in the overall process of sudden incidents report, is informed of a case including accident
The commander association of information, department's prediction and warning information, risk hidden danger monitoring information, love scene monitoring information, and accident
Adjust procedural information.
Parameter setting module 120 arranges data for receive current power repairing event.
Arranging data and specifically can include time of origin, scene, coverage etc., user can arrange data by input
Initial sight, rehearsal troop and assessment parameter etc. are configured.
Reasoning by cases module 130 is for being analyzed screening and obtain keyword message, according to keyword according to arranging data
Information obtains the case information matched from data memory module, and according to arranging at the data case information to obtaining
Reason generates rehearsal prediction scheme.
In one embodiment, arranging data and include setting event information and entity rule of ac-tion information of taking part in a performance, case pushes away
Reason module 130 includes information sifting module, case retrieval module, case summarizing module and case modular converter.
Information sifting module is for being analyzed screening, extraction to setting event information and entity rule of ac-tion information of taking part in a performance
Obtain keyword message.
First carry out the Analysis and Screening of data to setting event information, respectively entity rule of ac-tion information of taking part in a performance, extract therein
Keyword message, for the retrieval of case.Wherein, unstructured information extracting method based on unstructured information table, this non-knot
Structure information table deposits unstructured information main information keyword, can retrieve and believe in form from non-structured text
The content of manner of breathing symbol.
Case retrieval module is for retrieving all case informations comprising keyword message from data memory module.
Specifically, the multiple search strategies such as template retrieval, nearest neighbour method retrieval, inductive method retrieval can be used.First examine by template
Rope i.e. key search, according to the feature critical word filtered out, retrieves the institute comprising keyword from data memory module
There is case information.Also can use the mode of similar SQL query, data memory module carry out full-text search, then examines at this
On the basis of hitch fruit, utilize nearest neighbour method i.e. to use the weighted registration between feature to the similarity estimating between case, again enter
Line retrieval, sequence, finally utilize inductive method retrieval result finally to be sorted, and retrieval obtains the most similar case.
Case summarizing module extracts for the case information obtaining detection, conclude and merges, and forms case resource.
Retrieval result is collected, from case similarity prioritization, selects score value higher based on setting threshold values
Several cases as the data message source collected, then according to structurized scenario factors, case information extracted, return
Receive, merge, form new case scenarios.The selection of the higher case of score value is the total score Butut according to each case score value, utilizes
Between Initial Hurdle and case, score value variable gradient determines.Information extraction mode is to describe key element according to event sight and take part in a performance
Entity determines.Conclusion, merging are based on the information description of each case key element and carry out what information selection determined.
Case modular converter, for case resource being carried out analogy conversion and content modification according to setting event information, obtains
Rehearsal prediction scheme.
New case resource is carried out analogy conversion, content modification according to setting event information.Analogy is changed i.e. to source case
The sight of example describes and carries out instantiation amendment, by the specific description information in the case of source, is converted to the description letter of new settings event
Breath, in order to be applied in the description of new events analog simulation sight.For complex data message, can enter as required
Row is readjusted and is solved.
Rehearsal planning module 140, for rehearsal prediction scheme being disassembled and combined according to arranging parameter, obtains drill plan
And show.
Rehearsal prediction scheme is disassembled and is combined with specific reference to entity rule of ac-tion information of taking part in a performance by rehearsal planning module 140,
The personnel assignment and the sight that realize rehearsal such as arrange at the content, specifically can include setting up drill plan, set up organization, set up and drill
Practice scheme and scheme preview, finally give drill plan and show, it is provided that take part in a performance to unit of taking part in a performance.
Above-mentioned electric power first-aid rehearsal analogue system, the data that arrange according to receiving are retrieved in data memory module and are found phase
Generate rehearsal prediction scheme like case, and carry out effective reasoning by cases show that drill plan shows according to arranging parameter, it is provided that
Take part in a performance to unit of taking part in a performance, solve the Intelligent generation of simulated scenario and the problem of dynamic evolution, and make simulated maneuver
It is actual that sight more suits accident scene, real reach exercise and takes part in a performance troop, improves the effect of rehearsal actual effect, improves mould
Intend accuracy.
Above-mentioned electric power first-aid rehearsal analogue system is the simulated maneuver based on sight and role playing, has simulated maneuver feelings
Scape automatically generates, dynamic evolution and the laminating of real accident scene closely, intelligent strong, feature that accuracy is high, and tool
There is certain ability of self-teaching.Sight manufacturing technology deduces figure, visualization sight expression, sight parameter and model by sight
Set, sight event is worked in coordination with the making of instrument auxiliary sights such as writing and writes, it is adaptable to set up various types of emergent sight.
Use native system to be simulated rehearsal, the efficiency of simulated maneuver can be greatly improved, to reach to take exercise the purpose of the troop that takes part in a performance.
In one embodiment, as in figure 2 it is shown, electric power first-aid rehearsal analogue system also includes breath formula discs and evaluation module
150, breath formula discs and the evaluation module 150 rehearsal data of input after reception is drilled corresponding to planning scheme, according to
Rehearsal data genaration case information is also stored in data memory module 110.
Breath formula discs and evaluation module 150 are recorded rehearsal data after rehearsal terminates, and typing case library can conduct
The foundation of reasoning by cases later.Owing to the realization of native system is to decide, based on case, i.e. case library, the information that system is provided that
Content.Breath formula discs and evaluation module 150 specifically can realize the process of simulated maneuver scenarios generation case and from actual burst
The process of event typing case.
The information of case library increases, and the first is from simulated maneuver sight, carries out assessment, revised rehearsal sight
Preserving, the second is by actual burst event information case typing.
During simulated maneuver scenarios generation case, simulated maneuver sight is carried out the conversion mainly rehearsal of case
Sight assessment and rehearsal context data adjustment etc..During simulated maneuver, the rehearsal emulation sight that each rehearsal entity generates according to system
Take action, according to action result, sight present situation is evaluated and described.Finally according to case formatting requirements, feelings will be drilled
Scape is changed.
Actual burst event typing is the data such as news relevant for case, analysis comment, word video data to be recorded
Come, also include event itself, the impact that causes, the organization of participative decision making, the phasic course of disposal and achievement etc.
Details describe, and become a new history case and put preservation in storage after arrangement.
After the rehearsal of electric power first-aid analogue simulation terminates, by the evaluation of simulated maneuver, revise, sum up, and finally enter
Storehouse saves as new history case, it is achieved that the oneself of case library increases and the ability of self-teaching of simulative training system, for
Solid foundation has been established in the generation of rear simulated maneuver sight.
In one embodiment, electric power first-aid rehearsal analogue system also includes base support module 160, base support module
160 are used for obtaining the geographical position of the personnel that take part in a performance in rehearsal and movement track and showing.
During carrying out actual rehearsal, geographical position and movement track to the personnel of taking part in a performance show in real time, in order to
Control centre is monitored and dispatches, and improves operation ease.Specifically, in the present embodiment, base support module 160 includes ground
Reason information system, system for managing video, Internet of things system and mobile application system.
GIS-Geographic Information System is used for obtaining the geographical position of the personnel that take part in a performance in rehearsal and movement track and showing.Formal rehearsal
In can intuitively check the geographical position of the personnel that respectively take part in a performance, movement track.
System for managing video is for obtaining the on-the-spot video pictures of rehearsal and showing.It is existing that system for managing video can realize rehearsal
The video pictures of field calls.
Internet of things system is for obtaining the departmental staff of external system and the transfer situation of goods and materials and showing.Internet of things system
Realize interconnecting with other system, grasp the transfer situation of other departmental staffs and goods and materials comprehensively.
Mobile application system for Field Force position, and under send instructions to Field Force and receiving feedback information.
Positioned by Field Force, can quickly carry out instruction and issue and the interactive operations such as feedback.
Above-mentioned parameter arranges module 120, reasoning by cases module 130, rehearsal planning module 140, breath formula discs and assessment mould
Block 150 and base support module 160 constitute the application supporting layer of electric power first-aid rehearsal analogue system, and data memory module 110 is made
Data Layer for electric power first-aid rehearsal analogue system.Additionally, electric power first-aid rehearsal analogue system may also include application layer and basis
Supporting layer.
Application layer is mainly around two aspects, data and application.Application layer is used for management and the process of data of data, and
The data of process are combined with every profession and trade application.Simulated maneuver is exactly that the data of case library are tied mutually with current emulation sight
Close, finally infer concrete carrying into execution a plan, be particularly applicable to each operating system.Basic supporting layer is that software and hardware basis sets
Executing, this hardware/software infrastructure includes operating system, network service, middleware, data storage device, server apparatus and application
Work station.
In one embodiment, a kind of electric power first-aid rehearsal emulation mode, as it is shown on figure 3, comprise the following steps:
Step S110: receive current power repairing event arranges data.Data are set and specifically can include time of origin, send out
Radix Rehmanniae point, coverage etc., user can arrange data by input and set initial sight, rehearsal troop and assessment parameter etc.
Put.
Step S120: be analyzed screening obtain keyword message according to arranging data, and obtain according to keyword message
The case information matched.
In one embodiment, arrange data to include setting event information and entity rule of ac-tion information of taking part in a performance.Step
S120 includes step 122 and step 124.
Step 122: being analyzed screening with entity rule of ac-tion information of taking part in a performance to setting event information, extraction obtains key
Word information.
Step 124: retrieve all case informations comprising keyword message from data memory module.
Step S130: carry out the case information obtained processing generation rehearsal prediction scheme according to arranging data.
Further, in the present embodiment, step S130 includes step 132 and step 134.
Step 132: the case information obtaining detection extracts, concludes and merges, forms case resource.
Step 134: according to setting event information, case resource is carried out analogy conversion and content modification, obtain rehearsal pre-
Case.
Step S140: according to arranging parameter, rehearsal prediction scheme is disassembled and combined, obtain drill plan and show.
With specific reference to taking part in a performance, rehearsal prediction scheme is disassembled and is combined by entity rule of ac-tion information, it is achieved the personnel of rehearsal divide
Join and the content such as sight is arranged, specifically can include setting up drill plan, set up organization, set up drill plan and scheme is pre-
Look at, finally give drill plan and show, it is provided that take part in a performance to unit of taking part in a performance.
Above-mentioned electric power first-aid rehearsal emulation mode, the data retrieval that arranges according to receiving finds similar cases to generate rehearsal in advance
Case, and carry out effective reasoning by cases show that drill plan shows according to arranging parameter, it is provided that join to unit of taking part in a performance
Drill, solve the Intelligent generation of simulated scenario and the problem of dynamic evolution, and make simulated maneuver sight more suit burst thing
Part scene is actual, real reach exercise and takes part in a performance troop, improves the effect of rehearsal actual effect, improves simulation accuracy.
In one embodiment, as shown in Figure 4, after step S140, electric power first-aid rehearsal emulation mode also includes step
S150。
S150: receive the rehearsal data of input after drilling corresponding to planning scheme, according to rehearsal data genaration case
Information also stores.
After rehearsal terminates, rehearsal data being recorded, typing case library can be as the foundation of later reasoning by cases, can
Realize the process of simulated maneuver scenarios generation case and from the process of actual burst event typing case.
After the rehearsal of electric power first-aid analogue simulation terminates, by the evaluation of simulated maneuver, revise, sum up, and finally enter
Storehouse saves as new history case, it is achieved that the oneself of case library increases and the ability of self-teaching of simulative training system, for
Solid foundation has been established in the generation of rear simulated maneuver sight.
For ease of being further appreciated by above-mentioned electric power first-aid rehearsal analogue system and method, drill below in conjunction with power application repairing
White silk analogue system carries out the method for rehearsal planning and explains.
Power application repairing rehearsal analogue system carries out drilling the method for planning and includes rehearsal planning, rehearsal execution, breath formula
Discs evaluates three steps with assessment.
Rehearsal planning refers to carry out disassembling and combining of prediction scheme according to prediction scheme analysis, finally draws a planning scheme.Whole
Individual flow process includes setting up drill plan, sets up organization, sets up drill plan, scheme preview.
The first step: drill plan.Comprise the steps:
A) determine rehearsal purpose, clearly hold the effect that the reason of emergency drilling, rehearsal problem to be solved and expectation reach
Fruit etc..
B) system is according to the rehearsal purpose analysis rehearsal demand set, and draws preliminary prediction scheme, to event is previously set
On the basis of risk and emergency preplan carry out serious analysis, the technical ability that determine the rehearsal personnel that need to adjust, need to temper, need to check
The responsibility etc. that equipment, the perfect emergency disposal flow process of need and need are the clearest and the most definite.
C) determine rehearsal scope, according to the restriction of the conditions such as rehearsal demand, funds, resource and time, determine rehearsal event
Type, grade, region, take part in a performance mechanism and number, rehearsal mode etc..Again by the assembling of prediction scheme, carry out the amendment of prediction scheme.
D) schedule planning that rehearsal prepares and implements is arranged, including various rehearsal file edits and the time limit of authorization, goods and materials
On the date etc. that the time limit of equipment preparation, rehearsal are implemented, finally determine drill plan
E) final scheme carrying out statistical analysis, such as statistics establishment rehearsal appropriation budget, enters according to funds expenditure detail
Row analysis etc..
Set up organization except the staffs that takes part in a performance, also include setting up the rehearsal including drilling relevant unit leader composition
Leading group, rehearsal leading group generally divides into Planning Department, guarantee portion and evaluation group.Planning Department sets master planning, vice president's planning,
Official documents and correspondence group, coordination group, control group, publicity group etc. it are additionally provided with under this.Take part in a performance the relevant emergent pipe that troop includes that emergency preplan specifies
Reason department (unit) staff, all kinds of special part-time emergency management and rescue troop and Volunteer etc..System not only can freely set
Determine organization, also can freely set its concrete rehearsal task undertaken according to the different personnel that take part in a performance, for modeling event field
Scape makes emergency response action, is sometimes used as simulation personnel and substitutes the not on-the-spot unit personnel participating in rehearsal, or simulation thing
Therefore generating process, as release smog, simulated leakage etc..
Set up drill plan, i.e. protocol procedures, be made up of with reply two parts sight chain, sight.Sight chain is sent out with event
Each sight is constituted sight chain according to multiple stages by time sequencing and the logical relation of exhibition.Situated design is mainly to event class
Not, time place, development speed, intensity and scope dangerous, impacted, personnel and goods and materials distribution, the damage having resulted in occurred
The content such as lose, follow-up developments prediction, meteorological and other environmental conditions are, polygonal in the way of word, picture, sound, video etc.
Degree shows, and builds take part in a performance the immersion sense of personnel, sense of reality.For each Situated design reply item, examination subject, examination
Personnel, Assessment, concrete content of examination, the mode of assessment and means etc..Sight and reply are by rehearsal stage, sight, answer
People, the reply many key elements of item are connected, quickly drill plan is familiar with and understands.
Scheme preview provides time, space, event to develop three-dimensional integrated holographic allelopathic to know the visual angle of drill plan, represent
Drill plan overall process, in order to rehearsal Planning Work personnel carry out project setting and overall assurance.
Second step: rehearsal performs.Register including the personnel of taking part in a performance, start rehearsal, sight reply, subject examination and assessment, drill
Practice and terminate.Rehearsal organization and the personnel that view and emulate all can watch the overall process of rehearsal, and the personnel that take part in a performance are according to relevant to oneself
Sight is tackled, and subject examination and assessment are comprehensive by system automatic scoring and expert estimation two parts.The personnel that take part in a performance are in system
On register after, determine that personnel await orders, map show its corresponding position.Rehearsal commander in chief starts rehearsal, during sight foundation
Between order deduce the most forward, the personnel that take part in a performance according to oneself role for sight with prediction scheme for according to being disposed,
Information mutual communication, multidisciplinary coordination linkage;Platform whole process record rehearsal process also presents to drill organization and view and emulate personnel.Drill
Practicing executable portion and stress the one-to-one relationship of sight and reply, system provides five big class 18 reply item to carry out for the personnel of taking part in a performance
Skilled using, high spot reviews is taken part in a performance personal information circulation ability, equipment use ability, correct reply and response speed etc..
3rd step: breath formula discs is evaluated with assessment.Rehearsal discs uses time, space, event development three-dimensional integrated complete
The breath mode known of allelopathic, omni-directional entire process playback rehearsal, for inspection and promote prediction scheme, summarised assessment rehearsal, demonstration type are viewed and emulated,
Emergency materials and equipment updating provide strong foundation.
Reasoning by cases is the basis that whole scheme realizes, according to current setting event and the rule of ac-tion of entity of taking part in a performance, from
Case library is found the case the most similar to this event, and by the actual sight of this case, the simulated scenario as case is entered
Row display, by amendment, to be rapidly achieved simulation case sight true reappearance, temper simulated maneuver personnel and improve simulated maneuver
The effect of actual effect.
Each technical characteristic of embodiment described above can combine arbitrarily, for making description succinct, not to above-mentioned reality
The all possible combination of each technical characteristic executed in example is all described, but, as long as the combination of these technical characteristics is not deposited
In contradiction, all it is considered to be the scope that this specification is recorded.
Embodiment described above only have expressed the several embodiments of the present invention, and it describes more concrete and detailed, but also
Can not therefore be construed as limiting the scope of the patent.It should be pointed out that, come for those of ordinary skill in the art
Saying, without departing from the inventive concept of the premise, it is also possible to make some deformation and improvement, these broadly fall into the protection of the present invention
Scope.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.
Claims (10)
1. an electric power first-aid rehearsal analogue system, it is characterised in that including:
Data memory module, for the case information of storage organization;
Parameter setting module, for receive current power repairing event data are set;
Reasoning by cases module, for being analyzed screening obtain keyword message, according to described key according to the described data that arrange
Word information obtains the case information matched from described data memory module, and arranges the data case to obtaining according to described
Information carries out processing generating drills prediction scheme;
Rehearsal planning module, for described rehearsal prediction scheme being disassembled and combined according to the described parameter that arranges, obtains rehearsal side
Case also shows.
Electric power first-aid the most according to claim 1 rehearsal analogue system, it is characterised in that the described data that arrange include setting
Event information and entity rule of ac-tion information of taking part in a performance, described reasoning by cases module includes:
Information sifting module, for described setting event information and entity rule of ac-tion information of taking part in a performance are analyzed screening, takes out
Obtain keyword message;
Case retrieval module, for retrieving all cases letter comprising described keyword message from described data memory module
Breath;
Case summarizing module, extracts for the case information obtaining detection, conclude and merges, and forms case resource;
Case modular converter, for carrying out analogy conversion according to described setting event information to described case resource and content is repaiied
Change, obtain described rehearsal prediction scheme.
Electric power first-aid the most according to claim 1 rehearsal analogue system, it is characterised in that described data memory module bag
Include:
Job network library module, for storing electric power mechanism, the address list of electrical management personnel and contact method;
Case library module, is used for depositing described structurized case information;
Base module, is used for storing emergency first-aid repair relating basic concepts, theoretical knowledge, factual data, and the rule obtained
Rule, common-sense understanding, heuristic rule and experience and lessons information;
Document library module, is used for storing plain text, common document, XML file, image and voice data;
Event information library module, is used for storing sudden incidents report data.
Electric power first-aid the most according to claim 1 rehearsal analogue system, it is characterised in that also include breath formula discs and assessment
Module, described breath formula discs and the evaluation module rehearsal number of input after reception is drilled corresponding to described planning scheme
According to, according to described rehearsal data genaration case information and be stored in described data memory module.
Electric power first-aid the most according to claim 1 rehearsal analogue system, it is characterised in that also include base support module,
Described base support module is used for obtaining the geographical position of the personnel that take part in a performance in rehearsal and movement track and showing.
Electric power first-aid the most according to claim 5 rehearsal analogue system, it is characterised in that described base support module bag
Include:
GIS-Geographic Information System, is used for obtaining the geographical position of the personnel that take part in a performance in rehearsal and movement track and showing;
System for managing video, for obtaining the on-the-spot video pictures of rehearsal and showing;
Internet of things system, for obtaining the departmental staff of external system and the transfer situation of goods and materials and showing;
Mobile application system, for Field Force position, and under send instructions to described Field Force and receiving feedback information.
7. an electric power first-aid rehearsal emulation mode, it is characterised in that comprise the following steps:
Receive current power repairing event arranges data;
It is analyzed screening obtains keyword message according to the described data that arrange, and obtain according to described keyword message and match
Case information;
Carry out the case information obtained processing generation rehearsal prediction scheme according to the described data that arrange;
According to the described parameter that arranges, described rehearsal prediction scheme is disassembled and combined, obtain drill plan and show.
Electric power first-aid the most according to claim 7 rehearsal emulation mode, it is characterised in that the described data that arrange include setting
Event information and entity rule of ac-tion information of taking part in a performance;Described according to described arrange data be analyzed screening obtain keyword letter
Breath, and from described data memory module, the case information matched is obtained according to described keyword message, including:
Described setting event information and entity rule of ac-tion information of taking part in a performance are analyzed screening, and extraction obtains keyword message;
The all case informations comprising described keyword message are retrieved from described data memory module.
Electric power first-aid the most according to claim 8 rehearsal emulation mode, it is characterised in that described data are set according to described
Carry out processing to the case information obtained and generate drill plan, including:
The case information obtaining detection extracts, concludes and merges, and forms case resource;
According to described setting event information, described case resource is carried out analogy conversion and content modification, obtain described rehearsal pre-
Case.
Electric power first-aid the most according to claim 7 rehearsal emulation mode, it is characterised in that described according to described rehearsal side
Case carries out drilling personnel assignment and sight is arranged, and after obtaining planning scheme and showing, also includes:
Receive the rehearsal data of input after drilling corresponding to described planning scheme, believe according to described rehearsal data genaration case
Cease and store.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610575919.2A CN106202507A (en) | 2016-07-20 | 2016-07-20 | Electric power first-aid rehearsal analogue system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610575919.2A CN106202507A (en) | 2016-07-20 | 2016-07-20 | Electric power first-aid rehearsal analogue system and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106202507A true CN106202507A (en) | 2016-12-07 |
Family
ID=57491971
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610575919.2A Pending CN106202507A (en) | 2016-07-20 | 2016-07-20 | Electric power first-aid rehearsal analogue system and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106202507A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106934753A (en) * | 2017-03-09 | 2017-07-07 | 宁波鼎翔消防技术有限公司 | A kind of fire-fighting drill management method and system |
CN109300355A (en) * | 2018-10-17 | 2019-02-01 | 中国石油天然气股份有限公司 | Polygonal pornographic scape construction method and device for Petrochemical Enterprises scene emergency drilling |
CN109523421A (en) * | 2018-11-14 | 2019-03-26 | 遵义华正电缆桥架有限公司 | A kind of power construction maintenance training system |
CN109635009A (en) * | 2018-12-27 | 2019-04-16 | 北京航天智造科技发展有限公司 | Fuzzy matching inquiry system and method |
CN110188979A (en) * | 2019-04-15 | 2019-08-30 | 广州智联研究院有限公司 | Water industry Emergency decision generation method and device |
CN111523757A (en) * | 2020-03-18 | 2020-08-11 | 北京易华录国际技术有限公司 | Plan digital management system and method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103679611A (en) * | 2013-12-17 | 2014-03-26 | 东莞中国科学院云计算产业技术创新与育成中心 | City comprehensive emergency intelligent simulation system based on case-based reasoning and operation method thereof |
US20140137024A1 (en) * | 2012-11-13 | 2014-05-15 | Peter M. Curtis | Facility operations management and mobile systems |
CN104318483A (en) * | 2014-09-22 | 2015-01-28 | 国家电网公司 | Virtual electric power urgent repair plan training system |
CN105023200A (en) * | 2015-08-04 | 2015-11-04 | 中国南方电网有限责任公司 | Power emergency drilling system and emergency drilling method thereof |
-
2016
- 2016-07-20 CN CN201610575919.2A patent/CN106202507A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140137024A1 (en) * | 2012-11-13 | 2014-05-15 | Peter M. Curtis | Facility operations management and mobile systems |
CN103679611A (en) * | 2013-12-17 | 2014-03-26 | 东莞中国科学院云计算产业技术创新与育成中心 | City comprehensive emergency intelligent simulation system based on case-based reasoning and operation method thereof |
CN104318483A (en) * | 2014-09-22 | 2015-01-28 | 国家电网公司 | Virtual electric power urgent repair plan training system |
CN105023200A (en) * | 2015-08-04 | 2015-11-04 | 中国南方电网有限责任公司 | Power emergency drilling system and emergency drilling method thereof |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106934753A (en) * | 2017-03-09 | 2017-07-07 | 宁波鼎翔消防技术有限公司 | A kind of fire-fighting drill management method and system |
CN109300355A (en) * | 2018-10-17 | 2019-02-01 | 中国石油天然气股份有限公司 | Polygonal pornographic scape construction method and device for Petrochemical Enterprises scene emergency drilling |
CN109523421A (en) * | 2018-11-14 | 2019-03-26 | 遵义华正电缆桥架有限公司 | A kind of power construction maintenance training system |
CN109635009A (en) * | 2018-12-27 | 2019-04-16 | 北京航天智造科技发展有限公司 | Fuzzy matching inquiry system and method |
CN109635009B (en) * | 2018-12-27 | 2023-09-15 | 北京航天智造科技发展有限公司 | Fuzzy matching inquiry system |
CN110188979A (en) * | 2019-04-15 | 2019-08-30 | 广州智联研究院有限公司 | Water industry Emergency decision generation method and device |
CN110188979B (en) * | 2019-04-15 | 2021-11-16 | 广州智联研究院有限公司 | Water industry emergency decision generation method and device |
CN111523757A (en) * | 2020-03-18 | 2020-08-11 | 北京易华录国际技术有限公司 | Plan digital management system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106202507A (en) | Electric power first-aid rehearsal analogue system and method | |
CN104778073B (en) | A kind of safe attacking and defending experiment porch of novel information and its implementation | |
CN103679611B (en) | Operation method of city comprehensive emergency intelligent simulation system based on case-based reasoning | |
CN106205261A (en) | A kind of hazardous chemical is met an urgent need 3D pseudo operation examination system and the method for examination | |
Militello et al. | Decision-centered design | |
CN106682246A (en) | Graphical design platform for power grid emergency training schemes | |
CN104299464B (en) | Electric power safety technical ability simulation training system | |
KR102210504B1 (en) | System of customized education program using ai education platform based on big data | |
CN107369123A (en) | Emergent simulated maneuver scheme generation method, device, medium and computer equipment | |
CN106250989A (en) | Electric power first-aid drill plan dynamic creation method and system | |
CN109300355A (en) | Polygonal pornographic scape construction method and device for Petrochemical Enterprises scene emergency drilling | |
CN104899799A (en) | Project management system | |
Jenvald et al. | A framework for web-based dissemination of models and lessons learned from emergency-response exercises and operations | |
Chroust et al. | Regional disasters and systemic reactions | |
Ratnasari et al. | BPTrends Redesign Methodology (BPRM) for the Development Disaster Management Prevention Information System | |
Indriyanti et al. | Development of mapping area software for dismissal people affected by covid-19 | |
CN110362828A (en) | Network information Risk Identification Method and system | |
Grimaz et al. | UNESCO Guidelines for Assessing Learning Facilities in the Context of Disaster Risk Reduction and Climate Change Adaptation: VISUS Methodology | |
de Castro et al. | Selection of software development good practices in micro and small enterprises: an approach using knowledge-based systems | |
Watson et al. | Experiencing GMA as a means of developing a conceptual model of the problem space involving understanding cascading effects in crises. | |
Korsvold et al. | Creating an intelligent energy organization through collective learning | |
Rice | Capital Accumulation and Education | |
Muñoz et al. | Covering the human perspective in software process improvement | |
Bakar et al. | THE MATURITY MODEL OF IMMERSIVE TECHNOLOGY APPLICATIONS USED FOR SAFETY TRAINING IN CONSTRUCTION: A SCIENTOMETRIC ANALYSIS | |
Jakes | Social science informing forest management—Bringing new knowledge to fuels managers |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161207 |