CN106200704A - A kind of RB process main vapour pressure setting value operation method and system - Google Patents

A kind of RB process main vapour pressure setting value operation method and system Download PDF

Info

Publication number
CN106200704A
CN106200704A CN201610794080.1A CN201610794080A CN106200704A CN 106200704 A CN106200704 A CN 106200704A CN 201610794080 A CN201610794080 A CN 201610794080A CN 106200704 A CN106200704 A CN 106200704A
Authority
CN
China
Prior art keywords
value
main vapour
vapour pressure
pressure
target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610794080.1A
Other languages
Chinese (zh)
Other versions
CN106200704B (en
Inventor
黄卫剑
万文军
朱亚清
李锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Guangdong Power Grid Co Ltd
Original Assignee
Electric Power Research Institute of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Guangdong Power Grid Co Ltd filed Critical Electric Power Research Institute of Guangdong Power Grid Co Ltd
Priority to CN201610794080.1A priority Critical patent/CN106200704B/en
Publication of CN106200704A publication Critical patent/CN106200704A/en
Application granted granted Critical
Publication of CN106200704B publication Critical patent/CN106200704B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05DSYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
    • G05D16/00Control of fluid pressure
    • G05D16/20Control of fluid pressure characterised by the use of electric means
    • G05D16/2006Control of fluid pressure characterised by the use of electric means with direct action of electric energy on controlling means
    • G05D16/2013Control of fluid pressure characterised by the use of electric means with direct action of electric energy on controlling means using throttling means as controlling means
    • G05D16/2026Control of fluid pressure characterised by the use of electric means with direct action of electric energy on controlling means using throttling means as controlling means with a plurality of throttling means

Landscapes

  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Control Of Turbines (AREA)

Abstract

The embodiment of the invention discloses a kind of RB process main vapour pressure setting value operation method and system, finally determining suitable main vapour pressure setting value by the main vapour pressure desired value calculating different RB types or RB target load, the RB process in prior art that solves uses the technical problem being unfavorable for unit safety, stable operation caused with the properly functioning identical main vapour pressure setting value operational loop of unit.

Description

A kind of RB process main vapour pressure setting value operation method and system
Technical field
The present invention relates to fired power generating unit automation field, particularly relate to a kind of RB process main vapour pressure setting value computing side Method and system.
Background technology
For reducing the fossil power plant auxiliary engine fault trip risk to fired power generating unit safe operation, current fired power generating unit is equipped with Auxiliary machinery fault automatic load-reducing function, i.e. RUN BACK function, is called for short RB.When the employing such as blower fan, feed pump 2 or multiple stage are arranged side by side Run subsidiary engine in one or more tripping operation time, except need to be controlled mode switch, quickly reduce unit target load, unit The working medium flows such as fuel, feedwater, air quantity, also need to carry out unit main steam pressure conservative control, so that boiler feedwater, main steam The unit parameter transition such as temperature are the most stable.
At present, major part fired power generating unit RB process carries out the constant DP control side of conservative control employing to unit main steam pressure Method, i.e. uses and the properly functioning identical main vapour pressure setting value operational loop of unit.
But existing technology has certain defect, because main vapour pressure fall is big during unit RB, main vapour pressure Power, unit load are long for fall time, and main steam temperature and reheat steam temperature decline too much, normally transport with unit if used The main vapour pressure setting value operational loop that row is identical, is unfavorable for unit safety, stable operation.
Summary of the invention
Embodiments provide a kind of RB process main vapour pressure setting value operation method and system, by calculating difference RB type or the main vapour pressure desired value of RB target load finally determine suitable main vapour pressure setting value, solve existing In technology, RB process uses that causes with the properly functioning identical main vapour pressure setting value operational loop of unit to be unfavorable for that unit is pacified Entirely, the technical problem of stable operation.
Embodiments provide a kind of RB process main vapour pressure setting value operation method, it is characterised in that including:
RB pressure target value is calculated according to the described RB type obtained in advance or described RB target load;
Monitoring main vapour pressure value in real time;
According to the described RB actuating signal detected in advance and the main vapour pressure initial set value of described former control system, calculating Described RB pressure target value, the described main vapour pressure value of monitoring judges, if described RB pressure target value is less than described master During vapour pressure force value, main vapour pressure value described in main vapour pressure setting value tracking, if described RB pressure target value is higher than described main vapour pressure In the presence of force value and described RB actuating signal, described main vapour pressure setting value remains described RB pressure target value, if described RB Actuating signal not in the presence of, described main vapour pressure setting value switches to the described main vapour pressure initial set value of former control system.
Alternatively,
Also wrapped before calculating RB pressure target value according to the described RB type detected in advance or described RB target load Include:
Obtain RB type or RB target load and detect RB actuating signal, the main vapour pressure of former control system initially sets Value.
Alternatively,
Calculate RB pressure target value according to the described RB type detected in advance or described RB target load to specifically include:
According to the described RB type detected in advance, obtain RB pressure target value by switching mode;
According to the described RB target load detected in advance, carry out functional operation and obtain RB pressure target value.
Alternatively,
Also wrapped before calculating RB pressure target value according to the described RB type detected in advance or described RB target load Include:
Detection unit load.
Alternatively,
According to the described RB actuating signal detected in advance and the main vapour pressure initial set value of described former control system, meter Described RB pressure target value, the described main vapour pressure value of monitoring calculated judge, if described RB pressure target value is less than described During main vapour pressure value, main vapour pressure value described in main vapour pressure setting value tracking, if described RB pressure target value is higher than described main vapour In the presence of force value and described RB actuating signal, described main vapour pressure setting value remains described RB pressure target value, if described RB actuating signal not in the presence of, described main vapour pressure setting value switches to the described main vapour pressure initial set value of former control system The most also include:
Described unit load according to detection, the described RB target load of acquisition, the described RB actuating signal that detects in advance Judge, if in the presence of described unit load is less than described RB target load and described RB actuating signal, then sending steam turbine master Control subtracts block signal.
The embodiment of the present invention additionally provides a kind of system based on RB process main vapour pressure setting value operation method, its feature It is, including:
RB pressure target value computing unit, based on according to the described RB type obtained in advance or described RB target load Calculate RB pressure target value;
Monitoring means, for monitoring main vapour pressure value in real time;
Main vapour pressure setting value determines unit, for according to the described RB actuating signal detected in advance and described former control being The main vapour pressure initial set value of system, the described RB pressure target value of calculating, the described main vapour pressure value of monitoring judge, if When described RB pressure target value is less than described main vapour pressure value, main vapour pressure value described in main vapour pressure setting value tracking, if described In the presence of RB pressure target value is higher than described main vapour pressure value and described RB actuating signal, described main vapour pressure setting value remains Described RB pressure target value, if described RB actuating signal not in the presence of, described main vapour pressure setting value switches to former control system Described main vapour pressure initial set value.
Alternatively,
Described system based on RB process main vapour pressure setting value operation method also includes:
Obtain detector unit, for obtaining RB type or RB target load and detecting RB actuating signal, former control system Main vapour pressure initial set value.
Alternatively,
Described RB pressure target value computing unit includes RB type pressure desired value computing unit and RB target load target Value computing unit;
RB type pressure desired value computing unit, for according to the described RB type detected in advance, obtaining by switching mode Obtain RB pressure target value;
RB target load desired value computing unit, for according to the described RB target load detected in advance, carrying out function fortune Calculation obtains RB pressure target value.
Alternatively,
Described acquisition detector unit, is additionally operable to detect unit load.
Alternatively,
Described system based on RB process main vapour pressure setting value operation method also includes:
Safety detection unit, for described unit load, the described RB target load of acquisition according to detection, detects in advance Described RB actuating signal judge, if described unit load exists less than described RB target load and described RB actuating signal Time, then send turbine main control and subtract block signal.
As can be seen from the above technical solutions, the embodiment of the present invention has the advantage that
Suitable main vapour is finally determined by the main vapour pressure desired value calculating different RB types or RB target load Pressure set points, the RB process in prior art that solves uses identical main vapour pressure setting value computing properly functioning with unit to return What road was caused is unfavorable for the technical problem of unit safety, stable operation;Meanwhile, if unit load sets in advance less than RB target load In the presence of fixed value and RB actuating signal, then sending turbine main control and subtract block signal, be possible to prevent that steam turbine pitch closes is too small, makes Become the function of the additional disturbance of unit load, water supply system and vapor (steam) temperature.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, also may be used To obtain other accompanying drawing according to these accompanying drawings.
One embodiment of a kind of RB process main vapour pressure setting value operation method that Fig. 1 provides for the embodiment of the present invention Flow chart;
Another embodiment of a kind of RB process main vapour pressure setting value operation method that Fig. 2 provides for the embodiment of the present invention Flow chart;
The one of a kind of based on RB process main vapour pressure setting value operation method the system that Fig. 3 provides for the embodiment of the present invention The structural representation of individual embodiment;
A kind of based on RB process main vapour pressure setting value operation method the system that Fig. 4 provides for the embodiment of the present invention another The structural representation of one embodiment;
Fig. 5 is the one of a kind of based on RB process main vapour pressure setting value operation method the system that the embodiment of the present invention provides The structure principle chart of individual embodiment;
Fig. 6 is an embodiment of a kind of RB process main vapour pressure setting value operation method that the embodiment of the present invention provides Structure principle chart;
Fig. 7 is another embodiment of a kind of RB process main vapour pressure setting value operation method that the embodiment of the present invention provides Structure principle chart.
Detailed description of the invention
Embodiments provide a kind of RB process main vapour pressure setting value operation method and system, by calculating difference RB type or the main vapour pressure desired value of RB target load finally determine suitable main vapour pressure setting value, solve existing In technology, RB process uses that causes with the properly functioning identical main vapour pressure setting value operational loop of unit to be unfavorable for that unit is pacified Entirely, the technical problem of stable operation.
For making the goal of the invention of the present invention, feature, the advantage can be the most obvious and understandable, below in conjunction with the present invention Accompanying drawing in embodiment, is clearly and completely described the technical scheme in the embodiment of the present invention, it is clear that disclosed below Embodiment be only a part of embodiment of the present invention, and not all embodiment.Based on the embodiment in the present invention, this area All other embodiments that those of ordinary skill is obtained under not making creative work premise, broadly fall into present invention protection Scope.
Refer to Fig. 1, a reality of a kind of RB process main vapour pressure setting value operation method that the embodiment of the present invention provides Execute example to include:
101, calculate RB pressure target value according to the RB type obtained in advance or RB target load;
102, monitoring main vapour pressure value in real time;
103, according to the RB actuating signal detected in advance and the main vapour pressure initial set value of former control system, the RB of calculating Pressure target value, the main vapour pressure value of monitoring judge, if RB pressure target value is less than main vapour pressure value, main vapour pressure sets Definite value follows the tracks of main vapour pressure value, if in the presence of RB pressure target value is higher than main vapour pressure value and RB actuating signal, main vapour pressure sets Definite value remains RB pressure target value, if RB actuating signal not in the presence of, main vapour pressure setting value switches to former control system Main vapour pressure initial set value.
In the present embodiment, first calculate RB pressure target value according to the RB type obtained in advance or RB target load, then Monitoring main vapour pressure value in real time, the main vapour pressure finally according to the RB actuating signal detected in advance and former control system initially sets Value, the RB pressure target value calculated, the main vapour pressure value of monitoring judge, if RB pressure target value is less than main vapour pressure value Time, main vapour pressure setting value tracking main vapour pressure value, if RB pressure target value exists higher than main vapour pressure value and RB actuating signal Time, main vapour pressure setting value remains RB pressure target value, if RB actuating signal not in the presence of, main vapour pressure setting value switches to The main vapour pressure initial set value of former control system.
Refer to Fig. 2, Fig. 6 and Fig. 7, a kind of RB process main vapour pressure setting value operation method that the embodiment of the present invention provides Another embodiment include:
201, obtain RB type or RB target load and detect RB actuating signal, the main vapour pressure of former control system initially sets Definite value and unit load;
202, according to the RB type detected in advance, obtain RB pressure target value by switching mode;
203, according to the described RB target load detected in advance, carry out functional operation and obtain RB pressure target value;
204, monitoring main vapour pressure value in real time;
205, according to the RB actuating signal detected in advance and the main vapour pressure initial set value of former control system, the RB of calculating Pressure target value, the main vapour pressure value of monitoring judge, if RB pressure target value is less than main vapour pressure value, main vapour pressure sets Definite value follows the tracks of main vapour pressure value, if in the presence of RB pressure target value is higher than main vapour pressure value and RB actuating signal, main vapour pressure sets Definite value remains RB pressure target value, if RB actuating signal not in the presence of, main vapour pressure setting value switches to former control system Main vapour pressure initial set value;
206, judge according to the unit load of detection, the RB target load of acquisition, the RB actuating signal that detects in advance, If in the presence of unit load is less than RB target load and RB actuating signal, then sending turbine main control and subtract block signal.
In the present embodiment, first obtain RB type or RB target load and detect RB actuating signal, the master of former control system Steam pressure initial set value and unit load, according to the described RB type detected in advance, obtain RB pressure by switching mode Desired value such as following table one,
Sequence number RB type Main vapour pressure desired value (MPa)
1 Coal pulverizer RB 18
2 Send air-introduced machine RB 19.6
3 Primary air fan RB 16
4 Feed pump RB 16
Table one
Or according to the described RB target load detected in advance, carry out functional operation and obtain RB pressure target value such as following table Two,
Table two
Monitoring main vapour pressure value the most in real time, according to the RB actuating signal detected in advance and the main vapour pressure of former control system Initial set value, the RB pressure target value of calculating, the main vapour pressure value of monitoring judge, if RB pressure target value is less than main vapour During force value, main vapour pressure setting value tracking main vapour pressure value, if RB pressure target value is higher than main vapour pressure value and RB action letter In the presence of number, main vapour pressure setting value remains RB pressure target value, if RB actuating signal not in the presence of, main vapour pressure setting value Switch to the main vapour pressure initial set value of former control system, finally according to described unit load, the described RB of acquisition of detection Target load, the described RB actuating signal detected in advance judge, if described unit load moves less than RB target load and RB In the presence of making signal, then send turbine main control and subtract block signal.
Referring to Fig. 3 and Fig. 5, the one that the embodiment of the present invention provides is based on RB process main vapour pressure setting value operation method An embodiment of system include:
RB pressure target value computing unit, for calculating RB pressure according to the RB type obtained in advance or RB target load Desired value;
Monitoring means, for monitoring main vapour pressure value in real time;
Main vapour pressure setting value determines unit, for according to the RB actuating signal detected in advance and the main vapour of former control system Pressure set points, the RB pressure target value of calculating, the main vapour pressure value of monitoring judge, if RB pressure target value is less than main vapour During force value, main vapour pressure setting value tracking main vapour pressure value, if RB pressure target value is higher than main vapour pressure value and RB action letter In the presence of number, main vapour pressure setting value remains RB pressure target value, if RB actuating signal not in the presence of, main vapour pressure setting value Main vapour pressure setting value for former control system.
Referring to Fig. 4 and Fig. 5, the one that the embodiment of the present invention provides is based on RB process main vapour pressure setting value operation method Another embodiment of system include:
RB pressure target value computing unit, for calculating RB pressure according to the RB type obtained in advance or RB target load Desired value;
Monitoring means, for monitoring main vapour pressure value in real time;
Main vapour pressure setting value determines unit, for according to the RB actuating signal detected in advance and the main vapour of former control system Pressure set points, the RB pressure target value of calculating, the main vapour pressure value of monitoring judge, if RB pressure target value is less than main vapour During force value, main vapour pressure setting value tracking main vapour pressure value, if RB pressure target value is higher than main vapour pressure value and RB action letter In the presence of number, main vapour pressure setting value remains RB pressure target value, if RB actuating signal not in the presence of, main vapour pressure setting value Main vapour pressure setting value for former control system.
System based on RB process main vapour pressure setting value operation method also includes:
Obtain detector unit, for obtaining RB type or RB target load and detecting RB actuating signal, former control system Main vapour pressure initial set value.
RB pressure target value computing unit includes RB type pressure desired value computing unit and RB target load desired value meter Calculate unit;
RB type pressure desired value computing unit, for according to the RB type detected in advance, obtaining RB by switching mode Pressure target value;
RB target load desired value computing unit, for according to the RB target load detected in advance, carrying out functional operation and obtain To RB pressure target value.
Obtain detector unit, be additionally operable to detect unit load.
System based on RB process main vapour pressure setting value operation method also includes:
Safety detection unit, for the unit load according to detection, the RB target load of acquisition, the RB action that detects in advance Signal judges, if in the presence of unit load is less than RB target load and RB actuating signal, then sending turbine main control and subtract locking Signal.
Those skilled in the art is it can be understood that arrive, for convenience and simplicity of description, and the system of foregoing description, The specific works process of device and unit, is referred to the corresponding process in preceding method embodiment, does not repeats them here.
In several embodiments provided herein, it should be understood that disclosed system, apparatus and method are permissible Realize by another way.Such as, device embodiment described above is only schematically, such as, and described unit Dividing, be only a kind of logic function and divide, actual can have other dividing mode, the most multiple unit or assembly when realizing Can in conjunction with or be desirably integrated into another system, or some features can be ignored, or does not performs.Another point, shown or The coupling each other discussed or direct-coupling or communication connection can be the indirect couplings by some interfaces, device or unit Close or communication connection, can be electrical, machinery or other form.
The described unit illustrated as separating component can be or may not be physically separate, shows as unit The parts shown can be or may not be physical location, i.e. may be located at a place, or can also be distributed to multiple On NE.Some or all of unit therein can be selected according to the actual needs to realize the mesh of the present embodiment scheme 's.
It addition, each functional unit in each embodiment of the present invention can be integrated in a processing unit, it is also possible to It is that unit is individually physically present, it is also possible to two or more unit are integrated in a unit.Above-mentioned integrated list Unit both can realize to use the form of hardware, it would however also be possible to employ the form of SFU software functional unit realizes.
If described integrated unit realizes and as independent production marketing or use using the form of SFU software functional unit Time, can be stored in a computer read/write memory medium.Based on such understanding, technical scheme is substantially The part that in other words prior art contributed or this technical scheme completely or partially can be with the form of software product Embodying, this computer software product is stored in a storage medium, including some instructions with so that a computer Equipment (can be personal computer, server, or the network equipment etc.) performs the complete of method described in each embodiment of the present invention Portion or part steps.And aforesaid storage medium includes: USB flash disk, portable hard drive, read only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), magnetic disc or CD etc. are various can store journey The medium of sequence code.
The above, above example only in order to technical scheme to be described, is not intended to limit;Although with reference to front State embodiment the present invention has been described in detail, it will be understood by those within the art that: it still can be to front State the technical scheme described in each embodiment to modify, or wherein portion of techniques feature is carried out equivalent;And these Amendment or replacement, do not make the essence of appropriate technical solution depart from the spirit and scope of various embodiments of the present invention technical scheme.

Claims (10)

1. a RB process main vapour pressure setting value operation method, it is characterised in that including:
RB pressure target value is calculated according to the described RB type obtained in advance or described RB target load;
Monitoring main vapour pressure value in real time;
According to the described RB actuating signal detected in advance and the main vapour pressure initial set value of described former control system, the institute of calculating State RB pressure target value, the described main vapour pressure value of monitoring judges, if described RB pressure target value is less than described main vapour pressure During force value, main vapour pressure value described in main vapour pressure setting value tracking, if described RB pressure target value is higher than described main vapour pressure value And in the presence of described RB actuating signal, described main vapour pressure setting value remains described RB pressure target value, if described RB action Signal not in the presence of, described main vapour pressure setting value switches to the described main vapour pressure initial set value of former control system.
RB process main vapour pressure setting value operation method the most according to claim 1, it is characterised in that according to examining in advance The described RB type surveyed or described RB target load also include before calculating RB pressure target value:
Obtain RB type or RB target load and detect the main vapour pressure initial set value of RB actuating signal, former control system.
RB process main vapour pressure setting value operation method the most according to claim 1, it is characterised in that according to detecting in advance Described RB type or described RB target load calculate RB pressure target value specifically include:
According to the described RB type detected in advance, obtain RB pressure target value by switching mode;
According to the described RB target load detected in advance, carry out functional operation and obtain RB pressure target value.
RB process main vapour pressure setting value operation method the most according to claim 1, it is characterised in that according to examining in advance The described RB type surveyed or described RB target load also include before calculating RB pressure target value:
Detection unit load.
RB process main vapour pressure setting value operation method the most according to claim 4, it is characterised in that according to examining in advance The described RB actuating signal surveyed and the main vapour pressure initial set value of described former control system, the described RB pressure target of calculating Value, the described main vapour pressure value of monitoring judge, if described RB pressure target value is less than described main vapour pressure value, and main vapour pressure Main vapour pressure value described in power setting value tracking, if described RB pressure target value is higher than described main vapour pressure value and described RB action letter In the presence of number, described main vapour pressure setting value remains described RB pressure target value, if described RB actuating signal not in the presence of, institute Also include after stating the described main vapour pressure initial set value that main vapour pressure setting value switches to former control system:
Described unit load according to detection, the described RB target load of acquisition, the described RB actuating signal that detects in advance are carried out Judge, if in the presence of described unit load is less than described RB target load and described RB actuating signal, then sending turbine main control and subtract Block signal.
6. a system based on RB process main vapour pressure setting value operation method, it is characterised in that including:
RB pressure target value computing unit, for calculating RB according to the described RB type obtained in advance or described RB target load Pressure target value;
Monitoring means, for monitoring main vapour pressure value in real time;
Main vapour pressure setting value determines unit, for according to the described RB actuating signal that detects in advance and described former control system Main vapour pressure initial set value, the described RB pressure target value of calculating, the described main vapour pressure value of monitoring judge, if described When RB pressure target value is less than described main vapour pressure value, main vapour pressure value described in main vapour pressure setting value tracking, if described RB pressure In the presence of power desired value is higher than described main vapour pressure value and described RB actuating signal, described main vapour pressure setting value remains described RB pressure target value, if described RB actuating signal not in the presence of, described main vapour pressure setting value switches to the institute of former control system State main vapour pressure initial set value.
System based on RB process main vapour pressure setting value operation method the most according to claim 6, it is characterised in that also Including:
Obtain detector unit, for obtaining RB type or RB target load and detecting the main vapour of RB actuating signal, former control system Pressure initial set value.
System based on RB process main vapour pressure setting value operation method the most according to claim 6, it is characterised in that institute State RB pressure target value computing unit and include RB type pressure desired value computing unit and RB target load desired value computing unit;
RB type pressure desired value computing unit, for according to the described RB type detected in advance, obtaining RB by switching mode Pressure target value;
RB target load desired value computing unit, for according to the described RB target load detected in advance, carrying out functional operation and obtain To RB pressure target value.
System based on RB process main vapour pressure setting value operation method the most according to claim 7, it is characterised in that
Described acquisition detector unit, is additionally operable to detect unit load.
System based on RB process main vapour pressure setting value operation method the most according to claim 6, it is characterised in that Also include:
Safety detection unit, for the described unit load according to detection, the described RB target load of acquisition, the institute detected in advance State RB actuating signal to judge, if in the presence of described unit load is less than described RB target load and described RB actuating signal, Then send turbine main control and subtract block signal.
CN201610794080.1A 2016-08-31 2016-08-31 A kind of RB process main vapour pressure setting value operation method and system Active CN106200704B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610794080.1A CN106200704B (en) 2016-08-31 2016-08-31 A kind of RB process main vapour pressure setting value operation method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610794080.1A CN106200704B (en) 2016-08-31 2016-08-31 A kind of RB process main vapour pressure setting value operation method and system

Publications (2)

Publication Number Publication Date
CN106200704A true CN106200704A (en) 2016-12-07
CN106200704B CN106200704B (en) 2019-05-21

Family

ID=58086279

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610794080.1A Active CN106200704B (en) 2016-08-31 2016-08-31 A kind of RB process main vapour pressure setting value operation method and system

Country Status (1)

Country Link
CN (1) CN106200704B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002242615A (en) * 2001-02-19 2002-08-28 Hitachi Ltd Load run back control method
JP2008274816A (en) * 2007-04-27 2008-11-13 Hitachi Ltd Circulating water system protection device used for power-generating plant
CN101609327A (en) * 2008-06-18 2009-12-23 浙江省电力试验研究院 All-working-condition automatic RB control method
CN203656953U (en) * 2013-07-19 2014-06-18 国家电网公司 Desulfurization GGH (gas gas heater) RB (runback) system
CN105135405A (en) * 2015-08-17 2015-12-09 国家电网公司 Induced draft fan RB control method of high-sodium lignite tower boiler unit
CN105589481A (en) * 2015-03-31 2016-05-18 河南华润电力古城有限公司 Intelligent sliding pressure control method and system
CN105627287A (en) * 2015-12-23 2016-06-01 神华集团有限责任公司 Water feeding pump RB control system and method of supercritical CFB boiler generator set

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002242615A (en) * 2001-02-19 2002-08-28 Hitachi Ltd Load run back control method
JP2008274816A (en) * 2007-04-27 2008-11-13 Hitachi Ltd Circulating water system protection device used for power-generating plant
CN101609327A (en) * 2008-06-18 2009-12-23 浙江省电力试验研究院 All-working-condition automatic RB control method
CN203656953U (en) * 2013-07-19 2014-06-18 国家电网公司 Desulfurization GGH (gas gas heater) RB (runback) system
CN105589481A (en) * 2015-03-31 2016-05-18 河南华润电力古城有限公司 Intelligent sliding pressure control method and system
CN105135405A (en) * 2015-08-17 2015-12-09 国家电网公司 Induced draft fan RB control method of high-sodium lignite tower boiler unit
CN105627287A (en) * 2015-12-23 2016-06-01 神华集团有限责任公司 Water feeding pump RB control system and method of supercritical CFB boiler generator set

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
尹峰等: "火电机组全工况自动RB控制策略的研究与应用", 《浙江电力》 *
王晓勇等: "某超临界350MW机组增压风机(带旁路)的RB控制", 《中国电力》 *
马睿等: "600MW超临界循环流化床机组RB控制策略", 《中国电力》 *

Also Published As

Publication number Publication date
CN106200704B (en) 2019-05-21

Similar Documents

Publication Publication Date Title
CN101483078B (en) Nuclear power plant, water level control method and system for steam generator
CN109519233B (en) Online monitoring method and system for steam inlet regulating valve of steam turbine of nuclear power plant
CN108445258B (en) Diagnosis method for maglev train single-iron levitation acceleration sensor based on integrator
WO2015129084A1 (en) Power-system monitoring device, power-system control device, and power-system monitoring method
CN102638040A (en) Online setting method of safety and stability emergency control fixed value of electric power system
CN106294076A (en) A kind of server relevant fault Forecasting Methodology and system thereof
CN108733883B (en) Method for determining demand of subsequent spare parts of normal type unit
CN111123770B (en) Method and device for determining opening of bypass model under FCB working condition
CN107016448B (en) Periodic inspection equipment availability evaluation method with fault/maintenance time subjected to random distribution
CN106200704A (en) A kind of RB process main vapour pressure setting value operation method and system
KR101903073B1 (en) Method and Apparatus for prevention of Reactor Trip in a Loss of one Reactor Coolant Pump
Kumar et al. Performance modeling of furnace draft air cycle in a thermal power plant
CN110360064A (en) Wind power generating set control method and wind power generating set
Pan et al. Reliability analysis of turbine blades based on fuzzy response surface method
CN104791754B (en) Supercritical or ultra-supercritical generating set variable-load overshoot control method
CN100541213C (en) Electric network fault self-adapting diagnostic method based on element correlation analysis
CN105205492A (en) Fuzzy nearest neighbor fusion diagnosis method of thermodynamic system fault
CN109885983A (en) The high-impedance transformer impedance parameter of system short-circuit electric current is inhibited to determine method
CN113678107B (en) Method and computing device for detecting and locating faults in acquisition systems
CN111784106B (en) Active splitting section offline screening method and device based on disturbed track
CN107238102A (en) A kind of primary air fan RB control methods under full load mode
CN204404211U (en) A kind of thermal power plant pulverized coal preparation system
CN107144063B (en) Ice machine and ice blockage detection method and device
CN104165352B (en) A kind of nuclear power plant evaporator Water-Level Supervising System and method for supervising thereof
CN113565575A (en) Boiler wall temperature protection assessment and control method for steam pump fault combined electric pump

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant