CN106195440B CN201610725168.8A CN201610725168A CN106195440B CN 106195440 B CN106195440 B CN 106195440B CN 201610725168 A CN201610725168 A CN 201610725168A CN 106195440 B CN106195440 B CN 106195440B
Authority
CN
China
Prior art keywords
cylinder
pipeline
hydraulic cylinders
tube
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610725168.8A
Other languages
Chinese (zh)
Other versions
CN106195440A (en
Inventor
陈子传
周连国
唐胜天
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Stecol Corp
Original Assignee
Sinohydro Tianjin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Tianjin Engineering Co Ltd filed Critical Sinohydro Tianjin Engineering Co Ltd
Priority to CN201610725168.8A priority Critical patent/CN106195440B/en
Publication of CN106195440A publication Critical patent/CN106195440A/en
Application granted granted Critical
Publication of CN106195440B publication Critical patent/CN106195440B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/02Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes for connecting objects by press fit or for detaching same
    • B23P19/022Extracting or inserting relatively long parts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/02Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes for connecting objects by press fit or for detaching same
    • B23P19/025For detaching only
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/02Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes for connecting objects by press fit or for detaching same
    • B23P19/027Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes for connecting objects by press fit or for detaching same using hydraulic or pneumatic means
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Emergency Lowering Means (AREA)

Abstract

Water supply line construction pipe drawing device and tube drawing construction method, pipe drawing device include holding part and driving mechanism tightly, hold part tightly and use hooping structure, are bolted and are constituted respectively at both ends by two semicircular bands;Driving mechanism includes two hydraulic cylinders, two hydraulic cylinders are arranged in parallel in the same side of hooping structure, the cylinder rod end of two hydraulic cylinders forms with the both ends connecting portion of two semicircle bands connected respectively, two hydraulic cylinders are separately fixed on respective oil cylinder bracket, the hanging platform of cooperation can be formed with pipeline major part flange by being equipped with close to the inside of one end that hydraulic cylinder cylinder rod is stretched out on each oil cylinder bracket, and lanyard part is separately installed at the both ends of each oil cylinder bracket;Two hydraulic cylinders are connected by the oil supply system of pipeline and peripheral hardware respectively.Tube drawing construction method, step are;S1 pipe drawing devices are installed in place;S2 opens oil supply system, realizes tube drawing.The present invention is not limited by construction site, improves pipeline construction efficiency.

Description

Water supply line construction pipe drawing device and tube drawing construction method
Technical field
The invention belongs to water supply line technical field of construction, more particularly to water supply line construction is applied with pipe drawing device and tube drawing Work method.
Background technology
In the links of waterline construction, frequently encounters mounted pipe, short tube, suppresses the pipes such as plug with wanting Again the problem of transfering to.The extraction of this large scale ductile iron pipe, typically rely on large scale equipment such as excavator, loading machine, The cooperations such as crane are extracted, and are operated very troublesome, from time, cost and working efficiency for be very be unfavorable for scene Construction.In addition, some construction sites cannot be introduced into large scale equipment, in this way, further increasing the difficulty of tube drawing.
Invention content
The present invention provides a kind of water supply line construction pipe drawing device to solve technical problem present in known technology And tube drawing construction method, the pipe drawing device is simple in structure, is not limited by construction site, flexible and convenient to use, can reduce tube drawing Construction cost, the tube drawing construction method improve pipeline construction efficiency.
The present invention is adopted the technical scheme that solve technical problem present in known technology:
A kind of water supply line construction pipe drawing device, it is characterised in that:Include with the holding part of tube fit and with holding The driving mechanism of part connection, the holding part use hooping structure, hooping structure to be distinguished at both ends by two semicircular bands Composition is bolted;The driving mechanism uses hydraulic drive mechanism comprising two hydraulic cylinders, two hydraulic cylinders are parallel Be arranged in the same side of hooping structure, the cylinder rod ends of two hydraulic cylinders respectively with the both ends connecting portion shape of two halves circle band At being fixedly connected, two hydraulic cylinders are separately fixed on respective oil cylinder bracket, close to hydraulic cylinder on each oil cylinder bracket The inside of one end that bar stretches out is equipped with the hanging platform that cooperation can be formed with pipeline major part flange, distinguishes at the both ends of each oil cylinder bracket Lanyard part is installed;Two hydraulic cylinders are connected by the oil supply system of pipeline and peripheral hardware respectively.
Preferably:Two semicircular bands are by band iron material machine-shaping.
Preferably:Lanyard part uses hanging ring structure or hook structure.
A kind of tube drawing construction method, which is characterized in that use any water supply line constructions of claim 1-3 and use The step of pipe drawing device, tube drawing is:
S1 pipe drawing devices are installed in place:First by two semicircular bands under the shape body of separation, obvolvent one on the other On pipeline to be pulled out;Then manually or by small-sized pulling apparatus, by two drawstrings, wherein the both ends of a drawstring The two lanyard parts that two cylinder brackets are located at front end are connected, the both ends of another drawstring connect two extensions that two cylinder brackets are located at rear end It restricts part, two cylinder brackets and two hydraulic cylinder synchronous on cylinder bracket is transferred to and are connected with pipeline to be pulled out The both sides of fixed -piping, and so that the major part flange position of hanging platform and fixed -piping on two cylinder brackets is formed and be affiliated to cooperation;Most The connecting portion by the end of the cylinder rod of two hydraulic cylinders respectively with two semicircle band both ends is fixed by bolt afterwards Connection, while the hooping structure for making two semicircular bands be formed is held tightly on pipeline to be pulled out;
After S2 pipe drawing devices are installed in place, oil supply system is opened, two hydraulic cylinder synchronous actions apply outward to cylinder rod Launch force, two cylinder brackets are limited by the major part flange position of fixed -piping, so that two cylinder rods is passed through hooping structure and pass power It moves on pipeline to be pulled out, so that pipeline to be pulled out is obtained an outside pull out force, when the effect for being applied to both sides cylinder rod When power reaches the friction value of tube wall and cushion rubber, pipe is pulled out, and completes tube drawing action.
The invention has the advantages and positive effects that:
This pipe drawing device is mainly made of anchor ear, two hydraulic cylinders and two cylinder brackets, and overall structure is simple, is used When, anchor ear is held tightly on pipeline to be pulled out, two oil cylinders and two cylinder brackets be respectively arranged with pipeline to be pulled out The both sides of connected fixed -piping, except outside the hydraulic system that connects, mainly occupy the space in existing pipeline foundation pit, therefore not It is limited, is had the advantages that flexible and convenient to use by construction site.The pipe drawing device is set compared to the large size that existing tube drawing uses Standby, use cost is relatively low, in this way, the construction cost of tube drawing can be greatly lowered.It is constructed using the tube drawing of this pipe drawing device Method, since the installation of pipe drawing device and the operation of tube drawing are more convenient and time saving and energy saving, in this way, pipe is also greatly improved The efficiency of line construction.
Description of the drawings
Fig. 1 is the structural schematic diagram of pipe drawing device of the present invention and water pipeline cooperation.
In figure:1, part is held tightly;1-1, semicircular band;1-2, bolt;2, driving mechanism;2-1, hydraulic cylinder;2-2, oil Bracket cylinder;2-2-1, hanging platform;2-3, lanyard part;1 ', pipeline to be pulled out;2 ', fixed -piping;2-1 ', major part flange.
Specific implementation mode
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and coordinate attached drawing Detailed description are as follows:
Referring to Fig. 1, a kind of water supply line construction pipe drawing device, mainly by with tube fit holding part 1 and with embrace 2 two parts of driving mechanism of tight part connection are constituted.
The holding part uses hooping structure, hooping structure to pass through spiral shell respectively at both ends by two semicircular band 1-1 Bolt 1-2 is connected and composed, specifically, outwardly extending flanging, the flanging at both ends is arranged at both ends in two semicircular bands Bolt hole is provided on part, two semicircular bands are connected to form hooping structure by the flanging at both ends.
The driving mechanism uses hydraulic drive mechanism comprising two hydraulic cylinder 2-1, two hydraulic cylinders are arranged in parallel in The same side of hooping structure, the both ends connecting portion of the cylinder rod ends of two hydraulic cylinders respectively with two halves circle band form fixation Connection, specifically, flat structure is made in the cylinder rod end of two hydraulic cylinders, the cylinder rod end of two hydraulic cylinders is clamped in respectively It is next by bolt lock in respective side cooperation flanging between the respective side cooperation flanging of two semicircular bands, it also achieves With being fixedly connected for cylinder rod end.Two hydraulic cylinders are separately fixed on an oil cylinder bracket 2-2, are leaned on each oil cylinder bracket The inside of one end that nearly hydraulic cylinder cylinder rod is stretched out is equipped with the hanging platform 2-2-1 that cooperation can be formed with pipeline major part flange, in each oil The both ends of bracket cylinder are separately installed with lanyard part 2-3.Two hydraulic cylinders are connected by the oil supply system of pipeline and peripheral hardware respectively, are supplied Oil system refers to existing hydraulic cylinder oil supply system, includes mainly hydraulic pump, Fuel Tanking Unit, control valve and connecting line, at this In invention, hydraulic pump preferably uses the gasoline engine hydraulic pump structure of rated pressure 12.5MPA, it is possible to provide larger power output. Above-mentioned oil supply system is not shown in the accompanying drawings.
In above structure, two semicircular bands are preferably by band iron material machine-shaping.Specifically, 80*8 can be used Band iron machine-shaping.
In above structure, lanyard part uses hanging ring structure or hook structure.
The step of a kind of tube drawing construction method, uses above-mentioned water supply line construction pipe drawing device, tube drawing be:
S1 pipe drawing devices are installed in place:First by two semicircular bands under the shape body of separation, obvolvent one on the other On pipeline to be pulled out, specifically, keeping the tuck portion one at two semicircular band both ends a pair of just, at this time on flanging Bolt hole is also to positive status;Then artificial or by small-sized pulling apparatus, by two drawstrings, wherein drawstring Both ends connect the two lanyard parts that two cylinder brackets are located at front end, and the both ends of another drawstring connect two cylinder brackets and are located at rear end Two lanyard parts transfer to two cylinder brackets and two hydraulic cylinder synchronous on cylinder bracket and pipeline 1 ' to be pulled out The both sides of connected fixed -piping 2 ', i.e. a cylinder bracket and a hydraulic cylinder are arranged in the side of fixed -piping, another Cylinder bracket and another hydraulic cylinder are arranged in the other side of fixed -piping, and make the hanging platform on two cylinder brackets and fixed -piping Major part flange position 2-1 ' formation be affiliated to cooperation;Finally by the end of the cylinder rod of two hydraulic cylinders respectively with two halves circle band The connecting portion at both ends is fixedly connected by bolt, specifically, the flat end of two cylinder rods is inserted respectively into two halves circle Band both ends correspondence flanging between, and by the bolt of corresponding two flangings of connection, the flat end of cylinder rod is fixedly clamped, together When so that two semicircular bands is formed hooping structure hold tightly in pipeline to be pulled out;
After S2 pipe drawing devices are installed in place, oil supply system is opened, two hydraulic cylinder synchronous actions apply outward to cylinder rod Launch force, two cylinder brackets are limited by the major part flange position of fixed -piping, so that two cylinder rods is passed through hooping structure and pass power It moves on pipeline to be pulled out, so that pipeline to be pulled out is obtained an outside pull out force, when the effect for being applied to both sides cylinder rod When power reaches the friction value of tube wall and cushion rubber, pipe is pulled out, and completes tube drawing action.
Above-mentioned pipe drawing device and tube drawing construction method is also applied for suppressing the pipes such as plug and match in addition to being extracted suitable for pipeline The extraction of part.
Using this pipe drawing device, can after water pipeline bulge test, in the case where not damaging oversleeve, extract pipe or Person suppresses plug, does not need large scale equipment, it is only necessary to which simple manual operation makes construction simplify without geographical restrictions, and saving is set It is standby, fund is saved, production efficiency is greatly improved.This pipe drawing device is especially applied some large scale equipments are unapproachable Building site section, there is preferable application.

Claims (3)

1. a kind of tube drawing construction method, which is characterized in that using water supply line construction pipe drawing device:Include and tube fit The driving mechanism held part tightly and connect with holding part, the holding part use hooping structure, hooping structure semicircular by two Composition is bolted at both ends in band respectively;The driving mechanism uses hydraulic drive mechanism comprising two hydraulic cylinders, Two hydraulic cylinders are arranged in parallel in the same side of hooping structure, the cylinder rod ends of two hydraulic cylinders respectively with two halves circle band Both ends connecting portion forms a fixed connection, and two hydraulic cylinders are separately fixed on respective oil cylinder bracket, in each oil cylinder bracket The upper inside close to one end that hydraulic cylinder cylinder rod is stretched out is equipped with the hanging platform that cooperation can be formed with pipeline major part flange, in each oil cylinder The both ends of bracket are separately installed with lanyard part;Two hydraulic cylinders are connected by the oil supply system of pipeline and peripheral hardware respectively;Tube drawing Step is:
S1 pipe drawing devices are installed in place:First by two semicircular bands under the shape body of separation, obvolvent one on the other is waiting for On the pipeline of extraction;Then manually or by small-sized pulling apparatus, by two drawstrings, wherein the both ends connection of a drawstring Two cylinder brackets are located at two lanyard parts of front end, and the both ends of another drawstring connect two lanyards that two cylinder brackets are located at rear end Two cylinder brackets and two hydraulic cylinder synchronous on cylinder bracket are transferred to and are consolidated with what pipeline to be pulled out was connected by part The both sides in fixed tube road, and so that the major part flange position of hanging platform and fixed -piping on two cylinder brackets is formed and be affiliated to cooperation;Finally Company is fixed by bolt in connecting portion by the end of the cylinder rod of two hydraulic cylinders respectively with two semicircle band both ends It connects, while the hooping structure for making two semicircular bands be formed is held tightly on pipeline to be pulled out;
After S2 pipe drawing devices are installed in place, oil supply system is opened, two hydraulic cylinder synchronous actions apply outside release to cylinder rod Power, two cylinder brackets are limited by the major part flange position of fixed -piping, so that two cylinder rods is passed through hooping structure and arrive power transmission On pipeline to be pulled out, pipeline to be pulled out is made to obtain an outside pull out force, when the active force for being applied to both sides cylinder rod reaches When to the friction value of tube wall and cushion rubber, pipe is pulled out, and completes tube drawing action.
2. tube drawing construction method according to claim 1, it is characterised in that:Two semicircular bands are by band iron material Machine-shaping.
3. tube drawing construction method according to claim 1, it is characterised in that:Lanyard part is using hanging ring structure or hook knot Structure.
CN201610725168.8A 2016-08-25 2016-08-25 Water supply line construction pipe drawing device and tube drawing construction method Active CN106195440B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610725168.8A CN106195440B (en) 2016-08-25 2016-08-25 Water supply line construction pipe drawing device and tube drawing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610725168.8A CN106195440B (en) 2016-08-25 2016-08-25 Water supply line construction pipe drawing device and tube drawing construction method

Publications (2)

Publication Number Publication Date
CN106195440A CN106195440A (en) 2016-12-07
CN106195440B true CN106195440B (en) 2018-08-21

Family

ID=57524277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610725168.8A Active CN106195440B (en) 2016-08-25 2016-08-25 Water supply line construction pipe drawing device and tube drawing construction method

Country Status (1)

Country Link
CN (1) CN106195440B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108223913B (en) * 2018-03-07 2023-09-05 山东顺河路桥工程有限公司 Pipeline installation and backfill checking auxiliary tool
CN109895027A (en) * 2019-04-01 2019-06-18 中建新疆建工(集团)有限公司 Novel heavy socket pipe tube drawing device
CN111911711A (en) * 2020-07-15 2020-11-10 谢祥松 Natural gas energy pipeline laying construction method
CN112811350B (en) * 2021-02-04 2024-06-14 大连轩泰重工有限公司 Lifting pipe drawing trolley
CN113202975A (en) * 2021-05-20 2021-08-03 中铁隧道局集团有限公司 Underground obstacle pipeline processing method for urban restricted area
CN114211451B (en) * 2021-10-28 2023-12-05 上海外高桥造船有限公司 Tube drawing device for adjustable jig frame

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2113598B (en) * 1981-12-15 1985-12-11 Omega Software Heat exchanger maintenance
JPS61257723A (en) * 1985-05-04 1986-11-15 Chiyoda Chem Eng & Constr Co Ltd Extracting and extruding device of pipe bundle
JP2010017833A (en) * 2008-07-14 2010-01-28 Kurimoto Ltd Pipe joint dismantling device and dismantling method
CN201419313Y (en) * 2009-06-12 2010-03-10 上海船厂船舶有限公司 Assembly and disassembly device for ship coupling
CN203141057U (en) * 2012-12-18 2013-08-21 云南昆钢重型装备制造集团有限公司 Drawing device
CN103612107A (en) * 2013-11-25 2014-03-05 河北钢铁股份有限公司邯郸分公司 Universal tool capable of quickly disassembling various components
CN205978809U (en) * 2016-08-25 2017-02-22 中国水利水电第十三工程局有限公司 Pipe drawing device is used in water feeding line construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2113598B (en) * 1981-12-15 1985-12-11 Omega Software Heat exchanger maintenance
JPS61257723A (en) * 1985-05-04 1986-11-15 Chiyoda Chem Eng & Constr Co Ltd Extracting and extruding device of pipe bundle
JP2010017833A (en) * 2008-07-14 2010-01-28 Kurimoto Ltd Pipe joint dismantling device and dismantling method
CN201419313Y (en) * 2009-06-12 2010-03-10 上海船厂船舶有限公司 Assembly and disassembly device for ship coupling
CN203141057U (en) * 2012-12-18 2013-08-21 云南昆钢重型装备制造集团有限公司 Drawing device
CN103612107A (en) * 2013-11-25 2014-03-05 河北钢铁股份有限公司邯郸分公司 Universal tool capable of quickly disassembling various components
CN205978809U (en) * 2016-08-25 2017-02-22 中国水利水电第十三工程局有限公司 Pipe drawing device is used in water feeding line construction

Also Published As

Publication number Publication date
CN106195440A (en) 2016-12-07

Similar Documents

Publication Publication Date Title
CN106195440B (en) Water supply line construction pipe drawing device and tube drawing construction method
CN203519351U (en) Loading device for mooring test
CN107606383B (en) A kind of pneumatic locking type flexibility in-pipe robot of single-acting and its working method
CN105156117A (en) Tunnel-rescue pipe jacking machine and construction method thereof
CN105736829A (en) Mechanical installation method for pipelines in pipe ditch
CN201588236U (en) Hydraulic grab for construction of underground continuous wall and grab machine
CN205978809U (en) Pipe drawing device is used in water feeding line construction
CN108203992A (en) A kind of assembled underground pipe gallery
CN203654287U (en) Pile casing pulling device
CN204606137U (en) A kind of anchoring arrangement of hydraulic suction dredge
CN206635765U (en) A kind of conduit tip
CN204941546U (en) A kind of tunnel rescue push-bench
CN208534487U (en) Small-bore mire water equilibrium tube equipment slip casting tail sleeve device
CN201932891U (en) Extensible device with built-in pipe and combination of double-degree hydrocylinder and drag chain
CN204385740U (en) A kind of subaqueous construction two-stroke hydraulic pile hammer
CN209339072U (en) A kind of road sweeper imbitition connecter
CN105568964A (en) Umbrella-shaped assistant device for construction of tubular pile expanded-foot
CN104455742A (en) Clamp structure for underwater control cable
CN201825639U (en) Special tool for hoisting steering clutch of bulldozer
CN204456112U (en) One scraps well well casing plucking device
CN201810932U (en) Release type plugging device
CN204371413U (en) A kind of highstrenghtpiston's pipe for escaping
CN202203598U (en) Built-in pipeline traction device
CN108083117B (en) A kind of twin-tub rope telescopic system and crane for realizing the synchronous recycling of boom
CN207625241U (en) Gantry crane cable transfer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 300384 Tianjin Binhai New Area High-tech Zone Huayuan Industrial Area No. 2, 4-2101

Patentee after: China Construction Municipal Construction Group Co., Ltd.

Address before: 300384 No. 2, Rongyuan Road, Huayuan Industrial Area, Nankai District, Tianjin 4-2101

Patentee before: Sinohydro Tianjin Engineering Co.,Ltd.